Portal Frame 2
Portal Frame 2
CV61
Dr. G.S.Suresh
Civil Engineering Department The National Institute of Engineering Mysore-570 008
Mob: 9342188467
Email: [email protected]
Portal frames
INTRODUCTION A portal frame consists of vertical member called Columns and top member which may be horizontal, curved or pitched. Rigidly connected They are used in the construction of large sheds, bridges and viaducts. The base of portal frame may be hinged or fixed.
6
INTRODUCTION
For Shed
10
For Bridges
11
For Viaduct
12
INTRODUCTION The portal frames have high stability against lateral forces A portal frame is a statically indeterminate structure. In the case of buildings, the portal frames are generally spaced at intervals of 3 to 4m Reinforced concrete slab cast monolithically between the frames
13
INTRODUCTION
Frames
used for ware house sheds and workshop structures are provided with sloping of purlins and asbestos sheet roofing between the portal frames. The base of the columns of the portal frames are either fixed or hinged. Analysis of frames can be done by any standard methods Columns are designed for axial force and bending moment, whereas beam is designed for bending moment and shear force
14
15
INTRODUCTION Step1: Design of slabs Step2: Preliminary design of beams and columns Step3: Analysis Step4: Design of beams Step5: Design of Columns Step6: Design of footings
16
17
Problem 1
The roof of a 8m wide hall is supported on a portal frame spaced at 4m intervals. The height of the portal frame is 4m. The continuous slab is 120 mm thick. Live load on roof = 1.5 kN/m2, SBC of soil = 150 kN/m2. The columns are connected with a plinth beam and the base of the column may be assumed as fixed. Design the slab, column, beam members and suitable footing for the columns of the portal frame. Adopt M20 grade concrete and Fe 415 steel. Also prepare the detailed structural drawing.
18
Data given: Spacing of frames = 4m Span of portal frame = 10m Height of columns = 4m Live load on roof = 1.5 kN/m2 Thickness of slab = 120mm Concrete: M20 grade Steel: Fe 415
19
20
21
Step1:Design of slab Self weight of slab = 0.12 x 24 = 2.88 kN/m2 Weight of roof finish = 0.50 kN/m2 (assumed) Ceiling finish = 0.25 kN/m2 (assumed) Total dead load wd = 3.63 kN/m2 Live load wL = 1.50 kN/m2 (Given in the
data)
2 2 w L w L Maximum service load moment at interior support d L
8 . 5 kN m/m 10 9
From table 2 of SP16 pt=0.384; Ast=(0.384 x 1000 x 100)/100= 384 mm2 Spacing of 10 mm dia bars = (78.54 x 1000)/384= 204.5 mm c/c Provide #10 @ 200 c/c
23
Area of distribution steel Adist=0.12 x 1000 x 120 / 100 = 144 mm2 Spacing of 8 mm dia bars = (50.26 x 1000)/144= 349 mm c/c Provide #8 @ 340 c/c. Main and dist. reinforcement in the slab is shown in Fig.6.3
24
25
Step2: Preliminary design of beams and columns Beam: Effective span = 8m Effective depth based on deflection criteria = 8000/12 = 666.67mm Assume over all depth as 700 mm with effective depth = 650mm, breadth b = 400mm Column: Let column section be equal to 400 mm x 600 mm.
26
Step3: Analysis
Load on frame i) Load from slab = (3.63+1.5) x 4 =20.52 kN/m ii) Self weight of rib of beam = 0.4x0.58x24 = 5.56 kN/m Total 27.00 kN/m The portal frame subjected to the udl considered for analysis is shown in Fig. 6.4
27
28
Step3:Analysis(Contd)
The moments in the portal frame fixed at the base and loaded as shown in Fig. 6.4 are analysed by moment distribution IAB = 400 x 6003/12 = 72 x 108 mm4, IBC= 400 x 7003/12 = 114.33 x 108 mm4 Stiffness Factor: KBA= IAB / LAB = 18 x 105 KBC= IBC / LBC = 14.3 x 105
29
Step3:Analysis(Contd)
Distribution Factors:
Fixed End Moments: MFAB= MFBA= MFCD= MFDC 0 wL 27 x 8 MFBC= - 12 12 =-144 kN-m 27 x 8 and MFCB= wL =144 kN-m 12 12
2 2
2 2
5 K 18 10 BA D 5 0 . 55 BA 5 K 18 10 14 . 3 10 BA 5 K 14 . 3 10 BC D 5 0 . 45 BC 5 K 18 10 14 . 3 10 BC
30
31
32
Step3:Analysis(Contd) Design moments: Service load end moments: MB=102 kN-m, MA=51 kN-m Design end moments MuB=1.5 x 102 = 153 kN-m, MuA=1.5 x 51=76.5 kN-m Service load mid span moment in beam = 27x82/8 102 =114 kN-m Design mid span moment Mu+ =1.5 x 114 =171 kN-m Maximum Working shear force (at B or C) in beam = 0.5 x 27 x 8 = 108kN Design shear force Vu = 1.5 x 108 = 162 kN 33
Step4:Design of beams:
The beam of an intermediate portal frame is designed. The mid span section of this beam is designed as a T-beam and the beam section at the ends are designed as rectangular section.
34
Step4:Design of T-beam:
bf/bw=5 and Df /d =0.2 Referring to table 58 of SP16, the moment resistance factor is given by KT=0.459, Mulim=KT bwd2 fck = 0.459 x 400 x 6002 x 20/1x106 = 1321.92 kN-m > Mu Safe The reinforcement is computed using table 2 of SP16
35
Step4:Design of T- beam: Mu/bd2 = 171 x 106/(400x6002)1.2 for this pt=0.359 Ast=0.359 x 400x600/100 = 861.6 mm2 No of 20 mm dia bar = 861.6/(x202/4) =2.74 Hence 3 Nos. of #20 at bottom in the mid span
36
37
38
39
0 . 87 f A d 0 . 87 415 2 50 600 y sv 36 3 V 59 10 us
Two legged #8 stirrups are provided at 300 mm c/c (equal to maximum spacing)
41
Dr. G.S.Suresh
Civil Engineering Department The National Institute of Engineering Mysore-570 008
Mob: 9342188467
Email: [email protected]
42