Lift Classification Flow Chart
Lift Classification Flow Chart
TEST
LIFT CLASSIFICATION
REQUIRED ACTION
Does the gross load exceed 75% of the crane's total lifting capacity ? Does the gross load at any point during the lift exceed 80% of crane's capacity chart ? Does load replacement time exceed 10 days ? Will the loss of the load during installation cause a loss of production exceeding 10 days or a cost of $100,000. Will the loss of the load constitute a risk to the public or environment, i.e. chlorine or acid ? Does the lift require 2 or more cranes ? (Note: never exceed 75% of each crane's capacity in a multi-crane lift.) Will the load be swung over an unprotected plant, equipment or service ? Will the lift be performed in proximity of live electrical conductors ?
YES
Critical Lift
NO
YES
Standard Lift