Project Management - CPI SPI EAC
Project Management - CPI SPI EAC
In this project we developed the project budget and schedule as follows: Activity Duration Budgeted Cost 1 Mobilize the team $3,000 3 Lay the Cable (15 miles) $45,000 $5,000 Terminate & test the cable 1 5 $53,000 Total
EAC: Sum for all tasks: + ACWP (if task is complete) + Budgeted cost (if task is not started) + (ACWP/BCWP * Task Budget) if task is underw
b. At the end of week 1: i. What is your SPI? ii. What is your CPI? iii. What is your EAC?
EAC: Sum for all tasks: + ACWP (if task is complete) + Budgeted cost (if task is not started) + (ACWP/BCWP * Task Budget) if task is underw
c. At the end of the project: i. What is your SPI? ii. What is your CPI? iii. What is your EAC?
Activity
Scheduled Completion
Actual Completion
Mobilize the Team Lay the cable (15 miles) Terminate & test the cable Total
EAC: Sum for all tasks: + ACWP (if task is complete) + Budgeted cost (if task is not started) + (ACWP/BCWP * Task Budget) if task is underw
CPI = BCWP/ACWP
SPI = BCWP/BCWS
EAC
0.667
1.000
$54,500
CPI = BCWP/ACWP
SPI = BCWP/BCWS
EAC
0.554
0.545
$93,500
CPI = BCWP/ACWP
SPI = BCWP/BCWS
EAC
$65,000
0.815
1.000
$65,000