0% found this document useful (0 votes)
364 views

Activity Check Request Sheet

This activity check request sheet is for construction works related to the indoor sports gymnasium being built at the University of Engineering & Technology in Taxila. It requests a check for original works from M/s NESPAK (Pvt) Limited, and was issued by M/s BUILDFAST (Pvt) Limited. The sheet collects information on the structure, location, quantity, level, distance, pouring date and time, and any remarks from the consultant to approve or reject the request.

Uploaded by

JAZPAK
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
364 views

Activity Check Request Sheet

This activity check request sheet is for construction works related to the indoor sports gymnasium being built at the University of Engineering & Technology in Taxila. It requests a check for original works from M/s NESPAK (Pvt) Limited, and was issued by M/s BUILDFAST (Pvt) Limited. The sheet collects information on the structure, location, quantity, level, distance, pouring date and time, and any remarks from the consultant to approve or reject the request.

Uploaded by

JAZPAK
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

ACTIVITY CHECK REQUEST SHEET

For all Civil, Plumbing, Electrical, Road or Other Works.

Project Title: CONSTRUCTION OF INDOOR SPORTS GYMNASIUM AT UNIVERSITY OF ENGINEERING & TECHNOLOGY, TAXILA. Issued To: M/s NESPAK (Pvt) Limited, Islamabad. Issued By: M/s BUILDFAST (Pvt) Limited, Islamabad. 1. CHECK REQUEST FOR: 2. This is: an Original Check Request: _________ ,

Request Sheet No:

3387 Date of Submission: Time of Submission:

Resubmit: ___________

3. STRUCTURE/DESCRIPTION: 4. LOCATION/GRID: 5. QUANTITY (APPROX.): 6. LEVEL: 7. DISTANCE (FOR ROAD WORKS): 8. DATE OF POURING (FOR CONCRETE): 9. TIME OF POURING (FOR CONCRETE): 10. REMARKS OF THE CONSULTANT:

11. Approved: 12. Rejected/Re-Submit:

SIGNATURE :( Contractor):______________________

SIGNATURE :( Consultant):______________________