1. Create a planning scenario in T code MS31 and configure planning settings in OPU5 for planned orders for long-term planning. 2. Define requirements in MD61 in an inactive version and remove the active checkbox after defining requirements. 3. Assign the plan to the planning scenario in MS32, release it, and ensure planning file entries are created which can be checked using MS21.

Uploaded by

Mukesh Chauhan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as TXT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
192 views1 page

SAP LTP Business Process - Cycle

1. Create a planning scenario in T code MS31 and configure planning settings in OPU5 for planned orders for long-term planning. 2. Define requirements in MD61 in an inactive version and remove the active checkbox after defining requirements. 3. Assign the plan to the planning scenario in MS32, release it, and ensure planning file entries are created which can be checked using MS21.

Uploaded by

Mukesh Chauhan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as TXT, PDF, TXT or read online on Scribd
You are on page 1/ 1

1.

A plannig scenario has to be created for a plant in T code MS31 & for the same
Planning scenario

configuration settings has to be made in OPU5 for the planned orders for LTP.

2.Requirements has to be given in MD61 in an inactive version and also after giv
ing the requirements

kindly remove the tick mark against version- active check box.

3.Assign this plan to the planning scenario in MS32,release it and ensure the pl
anning file entries are

entered or created,the same can be checked using MS21.

4.After taking LTP simulation run in MS02(individual material) or MS01 you can s
ee the simulated

planned orders obtained in MS04 T code.

5.These Simulated planned orders can't be converted into production orders or it
cant be used for any

business confirmation purpose.

6. For capacity planning analysis,use T Code CM38,

Before that Ensure for all the work centers in CR03 which are used for operation
under capacity header

you have included the check box for Long term planning,otherwise in CM38 you can
't see any capacity

requirements data.

7.Before executing CM38,ensure under settings---> general you are giving the per
iod settings properly.
********************************************************************************
***************************************************************
Production Types:-
Discrete Manufacturing
EE Repetitive manufacturing
EE Process Manufacturing