Jadwal Pelaksanaan Pek - Perencanaan Wil - Papua Barat Th.2014 (Kurva-S Untuk Masa Layanan 3 Bulan)

This document provides a schedule for planning work on the Baum-Dasri Road and Klamono-Sorsel-Kambuaya Road improvement projects in West Papua Province from June 2014 to August 2015. It outlines five phases of work including preparation, surveys, design/planning, reporting, and quality control. For each task, it shows the planned timeline in weekly intervals, total percentage complete, cumulative percentage, and space to record actual progress and deviations from the plan. The schedule is approved by the project manager and engineering consultant.

Uploaded by

Yunitan Teguh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views2 pages

Jadwal Pelaksanaan Pek - Perencanaan Wil - Papua Barat Th.2014 (Kurva-S Untuk Masa Layanan 3 Bulan)

This document provides a schedule for planning work on the Baum-Dasri Road and Klamono-Sorsel-Kambuaya Road improvement projects in West Papua Province from June 2014 to August 2015. It outlines five phases of work including preparation, surveys, design/planning, reporting, and quality control. For each task, it shows the planned timeline in weekly intervals, total percentage complete, cumulative percentage, and space to record actual progress and deviations from the plan. The schedule is approved by the project manager and engineering consultant.

Uploaded by

Yunitan Teguh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

SATKER : PERENCANAAN DAN PENGAWASAN JALAN NASIONAL PROVINSI PAPUA BARAT

PPK : P2JN MANOKWARI-BINTUNI


NAMA PAKET / LOKASI PEKERJAAN : PERENCANAAN JALAN BAUM - DASRI
NO./TGL. KONTRAK :
NO./TGL. SPMK
KONSULTAN PERENCANA :
MEI 2014
1 2 3 4 5 6 7 8 9 10 11 12 13
26-30 31-06 07-13 14-20 21-27 28-04 05-11 12-18 19-25 26-01 02-08 09-15 16-23
I Tahap Persiapan
1 Review Dokumen Kontrak , Pengumpulan Data- Rencana 0.50 0.50 0.50 100%
Sekunder & Peraturan & Kriteria Kerja dan Realisasi
Koordinasi dg Balai/ Satker & Core TeamDesain.
2 Mobilisasi Team Rencana 2.00 2.00 2.00
Realisasi
II Tahap Pelaksanaan Konstruksi
1 Survey Pendahuluan Rencana 7.00 7.00 3.50 3.50
Realisasi
2 Survey Detail
a. Survey Topografi Rencana 7.00 7.00 2.33 2.33 2.33
Realisasi 75%
b. Survey Hidologi ,Hidrolika & Drainase Rencana 7.00 7.00 3.50 3.50
Realisasi
c. Survey Soil & Material, Geologi dan Geoteknik Rencana 7.00 7.00 1.17 1.17 1.17 1.17 1.17 1.17
Realisasi
d. S urvey Lalu Lintas Rencana 7.00 7.00 3.50 3.50
Realisasi
E. S urvey Kondisi Perkerasan Jalan (Existing) dan Rencana 7.00 7.00 3.50 3.50
Survey Harga Dasar & Harga Satuan Realisasi
F. Survey Lingkungan Rencana 7.00 7.00 3.50 3.50
Realisasi
III Tahap Proses Desain/Perencanaan
1 Analisis Data Primer (termasuk data laboratorium) Rencana 3.00 3.00 0.43 0.43 0.43 0.43 0.43 0.43 0.43
Realisasi 50%
2 Penyusunan Konsep Desain Awal Rencana 2.00 2.00 0.40 0.40 0.40 0.40 0.40
Realisasi
3 Penggambaran Desain (Jalan, Jembatan) Rencana 5.00 5.00 1.25 1.25 1.25 1.25
Realisasi
4 Penyusunan Engineering Estimate Rencana 2.00 2.00 0.40 0.40 0.40 0.40 0.40
Realisasi
5 Penysusunan Dokumen Lelang/Spesifikasi Teknis Rencana 3.00 3.00 0.60 0.60 0.60 0.60 0.60
Realisasi
IV Tahap Pelaporan Perencanaan Teknis
1 Laporan Pendahuluan Rencana 3.40 3.40 1.13 1.13 1.13
Realisasi
2 Laporan Bulanan Rencana 6.80 6.80 2.27 2.27 2.27
Realisasi
3 Laporan Antara Rencana 3.40 3.40 0.57 0.57 0.57 0.57 0.57 0.57
Realisasi
4 Draft Laporan Akhir Rencana 3.40 3.40 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 0.38 25%
Realisasi
5 Laporan Akhir Rencana 15.50 15.50 15.50
Realisasi
V Pengendalian Mutu Perencanaan Teknis
1 Asistensi Rencana 0.10 0.10 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Realisasi
2 Presentasi
a. Presentasi Laporan Pendahuluan Rencana 0.30 0.30 0.30
Realisasi
b. Presentasi Laporan Antara Rencana 0.30 0.30 0.30
Realisasi
c. Presentasi Draft Laporan Akhir Rencana 0.30 0.30 0.30 0%
Realisasi
Jumlah 100.00 100.000
Rencana Mingguan (%) 0 7.14 4.64 17.47 17.07 7.55 4.20 4.20 4.20 5.20 6.11 1.39 1.39 19.45
Rencana Kumulatif (%) 0 7.14 11.78 29.26 46.33 53.87 58.07 62.27 66.47 71.66 77.78 79.16 80.55 100.00
Realisasi Mingguan (%) 0
Realisasi Kumulatif (%) 0
Deviasi (%)
DISETUJUI OLEH : DIPERIKSA OLEH : DIBUAT KONSULTAN PERENCANA
PPK P2JN MANOKWARI & BINTUNI PT. ..
1.7000
0.0267
Ir. SUPRANOTO
NIP. TEAM LEADER DIREKTUR TEAM LEADER
JADWAL PELAKSANAAN PEK.PERENCANAAN WIL.PAPUA BARAT TH.2014 (KURVA-S UNTUK MASA LAYANAN 3 BULAN)
NO URAIAN PEKERJAAN
JUMLAH
PERSENTASE
PER KEGIATAN
(%)
BOBOT (%)
JUNI 2014 JULI 2015 AGUST 2014
KET
RENCANA
SATKER : PERENCANAAN DAN PENGAWASAN JALAN NASIONAL PROVINSI PAPUA BARAT
PPK : P2JN MANOKWARI-BINTUNI
NAMA PAKET / LOKASI PEKERJAAN : PERENCANAAN PENINGKATAN RUAS JALAN KLAMONO-BTS. SORSEL-KAMBUAYA
NO./TGL. KONTRAK :
NO./TGL. SPMK
KONSULTAN PERENCANA :
1 2 3 4 5 6 7 8 9 10 11 12 13
16--23 24-30 31-06 07-13 14-20 21-27 28-04 05-11 12-18 19-25 26-01 02-08 09-13
I Tahap Persiapan
1 Review Dokumen Kontrak , Pengumpulan Data- Rencana 0.50 0.50 0.50 100%
Sekunder & Peraturan & Kriteria Kerja dan Realisasi
Koordinasi dg Balai/ Satker & Core TeamDesain.
2 Mobilisasi Team Rencana 2.00 2.00 2.00
Realisasi
II Tahap Pelaksanaan Konstruksi
1 Survey Pendahuluan Rencana 7.00 7.00 3.50 3.50
Realisasi
2 Survey Detail
a. Survey Topografi Rencana 7.00 7.00 2.33 2.33 2.33
Realisasi 75%
b. Survey Hidologi ,Hidrolika & Drainase Rencana 7.00 7.00 3.50 3.50
Realisasi
c. Survey Soil & Material, Geologi dan Geoteknik Rencana 7.00 7.00 1.17 1.17 1.17 1.17 1.17 1.17
Realisasi
d. S urvey Lalu Lintas Rencana 7.00 7.00 3.50 3.50
Realisasi
E. S urvey Kondisi Perkerasan Jalan (Existing) Rencana 7.00 7.00 3.50 3.50
Survey Harga Dasar & Harga Satuan Realisasi
F. Survey Lingkungan Rencana 7.00 7.00 3.50 3.50
Realisasi
III Tahap Proses Desain/Perencanaan
1 Analisis Data Primer (termasuk data laboratorium) Rencana 3.00 3.00 0.43 0.43 0.43 0.43 0.43 0.43 0.43
Realisasi 50%
2 Penyusunan Konsep Desain Awal Rencana 2.00 2.00 0.40 0.40 0.40 0.40 0.40
Realisasi
3 Penggambaran Desain (Jalan, Jembatan) Rencana 5.00 5.00 1.25 1.25 1.25 1.25
Realisasi
4 Penyusunan Engineering Estimate Rencana 2.00 2.00 0.50 0.50 0.50 0.50
Realisasi
5 Penysusunan Dokumen Lelang/Spesifikasi Teknis Rencana 3.00 3.00 0.75 0.75 0.75 0.75
Realisasi
IV Tahap Pelaporan Perencanaan Teknis
1 Laporan Pendahuluan Rencana 3.40 3.40 1.13 1.13 1.13
Realisasi
2 Laporan Bulanan Rencana 6.80 6.80 2.27 2.27 2.27
Realisasi
3 Laporan Antara Rencana 3.40 3.40 0.57 0.57 0.57 0.57 0.57 0.57
Realisasi
4 Draft Laporan Akhir Rencana 3.40 3.40 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 25%
Realisasi
5 Laporan Akhir Rencana 15.50 15.50 15.50
Realisasi
V Pengendalian Mutu Perencanaan Teknis
1 Asistensi Rencana 0.10 0.10 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Realisasi
2 Presentasi
a. Presentasi Laporan Pendahuluan Rencana 0.30 0.30 0.30
Realisasi
b. Presentasi Laporan Antara Rencana 0.30 0.30 0.30
Realisasi
c. Presentasi Draft Laporan Akhir Rencana 0.30 0.30 0.30 0%
Realisasi
Jumlah 100.00 100.000
Rencana Mingguan (%) 0 2.50 4.64 4.64 17.48 17.07 7.60 4.25 4.25 4.25 5.50 6.41 1.68 19.75
Rencana Kumulatif (%) 0 2.50 7.14 11.78 29.26 46.33 53.92 58.17 62.41 66.66 72.15 78.57 80.25 100.00
Realisasi Mingguan (%) 0
Realisasi Kumulatif (%) 0
Deviasi (%)
DISETUJUI OLEH : DIPERIKSA OLEH : DIBUAT KONSULTAN PERENCANA
PPK P2JN MANOKWARI & BINTUNI PT. ..
1.7000
0.0267
Ir. SUPRANOTO
NIP. TEAM LEADER DIREKTUR TEAM LEADER
KET
MEI 2014 AGUST 2014 JULI 2015
JADWAL PELAKSANAAN PEK.PERENCANAAN WIL.PAPUA BARAT TH.2014 (KURVA-S UNTUK MASA LAYANAN 3 BULAN)
NO URAIAN PEKERJAAN
JUMLAH
PERSENTASE
PER KEGIATAN
(%)
BOBOT (%)
JUNI 2014
RENCANA