Practical Case #B - C: Problem: Ventilation of Company Changing Details: Room of 64 M
Practical Case #B - C: Problem: Ventilation of Company Changing Details: Room of 64 M
B UILDING
RENOVATION .
C OMMERCIAL
Problem: Ventilation of company Changing Rooms in Seville. Details: Room of 64 m2 x 2.5m high and 15 m of ducting already installed with a diameter of 250 mm and two elbows. Requirements: 1600 m3/hour Pressure drop: 17 mm w.g. Solution: 1xTD-2000/315, 2 GRI-200 Inlet grilles and 1 PER -250 W. Observations: It was recommended to install a grille of at least 0.5 m2 to allow air to pass through the access the door at a speed of less than 1 m/s. 10 air changes per hour calculated.