Capacity Planning
1
Capacity Planning
Capacity is the upper limit or ceiling on the load that an operating unit can handle. The basic questions in capacity handling are:
What kind of capacity is needed? How much is needed? When is it needed?
Various Capacities
Design capacity
Maximum obtainable output
Efficiency =
Effective capacity
Actual output
Utilization = Design capacity
This definition of efficiency is not used very much. Utilization is more important.
5
Actual Output 36 units / day Efficiency 90% EffectiveCapacity 40 units / day Actual Output 36 units / day Utilization 72% Design Capacity 50 units / day
6
Caution: While discussing these the book considers effective capacity almost synonymous to output.
Volume
Volume
Growth
Time
Decline
Time
Figure 5-1
Volume Volume
Cyclical
Stable
Time
Time
8
Rate of output
11
Small
plant
Medium plant
Large plant
Output rate
12
13
Product
Annual Demand
#1 #2 #3
Cost-Volume Relationships
Amount ($)
Cost-Volume Relationships
Amount ($) 0
Q (volume in units)
16
Amount ($)
3 machines
2 machines 1 machine
Quantity Fixed costs and variable costs. Thick lines are fixed costs.
18
Cost-Volume(Break-even) Analysis
Break-even quantity: Level of production that equates total costs to total revenues Assumptions: One product is involved Everything produced can be sold Variable cost per unit is the same with volume Fixed costs do not change with volume Revenue per unit constant with volume Revenue per unit exceeds variable cost per unit
20
21
Decision Theory
equipment selection
22
Decision Theory Elements A set of possible future conditions (call them scenarios) exists that will have a bearing on the results of the decision
Uncertain scenarios
$7 $-4
$12 $2
$12 $16
Example: Hyatt at the Airport some time ago Construct the payoff matrix
Airport location Airport Location Las Colinas Richardson
Purchase Price PV of hotel if airport is built here $18 $31 $12 $23
$4
27
Regret: What I have done against what I could have done. MiniMax Regret.
Airport location Las Colinas Buy Las Colinas Buy Richardson Buy Both Buy None $0=no regret $21 $8 $13 Airport location Richardson $23 $0=no regret $12 $11
29
Summary Capacity types Efficiency, utilization Break-even analysis Decision Theory (decision making under uncertainty)