Part Testing Summary (API 6A)

This document outlines testing procedures for valves and equipment. It discusses primary and secondary pressure holding tests where pressure is applied to each side of a gate or plug individually while the other side is open to atmosphere. Bidirectional valves undergo additional tests where pressure is applied under full differential pressure and held for periods of time. Unidirectional valves are also tested by applying pressure in the direction indicated on the body. Gas tests involve submerging equipment in water and applying and holding pressure for specified periods.

Uploaded by

kumaranmekala
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
859 views

Part Testing Summary (API 6A)

This document outlines testing procedures for valves and equipment. It discusses primary and secondary pressure holding tests where pressure is applied to each side of a gate or plug individually while the other side is open to atmosphere. Bidirectional valves undergo additional tests where pressure is applied under full differential pressure and held for periods of time. Unidirectional valves are also tested by applying pressure in the direction indicated on the body. Gas tests involve submerging equipment in water and applying and holding pressure for specified periods.

Uploaded by

kumaranmekala
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Parameter Traceability Serialization Full bore Valve X-mas Tree Single Equipment Unit Xmas Tree

Drift test

PSL 2 Not Required Not Required Not Required Required Tested after valve been assy;operated & pressure test Pass through main bore of Xmas tree PSL 1 Primary pressure Holding (3 min) (1.5*W.P) Reduction pressure to Zero Secondary pressure holding (3 min) (1.5*W.P) Pressure applied to each side of gate/plug & other side open to atmosphere Holding Period (3 min) Reduction pressure to zero between holding period Test min 2 times each side of gate/plug

Subclause Reference PSL 3 Required Required

PSL 3G Required Required

body

Primary pressure Holding (3 min) (1.5*W.P) Reduction pressure to Zero Secondary pressure holding (15 min) (1.5*W.P)

Bidirectional Valve Hydrostatic test seat

Pressure applied to each side of gate/plug & other side open to atmosphere Holding Period (3 min) Open valve under full differential pressure except fr check valve (Repeat 2 times) Holding Period (3 min

Pressure applied to each side of gate/plug & other side open to atmosphere Holding Period (3 min) Open valve under full differential pressure except fr check valve Holding Period (15 min) Open valve under full differential pressure Holding Period (15 min)

Pressure applied to direction indicated on the body except check valve test on down stream Holding Period (3 min) Unidirectional Valve Reduction pressure to zero between holding period Test min 2 times each side of gate/plug

Pressure applied to direction indicated on the body except check valve test on down stream Holding Period (3 min) Reduction pressure to zero between holding period Test min 2 times each side of gate/plug

Pressure applied to direction indicated on the body except check valve test on down stream Holding Period (3 min) Holding Period (15 min) Holding Period (15 min)

body

Gas test seat

Bidirectional Valve Unidirectional Valve

Test perform at ambient temp using nitrogen as test medium. Equipment completely submerged in the water Holding period (15 min) (W.P) Pressure applied to each side of gate/plug & other side open to atmosphere Holding Period (15 min) (W.P) Holding period (15 min) (300 psi)2

back seat

NOTES:-

1 Equipment with end or outlet connection have diff W.P use low W.P except fr X-over connector & Chokes 2 Split gate valve may have both seats tested simultaneously