Earned Value Professional (EVP) Sample Examination
Earned Value Professional (EVP) Sample Examination
2. Which of the following steps would be considered the least desirable corrective action for a project that has an unfavorable SPI? a. b. c. d. Revise activities on the critical path Rebaseline to eliminate schedule variance Crash the schedule Review activities with positive float
3. The Performance Measurement Baseline includes the following: a. Summary level planning packages, control account budgets, and undistributed budget b. Indirect costs, control account budgets and management reserve c. Direct costs, control account budgets and management reserve d. Direct costs, indirect costs and management reserve
4. The _______is the point at which work is planned, progress is measured, and earned value is computed a. b. c. d. Work package Control account Activity/Task WBS element
5. Which method should be used to calculate earned value for tasks that are related in direct allocation to a base work package? a. b. c. d. Level of effort Allocated effort Percent Complete Apportioned effort
6. Which method can be used to calculate BCWP? a. b. c. d. ACWP/EAC ACWP/BCWS % Complete * BAC % Complee * EAC
7. Given the following information, calculate the cost and schedule variances: BAC = $50,000 EAC = $55,000 BCWS = $15,000 BCWP = $20,000 ACWP = $25,000 a. b. c. d. CV = ($5,000); SV = $5,000 CV = $5,000; SV = ($5,000) CV = ($10,000); SV = $10,000 CV = $10,000; SV = ($10,000)
8. What is the primary benefit of the To Complete Performance Index (TCPI)? a. Projects final cost b. When compared to the other performance indices it provides a forecast of how much of a productivity improvement is required to finish the project on budget c. Shows the required efficiency to complete the project as forecasted by the EAC d. Provides a historical perspective of the project
9. Which of the following provides a statistical forecast of the final EAC assuming that all remaining work will be done at the budgeted rate? a. b. c. d. [(BAC - EV) / (CPI x SPI)] + actual to date = EAC [(BAC + EV) / (CPI x SPI)] + actual to date = EAC [(ETC) / (CPI x SPI)] + actual to date = EAC (BAC - EV) + actual to date = EAC
10. Which of the following is not required for a critical path schedule: a. b. c. d. Resources Milestones and key contractual events Subcontractor schedules Logical relationships between activities (tasks)
TCPIEAC 1.36
2.3 Which one of the following conditions is most likely to apply? a. Because the project is ahead of schedule, the EAC will be less than the BAC b. The EAC is statistically not probable based on the variance between CPI and TCPIBAC c. There is a labor shortage d. None of the above 2.4 The calculated EAC based on the cumulative cost and schedule performance is? a. $10,612 b. $10,510 c. $9,467 d. $9,803
AACE International - Earned Value Professional Sample Examination 3
Answers
Section I and II : 1-d, 2-b, 3-a,4-a, 5-d, 6-c, 7-a, 8-c, 9-d, 10-a Section III : 2.1-a, 2.2-b, 2.3-d, 2.4-b