01 - Demolisher (2005)
01 - Demolisher (2005)
NO 1
DESCRIPTION OF WORK Brick work in Cement, demolished brick stacked and debris cleared. Brick work in lime, demolished brick stacked and debris cleared. Cadjan roofing or walling dismantled timber stacked and debris cleared. Ceiling, existing removed materials stacked and debris cleared. Cement concrete demolished, and debris cleared away.
BSR No
(Item No/Page No)
RATE (2nd) 1,197.00 423.00 958.00 338.00 98.00 11.00 314.00 34.00 4,104.00 2052.00 221.00 8892.00 2964.00 319.00
1/1
2/1
3/1
4/2
5/2
Cement concrete, reinforced demolished in suspended floors reinforcement removed and debris cleared. Corrugated Sheets, Iron, Asbestoes or Aluminium Alloy removed from roof or walls and stacked. Door or Window, size up to 40 S.ft removed from existing walls and door or stacked. Doors for window, size over 40 S.ft removed - do - do -
6/2
7/3
Sqr M2
359.00 39.00
8/3
No
456.00
9/3
No
684.00
10 Door or window, sash only, up to 40 S.ft removed from existing walls and stacked. 11 Door or window, sash only, over 40 S.ft - do - do 12 Down pipes, 4" to 6" dia G.I old or decayed, removed from existing building and stacked. 13 Drains demolished and debris cleared
10/3
No
71.00
11/4
12/4 13/4
14 Fence uprooted, barbed wire rolled up and all materials stacked (length of fencing to
L.ft
22.00
01 - Demolisher Mannar
14/4
L.m Sqr m2
15/5
NO
DESCRIPTION OF WORK
BSR NO
(Item No/Page No)
UNIT
RATE (2nd)
16 Gate sash removed and stacked after demolishing cement concrete blocks or removing posts and separating pintols (demolishing brick work where necessary paid for separately). 17 Glass panes in doors, windows and fanlights removed and stacked. 18 Gutter, Eaves, removed and stacked from roofs of single story buildings. 19 Gutter, Eaves removed from roofs of two storeyed buildings and stracked. 20 Partitions removed and stacked at side, including making goodnes two walls and floors. 21 Lime plastering chipped and debris cleared away.
16/5
456.00 21.00 230.00 3.00 10.00 4.00 13.00 17.00 183.00 171.00 18.00 513.00 55.00 770.00 83.00
17/5
18/5
19/6
20/6
21/6 22 Rendering cement, chipped and debris cleared away from brick walls and floors. 23 Rendering cement, chipped and debris cleared away from cement concrete floors and walls. 24 Roofing removing tiles and timber stacking, serviceable materials and cleaning debris in single storey building. 25 Roof, removing tiles and timber stacking serviceable material and cleaning debris in two storeyed building. 26 Rubble masonry in cement, demolished rubble stacked and debris cleared away. 27 Tiles glazed demolished and debris cleared away.
22/7
23/7
24/7
658.00 71.00 898.00 97.00 1,496.00 529.00 912.00 98.00 239.00 26.00 359.00 39.00
25/8
26/8 27/8
28 Tiles calicut or half round, removed from roof of single storey buildings and stacked. 29 Tiles calicut of half round removed from roof of two storeyed buildings and stacked.
28/9
29/9
01 - Demolisher Mannar
3 30 Water proof treatment of bitumen taken off from flat roof and debris cleared away. 31 Ceiling asbestoes removing including timber frame work, stacking serviceable materials single storey building (and debris cleared away in single). 32 Ceiling asbestos removing including timber frame work, - do - do in two storeyed building. 30/9 Sqr m2 912.00 98.00
31/10
Sqr m2
1,197.00 128.00
32/10
Sqr m2
1,436.00 154.00
NO
DESCRIPTION OF WORK
BSR NO
(Item No/Page No)
UNIT
RATE (2nd)
33 Valance/ Barge boarding removed materials stacked and debris cleared away in single storey building.
33/10
L.ft L.m
3.00 10.00
34
- do 34/11
L.ft L.m
4.00 13.00
35/11
Sq.ft m2
673.00 72.00
01 - Demolisher Mannar
33.76 34.00
Cement concrete demolished, and debris cleared away. Per Sqrs (6" floor) 4 1/2 Day Day Labourers Labourer for Transporting Over heads Say per Cube Say Rs Per Sqrs Say Rs Per m2 Say per m2 :Cement concrete,reinforced,demolished in suspended floors,reinforcement removed and debris cleared. Per Sqrs. (4" floor) 6 1/2 Day Day Labourers Labourers for Transporting Over heads Per Cube Say per Cube Per Sqrs Say per Sqrs Per m2 Say per m2 Corrugated sheets, Iron, Asbestoes or Aluminium Alloy, removed from roof or walls and stacked. Per Sqrs. 2 3 Hour Blacksmith Hour Labourer Allow for scaffolding Over heads Per square Say per Sqrs Per m2 Say per m2 Door or window,size up to 40 S.ft removed from existing walls and stacked per door or window. Per No. 600 400 150.00 150.00 15.00 400 400 2,400.00 200.00 400 400 1,600.00 200.00
01-Demolisher Mannar
6 1/2Day Labourer Over heads Per No Say Rs Door window, size over 40 S.ft removed - do - do Per No. 1/2Day Labourer Over heads Per No Say Rs :Door or window, sash only, upto 40 S.ft removed from existing walls and stacked. Per Sash. Hour Carpenter Hour Labourer Over heads Per sash Say Rs Door or window, sash only, over 40 S.ft - do - do Per Sash. Hour Carpenter Hour Labourer Over heads Per sash Say Rs Down pipes, 4" to 6" dia. G.I old or decayed, removed from existing building and stacked. Per 12.0 L.ft.Length Hour Labourer Over heads Per L.ft Say per L.ft. Per L.m Say per L.m. Drains demolished and debris cleared. Per 10.0 L.ft Brick in cement demolished (as in Item 1 less scaffolding) Over heads Per L.ft Say per L.ft. Per L.m Say per L.m. 01-Demolisher Mannar
400
400.00
400
600.00
10
1/2 1/2
600 400
37.50 25.00
11
3/4 3/4
600 400
56.25 37.50
12
400
50.00
13
0.13
Cube
1,000.00
1,000.00
14
7 Fence uprooted, Barbed wire rolled up and all materials stacked (length of fencing to measured).
3 2
15
Per 50 L.ft. (6 posts) Hour Labourers (Digging up) Day Labourers (Dismantling & rolling) Over heads Per L.ft Say per L.ft. Per L.m Say per L.m. Floors brick paved, demolished and debris cleared away. Per Sqrs 3" thick demolition as in item 2 (less scaffolding). Add 50% for extra difficulty. Overheads Per square 3" thick Say per Sqrs Per m2 Say per m2 Gate sash removed and stacked after demolishing cement concrete blocks or removing posts and separating pintles (demolishing brick work where necessary paid for seperately).
400 400
150.00 800.00
1/4
Cube
800
200.00 100.00
16
1/2Days Labourers Overheads Per No Say Rs Glass panes in doors and windows and fanlight removed and stacked. Per 6 S.ft./ Per 8 Panes Hour Carpenter Over heads Per S.ft Say per S.ft. Per M2 Say per M2. Gutter, eaves, removed and stackedfrom roof of single storeyed building Per 40.0 L.ft. 1Hour Labourers Allow for scaffolding Over heads 01-Demolisher Mannar
400
400.00
17
1 1/2
600
112.50
18
400
100.00 5.00
105.00 14.70
19
8 Per L.ft Say per L.ft. Per L.m Say per L.m. Gutter, eaves, removed from roofs of 2 storeyed building and stacked. Per 40.0 L.ft. 1Hour Labourers Add 50% Allow for scaffolding 5% Over heads Per L.ft Say per L.ft. Per L.m Say per L.m. Partitions removed and stacked at site, including making good to walls and floors. Per 105.0 Sq.ft.(15' x 7') 1 2 1/4 Day Day Day Carpenter Labourers Mason Allow for cement, sand etc. Over heads Per S.ft Say per S.ft. Per M2 Say per M2 Lime plastering chipped and debris cleared away. Per Sqrs. 3 Hour Labourer Overheads Per square Say per Sqrs Per m2 Say per m2 400 150.00 600 400 600 600.00 800.00 150.00 50.00
400
20
21
22
Rendering, cement, chipped and debris cleared away from brick walls and floors. Per Sqrs. 9 Hour Labourer 01-Demolisher Mannar 400 450.00 450.00
Over heads Per square Say per Sqrs Per m2 Say per m2 23
Rendering, cement, chipped and debris cleared away from cement concrete floors and walls. Per Sqrs. 9 Hour Labourer Add 50% Over heads Per square Say per sqrs per m2 Say per m2 400 450.00 225.00
24
Roof, removing tiles and timber, stacking serviceable material and cleaning debris in single storeyed building. Per Sqrs. 1/4 4 Day Carpenter 1/4Day Labourers Allow for scaffolding 5% Over heads Per square Say per square Per m2 Say per m2 Roof, removing tiles and timber - do - do - in 2 storeyed buildings. Per Sqrs. 1/4 4 2 Day Carpenter 1/4Day Labourer 1/4Day Labourer Allow for scaffolding 5% Over heads 14% Per square Say per square Per m2 Say per m2 Rubble masonary in cement, demolished, rubble stacked and debris cleared. 600 400 400 150.00 400.00 200.00 37.50 600 400 150.00 400.00 27.50
25
26
01-Demolisher Mannar
Per Cube. 2 1/2 Day Labourer Add 25% Allow for scaffolding 5% Overheads 14% Per cube Say per cube Per m3 Say per m3
27
Tiles, glazed demolished and debris cleared. Per Sqrs. 2 Day Labourer Overheads 14% Per Square Say per square Per m2 Say per m2 400 800.00 800.00 112.00 912.00 912.00 98.04 98.00
28
Tiles calicut or half round, removed from roof of single storeyed buildings and stacked at site. Per Sqrs. 4 Hour Labourer Allow for scaffolding 5% Overheads 14% Per square Say per square Per m2 Say per m2 Tiles calicut or half round removed from roof of 2 storeyed buildings and stacked. Per Sqrs. Hour Labourer Hour 2 Labourer Allow for scaffolding 5% Overheads 14% Per square Say per square Per m2 Say per m2 400 200.00 10.00
29
4 1
400 400
01-Demolisher Mannar
30
11 Waterproof Treatment of hot bitumen taken off from flat roof and debris cleared away. Per Sqrs. 2 Day Labourer Overheads 14% Per square Say per square Per m2 Say per m2 Ceiling Asbestoes, removing including timber frame work, stacking serviceable materials storeyed building- (and debris cleared away in single). Per Sqrs. Carpenter Labourer Allow for scaffolding 5% Overheads 14% Per square Say Rs Per m2 Say per m2 Ceiling Asbestoes removing including timber frame work - do - do in 2 storeyed building. Per Sqrs. 1 1 1/4 Day Day Day Carpenter Labourer Labourer (02) Allow for scaffolding 5% Overheads 14% Per square Say per square Per m2 Say per m2 Valance/Barge boarding removed, materials stacked and debris cleared away in single storeyed building. Per 40.0 L.ft 2 1Hour Labourer Allow for scaffolding 5% Overheads 14% Per L.ft 01-Demolisher Mannar 400 100.00 5.00 600 400 400 600.00 400.00 200.00 60.00 400 800.00 800.00 112.00 912.00 912.00 98.04 98.00
31
1 1
Day Day
600 400
32
33
34
12 Say per L.ft. Per L.m Say per L.m. Valance/Barge boarding removed - do - do in 2 storeyed building. Per 40.0 L.ft. 2 11/2hr Labourer Allow for scaffolding 5% Overheads 14% Per L.ft Say per L.ft. Per L.m. Say per L.m. Cement plastering, soffit chipped, and debris cleared away. Per Sqrs. 1 1/8 Day Labourer Add 25% for extra difficulty Allow for scaffolding 5% Overheads 14% Per square Say per square Per m2 Say per m2 400 450.00 112.50 28.13 400 150.00 7.50
35
01-Demolisher Mannar
Page 12
Description
01. Demolisher