Research Project Gantt Chart

The Gantt chart outlines a research proposal timeline from June 2013 to January 2014. It involves 17 activities including submitting and revising the proposal, presenting it, gathering and analyzing data, writing conclusions, defending the research, and disseminating the results. Each activity is assigned a start date, duration, and end date to map out the 7 month process.
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
706 views

Research Project Gantt Chart

The Gantt chart outlines a research proposal timeline from June 2013 to January 2014. It involves 17 activities including submitting and revising the proposal, presenting it, gathering and analyzing data, writing conclusions, defending the research, and disseminating the results. Each activity is assigned a start date, duration, and end date to map out the 7 month process.
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

RESEARCH PROPOSAL GANTT CHART (June 2013- January 2014) ACTIVITIES 1.Submission of Research Proposal to the Adviser 2.

Enrich Proposal with the Adviser 3.Research Proposal to the Dean 4.Research Proposal Presentation 5.Revision and Finalization of Research Proposal
6.Validation/Pilot Testing of Data Gathering Instruments

7.Getting Permission for the Distribution of Data Gathering Instruments 8.Gathering of Data from the Respondents 9.Collating and Tabulating the Obtained Data 10.Making Interpretation and Analysis to the Data 11.Making of Summary, Conclusion and Recommendation 12.Finalizing Chapters 4 and 5 13.Finalization of All Parts 14.Submission of Hard Copy to the Panelists for the Oral Defense 15.Pre-Oral Defense and Final Defense 16.Research Finalization 17.Research Dissemination and Utilization

Start Date 11-Jun 11-Jun 9-Jul 16-Jul 23-Jul 6-Aug 20-Aug 27-Aug 22-Sep 29-Oct 19-Nov 3-Dec 10-Dec 17-Dec 24-Dec 14-Jan 21-Jan

Duration (days) 7 28 7 7 14 14 7 56 7 21 14 7 7 7 21 7 7

End Date 10-Jun 8-Jul 15-Jul 22-Jul 5-Aug 19-Aug 26-Aug 22-Oct 28-Oct 18-Nov 2-Dec 9-Dec 16-Dec 23-Dec 13-Jan 20-Jan 27-Jan

Jun

July

Aug

Sep

Oct

Nov

Dec

Jan