75% found this document useful (4 votes)
3K views

PMI Practice Standard For Scheduling

PMI-Practice-Standard-for-Scheduling

Uploaded by

Ajay Kumar
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
75% found this document useful (4 votes)
3K views

PMI Practice Standard For Scheduling

PMI-Practice-Standard-for-Scheduling

Uploaded by

Ajay Kumar
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 29

Acumen Annual Summit

PMI Practice Standard for Scheduling


September 18, 2012

Mike Mosley Director, Project Management Processes

Standards Overview Presentation

PMIs standard development process (cont)

Preliminary planning team is organized Charter/Scope is finalized and approved Volunteers are on-boarded onto the team Content is developed Exposure Draft Appeals Body Consensus Body Balloting Publication!

What is a standard?

PMI Standard - A document established by consensus and approved by a recognized body that provides, for common and repeated use, rules, guidelines or characteristics for activities or their results, aimed at the achievement of the optimum degree of order in a given context.

Voluntary Consensus
Written in a open environment by professionals from both the private and public sector Follows a process based on openness and balance leading to consensus

PMI Standards Background

1969 PMI founded 1983 PMI Special Report on Ethics, Standards, and Accreditation the Standards portion was The Project Management Body of Knowledge (PMBOK) 1987 PMBOK Standard was published 1996 A Guide to the Project Management Body of Knowledge (PMBOK Guide) [first edition] published 1998 PMI accredited as a Standards Development Organization (SDO) by ANSI 2000 The PMBOK Guide - 2000 Edition [second edition] published 2004 The PMBOK Guide - Third Edition published 2008 25th Anniversary of the PMBOK Guide [fourth edition published] 2012 The PMBOK Guide - Fifth Edition targeted for publication
5

PMI Standards: Globally Recognized

PMIs standard development process

Research is conducted to identify possible new standards for development, or, if existing standards need updating Research is validated by PMI, the Standards MAG and others Budget is written up and approved Draft Charter and Scope Statement are developed Voluntary Project Manager (Chair) is hired
7

PMIs standard development process (cont)

Preliminary planning team is organized Charter/Scope is finalized and approved Volunteers are on-boarded onto the team Content is developed Exposure Draft Appeals Body Consensus Body Balloting Publication!

Practice Standard for Scheduling Second Edition


Committee Eight Members

Qualifications: Eight PMP Five PMP-SP One PMI-RMP Geographic: Five North America (four states, coast to coast) One EMEA (Lithuania) Two Asia Pacific (Israel and India) Two Latin America (Curacao & Brazil)
effort.

Note This totals more than eight as there was movement of the members during the course of the

Practice Standard for Scheduling Second Edition


Project chartered to define revision and recommend updates to the Practice Standard for Scheduling for consensus review and publication as a second edition. Charter signed at PMI Leadership Meeting - January 2010 Development Process: First Meeting February 2010 Development - February thru August 2010 PMI Edits, Exposure Draft Prep August thru October 2010 Exposure Draft October thru December 2010 Exposure Draft Comment Adjudication December thru February 2011 Appeals Process February 2011 Publication July 2011

Practice Standard for Scheduling Second Edition

Final Statistics (not counting editorial comments): Total comments Accepted 837 22.8% 88.7%

Accepted w/Mods 65.9% Incorporated Deferred (8) Rejected 0.01% 3.6%

One Appeal received, Adjudicated as Accepted

The Committee The Practice Standard for Scheduling Second Edition


Team photo at lessons learned meeting, with published Standard.

Key Points:

Schedule What do you want? What is critical?

0311.1

13

Schedule What do you want?

Have you been asked to provide: A schedule In electronic format In native format
0311.1

14

A Schedule:

PMI Defines a schedule as:

The planned dates for performing schedule activities and the planned dates for meeting schedule milestones.

0311.1

15

A Schedule:

0311.1

16

In Electronic Format:

Do the following serve: Excel Visio PDF


0311.1

17

In Native Format:

Do the following serve: Excel Visio XER or MPP


0311.1

18

How About a Schedule Model:


PMI Defines a schedule model as:

A dynamic representation of the plan for executing the projects activities developed by the project stakeholders applying the schedule method to a scheduling tool using project specific data such as activity lists and activity attributes.
0311.1

19

How About a Schedule Model:

Dynamic:

The model reacts to inputs as the project team expects the project to react.

0311.1

20

How About a Schedule Model:


PMI Defines Activity Attributes:

0311.1

Multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
21

De ne Critical:
CPM in Construction Management (James OBrien/Fred Plotnick):

The classic definition of critical, as on the critical path, is where total float equals zero.
PMI describes the critical path:

It is the longest path through the project.


0311.1

22

Schedule Calculations Network Logic

All Durations in Weeks


0311.1

23

Schedule Calculations Network Solution

0311.1

24

Schedule Calculations Network Logic


Days, 4-10s w/o Constraint
99 99 16 0 123 123

1 1

12 0

18 18

22 22

12 0

39 39

43 43

32 0

95 95

22 57

24 20

60 95

0311.1

25

Schedule Calculations Network Logic Ex. 4


Days, 4-10s Ex Act 5 7-10s w/ Constraint
96 96 16 0 111 111

1 1

12 0

18 18

22 22

12 0

39 39

43 43

32 0

95 95

22 22

24 0

60* 60

0311.1

26

Schedule Calculations Network Logic Ex. 5


22 29 12 4 43 50 95 102

1 8

12 04

18 25

39 46

32 4

Days, 4-10s Ex Act 5 7-10s w/ Constraint


96 106 16 10 111 121

22 22

24 0

60* 60

121*

LF Constraint on End= 121


0311.1

27

Refined Definitions for Critical


Consider these points from the earlier definitions: An activity with zero float Determines the project finish date, either by total float or longest path Zachry definitions: Critical Activity -Any schedule activity on a critical path in a project schedule. Critical Path - The path of activities that determine the date of a critical milestone. The critical path is usually to the constrained milestone upon which liquidated damages will be assessed. A critical path could be to another, selected milestone signifying the completion of a substantive portion of the work; such as boiler hydro, first fire, etc.
28

0311.1

Thank You!

Harold Mike Mosley, Jr., P.E., PMP Director, Project Management Processes Zachry Industrial, Inc. San Antonio, TX [email protected] (210) 588-5411

You might also like