Mainit, Servantes P.
Mainit, Servantes P.
SUMMARY
ITEM
NO.
I
ESTIMATED
QTY
DESCRIPTION
Mobilization
QUANTITY
1
day
UNIT COST
(Php)
30,000
TOTAL I
II
Excavation/Backfill
a. Excavation
b. Backfill
c. Earthfill
152.896 cu. m
45.8688 cu. m
253.44 cu. m
1/4
153.00
46.00
253.44
day/cu. m
cu. m
cu. m
cu. m
90.00
90.00
90.00
TOTAL II
III
Concrete Works
a. Footing
Portland Cement
Washed Sand
Gravel or Crushed Stones
Steel Bar - 16 mm x 6.0 m
No. 16 Tie Wire
34.992 cu. m
333 bags
17.496 cu. m
34.992 cu. m
164 pcs
14 kg
TOTAL COST
(Php)
30000.00
30000.00
13770.00
4140.00
22809.60
40719.60
333
17.496
34.992
164
14
bags
cu. m
cu. m
pcs
kg
223.00
74259.00
250.00
4374.00
350.00
12247.20
306.00
50184.00
80.00
1120.00
Material Cost 142184.20
Labor Cost 42,655.26
TOTAL III-a 184839.46
UNITS COST
b. Column
Portland Cement
Washed Sand
Gravel or Crushed Stones
Steel Bar - 16 mm x 6.0 m
Lateral Tie - 16 mm x 6.0 m
No. 16 Tie Wire
bags
cu. m
cu. m
pcs
pcs
kg
223.00
250.00
350.00
306.00
306.00
80.00
Material Cost
Labor Cost
TOTAL III-b
134246.00
8350.00
23380.00
123012.00
139842.00
4963.20
433793.20
130,137.96
563,931.16
UNITS COST
c. Wall Footing
Portland Cement
Washed Sand
Gravel or Crushed Stones
Steel Bar - 10 mm x 6.0 m
Lateral Tie - 10 mm x 6.0 m
No. 16 Tie Wire
bags
cu. m
cu. m
pcs
pcs
kg
223.00
250.00
350.00
121.00
121.00
80.00
Material Cost
Labor Cost
TOTAL III-c
4014.00
225.00
630.00
726.00
726.00
41.60
6362.60
1,908.78
8271.38
UNITS COST
18
0.9
1.8
6
6
0.52
IV
23.868 cu. m
215 bags
11.934 cu. m
23.868 cu. m
236 pcs
337 pcs
47 kg
215
11.934
23.868
236
337
47
bags
cu. m
cu. m
pcs
pcs
kg
223.00
47945.00
250.00
2983.50
350.00
8353.80
306.00
72216.00
121.00
40777.00
80.00
3760.00
Material Cost 176035.30
Labor Cost 52,810.59
TOTAL III-d 228,845.89
UNITS COST
e. Beam (1 & 2)
Portland Cement
Washed Sand
Gravel or Crushed Stones
ReBar - 20 mm x 6.0 m
Stirrups - 10 mm x 6.0 m
No. 16 Tie Wire
179
9.945
19.89
275
342
59
bags
cu. m
cu. m
pcs
pcs
kg
223.00
39917.00
250.00
2486.25
350.00
6961.50
306.00
84150.00
121.00
41382.00
80.00
4720.00
Material Cost 179616.75
Labor Cost 53,885.03
TOTAL III-e 233,501.78
UNITS COST
f. Slab (1-5)
Portland Cement
Washed Sand
Gravel or Crushed Stones
Temp Bar - 10 mm x 6.0 m
Main Bar - 12 mm x 6.0 m
Cut Bar - 12 mm x 6.0 m
No. 16 Tie Wire
344
27.21
38.22
611
234
59
8
bags
cu. m
cu. m
pcs
pcs
pcs
kg
223.00
76712.00
250.00
6802.50
350.00
13377.00
121.00
73931.00
172.00
40248.00
172.00
10148.00
80.00
640.00
Material Cost 221858.50
Labor Cost 66,557.55
TOTAL III-f 288,416.05
4,980 pcs
4,980
pcs
12.00
59760.00
208 bags
18 cu. m
208
18
bags
cu. m
223.00
250.00
46384.00
4500.00
298 bags
17 cu. m
250 pcs
10 kg
298
17
250
10
bags
cu. m
pcs
kg
223.00
250.00
121.00
80.00
66454.00
4250.00
30250.00
800.00
UNITS COST
Masonry
4" CHB
Mortar
CHB,Type B Mixture)
Portland Cement
Washed Sand
Cement Plaster
(25mm thk, Type A Mixture)
Portland Cement
Washed Sand
ReBars - 10 mm x 6.0 m
No. 16 Tie Wire
(4"
VI
Ceiling Works
1/4 " thk. Marine Plywood
2" x 4"x 10' Good Lumber
2" x 2"x 10' Good Lumber
75 pcs
144 pcs
75
144
pcs
pcs
545.00
40875.00
99.00
14256.00
Material Cost 267529.00
Labor Cost 80,258.70
TOTAL IV 347,787.70
64 pcs
53 pcs
8 pcs
64
53
8
pcs
pcs
pcs
545.00
99.00
30.00
Material Cost
Labor Cost
TOTAL IV
34880.00
5247.00
240.00
40367.00
12,110.10
52,477.10
8 set
set
2050.00
16400.00
2750.00
44000.00
set
1250.00
20000.00
Aluminum framed fixed window powder coated- white finish with blue glass panel
Fixed Window
16 set
16
set
Aluminum framed awning window powder coated- white finish with blue glass panel
16 set
16
Aluminum framed sliding door on analok finish with clear glass panel
1 set
set
4700.00
4700.00
6 set
set
4200.00
25200.00
8 set
set
Tile Works
20 x 20 cm Glazed Wall Tiles
20 x 20 cm Unglazed Floor Tiles
Cement Mortar
White Cement
Tile Adhesive
4392 pcs
784 pcs
3 bags
13 kg
3 bags
4392
784
3
13
3
pcs
pcs
bags
kg
bags
67.50
55.50
480.00
65.00
1240.00
Material Cost
Labor Cost
TOTAL IV
Roofing Works
No. 26 Corr. G.I. Sheet x 8'
Ridge Roll
Gutter
Teks Screw
2"x4" Steel C-Purlins
230 pcs
8 pcs
28 pcs
5750 pcs
98 pcs
230
24
81.5
5750
98
pcs
m
m
pcs
pcs
101660.00
442.00
4272.00
178.00
14507.00
178.00
28750.00
5.00
53900.00
550.00
Material Cost 203089.00
Labor Cost 60,926.70
VII
VIII
2500.00
20000.00
Material Cost 130300.00
Labor Cost 39,090.00
TOTAL IV 169,390.00
296460.00
43512.00
1440.00
845.00
3720.00
345977.00
103,793.00
449,770.00
TOTAL IV
IX
264,015.70
Plumbing Works
(SF/WC-DF CARDINAL II PB WHITE W/EZ CLOSE SC)
Water Closet
16 pcs
16
pcs
5845.00
93520.00
pcs
1408.00
11264.00
Faucet
8 pcs
XI
Lavatory
Floor Drain
Gate Valve
Check Valve
Water meter
Cistern
Septic Tank
3/4" Blue PVC Pipe
2" Orange PVC Pipe
8 pcs
24 pcs
1 pc
1 pc
1 pc
1 pc
1 pc
66 m
66 m
8
24
1
1
1
1
1
66
66
pcs
pcs
pc
pc
pc
pc
pc
m
m
720.00
5760.00
208.00
4992.00
525.00
525.00
30.00
30.00
2150.00
2150.00
9900.00
9900.00
13200.00
13200.00
120.00
7920.00
165.00
10890.00
Material Cost 160151.00
Labor Cost 48,045.30
TOTAL IV 208,196.30
Electrical Works
6" Pinlight with SL 18 Bulb
4" Pinlight with SL 12 Bulb
T5 Flourescent Lamp
Electrical Wires
Wiring Devices
Panel Boards & Circuit Breaker
14 pcs
72 pcs
17 pcs
154.49 sq. m
154.49 sq. m
154.49 sq. m
14
72
17
154.49
154.49
154.49
pcs
pcs
pcs
sq. m
sq. m
sq. m
150.00
2100.00
108.00
7776.00
185.00
3145.00
316.00
48818.84
56.00
8651.44
284.00
43875.16
Material Cost 114366.44
Labor Cost 34,309.93
TOTAL IV 148,676.37
34 gal
68 gal
34
68
gal
gal
520.00
605.00
17680.00
41140.00
14 gal
28 gal
14
28
gal
gal
520.00
605.00
7280.00
16940.00
19 gal
38 gal
19
38
gal
gal
Painting Works
a. Interior and Exterior Wall
Primer
Topcoat - Latex (water-based)
b. Roofing
Primer
Topcoat
c. Ceiling
Primer (wood)
Topcoat-Quick Enamel(thinner)
545.00
10355.00
590.00
22420.00
Material Cost 115815.00
Labor Cost 34,744.50
TOTAL IV 150,559.50
INDIRECT COST
Contractor Tax
572797.66
Contractor Profit
673879.60
Contingency
505409.70
TOTAL INDIRECT COST 1752086.96