SCOPE of Works For A Building Construction
SCOPE of Works For A Building Construction
P R EP A R ED BY : L A ZA , L EM ER S O N J .
P R ES E N TE D T O: E N G R . BO B BY P . C A LI C D A N
S.Y. 2012-2013
SCOPE OF WORKS
Two-Storey Residential Building
I.
II.
EARTHWORK
All existing structure/tree must be removed prior to layout; Excavation should be undertaken as per approved designed depth and should be for final approval of the Engineer in charge. Backfilling should be done in such a way it would leave. Soil should be compacted up to the maximum allowable percentage prior to concreting.
III. S T R U C T U R A L
A. C O N C R E T I N G 1. F O U N D A T I O N 2. COLUMNS 3. BEAMS B. R E I N F O R C E M E N T C. S T E E L R O O F F R A M E D. M A S O N R Y W O R K S 1. W A L L S E. R O O F I N G
V.
ARCHITECTURAL/FINISHING
A.
B. C. D. E.
FLOOR FINISHES WALL FINISHES CARPENTRY WORKS DOORS AND WINDOWS FINISHING HARDWARE
V I. E L E C T R I C A L FIXTURES
A. B. C. D. E. F. G. CIRCUIT BREAKERS ELECTRICAL PIPES AND FITTINGS ELECTRICAL G.I. BOXES WIRES AND CABLES SWITCHES CEILING EAVES OUTLETS LIGHTING OUTLETS
V III.
PAINTING
ROUGHING-IN WORKS
ACTIVITY
A. TEMPORARY FACILITIES B. EARTHWORKS C. TERMITE PROOFING D. FOUNDATION E. PLUMBING ROUGHING IN G/F F. ELECTRICAL ROUGHING IN G/F G. COLUMNS G/F H. WALLS G/F I. BEAMS (FOR 2ND FLOOR) + SLAB (2ND FLOOR) J. PLUMBING ROUGHING IN 2ND /F K. ELECTRICAL ROUGHING IN 2ND/F L. COLUMNS 2 /F M. WALLS 2ND/F N. BEAMS (FOR ROOF) O. TRUSSES INSTALLATION P. ROOFING
ND
DEPENDENCY
A B C D D E E, F G, H I I J J, K L, M N O
DURATION (DAYS)
6 12 3 12 6 6 6 12 12 6 6 6 12 4 18 6
FINISHING WORKS
ACTIVITY
A. FLOOR FINISHING B. WALL FINISHING C. WATER PROOFING D. CARPENTRY WORKS (CEILING, FASCIA BOARD) E. DOORS AND WINDOWS+ FINISHING HARDWARE (DOOR LOCKS, HINGES) F. CABINETS G. PAINTING H. ELECTRICAL FIXTURES INSTALLATION I. PLUMBING FIXTURES INSTALLATION J. TILEWORKS
DEPENDENCY
A, B A, B
DURATION (DAYS)
10 10 6 18 12
D E, F E C G, H, I,
9 30 6 6 24