Operations Management - Oct 27
Operations Management - Oct 27
Scheduling
PRODUCT
HR
PROCESSES
OPERATION MANAGEMENT
MATERIALS
FACILITIES
SCHEDULING
LAYOUT
PLANNING
Inventory Control
Importance of materials availability at various stages of production. Inventory Control & Stores Management Complex Function
No over stocking
Finance Obsolescence Space etc
Inventory Control
No stock Outs Loss of production, Loss of business Imbalances adding costs
Inventory Management
What is meant by Inventory? Why inventory is necessary? What are the various forms of the inventory? What are the costs involved in inventories? What are the risks associated with the inventories?
Materials Management
Importance :
- Materials form major part of the Product cost 60% or so - With contribution at say 15%, every % saved in materials is equal to approx 4% increase in Sales. - Has direct bearing on the profitability - Timely and right quality of materials availability decides the overall productivity of any organisation. - Cannot afford too much or too little both dangerous for survival and growth.
Materials Management
Functions: - Material Planning and controlling
- Purchasing/Vendor development
- Stores and inventory control
Inventory Management
Forms bulk of current assets. Stock outs - Loss of profit from the missed sales - Loss of customer and good will - Loss of production - Reduced machine/men utilization Excessive Inventory - Inventory carrying costs - Cost of storage - Deterioration/obsolescence/pilferage
SCHEDULING
- Business plan transformed into a Master Production plan
- Master production plan Derive resource requirements and check availability - Labour, skills/numbers - Plant & machinery - Finance - Utilities and services and decide and/or agree on the plan
SCHEDULING
Scheduling is the final stage of PPC, where all the production activities are coordinated and projected on a time scale. It tells what resource should be doing what and when. Varies with the manufacturing process It involves a process with which we try to match the requirements set out in the production plan ( quantities,delivery) with the available facilities, including vendors.
SCHEDULING
Several ways to meet the requirements, different routings through machines or processes, sequence of products, priority scale, when and how to expand facilities incl. short term through overtime etc. The best method is decided costs which meets the objectives
SCHEDULING
Objectives
Meet due dates Minimise late completion of jobs or tardiness Minimise completion time Minimise response time Minimise idle time Minimise overall costs Minimise WIP and other inventories Maximise resource utilisation.
SCHEDULING
Forms of scheduling
SCHEDULING
Basic scheduling problems
Flow production scheduling for fluctuating demands Smoothening problems Batch production scheduling, when products are manufactured consecutively Assignment problems Scheduling orders with random arrivals - Product sequencing
SCHEDULING
SCHEDULING
Basic scheduling problems
Flow production scheduling for fluctuating demands
- When sales of some products are subject to seasonal fluctuations, it can be met in one of the following ways; 1. Have a static production programme, coupled with sufficient inventory to satisfy the fluctuating demands. Inventory levels will vary with fluctuating demands but replenishment at constant flow. 2. Have a fluctuating production programme, to cater to changing demand and keep constant inventories with safety cushion between production and marketing. 3. A combination of the two systems, with total costs at minimum, through proper balance between the amount of fluctuations and stock levels.
SCHEDULING
Basic scheduling problems
Batch production scheduling, when products are manufactured consecutively
When the rate of production is higher than the rate of consumption, the plant resorts to batch production. To fully utilise the available time, plant undertakes production of several products in succession. The scheduling has to consider the plant to produce n products one at a time and the manufacturing cycle is concluded when all products have been produced. The cycle length is determined by the total time for all the products in the cycle. The quantities of each products produced must be sufficient to cover the requirements of the cycle time, to avoid overstocking or stock outs. The quantities are governed by the batch production principles.
SCHEDULING
Basic scheduling problems
Batch production scheduling, when products are manufactured consecutively
The issues to be analysed include: - How to go about optimising the whole schedule - Criterion for optimisation - Optimum schedule and optimum batch quantities for individual products - To balance the two objectives More complex situation arise when products are manufactured on a batch basis, some consecutively and some concurrently, with overlapping production time. Requires combination of techniques including linear programming/assignment models etc.
SCHEDULING
Basic scheduling problems
Batch production scheduling, when products are manufactured consecutively
The assignment problem: - To assign the tasks to the machines or to the operators in such a manner as to minimise the processing cost and time. - Distribution according to capacity: Effective utilisation of process capacity with the best mix. Assign the given tasks to the available machines and work out the cost of operating production facilities with alternatives, using linear programming model. - Effects of Overtime or subcontracting, though may provide extra capacity, it is to be evaluated wrt the extra costs
SCHEDULING
Two objectives, which may not be compatible:
- Batch size optimisation for individual products - Optimal solution for the whole production schedule The batch sizes for optimal schedule may differ from the respective batches required for individual product optimization, and in order to reconcile the two, a compromise production schedule is constructed. This requires production range which specifies the allowable deviations from the individual optimums and thereby provides a certain amount of flexibility in constructing the schedule. The fluctuations in consumption are taken care of through appropriate Safety stocks. The changes in average consumption and trends in consumption may affect the batch size and the schedule. This requires constant revaluation in the light of changing circumstances.
SCHEDULING
Critical Path Scheduling:
- Large & Complex projects, with interrelationship among these tasks, like design and manufacture of special purpose machine or development and introduction of a new product or construction of a building.
Techniques:
- The Critical Path Method (CPM) - Project Evaluation and review Technique (PERT)
SCHEDULING
Critical Path Method:
- Begins with determination of each job that makes up the project - Relationship of jobs with each other (preceding/succeeding or independent) - Time for each job Usually expressed in days/weeks Job Description Imm. Predecessor Time-days G Start 0 H Procure matl for part 1 G 4 I Procure matl for part 2 G 3 J Machine part 1 H 6 K 2 I 5 L Assemble 1 and 2 J&K 2 M Inspect & Test L 1 N Finish M 0
SCHEDULING
Critical Path Method: To draw network, we need to find S earliest start for the project ES earliest start for each job t - time required to complete the job EF - ES+t F - earliest finish for the project
G---H-----J----L----M----N G---I------K----L
SCHEDULING
Critical Path Method: To draw network, we need to find T target completion LF - latest finish without delay in T t - Time for the job LS LF-t Slack = LS-ES or LF-EF
SCHEDULING
Critical Path Method:
Job G H I J K L M N Possible start time ES 0 0 0 4 3 10 12 13 LS 0 0 2 4 5 10 12 13 Possible finish time EF 0 4 3 10 8 12 13 13 LF 0 4 5 10 10 12 13 13 Slack time 0 0 2 0 2 0 0 0
SCHEDULING
Critical Path Method:
Benefits : - Determines probable completion dates with alternate plans - Evaluation of progress - Corrective steps and effect on cost and completion - To evaluate ways to reduce completion ,if required through looking at activities on critical path, continuous review - To explore possible reduction in costs, utilising slacks
SCHEDULING
PERT A refined CPM
- Analyse description of project in terms of activities and events - Activity is performance of a Task and is like a job in CPM - An event represents the start or completion of a task - Time estimates for each activity are made on the basis of; - optimistic time , a - most likely time , m - pessimistic time , b and Average is taken as (a+4m+b)/6
SCHEDULING
PERT A refined CPM
Example Event 10 Start material procurement 20 Complete part 1 material procurement 30 Complete part 2 material procurement 40 Complete part 1 machining 50 Complete part 2 machining 60 Start assembly 70 Complete assembly 80 Complete inspection and testing
SCHEDULING
PERT A refined CPM
Event 10 20 30 40 50 60 70 80 TE 0 4.2 3.0 10.2 7.8 10.2 10.2 13.3 TL 0 4.2 5.4 10.2 10.2 10.2 10.2 13.3 Slack TL-TE 0 0 2.4 0 2.4 0 0 0 a=3, m=4,b=6
SCHEDULING
PERT and CPM, limitations: - Requires clear understanding of interrelationships of activities. - Estimation of time, with resource and other factors - Cost comparisons of alternatives - Skilled job and also costly
Thank you