0% found this document useful (0 votes)
237 views1 page

Check List Instrument - New

This document provides a checklist for inspecting ladder and tray support mechanical completion for the Wortel Field Development Project by Santos (Sampang) Pty. Ltd. The 12-item checklist verifies that the supports have the correct specifications, dimensions, fabrication, installation, location, welding, and finishing according to design drawings and specifications.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
237 views1 page

Check List Instrument - New

This document provides a checklist for inspecting ladder and tray support mechanical completion for the Wortel Field Development Project by Santos (Sampang) Pty. Ltd. The 12-item checklist verifies that the supports have the correct specifications, dimensions, fabrication, installation, location, welding, and finishing according to design drawings and specifications.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

INSTRUMENT MECHANICAL COMPLETION CHECK SHEETS

SANTOS (SAMPANG ) PTY LTD

LADDER AND TRAY SUPPORT

Project Name Customer Drawing Reff. / Rev P&ID No. / Rev Location / Area

: WORTEL FIELD DEVELOPMENT PROJECT : SANTOS (Sampang) Pty. Ltd. : : : System / Sub No. System Desc. Sub System Desc. : : : Tag No. I01MC

No.

Inspection Check List

1 2 3 4 5 6 7 8 9 10 11 12

Check support support material have correct specifiction and size Check support design accordance with design drawing Check support have correct dimension accordance to design drawing Check that support have completed fabrication work Check that instrument support location refer to lay out Check support installation are level, correct elevation and adequate for ladder and tray installation Check welding visualy inspected where apllicable Check that support have completed finishing work Check that Support are tight installed

Notes :

Description Company

Performed by

Witnessed / Approved by

Witnessed / Approved by

Signature

Print Name Date