Flow Chart For Road Work
Flow Chart For Road Work
MATERIALS
I
ST
Stage Weighing and Batching of Resin, Tio2, Minerals, Glass Beads,
Waxes, Oil in Powder form.
II
nd
Stage Lifting the above Batched material in a Mechanical Cage Lift in the
Blender at 20 feet Height.
III
rd
Stage Putting the Batch in Dry powder form in the Blender.
IV
th
Stage Blending Material time 10 to 12 Minutes.
V
th
Stage Discharging the Blended material to Stainless Steel Hopper.
VI
th
Stage Weighing, Bagging and packing manually in Bags by Stitching
machine.