Ibs Complete
Ibs Complete
In the United States, the use of precast building components in the construction
industry began in the construction of prefabricated steel house by General House
in 1930. However the early efforts of rationalizing and implementation faded
quickly due to price in competitiveness, high capital and inconsistent local codes.
The use of precast building components increased sharply after the Second
World War due to the need to resolve critical shortage of houses.
The idea of industrialised building system (IBS) has received much attention in
the devastated countries after the Second World War. Though, Malaysia did not
suffer the impact of the war, the need to supply its population with affordable and
quality houses has prompted the government to promote the use of IBS as an
alternative to conventional building system.
Esa and Nuruddin (1998) asserted that IBS is a continuum beginning from
utilising craftsmen for every aspect of construction to a system that make use of
manufacturing production in order to minimise resource wastage and enhance
value for end users.
Perhaps the most comprehensive definition of IBS was clarified by Junid (1986).
He mentioned that IBS in the construction industry includes the industrialised
process by which components of a building are conceived, planned, fabricated,
transported and erected on site. The system includes a balanced combination
between the software and hardware components.
Meanwhile, the hardware elements are categorised into three major groups.
These include frame or post and beam system, panel system, and box system.
The framed structures are defined as those structures that carry the loads
through their beams and girders to columns and to the ground whilst in panel
system load are distributed through large floor and wall panels. The box systems
include those systems that employ three-dimensional modules (or boxes) for
fabrication of habitable units are capable of withstand load from various
directions due to their internal stability.
According to Badir- Razali, generally, there are four types of building systems
currently available in Malaysia’s building system classification (Badir et al. 1998),
namely conventional, cast in-situ, prefabricated and composite building systems.
Each building system is represented by its respective construction method which
is further characterised by its construction technology, functional and geometrical
configuration.
Figure 1.6 Lightweight concrete blocks are used for wall construction
The pre-cast concrete components are among the most common prefabricated
elements that are available both locally and abroad. The pre-cast concrete
elements are concrete products that are manufactured and cured in a plant
environment and then transported to a job site for installation. The elements are
columns, beams, slabs, walls, 3-D elements (balconies, staircase, toilets, and lift
chambers), permanent concrete formwork and etc.
The steel formwork is prefabricated in the factory and then installed on site.
However the steel reinforcement and services conduit are installed on site before
the steel formwork are installed. The installation of this formwork is easy by using
simple bracing system. Then concrete is poured into the formwork and after
seven days, the formwork can be removed and there is some system whereby
the formwork served as a part of the structure itself after concreting. The steel
formwork systems are used in tunnel forms, beams, column moulding forms and
permanent steel formworks.
The elements of steel framing system are rolled into the specific sizes and then
the elements are fabricated that involves cutting, drilling, shot blasting, welding
and painting. Fabricated elements are sent to the construction site to be then
erected whereby welding and the tightening of bolts at joints are conducted. The
elements include steel beams and columns, portal frames and roof trusses.
The elements of block work system include interlocking concrete masonry units
(CMU) and lightweight concrete blocks.
The elements are fabricated and cured in the factory. The elements are normally
used as bricks in structures and interlocking concrete block pavement.
The modular co-ordination for building component apply the basic length
unit or module of M=100cm. This allows the designer to apply this size or
its multiple in the production of building components.
1.3.6 Specialisation
1.3.8 Integration
1.3.10 Transportation
IBS in Malaysia has begun in early 1960’s when Ministry of Housing and Local
Government of Malaysia visited several European countries and evaluate their
housing development program (Thanoon et. al., 2003). After their successful visit
in 1964, the government had started first project on IBS aims to speed up the
delivery time and built affordable and quality houses. About 22.7 acres of land
along Jalan Pekeliling, Kuala Lumpur was dedicated to the project comprising
seven blocks of 17 storey flat there are 3000 units of low-cost flat and 40 shops
lot. This project was awarded to Gammon/ Larsen Nielsen using Danish System
of large panel of pre-fabricated system (CIDB, 2003b).
In 1965, the second housing project initiated by the government of Malaysia, the
project comprising a 6 block of 17 storey flat and 3 blocks of 18 storey flat at
Jalan Rifle Range, Penang. The project was awarded to Hochtief/Chee Seng
using French Estoit System (Din, 1984). Among the earliest housing
development project using IBS was Taman Tun Sardon, Penang. IBS pre-cast
component and system in the project was designed by British Research
Establishment for low cost housing in tropical countries. Nonetheless, the
building design was very basic and not considering the aspect of serviceability
such as the need of wet toilet and bathroom (Rahman and Omar, 2006).
Between 1981 and 1993, Perbadanan Kemajuan Negeri Selangor (PKNS) a
state government development agency acquired pre-cast concrete technology
from Praton Haus International based on Germany to build low cost house and
high cost bungalow in Selangor (CIDB, 2003b). The usage of steel structure as
part of IBS, first gained attention with the construction of 36-storeys Dayabumi
complex that was completed in 1984 by Takenaka Corporation of Japan (CIDB,
2003b).
From the survey conducted by CIDB of Malaysia in 2003, the usage level of IBS
in local construction industry stands at 15% (CIDB, 2003b). The total registered
IBS contractors in Malaysia stand for 1,993 in year 2007 (Table 3 and 4) and
registered IBS manufacture in Malaysia until 2007 is 138 producing 347 IBS
products available in the market shown in Table 5.
Since 1980’s there are intensive marketing strategies launched by the Malaysian
Government t o introduce modular coordination, its acceptance has received
poor responses for the building industry. As a result even partial introduction on
IBS such as lintels and staircase has not been possible (Trikha, 1999).
Previously in the 7th Malaysia Plan, the country intended to construct about
800,000 units of houses for its population using the IBS construction, Indeed
585,00 units planned for the low and low medium cost houses. However the
achievements are disappointing with only 20% completed houses reported due to
use of conventional construction method. Although the government introduce
numerous incentives and promotions to encourage housing developer’s t invest
in such housing category (Ismail, 2001).
Under the 7th Malaysian Plan, the enforcement of modular Coordination through
the construction Industry Standard 1 & 2 only applies to the low cost housing
projects initiated by the ministry of Housing and Local Government Malaysia
(CIDB 2001). The enforcement by the local authorities did not apply to all the
parties involve in the construction contribute to the failure or the implementation
in Malaysia. Furthermore the incentives that promised to be given to developers
by the government does not clearly stated in the law of Malaysia.
This is non conformance leads to the use conventional method which is less risky
to the developers.
In the 1998, the ministry of housing and local government and CIDB has come
up with the modular design guide which contain the modular coordination
concepts, the design rules, drawings and preferred dimensions for architectural
finishes material such as bricks, glass, gypsum board and etc. the important
aspects of prefabricated concrete in terms of modular dimensions, strength,
stability and the fire protection specifications are not indicated. The uniform
building by law (UBBL) has introduced several clauses to encourage the use of
IBS include the sub clause of 42(1):
a) The second line mentioned that ’11 meter square gross area’ is
replace by the ’10.8 meter square net area’ this is suitable for the area
room that has the dimension of 3000x3600mm and using the modular
dimension.
b) The forth line, ‘9.3 square gross area’ is replace by the ‘9.0 meter
square net area.’
c) The fifth line, ‘6.5 meter square gross area’ is replace by’6.3 meter
square net area
In the conventional construction the local authority only given the authority to
inspect the work after the completion of the project which is not practical. The
government should look into allowing the local authority to inspect the work in the
manufacturing process up the construction stage and lastly to the project
completion to ensure the quality is not compromised.
In the year 2001, the government set the Malaysia standard 1064 in order to
standardize the IBS components in terms of dimensions. However the MS 1064
still have a lot of loop holes that still can be improve.
The government is the major key player in the construction industry has spent
billions of ringgit over the pat several Malaysia Plans to develop the country.
However the plans are the characterized by short falls, delays and lack of
coordination between all parties including the agencies at federal and state levels
and other major players in the constructions industry. The government has not
taken necessary actions for the globalization and the industrialization of the
construction industry. The selection of the IBS has been hindered by lack of
assessment criteria set by the approving authorities.
An IBS system can only be practiced by the practitioner if its major advantages
are valuable compare to the conventional system. However up to date, there is
inadequate collaborative scientific research undertaken to substantiate the
benefit of IBS system. Therefore it can be clearly seen that the implementation of
IBS is hindered by lack of scientific information. The academic curriculum in the
university seldom in corporate courses that technology, organization and the
construction and the design of IBS. Lack of the research and development to use
the local materials causes the dependence of foreign technology can be
expensive and quality of products may be compromised
All parties involve in the construction industry should collaborate and to work
together in order to achieve the full utilization of IBS.
The government play very important role in imposed new regulation, standard
and training in terms of knowledge, experience and construction method.
Moreover the standardization of dimensions of material needs to provide a
feedback loop from the constructor to enable the implementation to be improving
from time to time.
3.1 Introduction
CIDB has published IBS Roadmap 2003- 2010 which entailed the needs and
requirement of Malaysian construction industry. This roadmap was endorsed by
Cabinet on 29th October 2003. The roadmap is a comprehensive document that
divides the IBS programmed into five main focus areas that reflect the inputs
needed to drive the programmed. They are Manpower, Materials, Management,
Monetary, and Marketing (CIDB, 2003a).
The inputs are then divided into elements and the activities to be implemented for
each element are then identified and included into the time span of the roadmap
in order to achieve the mission within the stipulated time-frame. The content of
this roadmap is focused towards achieving the industrialization of the
construction sector and the longer term objective of Open Building concept. It
has been five years since the launching of the roadmap and more than half-way
through the mission of industrializing construction (Hussein, 2007).
It is now pertinent to examine the progress and how close to the completion of
the mission to date. More importantly, it is imperative to evaluate whether the
implementation of the roadmap has met the market response to the IBS
programmed so far. Most policy issues have been resolved and implemented,
while all relevant documents required to support the programmed have been
developed. Notwithstanding these achievements a number of implementation
snags were identified as being potential hurdles to the full implementation of the
roadmap.
These include the following which have been identified by IBS Steering
Committee 2003- 2005 (Hussein, 2007):
`Realizing the implementation of IBS is still to make headway, CIDB through its
research arm, Construction Research Institute of Malaysia (CREAM) has taken
the initiative from the problem identified earlier and has conducted three
workshops session with the industry between 2006 and 2007.
After a lengthy deliberation with the stakeholders, it was concluded that the
factors contributing to the delays of IBS implementation are as follows:-
There have been quite a number of cases where the use of IBS had lead
to such drawbacks. For example, in the case of Pekeliling Flats in Kuala
Lumpur and Taman Tun Sardon, Gelugor, Penang. These two early pre-
fabricated flats were constructed in mass to produce low cost
accommodation for lower income groups. In the case of Taman Tun
Sardon, the IBS precast system was designed by British Research
Establishment, UK for low cost housing in tropical countries.
However, the design was very basic and not considering the aspect of
serviceability such as the need for wet toilets and bathrooms. Lacking in
this design consideration leads to problems of leakage that becomes the
common issue with precast buildings. In addition, in many cases the low
cost housings are not maintained properly, thus contributing further to the
poor image of IBS buildings.
For example, the steel mould used to form beams and columns must have
high degree of precision to produce accurate and consistent dimensions of
width, breadth and length and other related dimensions. The mould should
be of high quality with enough durability and strength and not easily
becomes dented or buckled during compaction of the concrete. In the
case of mechanical connections, the built in connection accessories to be
cast in the concrete component, must be located precisely prior to
concreting. Similarly any sleeves or opening in the component must be
done accurately.
However, IBS has demonstrated that the savings in the construction time
is able to compensate the higher construction cost incurred.
3.2.6 Awareness
In order for IBS system to be understood and used widely, the challenge is
to create mechanism of awareness. Many contractors and even engineers
are not well aware of the IBS system and not involved with the use of any
IBS system in their construction methods. Therefore, in order to create
awareness among practicing engineers and contractors, campaign to
reassure that IBS systems are able to provide fast, economical and high
quality products should be carried out.
The awareness campaigns may include seminars and short courses. For
example, CIDB in collaboration with universities, manufacturers and
professional bodies have carried out extensive seminars and roadshow to
give exposure to contractors and engineers about the IBS system. Also,
hands-on trainings in specialised works such as operating cranes and
welding works are also conducted to provide specilised and trained
workers in the IBS industry.
3.2.7 Knowledge
Specialized and additional engineering knowledge will be required to
design, manufacture and construct a good IBS system. All parties involved
from designers to erectors must have enough knowledge about the pre-
fabricated component based construction. In terms of design, the
engineers must have competent knowledge in analysis and design. In the
construction field, the contractors and site engineers must have enough
knowledge on the safe and accurate methods of erecting and assembling
loose components into a global structure.
Rahman & Omar (2006) observed that the term IBS is often misinterpreted
with negative image due to its past failures and unattractive architecture.
These buildings are normally associated with pre-fabricated, mass
construction method, low quality buildings, leakages, abandoned projects,
unpleasant architectural appearances and other drawbacks. Due to the
poor architectural design, the old pre-fabricated buildings have given the
public, bad impression about pre-cast concrete. Clients are often in doubt
of using IBS because of fear of customer rejection. Even construction
professionals are in doubt in IBS technology and relate IBS with a
potential post-construction problem. In addition, it is always not popular
among the designers as they found pre-fabrication has limiting their
creativity in design process (Hamid et al. 2008).
It is observed that lack of IBS branding and promotion taking place in the
market as the end user are neither misinterpret nor unaware of this
construction method. As a result, IBS is not creating enough pull factors to
encourage developers to adopt IBS. In comparison, IBS development in
Scandinavian and Japan provide higher customer focus and adopt mass-
customization of to enrich customer option. In UK, IBS is well associate
with sustainability and green construction.
In such arrangement the risk involve with any construction quality and
tolerance are also clearly identify and the party responsible for taking
corrective action is agreed from the outset of a project. Extensive
integration requires good IT tools to ensure supply chain continuity and
synchronization. Integration also includes developing supplier partnership
and establishes clear information flow using IT (Oostra & Jonson, 2007).
However, the current state of construction industry is being considered as
fragmented where the whole supply chains get their own strategy and
agenda. To worsen the situation, IT adoption in Malaysia is still low and
contribute to loose supply chain coordination and integration between
design and manufacture which is vital to IBS implementation.
Policy Makers- It is also observed by Chung & Kadir (2007) recently that
of local authorities in Malaysia are unlikely to change local building
regulation to suit IBS as the amendment will consume a lot of time and
cost.
site to cast, I'm going to the factory to do the casting and then putting them
together at the job site. So how can you do pre-cast without the wet-trade
workers. He stressed that there's still a lack of skilled local workers
because of the mismatch between the training the CIDB provides and
industry needs (NST 30/8/2008)
The overall project should be planned in such way that as soon as the
components are manufactured, it is possible to transport it to the
construction site and assemble it. Any delays either on manufacturing floor
or construction site has severe impact on staging requirement and
production planning where components from several construction projects
are scheduled for production at the same time.
Result - There are cases, where building projects are awarded and
constructed using IBS system but were carried out with many difficulties.
The most common problems encountered are improper assembly of the
components that normally involved the beam-to-column and column-to-
base connections due to impropoer planning and coordination at design
stage (Rahman & Omar, 2006)
"The potential for IBS sector in Malaysia is enormous to say the least. The
conservative estimate of the industry is approximately to RM2 billion,
making the future of the industry secure" (IBS Modular @
http://ibsmodular.blogspot.com/)
One of the biggest drawbacks for IBS adoption is the tendency to post
construction failure. It is much related to improper installation by untrained
constriction workforce and relatively wet climate in Malaysia.
For example, Lumut Naval Base project which consists of 29 blocks of 11-
storey apartments which was constructed in 1976 by Hazama Gumi and
supervised by FH Kocks GmBH who is the consulting engineers at that
time. The 11-storey apartments are built using pre-cast concrete walling
system. The apartments are still facing problems until today with regards
to defects caused by water penetrations and leakages largely due to the
construction joints and panel integration between the wall system and the
floor system (Anon, 2008). There's also an issue of renovation works
carried out which is constraint by the pre-cast system design and also the
M & E system. It will make IBS system not popular choice for developer
and customer because the majority of house owner in Malaysia would like
to renovate their dwelling at some point of their tenancy.
The paper has agreed and accepted that IBS is ideal conceptualization
and simplifying construction work. However, the reality in the projects is
far from practical idealism in Malaysia. The transformation is not green a
good respond due to the unlikely construction readiness (Hamid et al.
2008). Superior construction technology requires highly skilled workers to
replace foreign workers but contractors left with no other choice.
4.1Introduction
4.2.1 K-Management
As the era of the K-economy enters into it’s stride, it is obvious that Global
players competing to provide unique services, processes, materials and systems
tends to impart better quality, higher speed and competitive costs. However,
there is deep concern that the construction industry as a whole is
underachieving. It has for many years maintained the time-tested but labour
intensive traditional approach in construction and investing too little in research
and development (R&D) and training even in this knowledge era. (IBS
Digest,2006)
Technological advances shall play a major role in changing the competitive work
environment in the construction industry and in providing companies with
capabilities to successfully produce and field new products, processes and
systems. The construction industry must indulge itself in innovations and
supportive of new ways of doing things. (IBS Digest,2006)
Knowledge was the driving force behind the Industrial Age. It was somehow
subsided and nearly forgotten until the next wave arrived which is the Digital Age.
This new age has resurfaced knowledge again as one of the key dimension to
propel global growth. Hence, Knowledge Management (KM) is now an important
discipline and an essential source that our economy cannot afford to do without,
if we were to have competitive advantage and remained relevant. (IBS
Digest,2006)
We have also seen over the last ten years, highly significant event took placed
on the advancement and explosion of information and communication technology
(ICT) driven by the liberalization of global economies. This has lead to
tremendous transformation in the manner businesses are being executed. (IBS
Digest,2006)
The world is not only becoming borderless but also flatter instead of round as the
bestseller writer, Thomas L Friedman put it. Information are now highly
accessible and being exploited to an unimaginable scale.
The rat race for market positioning is as fierce as ever through the capitalization
of information, knowledge and innovation.This scenario has also lead major
economies to have greater access than ever before into countries such as India
and China to exploit its competitive resources leading to a more competitive
product and services in the marketplace. With this challenging phenomenon, it is
now overdue and absolutely critical that we need to expedite our readiness, the
know-how and competitiveness of our Malaysian Construction Industry in order
to survive and sustain; an industry which is now minus 1.6 % growth based on
2005 government statistics. (IBS Digest,2006)
As part of efforts to steer various sectors towards our Vision 2020, the Malaysian
government has also launched the National Knowledge-Based Economy
Masterplan which was first announced by the government in the Budget 2000.
This masterplan marks yet another key government initiative to further accelerate
the development of the nation into a knowledge-based economy. It provides
strategic framework outlining the changes to the fundamentals of the economy.
(IBS Digest,2006)
One of the major factor for this delay is that the industry by nature, is very much
project based instead of program based. The soft aspect has not been fully
exploited especially on the management of industry knowledge.
(IBS Digest,2006)
The ultimate way forward is for us to inject into ourselves intellectual knowledge
which will lead us to the Know-How by becoming the specialist within the
marketplace. This can be achieved by being more open minded, unbiased,
neutral, patriotic, passionate and aggressive in our efforts to support and
participate in the realisation of our National IBS Agenda .IBS on the other hand,
is a new industry with endless opportunities. In order to commence with this
exploration, it has to start with knowledge sharing as the new working culture
within the industry. This approach encourages investment on ‘trust’ which in turn,
will lead companies who used to be in competition, to better understand each
other and collaborate for improved market positioning in this new ‘Blue Ocean’
industry.(IBS Digest,2006)
It is only with this ‘Open Collaboration’ environment that we are able to induce
participation, develop and steer, impactful downstream strategies to support the
roadmap implementation.This effort on KM however, need to be driven from both
top and bottom ends of industry heirarchy. Apart from being policy driven, each
industry organization plays an equally crucial role in developing industry’s
intellectual capability. This effort will result in the organization to be more
specialize and therefore provides an improved strategic positioning for the
industry as a whole. (IBS Digest,2006)
Based on the above, we need to create our own speciality and niche in order to
sustain. It is only through KM that this can be achieved and therefore,
necessitates companies to review their internal organizational strategies and
methodologies(IBS Digest,2006)
capital, social capital and corporate capital. All three are essential components of
enterprise knowledge (see diagram) (IBS Digest,2006)
The current industry however, perceived as having assets, financial capital and
staff would be sufficient to realize company objectives. It is more focus on the
tangible aspect of the organization. The crucial intangible elements were
completely overlooked and this has impacted our competitiveness (IBS
Digest,2006)
CIDB believes that R&D is the way forward for developing IBS. The R&D themes
and topics for IBS are aligned to the requirements of the IBS Roadmap 2003-
2010. Although the initiatives in IBS are lead by CIDB, participation from
contractors, consultants, academia, companies and research institutes are
critical. It is a daunting task as 2010 is just around the corner. The processes and
mechanisms to accomplish the target depend on the integration and acceptance
of IBS by players.
The coming three years will be very challenging. A strategic approach will be the
way forward. As the R&D arm for CIDB, CREAM’s R&D output will geared
towards industry’s application and requirements.
Despite policy and promotion of IBS, the implementation is still slow except in
Klang Valley. The common critical success factors identified to address the slow
uptake of IBS by the construction stakeholders include:
o Lack of driver/s from the construction industry stakeholders,
o Government initiatives (i.e. directives, incentives, secure projects) are
required,
o Price competitiveness
o Whole life cycle costing
o IBS Supply Chain
o Information Sharing
o One channel of implementation from Government Agency(i.e. JKR, KPKT)
o Centre of Research Excellence for the implementation of IBS
o Aesthetics
o Quality Control, speed
o Lack of knowledge on IBS
Strategic Thrust 5
In order to realize the implementation and expected target of IBS in Malaysia,
CIDB together with the stakeholders and experts have successfully published a
document titled IBS Roadmap 2003-2010 (summarized in Figure 2) as the action
plan for the industry to refer to and implement.
CIMP 2006-2015 and IBS Roadmap 2003 - 2010 are the strategic directions for
the industry to move forward. The understanding of each of the document needs
to be discussed with the stakeholders to strategize and to implement IBS.
The roadmap is a comprehensive document that divided the IBS programme into
the five main focus areas that reflect the inputs needed to drive the programme
(Manpower, Materials, Management, Monetary, and Marketing) (IBS Roadmap,
2003).
Prior that, IBS Roadmap 2003-2010 has been published by the Government of
Malaysia to guide the practitioners, government agencies and professional
bodies with the strategies and implementation plan. Construction Industry Master
Plan (CIMP 2006-2015) has also higlighted the important of IBS under Strategic
Thrust 5. Nevertheless, despite the plausible advantages and strong support
from the government, IBS adoption in Malaysia has yet to obtain a good
response. This research is one of the innitiative by Construction Research
Institute of Malaysia (CREAM) and Construction Industry Development Board
(CIDB) Malaysia to benchmark best practice in those Critical Success Factors of
IBS companies in UK and Europe.
Having identified the major impediments to the introduction of IBS in the country,
it is important to suggest measures to facilitate adoption of IBS. As we can
clearly see that lack of enforcement of the legislation, regulations, guidelines and
standards are major hindrances. Therefore the process of enforcement of
regulations needs to be done step by step to enable the IBS to be standardized
through modular coordination.
The first step is to study the current status of the construction industry in terms of
controlling the dimension of the prefabricated concrete product. The study
involves legislations, planning, design, manufacturing industry, construction
technology, surveying work and etc. The result of the study is used as a
foundation to plan for the implementation of modular coordination in IBS in
Malaysia. It is also used to formulate the National Modular Coordination Standard
MS 1064 as a basis to standardize the dimension for the design of building and
the fabricated components using metric system.
Next, the strategic planning for the implementation of modular coordination need
to be done. This strategic implementation plan needs to consider the construction
organization structure, the collaborative measures and the further improvement
that can be made to the current system practiced. This is to ensure that the
implementation of IBS using the modular coordination can be done successfully.
Then, The effort will focus on the preparation of Malaysia Standard (MS) 1064 :
Guide to Modular Coordination in Building. Currently, there are 15 parts has been
approved for implementation by the Government of Malaysia.
With the advanced knowledge in computer aided design, IBS buildings can be
designed and visualised analytically prior to the actual construction. The 3-
dimensional drawings can be developed to provide accurate component
dimensions and hence ensure buildability. Erection and construction procedures
can also be simulated and properly planned with the use of computer softwares.
Feasibility studies on the different building systems can be performed without
incurring much cost. Problems during construction can also be observed and
predicted. Any rectifications to the component design can be done before the
manufacturing process. These computer tools contribute to a well-planned and
systematic IBS system.
One good example is the Brickfields Secondary School 1. The school is located
in a busy and limited access site. With such construction constraints and to
expedite construction period, a building system utilising about 75% of pre-
fabricated components of precast concrete beams, columns, hollow core slabs
and solid planks were adopted. The precast concrete skeletal framed IBS system
is also widely used in many other projects. Figures 6 and 7 show the precast
concrete buildings that were built using precast concrete components of beams,
columns and slabs.
In the case of steel structures, there are also many successful IBS projects.
Figure 9 shows the KLCC convention centre, an icon building in the prestigious
Kuala Lumpur city centre. The building was built using a combination of
prefabricated steel roof truss with composite steel deck flooring system.
5.0 Conclusion
Survey on IBS system has been conducted through out Malaysia in 1996. The
purpose of this survey is to gather information on IBS buildings in Malaysia.
Besides that, a visual inspection study was also conducted to observe of any
problems related to IBS system. IBS features potential construction system for
the future with emphasis on quality, higher productivity and less labor intensive.
Besides the aim of gradually reducing the dependency on foreign labor and
saving the country’s loss in foreign exchange, IBS provides the opportunity for
the players in the construction industry to project a new image of the industry to
be at par with other manufacturing-based industry such as the car and electronic
industries.
The adoption of IBS promises to elevate every level of the construction industry
to new heights and image of professionalism. Finally, IBS should be seen as the
modern methods of construction where modern and systematic methods of
design, production planning and mechanized methods of manufacturing and
erection are applied.
The government through CIDB has embarked the IBS Roadmap 2003-2010 that
outlines several well-thought strategies and aggressive steps to promote the use
of IBS in Malaysia To facilitate further, the government has encouraged the use
of IBS for the construction of new government quarters. Contractors adopting the
IBS system are given incentive such as levy exemption based on the percentage
of IBS usage in a project.. The government is taking the leading role in
persuading the construction industry to adopt a more systematic approach and
methodology in construction.
costs and time. It will also help reduce dependence on foreign workers from
320,000 now to 250,000 by 2015. Works Minister Datuk Mohd Zin Mohamed had
said that more than two-thirds of the RM9.6 billion infrastructure projects under
the Public Works Department and related agencies must use IBS.
The IBS is a strategic step to move the local construction industry further up the
value chain, transforming it into a service industry that deals with components
manufactured in factories. "To achieve the objective, industrialisation of IBS
is essential to utilise market forces to bring down prices. We must also
review the IBS scoring system and separate the data on infrastructure
fabricated components from building IBS,"
References :