Checklist - Pre Concrete

This checklist is for pre-pour concrete inspection of walls and columns for a 132/33/11&132/11kV substation project by Larsen & Toubro Limited for Federal Electricity & Water Authority and Energoprojekt Entel Co Ltd. The checklist ensures that formwork, reinforcement, planning, equipment, safety requirements and installations are in order before the concrete pour. Key items include approved drawings, cleaned surfaces, proper supports and alignment, reinforcement as per schedule, available equipment and fulfillment of environmental health and safety requirements.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
215 views

Checklist - Pre Concrete

This checklist is for pre-pour concrete inspection of walls and columns for a 132/33/11&132/11kV substation project by Larsen & Toubro Limited for Federal Electricity & Water Authority and Energoprojekt Entel Co Ltd. The checklist ensures that formwork, reinforcement, planning, equipment, safety requirements and installations are in order before the concrete pour. Key items include approved drawings, cleaned surfaces, proper supports and alignment, reinforcement as per schedule, available equipment and fulfillment of environmental health and safety requirements.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

IR No:

Date :
Location:
Client: Federal Electricity & Water Authority(FEWA) Consultant: Energoprojekt Entel Co Ltd
Project name Contractor: Larsen & Toubro Limited
Description of structure / Member :
Checklist : Civil ( Put releveant ok/not ok/NA marks)
Setting Out/Dimension Line Level Cut-out Dimension
Formwork Line Level Chamfer Alignment
Size Spacing Laps Nos.
Chairs Cover Blocks Dowels Alignment
Embedment Channels Inserts Bolts Conduits
J oint details/water bar Const. J t Exp. J t Water Bar
Surface prep/cleaning Formwork Rebar General
Clearence :
1
2
Remarks
Ok / Not Ok / NA
Approvals/ Documents
Approved shop drawings, concrete mix design and relevant method
statements available.
Formwork, scaffolding & reinforcement works
Consultant
a) Formwork alignment verticallity levels and supports groove strip fixed
Status
L&T
Reinforcement
Document Title : Checklist - Pre pour Concrete for Wall &
Column
132/33/11&132/11kV Substation works -E11/2011(1)
3
4
5
6
7
8
Additional comments (if any) :
Name
Si
Pour sequence planned , pour plan and Confirmation for continuous supply
letter from concrete supplier attached.
Curing Arrangements/Hotweather protection
Environment, Health & Safety
EHS requirement ( safe access, lighting arrangement, causion sign boards
etc.) fulfilled/ EHS clearance.
L&T_QA/QC & Site Manager Consultant Engr. Authority Engr.
Curing water , hessian cloth, Polythene sheet availability at site.
a) Construction joint preparation & cleaning prior to close shutter.
b) Surface cleaning done and bonding agent applied where ever
necessary.
Planning of concrete pour
Adequacy of P & M
Adequate plant & machinaries(working and stand by concrete
pump,viberators with needles,alum.Strip,artificial/flood lighting facilities etc.)
required for the concrete pouring are available at site.
MEP Installations (Electrical, AC, Plumbing & Fire fighting)
All Conduits, Inserts and sleeves have been provided as per relevant
approved MEP/ LSP/FPS drawings (Clearance attached ).
Cleaning & Joints Preparation
a) Formwork alignment, verticallity,levels and supports, groove strip fixed
for water proofing termination.
b) Scaffolding erected as per shop drawing ,inspected by L&T EHS
engineer
c) Reinfocement work completed as per approved RFC drawing,Approved
Shop drawing / barbending schedule.
Sign
Date