Introduction
The quest for value for money in government activities has brought monitoring and evaluation (M&E) to the fore of development management. Within the realm of development management, M&E provides all stakeholders of development a better means of learning from past experience, particularly as it relates to improving service delivery, as well as planning and allocation of resources.
5/20/2009
Public sector managers generally use M&E for two overt purposes i.e. management and accountability. In the past, not much attention was paid to M&E in the development process in Nigeria. Lip service attention was paid to M&E without any significant bearing on project outcomes. That, to a large extent explained the large number of erstwhile uncompleted/abandoned projects. While, for those that were eventually completed, the completion time became greatly lengthened resulting in cost overrun. 5/20/2009
The primary reasons often mentioned for the proliferation of uncompleted projects include unnecessary delays in project completion and cost overrun. The need to address these issues underscores the importance of project monitoring and evaluation in the country.
5/20/2009
Monitoring and Evaluation is concerned with one or more of the following aspects of programme/project performance
Effectiveness: To what extent has the programme/project achieved its objective and reaches its target group(s)? Efficiency: Relevance: Impact: Do the expected programme/project results continue to justify the costs incurred? Does the programme/project continue to make sense? Is there a perceived change in the status quo i.e the degree to which the beneficiaries are affected positively or otherwise?
5
5/20/2009
What is the level of acceptance, cooperation or otherwise of the target beneficiaries? Is the design logical and coherent? What specific factors or events have affected the programme/project results?
5/20/2009
Unanticipated: Is the programme/project having any significant (positive and/or negative) effects which were not foreseen? Alternative Is there, or would there have been, a more effective way, strategies to address the problem(s) and achieve the objective(s)
5/20/2009
What is Monitoring?
Monitoring is the continuous or periodic review of programme/project implementation to assess delivery, identify difficulties, ascertain problem areas and recommend remedial actions. Budget monitoring involves the collection and analysis of data about budget activities. The data should be easy to understand. It allows budget operators to keep track of budget activities to determine whether budget objectives are being achieved and to make whatever changes that are necessary to improve budget performance. The purpose of monitoring is to ensure the efficient and effective programme/project implementation. It provides timely information on the work planned and done to all the parties concerned. Primarily concerned with the delivery process, ensuring that inputs, through activities, are transformed into outputs, and analyzing their 5/20/2009 quantity and quality.
programme/project as it relates to performance, costs and time schedule relative to the original plan
(ii) Identify constraints to performance, their sources and
5/20/2009
analyses by presenting a range of logical options requiring decisions by management. The logical options should include, among others, suggested solutions, and /or actions needed to be taken to put the project on course.
9
Types of Monitoring
Start up Monitoring Financial Monitoring ensures that fund released for execution of project is expended as planned Physical Monitoring involves critical examination of activities such as purchases, construction, etc Inputs Output Analysis Monitoring it determine the efficiency and effectiveness of the system and shows whether the level of output is commensurate with inputs consumed. 10 5/20/2009
What is Evaluation?
Evaluation is a sporadic or spontaneous process or
act of assessing a projects effectiveness, efficiency, costs, relevance and impact based on specified objectives and from the information obtained laid a solid foundation for a better execution of similar project in future. Evaluation is meant to improve both an on going project and the planning, programming and decision making of future projects
5/20/2009
11
Measures achievement in relation to institutional objectives and goals set for each operation. Is designed to provide an objective basis for assessing the performance of policies, programmes, projects and processes. Improves policies, programme and projects by identifying and disseminating the lessons learned from experiences.
12
5/20/2009
Types of Evaluation
Ex- Ante Evaluation On-going Evaluation Terminal Evaluation Ex- Post Evaluation
5/20/2009
13
Budget Monitoring and Evaluation serves several purposes: facilitates the identification and resolution of
problems; enhances budget performances and ensures congruence with the overall government policy criteria; provides the basis for technical and financial accountability; builds local capacity to implement and manage projects successfully; and, promotes the identification and dissemination of lessons learned which is then applied in the implementation of successive budgets/projects
14
5/20/2009
personnel Shortage of materials/facilities Poor data base Insufficiency Coordination among various level of M&E The time-span for the monitoring for many projects is too short for any meaningful assessment of project. Lack of understanding of monitoring by many organizations.
5/20/2009
15
Factors Contd.
Failure to involve end-users in the planning and evaluation
of development projects. Associated with the above factors are the following fundamental facts:-
Projects NEEDS (PRSP), only serve as Proxy for National Development Plan but not a plan MTSS is only applicable in some selective sectors and as such not the entire budget is MTEF compliant There is limitation in the use of MTSS and MTEF as they relate to growth in developing countries Evidence shows that most countries with double digit growth are the one operating development plans, eg Indian, China, Malaysia, etc 5/20/2009 projects admitted into the budget do not pass through the MTSS Many 16
Factors Contd.
The implication of the above is that : The whole discussion on M&E is turned to a mere rhetoric as there are no effective M&E framework built into the budget
Ability to engage in any meaningful monitoring and
performance evaluation is impaired as there are no comprehensive verifiable and measurable targets against which to monitor and evaluate budget performance
The best that be done is to evaluate performance on the
5/20/2009
Factors Contd.
Budget performance should be evaluated against
5/20/2009
18
Which way out? Need to Return to Formal Planning for effective M&E
Nigeria vision 20: 2020 is a perspective plan To be translated into medium term plans of between 3 and 5 year time
horizon Budgeting system will move away from the traditional line item type to a performance-based system Programmes and projects admitted into the budget will be based on policy objectives of the National development plan Programmes and projects will be fully costed and targets attached There will be buy-in by all stakeholders especially the legislature in the plan making process
5/20/2009 19
measurable indicators, Re-invigoration of the role of the National Planning Commission and the Federal Ministry of Finance in plan formulation, budget preparation, monitoring and evaluation. Ensure regularly and timely submission of progress report (preferably quarterly), giving details of activities and progress, measured against targets and statement of income and expenditure. 20 5/20/2009
and the progress review. While the work plan indicates what will be done, the progress review examines work actually carried out.
The work plan should provide:
The outputs and activities described in a schedule Sequence in relation to each immediate objective Their planned starting and completion dates The person(s), organisation and/or institution responsible for carrying out the work
21
5/20/2009
Are inputs being made available as planned? Are activities being carried out according to the work plan? Are outputs being produced as scheduled? What changes have taken place, particularly, if any additions or deletions were made?
What problems or difficulties have been encountered? What remedial actions have been taken or are planned?
22
5/20/2009
design: When data will be collected and by whom, what interventions are likely to interfere with project activities, etc.
that times lines and data-collection methods can be altered midstream( if necessary).
results, and a joint interpretation of results before conclusions are drawn and decisions made.
5/20/2009
24
participatory component. Participatory monitoring and assessment involves early consultation with the community members and stakeholders about:
5/20/2009
project design, the problems to be addressed, potential courses of action, community resources which can be brought to bear, the role of external support, participatory research to complete baseline information, participatory definition and agreement on project concept, consensus about the project objectives and activities
25
(i) Adequate staff in terms of quality, quantity and experience should be deployed to the M & E departments. (ii) Release of funds for projects should be based on a clean report from the M&E Departments on the earlier projects executed or funds released.
5/20/2009
26
objectively there is the need for proper funding of M&E Department/Units with running grants as well as appropriate equipment.
various levels to allow for free flow of information and minimization of conflicts.
27
5/20/2009
in all projects. No project should be admitted into the budget or approved without explicit statement of how it will be monitored and evaluated, including where possible quantifiable indicators and targets.
(vii) All budget proposals should also be required to present a Risk Analysis stating the critical assumptions and external factors upon which the achievement of budget objective depends
5/20/2009
28
Budget/Project Reporting
Reporting is an essential component of budget and project
management It is the formal presentation of monitoring information. The main reasons for reporting are the following: (a) To formally inform management : Reporting ensures that management, particularly the project coordinators supervisor or project manager, is formally appraised of the progress made in project implementation and the supervisor or project manager is aware at an early stage of actual and potential problems and any remedial action taken;
5/20/2009 29
Reporting Contd.
(d) To serve as a reference for future projects: Reporting serves as a vital resource for ensuring that lessons learned (project successes, failures, best practices) through project implementation are available for consideration when formulating and implementing future projects; (e) To report to the donors on the projects progress: Often, reporting is requested by donors as they have shared interests in the success of projects. Donors sometimes fund projects contingent upon satisfactory progress. They increasingly ask for progress and final reports at the 5/20/2009 results and objectives level rather than at the level of 31 output or activity delivery.
from the various government supervisory agencies such as the budget office, National Assembly and the Fiscal Responsibility Commission in compliance with the Fiscal Responsibility Act, 2007;
5/20/2009
32
generally done towards the end of the budget year or project implementation, but as matter of effectiveness, it should be regularized and should be included along with monitoring in project design.
5/20/2009
33
Concluding Remarks
The result of monitoring and evaluation must be fed back into the implementation of on-going activities and the planning of future ones, as part of lessons learnt. However, while a monitoring and evaluation framework should be systematic, it should also allow for unexpected occurrences and results.