Explore 1.5M+ audiobooks & ebooks free for days

Only $12.99 CAD/month after trial. Cancel anytime.

Project Pre-Check: The Stakeholder Practice for Successful Business and Technology Change
Project Pre-Check: The Stakeholder Practice for Successful Business and Technology Change
Project Pre-Check: The Stakeholder Practice for Successful Business and Technology Change
Ebook416 pages2 hours

Project Pre-Check: The Stakeholder Practice for Successful Business and Technology Change

Rating: 0 out of 5 stars

()

Read preview

About this ebook

Projects which implement major business and technology change have been, and will continue to be, risky ventures. The chance of success is generally well below 50%. However, there are well established, proven practices that can reduce the risks of failure dramatically. The challenge is to identify and apply the best practices that deliver maximum value for each change initiative.

Project Pre-Check gathers these best practices for consideration by a project's key stakeholders, the guiding coalition for a change. It is based on this premise: if the key stakeholders for a given change are actively involved in and agree with each decision, and all the vital decisions are addressed, the project will be successful.

Project Pre-Check includes three building blocks to ensure project success; Stakeholders, Processes and the Decision Framework. These building blocks provide the key decision makers with a roadmap to success and the best practice framework to ensure successful change.

Project Pre-Check includes planning, governance and project assessment processes to facilitate active stakeholder involvement very early in a project's life cycle. It enables rapid assessment of stakeholder agreement on 125 key decision areas to identify gaps that may require remedial action. It can be applied effectively in the pre-launch stages, as part of or immediately after project initiation, up until solution delivery and on a release by release basis. Whenever it's used, it will help identify and remove those fatal flaws that can lead to project ruin.

LanguageEnglish
PublisherTrafford Publishing
Release dateDec 13, 2007
ISBN9781466958210
Project Pre-Check: The Stakeholder Practice for Successful Business and Technology Change
Author

R. Andrew Davison

R. Andrew Davison is principal consultant in Davison Consulting, a process consulting firm which focuses on project, program and portfolio management, strategy formulation, process and practice development and the implementation of high performance teams. Previously, he was an information technology practitioner, manager and executive in the financial services industry. He studied history at Carleton University in Ottawa, Ontario, holds a fellowship from the Life Office Management Association and has nurtured a passion for continuous improvement throughout his career. When he’s not helping organizations improve their practices and performance, he can be found walking or biking the roads and trails around Long Point, Balsam Lake, reading, cooking (in a pinch) and enjoying the sunsets and a glass of wine with his wife Louise and Bearded Collie Tillie (who doesn’t drink wine but likes the sunshine).

Related to Project Pre-Check

Related ebooks

Business For You

View More

Reviews for Project Pre-Check

Rating: 0 out of 5 stars
0 ratings

0 ratings0 reviews

What did you think?

Tap to rate

Review must be at least 10 words

    Book preview

    Project Pre-Check - R. Andrew Davison

    © Copyright 2007 R. Andrew Davison.

    All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the written prior permission of the author.

    Note for Librarians: A cataloguing record for this book is available from Library and Archives Canada at www.collectionscanada.ca/amicus/index-e.html

    ISBN: 978-1-4120-9074-2 (Softcover

    ISBN: 978-1-4669-5821-0 (Ebook)

    We at Trafford believe that it is the responsibility of us all, as both individuals and corporations, to make choices that are environmentally and socially sound. You, in turn, are supporting this responsible conduct each time you purchase a Trafford book, or make use of our publishing services. To find out how you are helping, please visit www.trafford.com/responsiblepublishing.html

    Our mission is to efficiently provide the world’s finest, most comprehensive book publishing service, enabling every author to experience success. To find out how to publish your book, your way, and have it available worldwide, visit us online at www.trafford.com/10510

    Image469.JPG

    www.trafford.com

    North America & international 

    t oll-free: 1 888 232 4444 (USA & Canada)

    phone: 250 383 6864 ♦ fax: 250 383 6804 ♦ email: [email protected]

    The United Kingdom & Europe 

    p hone: +44 (0)1865 722 113 ♦ local rate: 0845 230 9601 facsimile: +44 (0)1865 722 868 ♦ email: [email protected]

    10 9 8 7 6 5 4 3

    Contents

    TABLE OF FIGURES

    PART I Introduction

    1 HOW THIS BOOK IS ORGANIZED

    2 WHO SHOULD READ THIS BOOK

    3 ACKNOWLEDGEMENTS

    4 I’D LIKE TO HEAR FROM YOU!

    PART II Overview

    5 WHY PROJECTS FAIL

    6 HOW PROJECT PRE-CHECK HELPS

    7 BUILDING BLOCKS

    7.1 Stakeholders

    7.1.1 Sponsor

    7.1.2 Change Agent

    7.1.3 Target

    7.1.4 Champion

    7.1.5 Changes in Perspective

    7.1.6 Stakeholder Guidelines

    7.2 Project Pre-Check Processes

    7.2.1 Diagnostic Process

    7.2.2 Framing Process

    7.2.3 Oversight Process

    7.3 Decision Framework

    7.3.1 Change Domain and Factors

    7.3.2 Environment Domain and Factors

    7.3.3 Assets Domain and Factors

    7.4 Managing Decision Areas

    7.4.1 Definitions: Best Practice and Decision Area

    7.4.2 Mapping Best Practices to Decision Areas

    7.4.3 Which Practice to Use

    7.4.4 Using Decision Areas

    7.4.5 The Decision Framework Value Added

    8 USING PROJECT PRE-CHECK

    8.1 Fast Start-For Active Projects

    8.2 Optimum Value-For New Projects

    8.3 Maximum Impact-For All Projects

    8.4 Lead by Example-For All Projects

    PART III

    Project Pre-Check Processes

    9 DIAGNOSTIC PROCESS

    9.1 Engagement Stage

    9.1.1 Input

    9.1.2 Process 

    9.1.3 Output 

    9.2 Orientation Stage

    9.2.1 Process 

    9.2.2 Output 

    9.3 Assessment Stage

    9.3.1 Process 

    9.3.2 Output 

    9.4 Action Plan Stage

    9.4.1 Input

    9.4.2 Process 

    9.4.3 Output 

    10 FRAMING PROCESS

    10.1 Discovery Stage

    10.1.1 Input

    10.1.2 Process 

    10.1.3 Output 

    10.2 Introduction Stage

    10.2.1 Process 

    10.2.2 Output 

    10.3 Assignment Stage

    10.3.1 Process 

    10.3.2 Output 

    10.4.1 The Framing Plan

    10.4.1 Input

    10.4.2 Process 

    10.4.3 Output 

    11 OVERSIGHT PROCESS

    11.1 Relevancy Control Stage

    11.1.1 Input

    11.1.2 Process 

    11.1.3 Output

    11.2 Specification Control Stage

    11.2.1 Input

    11.2.2 Process 

    11.2.3 Output

    11.3 Change Control Stage

    11.3.1 Input

    11.3.2 Process

    11.3.3 Output

    11.4 Completion Stage

    11.4.1 Input

    11.4.2 Process 

    11.4.3 Output 

    12 MANAGING THE PROCESSES

    12.1 Using with Other Standard Methods

    PART IV

    Decision Framework

    13 CHANGE DOMAIN

    13.1 Dimensions Factor

    13.1.1 Burning Platform

    13.1.2 Business Need or Opportunity

    13.1.3 Business Goals and Objectives

    13.1.4 Worth

    13.1.5 Requirements

    13.1.6 Benefits

    13.1.7 Locations

    13.1.8 Targets Dates

    13.1.9 Phasing & Staging

    13.1.10 Assumptions

    13.1.11 Volumes, Mix, Peak Periods

    13.2 Quality Factor

    13.2.1 Authorization

    13.2.2 Audit Trail

    13.2.3 Correctness

    13.2.4 Continuity of Processing

    13.2.5 Service Levels

    13.2.6 Security

    13.2.7 Compliance

    13.2.8 Ease of Use

    13.2.9 Portability

    13.2.10 Coupling

    13.2.11 Scalability

    13.2.12 Flexibility

    13.2.13 Localizability

    13.3 Investment Evaluation Factor

    13.3.1 Economic Impact

    13.3.2 Competitive Advantage

    13.3.3 Strategic Fit

    13.3.4 Competitive Risk

    13.3.5 Project or Organizational Risk

    13.4 Stakeholder Capability Factor

    13.4.1 Roles and Responsibilities

    13.4.2 Sponsor Commitment

    13.4.3 Sponsor Communication

    13.4.4 Sponsor Capability

    13.4.5 Change Agent Commitment

    13.4.6 Change Agent Communication

    13.4.7 Change Agent Capability

    13.4.8 Target Commitment

    13.4.9 Target Communication

    13.4.10 Target Capability

    13.4.11 Target Skill Requirements

    14 ENVIRONMENT DOMAIN

    14.1 Business Plan Factor

    14.1.1 Mission

    14.1.2 Vision

    14.1.3 Culture and Core Values

    14.1.4 Strategies

    14.1.5 Enterprise Priorities

    14.1.6 Dependencies

    14.1.7 Programs

    14.1.8 Timing

    14.2 Current State/Future State Factors

    14.2.1 External Relationships

    14.2.2 Products and Services

    14.2.3 Processes and Functions

    14.2.4 Interfaces

    14.2.5 Information

    14.2.6 Technology

    14.2.7 Resources and Facilities

    14.2.8 Organization

    14.2.9 Inter-relationships among Decision Areas

    15 ASSETS DOMAIN

    15.1 Resources Factor

    15.1.1 Skill & Capacity

    15.1.2 Skill Development

    15.1.3 Resource Procurement

    15.1.4 Resource Contract Management

    15.1.5 Team Formation

    15.1.6 Performance Management

    15.1.7 Succession Planning

    15.2 Delivery Factor

    15.2.1 Management of Change

    15.2.2 Software Delivery

    15.2.3 Technology Change

    15.2.4 Quality Assurance

    15.2.5 Prototyping

    15.2.6 Partitioning

    15.2.7 Time Boxing

    15.2.8 Reuse

    15.2.9 Project Close

    15.3 Project Management Factor

    15.3.1 Project Management Process

    15.3.2 Organization

    15.3.3 Estimating

    15.3.4 Project Communication

    15.3.5 Requirements Management

    15.3.6 Risk Management

    15.3.7 Issue Management

    15.3.8 Change Control

    15.3.9 Defect Tracking

    15.3.10 Gating

    15.4 Business Operations Factor

    15.4.1 Budgeting and Cost Management

    15.4.2 Compliance

    15.4.3 Corporate Tracking and Reporting

    15.4.4 Strategic Planning

    15.4.5 Content Management

    15.4.6 Business Continuity Planning

    15.4.7 Contract Management

    15.5 Security Administration Factor

    15.5.1 Security Policy

    15.5.2 Physical Security

    15.5.3 Information Security

    15.5.4 Human Resources Security

    15.6 Technology Operations Factor

    15.6.1 Service Desk

    15.6.2 Change Management

    15.6.3 System Administration

    15.6.4 Print and Output Management

    15.6.5 Technology Installation

    15.6.6 Service Level Management

    15.7 Infrastructure Factor

    15.7.1 Client Capacity

    15.7.2 Server Capacity

    15.7.3 Network Capacity

    16 PROJECT DOMAIN

    16.1 Planning Factor

    16.1.1 Business Alternatives

    16.1.2 Technology Alternatives

    16.1.3 Release Plan

    16.1.4 Cost Estimates

    16.1.5 Benefit Plan

    16.1.6 Quality Plan

    16.1.7 Resources and Facilities Plan

    16.1.8 Contracts Plan

    16.1.9 Communication Plan

    16.1.10 Risk Plans

    16.2 Organization Factor

    16.2.1 Project Organization

    16.2.2 Project Roles and Responsibilities:

    16.2.3 Team Formation Plan

    16.3 Control Factor

    16.3.1 Release Plan Performance

    16.3.2 Contracts Plan Performance

    16.3.3 Risk Plan Performance

    16.3.4 Change Tracking and Reporting

    16.3.5 Issue Tracking and Reporting

    16.3.6 Project Completion

    16.4 Communication Factor

    16.4.1 Monitor Updates

    16.4.2 Monitor Feedback

    APPENDICES

    A. DECISION AREA SOURCES

    B. ADDITIONAL SOURCES

    ABOUT THE AUTHOR

    NOTES

    TABLE OF FIGURES 

    Figure 1 - Project Pre-Check Building Blocks

    Figure 2 - Stakeholder Roles

    Figure 3 - Creating the Stakeholder Group

    Figure 4 - Project Pre-Check Processes

    Figure 5 - Using Project Pre-Check Processes

    Figure 6 - Decision Framework Domains

    Figure 7 - Decision Framework Domains & Factors

    Figure 8 - Mapping Best Practices to Decision Areas

    Figure 9 - Project Pre-Check Domains, Factors and Decision Areas

    Figure 10 - Building Blocks Working Together

    Figure 11 - Project Pre-Check Processes

    Figure 12 - Diagnostic Process

    Figure 13 - Sample Completed Diagnostic Questionnaire

    Figure 14 - Sample Diagnostic Consolidation

    Figure 15 - Sample Diagnostic Action Plan

    Figure 16 - Framing Process

    Figure 17 - Sample Completed Assignment Questionnaire

    Figure 18 - Sample Assignment Consolidation

    Figure 19 - Sample Framing Plan

    Figure 20 - Oversight Process 96

    Figure 21 - Sample Oversight Scorecard

    Figure 22 - Completion Questionnaire

    Figure 23 - Consolidated Completion Results

    Figure 24 - Using Project Pre-Check With Other Standard Methods

    Figure 25 - Decision Framework Domains & Factors

    Figure 26 – Decision Framework Domains, Factors & Decision Areas

    Figure 27 - Change Domain Factors

    Figure 28 - Environment Domain Factors

    Figure 29 - Assets Domain Factors

    Figure 30 - Project Domain Factors

    Figure 31 - Profile Chart

    In Memory

    William Gordon Davison

    1910-2005

    PART I

    Introduction 

    1.   How This Book Is Organized

    2.   Who Should Read This Book

    3.   Acknowledgements

    4.   I’d Like To Hear From You

    "Utopia:

    Everything works right the first time. Everyone quests for doing it better tomorrow than today. Customer needs are constantly met. Products work better, last longer. Waste disappears from the system. People love their jobs."

    Joel Barker-Future Edge

    It really is possible! To envisage a change, a new venture, a new opportunity, and deliver it successfully. To deliver the right capability, that adds the most value. At a reasonable cost. When it’s needed. With functionality that works. That meets the needs of each audience. Joel Barker’s quote above describing his view of Utopia can become our new, everyday reality.

    That’s the aim of this book and the book’s subject matter, Project Pre-Check: to help stakeholders deliver major business and technology change successfully.

    What is a stakeholder? In the context of this book, it is a decision maker who:

    o Directs an organization that initiates, is affected by or is charged with 

    m anaging all or part of a change,  

    o Has the authority to set direction, establish priorities, make decisions, commit money and resources and

    o Is accountable for delivering the planned benefits on budget and on plan.

    Stakeholder involvement and commitment is one of the most important key success factors for successful business and technology change. Without it, a project is pretty well doomed. There are thousands of organizations that focus on effective project and change management, lots of books and a veritable avalanche of periodicals and articles about both subjects. But there are few, if any, tools that focus exclusively on stakeholders-until now!

    Project Pre-Check provides a unique practice for stakeholders that is easy to learn, easy to apply and quick to deliver value. Stakeholders can garner meaningful insight into a project’s strengths and weaknesses in a matter of days. The results provide a comprehensive platform for pro-active and remedial action that ensures the focus is always on the real goal-delivering targeted benefits to the organization.

    Project Pre-Check is built on years of real world experience and involvement, and exposure to the best and the worst. It reflects the insight gained from outstanding successes and a few excruciating failures, from great leaders and knowledgeable and talented practitioners, and from a few charlatans and hacks.

    It was designed to leverage the successes, to make sure that the insights gained and the lessons learned are applied to future undertakings and by future generations. It was developed in response to the failures, to ensure that they never happened again on our watch. It was designed to enable stakeholders to deliver still greater value, consistently, time after time.

    "Those who do not remember the past are condemned

    to repeat it"

    From The Life of Reason by George Santayana

    The business and technology press cite numerous studies that indicate the chances of implementing a major business or technology change successfully are significantly less than 50 %. There are regular revelations in the press about companies’ struggles with project cost overruns, damaging schedule delays, disruptive quality problems, injurious security issues or projects abandoned outright.

    A sampling of seven of the 88 information technology projects launched since 2003, worth $7.1 billion, found rampant mismanagement. Many were far over budget and past deadline.

    From the annual report of Canada’s Auditor General as reported in the November 29, 2006 Toronto Star

    There are thousands of books, periodicals, and articles that purport to tell us why major projects fail and how to ensure success. But projects continue to fail, wasting billions in sunk costs and lost opportunity. Why? Because each change is unique, and organizations lack the collective will, knowledge and capability-time, money, expertise and appropriate frameworks-to absorb and apply the available wisdom effectively to each particular situation.

    Project Pre-Check provides an extensible framework that helps stakeholders manage and access proven practices and leverage potential opportunities. It leads stakeholders to consider a broad range of concerns; business, technology, strategic directions, operational issues and the logistics of managing change to ensure project success.

    But, most importantly, Project Pre-Check requires and enables stakeholder collaboration. It is the key element that makes Project Pre-Check work and it is a pre-requisite for successful change. As Robert Kaplan and David Norton state in their book, The Strategy-Focused Organization, If those at the top are not energetic leaders of the process, change will not take place, strategy will not be implemented, and the opportunity for breakthrough performance will be missed.²

    Experience has repeatedly shown that the single most Important condition for success is the ownership and involvement of the executive team.

    Robert Kaplan & David Norton-The Strategy-Focused Organization

    1 HOW THIS BOOK IS ORGANIZED 

    Learning a new practice, a new way of managing change, always requires an investment of time, effort and energy. For some, Project Pre-Check will be a natural extension to an existing collaborative milieu. For others, applying Project Pre-Check will be a significant cultural change. Each individual and each organization needs to determine the most effective path for delivering value. This book is organized to provide each reader with a variety of choices as to how to explore Project Pre-Check and address their particular needs.

    Part I-Introduction, describes the rationale for the book, its organization, the players that will benefit from the material presented and the events and people that shaped the ideas and content.

    Part II-Overview, describes the context for Project Pre-Check. It includes opinions on why projects fail, how Project Pre-Check can help, an introduction to the Project Pre-Check building blocks and how they can be used to ensure project success.

    Building Blocks describes the three key components of Project Pre-Check: Stakeholders, Processes and the Decision Framework. It also explains how they work together to help stakeholders deliver value to their organizations.

    Please make sure you read this section. An understanding of the building blocks is essential for forming the stakeholder group, using the processes and leveraging the Decision Framework effectively.

    Part III-Project Pre-Check Processes provides step by step coverage for each of the three Project Pre-Check processes-Diagnostic, Framing and Oversight. It identifies the inputs and outputs and provides guidance for each step.

    Part IV-Decision Framework includes the Decision Area catalogue which describes the Domains, Factors and Decision Areas that stakeholders need to consider when assessing, planning and controlling a change. Most of the

    Decision Areas can be accessed through the use of the appropriate templates. However, for an understanding or a refresher on the meaning of a particular Decision Area or ideas on specific best practices, this section can serve as a valuable reference.

    Appendices-include listings of a variety of industry sources and best practices that provide the foundation for this

    Enjoying the preview?
    Page 1 of 1