Unit Com
Unit Com
G
G G G
With a given set of units running, how of the load much should be generated at each to cover the load and losses? This is the question of Economic dispatch. The solution is for the current state of the network and does not typically consider future time periods.
When should the generating units (G) controlled by the GENCO be run for most economic operation?
Concern must be given to environmental effects
How does one define economic operation? Profit maximizing? Cost minimizing? Depends on the market youre in.
Problem Setup
Last meeting we discussed the economic dispatch problem Now we will see how the unit commitment fits into the general picture Unit commitment is bound to the economic dispatch Use similar optimization methods
U may be only 0 or 1
0 = d/dx2(0.255x22 + 15 - x2l1)
same as above