0% found this document useful (0 votes)
199 views5 pages

Cost Break Down Weld Split Tee

The document is a cost breakdown form for a project involving welding and inspection of split tees for hot tapping. It provides a breakdown of costs for various items including engineering costs, construction costs for mobilization and fitting/welding split tees of various sizes, costs for non-destructive examination, equipment costs, and totals. It notes that the price excludes scaffolding work and is based on a Monday through Saturday work week with a holiday factor of 1.2 applied to construction costs. The total cost of the project is estimated to be 696,983.96 Baht.

Uploaded by

toylovechom
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
199 views5 pages

Cost Break Down Weld Split Tee

The document is a cost breakdown form for a project involving welding and inspection of split tees for hot tapping. It provides a breakdown of costs for various items including engineering costs, construction costs for mobilization and fitting/welding split tees of various sizes, costs for non-destructive examination, equipment costs, and totals. It notes that the price excludes scaffolding work and is based on a Monday through Saturday work week with a holiday factor of 1.2 applied to construction costs. The total cost of the project is estimated to be 696,983.96 Baht.

Uploaded by

toylovechom
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 5

COST BREAK DOWN FORM

PROJECT NO.
PROJECT NAME.:Welding & Inspection split tees for hot tapping
Prepared By Checked By

Item
A

Description

Approved By

25/07/2012

Unit P

Amount

Q'ty

Unit

WPS/PQR/WQT

Lot

35,000

35,000

Welding Record and Inspection Report

Lot

12,500

12,500

Lot

45,000

45,000

- 12" onto 24"

Sets

31,819

63,638

- 10" onto 20"

Sets

26,634

26,634

- 16" onto 18"

Sets

28,521

85,562

- 4" onto 10"

Sets

12,810

12,810

- 4" onto 12"

Sets

14,822

14,822

- 6" onto 20"

Sets

24,034

24,034

- 8" onto 12"

Sets

17,422

17,422

-RT 100% Buttweld(Fitting)

Lot

20,000

20,000

-PT Fillet /BW Split tee

Lot

8,500

8,500

75,000

75,000

Engineering Cost

Construction Cost
Mobilization
Fitup&Weld Split tees

NDE

Equipment/tool
-Weld generator/Haib/etc.

1
Lot
Sub Total for Labour Cost

Sub Total Cost


OPT

20%

88,184.48

Vat

7%

37,037.48

Total Cost ( Baht )


NOTE :

440,922
440,922.40

1.This price excluding scafloding work


2.This price base on working day time(mon-sat) for holiday factor 1.2 multiply Item B.cost

566,144.36

COST BREAK DOWN FORM


PROJECT NO.
PROJECT NAME.:Welding & Inspection split tees for hot tapping
Prepared By

Item
A

Description

Q'ty

Engineering Cost
WPS/PQR/WQT

Welding Record and Inspection Report

Construction Cost
Mobilization

Fitup&Weld Split tees


- 12" onto 24"

- 10" onto 20"

- 16" onto 18"

- 4" onto 10"

- 4" onto 12"

- 6" onto 20"

- 8" onto 12"

-RT 100% Buttweld(Fitting)

-PT Fillet /BW Split tee

NDE

Equipment/tool
-Weld generator/Haib/etc.

1
Sub Total for Labour Cost

Sub Total Cost


OPT

20%

Vat

7%

Total Cost ( Baht )


NOTE :

1.This price excluding scafloding work


2.This price base on working day time(mon-sat) for holiday factor 1.2 multiply Item B.cost

DOWN FORM

Checked By

Approved By

25/07/2012

Unit

Unit P

Amount
Size

db(bw)

db(fw)

Lot

35,000

35,000

12"*24"

24

48

Lot

12,500

12,500

10"*20'

20

40

16"*18"

36

36

4"*10"

20

4"*12"

24

Lot

45,000

45,000

Sets

39,619

79,238

6"*20"

12

40

Sets

33,134

33,134

8"*12"

16

24

Sets

41,521

124,562

124

232

Sets

15,410

15,410

Sets

17,422

17,422

Sets

27,934

27,934

Sets

22,622

22,622

film
Size

Qty

sht

12

Lot

20,000

20,000

10

Lot

25,000

25,000

16

85,000

542,822

Lot

Sub Total for Labour Cost

85,000

542,822.40
108,564.48
45,597.08
696,983.96

1.2 multiply Item B.cost

FitUp

Weld

bw(l)

Cdb(bw)

Cdb(fw)

0.864

200

150

1,000

12,864

450

300

1,800

26,755

0.762

200

150

1,000

10,762

450

300

1,800

22,372

0.686

200

150

1,000

13,286

450

300

1,800

28,235

0.432

200

150

1,000

5,032

450

300

1,800

10,378

0.508

200

150

1,000

5,708

450

300

1,800

11,714

0.762

200

150

1,000

9,162

450

300

1,800

18,772

0.508

200

150

1,000

7,308

450

300

1,800

15,314

4.522

tota'
long
3

15
4
4
4

Cbw(l)

Totalcost

Cdb(bw)

Cdb(fw)

Cbw(l)

Totalcost

Total/Joint

39,619
33,134
41,521
15,410
17,422
27,934
22,622

You might also like