1. Dalhousie University was performing maintenance on electrical equipment that powers buildings like the Memorial Arena. 2. The procedure involved de-energizing equipment by opening circuit breakers and disconnect switches at the Arena Electrical Vault and Killam Vault to safely work on a breaker and transformer. 3. After maintenance was completed, the procedure was reversed by closing circuit breakers and disconnect switches to re-energize the buildings.

Uploaded by

Allison Payne
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
87 views

Arena Switching Procedure

1. Dalhousie University was performing maintenance on electrical equipment that powers buildings like the Memorial Arena. 2. The procedure involved de-energizing equipment by opening circuit breakers and disconnect switches at the Arena Electrical Vault and Killam Vault to safely work on a breaker and transformer. 3. After maintenance was completed, the procedure was reversed by closing circuit breakers and disconnect switches to re-energize the buildings.

Uploaded by

Allison Payne
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

25801271 DALHOUSIE UNIVERSITY

HIGH VOLTAGE SWITCHING PROCEDURE

DATE: December 18, 2009 Est Start Time: 23:30/ Dec 18th

LOCATION: Arena Electrical Vault, & Killam Vault (Meet in Arena


Est Finish Time: 03:00/ Dec 19th
lobby at [22:30], [December 18, 2009])
PURPOSE: Maintenance of the Arena magna blast breaker at Killam Vault.

PERFORMED INITIAL
STEP PROCEDURE TIME
BY S
Arena Electrical Vault - Notify Security (6400); Thermal Plant
1 control room Operators (2435); UCIS Help Desk (2662) that switching Dal
procedure to isolate equipment is starting.
Arena Electrical Vault - Ensure all personnel are standing clear of
2 Dal
all electrical gear before beginning the switching procedure.
Killam Vault - Open and rack down 1200A draw-out type breaker,
feeding the "Arena (Rink)". Ensure all control circuits are de-
3 energized and that the breaker is removed out from the switchiboard Dal/Siemens
unit. This will de-energize the Memorial Arena, Wickwire Field, and
Studley Gym. Lock/ Tag out door.
Arena Electrical Vault - Open 600A Disconnect Switch and verify no
4 voltage is present on the 4.16kV main bus. Apply grounds (See Dal/Siemens
attached diagram)
Killam Vault/Arena Electrical Vault - Work may now begin at the
Killam Vault and Arena Vault simultaneously with two crews to
perform the following: 1- The maintenance of the magna blast
5 Siemens
breaker that feeds the Arena located in Killam Vault, and 2- The
maintenance of the 4.16kV 600A (100E) Switch and the 750kVA
4.16kV-600/347VTransformer located at Arena Electrical Vault.

Killam Vault - Make sure that all tools and equipment have been
6 Dal/Siemens
removed from the cabinets.
Arena Electrical Vault - Remove ground from the 4.16kV main bus
7 and close the 600A Disconnect Switch. Ensure all cabinets are shut Dal
and locked, and that there are no exposed connections.
Killam Vault - Close and rack up the 1200A draw-out type breaker,
feeding the "Arena (Rink)". This will energize the Memorial Arena,
8 Dal
Wickwire Field, and Studley Gym.Visually confirm the breaker is
closed.
Arena Electrical Vault - Notify Security (6400); Thermal Plant
9 control room Operators (2435); UCIS Help Desk (2662) that switching Dal
procedure is complete and all building loads are back to normal.

PROCEDURE REVIEWED BY