The document outlines the design conditions and specifications for a semi-automatic wastewater treatment plant with a planned capacity of 50 m3 per day. It will use a conventional biofilter system and treat wastewater to comply with relevant effluent standards. The system includes various tanks for equalization, separation, reaction, and filtration, as well as components like pumps, blowers, and a control panel for automatic operation.

Uploaded by

David Lambert
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
177 views

Ipal Wika

The document outlines the design conditions and specifications for a semi-automatic wastewater treatment plant with a planned capacity of 50 m3 per day. It will use a conventional biofilter system and treat wastewater to comply with relevant effluent standards. The system includes various tanks for equalization, separation, reaction, and filtration, as well as components like pumps, blowers, and a control panel for automatic operation.

Uploaded by

David Lambert
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Design Conditions (SEMI AUTOMATIC RUNNING)

STP Merk BIOFLA 1(SATU) SET


INCLUDE OF WORK
KETERANGAN
Kapasitas Rencana : 50 m
BOD Masuk : 400 mg/liter
SS masuk : 200 mg/liter
Efisiensi pengolahan : 90-95 %
BOD Keluar : 20 mg/liter
SS Keluar : 20 mg/liter
Mutu hasil olahan (efluent) Sesuai dengan Kep 58/MENLH/12/1995
Sistem Bio Filter - Metode Konventional
Sistem kerja IPAL Semi Otomatis
Kebutuhan Luas Lahan 35 m
Konstruksi Concrete + Coating sesuai dokumen teknis
Material : PVC Sheet
Ketebalan : 0.15-0.23 mm
Luas Kontak Spesifik : 30 - 35 m / m
Diameter Lubang : 2 cm x 2 cm
Berat Spesifik : 30 - 35 kg / m
Porositas Rongga : 0.98
Injek chlor Automatic Water pump sensor detector sesuai dokumen teknis
Rumah Alat Konstruksi Bangunan batu bata 2 x 2 meter sesuai dokumen teknis
Rumah Ipal Konstruksi Tiang MS Canal Double, Atap Asbes sesuai dokumen teknis
PVC 6", 4", 2", 1"
Penyambungan pipa dengan saluran dari existing gedung dan bak septic tank
Grease Trap Unit SS 304 Dimensi (p x l x t) 1 x 0.75 x 1 meter sesuai dokumen teknis
Bar Screen SS 304 Dimensi (p x l x t) 1 x 0.75 x 1 meter sesuai dokumen teknis
Submersible pump Type SS N.0520 / setara sesuai dokumen teknis
Silent Blower Type HP 200, 210 watt, 220-240 volt, 20kpa (8 unit) sesuai dokumen teknis
Diffuser Type coarse bubble, Dia 6" sesuai dokumen teknis
Dosing Pump Pressure = 7 bar, kapasitas = 4.7 liter/jam (2 unit) sesuai dokumen teknis
Tangki Kimia Fibre Tank sesuai dokumen teknis
Mixer / Agitator Type vertical C1T 0.75, 0.75kW, Agitation shaft length 2200 mm, Dia. 45 mm (1 unit) sesuai dokumen teknis
Centripugal Pump Head pump 9 meter, 125 watt, 220 volt (2 unit) sesuai dokumen teknis
Panel Control Autonic komponen sesuai dokumen teknis
PH Control Automatic control Water PH balance with chemical injection pump sesuai dokumen teknis
Radar / pelampung Lokal sesuai dokumen teknis
Filter Tank unit Fibre glass tank size 20" sesuai dokumen teknis
Konstruksi concrete K-275
Detention time 1 jam
Dimensi bak (p x l x t) 100 x 75 x 75 cm
Konstruksi concrete K-275
Dimensi bak (p x l x t) 60 x 60 x 60 cm
Konstruksi concrete K-275
Kapasitas Bak : 12 m
Konstruksi concrete K-275
Detention time 30 menit
Konstruksi concrete K-275
Detention time 30 menit
Kapasitas Rencana : 50 m/Hari
BOD Masuk : 400 mg/liter
SS masuk : 200 mg/liter
Waktu tinggal : 9 jam
Volume Bak : 19 M
Dimensi Bak : Lebar : 3 meter, Panjang : 3.2 m, Kedalaman : 2 m, Tinggi ruang bebas : 0.5 m
Konstruksi concrete K-275
Kapasitas Rencana : 50 m/Hari
BOD Masuk : 160 mg/liter
Efisiensi pengolahan : 25 %
BOD Keluar : 120 mg/liter
Waktu tinggal : 2 jam
Volume Bak : 4.5 M
Bak Pengumpul
Sumber Limbah : Kamar mandi, Ruang
pencucian (Laundry), Ruang Gizi
(kitchen), Lab, Ruang Poly, Ruang
Pembilasan Radiologi
Media tumbuh bakteri : Sarang Tawon
Piping & aksesories, CO
Bak netralisasi
Bak Kontrol
Bak Grease Trap
Bak Equalisasi
Bak Pengendapan awal
URAIAN PEKERJAAN SAT
SPESIFIKASI TEKNIS IPAL
sesuai dokumen teknis
sesuai dokumen teknis
sesuai dokumen teknis
sesuai dokumen teknis
sesuai dokumen teknis
sesuai dokumen teknis
sesuai dokumen teknis
sesuai dokumen teknis
Dimensi Bak : Lebar : 2 meter, Panjang : 1.25 m, Tinggi : 2 m, Tinggi ruang bebas : 20 cm
Center Feeding Flow Process An aerob Reaktor System
Konstruksi concrete K-275
BOD Masuk : 400 mg/liter
Efisiensi pengolahan : 60 %
BOD Keluar : 160 mg/liter
Standar beban BOD per volume media 0.4-4.7 kg BOD/m.hari. Ditetapkan Beban BOD yang digunakan 2.5 k
Beban BOD di dalam air limbah = 50 m/hari x 400 g/m = 20,000 g/hari = 20 kg/hari
Volume media yang dibutuhkan = 20 kg/hari : 2.5 kg BOD/m.hari = 8 m
Volume media = 70 % dari total volume reaktor
Volume reaktor yang diperlukan = 10/7 x 8 m = 11.5 m
Waktu tinggal reaktor Anaerob yang dibutuhkan = (11.5 m : 50 m/hari) x 24 jam/hari = 5.5 jam
Dimensi bak : Lebar : 2 m, Panjang : 2.9 m, kedalaman air efektif : 2 m, Ruang bebas : 20 cm
Kapasitas rencana : 50 m
BOD Masuk : 120 mg/liter
Efisiensi pengolahan : 60 %
BOD Keluar : 48 mg/liter
Ditetapkan beban BOD yang digunakan = 1.0 kg BOD/m.hari
Beban BOD air limbah = 50 m/hari x 120 g/m = 6 kg/hari
Volume media yang dibutuhkan = 6 kg/hari : 1.0 kg BOD/m.hari = 6 m
Volume media = 60 % dari total volume reaktor
Volume reaktor yang diperlukan = 10/6 x 6 m = 10 m
Waktu tinggal reaktor zona Anoksik (anaerob) yang dibutuhkan = (10 m : 50 m/hari) x 24 jam/hari = 4.8 jam
Dimensi bak yang dibutuhkan : Lebar : 2 m, Panjang : 2.5 m, Tinggi : 2 m, Ruang kosong : 20 cm
Konstruksi concrete K-275
Kapasitas rencana : 50 m
BOD Masuk : 48 mg/liter
Ditetapkan beban BOD yang digunakan = 1.0 kg BOD/m.hari
Beban BOD air limbah = 50 m/hari x 48 g/m = 2.4 kg/hari
Jumlah BOD yang dihilangkan = 0.5 x 2.4 kg/hari = 1.2 kg/hari
Volume media yang diperlukan = 1.2 kg/hari : 1.0 kg/m.hari = 1.2 m
Volume media = 50 % dari total volume Reaktor
Volume reaktor yang diperlukan = 10/5 x 1.2 m = 2.4 m
Waktu tinggal aerob yang dibutuhkan = (2.4 m : 50 m/hari) x 24 jam/hari = 2.3 jam
Dimensi bak yang dibutuhkan : Lebar : 2 m, Panjang : 3 m, Tinggi : 2 m, Ruang kosong : 20 cm
Kebutuhan oksigen :
Kebutuhan oksigen dalam reaktor aerob sebanding dengan jumlah BOD yang dihilangkan = 1.2 kg/hari
Factor keamanan 1.4
Kebutuhan oksigen = 1.4 x 1.2 kg/hari = 1.7 kg/hari
Temperatur udara rata-rata 28 C
Berat udara pada suhu 28 C = 1.1725 kg/m
Diasumsikan jumlah oksigen dalam udara sebesar 23.2 %
Maka jumlah kebutuhan udara = 1.7 kg/hari : 1.1725 kg/m x 0.232 g O2/g udara = 6.25 m/hari
Efisiensi difuser = 2.5 %
Kebutuhan udara aktual = 6.25 m/hari : 0.025 = 250 m/hari = 0.250 m/menit
Konstruksi Concrete K-275
Kapasitas rencana : 50 m
3
BOD masuk : 24 mg/liter
Efisiensi Pengolahan : 5%
BOD keluar : 22.8 mg/liter
Waktu tinggal : 2 jam
Volume bak : 4.2 m
3
Dimensi bak : Lebar : 2 m, Panjang : 1.2 m, Tinggi : 2 m, Ruang kosong : 20 cm
Konstruksi Concrete K-275
Detention time 1 jam
Volume bak : 2 m3
Kolam Biologi/Ikan Konstruksi batu bata sesuai dokumen teknis
Bak Penampungan Air Bersih Dimensi bak (p x l x t) 2.5 x 2 x 1.5 meter sesuai dokumen teknis
Water Proofing / coating Material Acrylic, fleksible sesuai dokumen teknis
PEKERJAAN PEMASANGAN
TRANSPORTASI IPAL Transportasi dari Bandung ke Lokasi Proyek
EXCLUDE OF WORK
Pekerjaan Sipil
Pekerjaan Loading Tangki
Pekerjaan Plumbing
* Penyambungan pipa INLET dari gedung ke instalasii IPAL dan
sesuai dokumen teknis
Bak Pengendapan Akhir
Bak Chlorine
Bak Pengendapan awal
Bak Reaktor Anaerob
Biofilter zona anoksik (anaerob)
Bak Reaktor Aerob/aerasi (2 unit)
Dikerjakan / Dipersiapkan oleh
Kontraktor Lain
sesuai dokumen teknis
sesuai dokumen teknis
sesuai dokumen teknis
sesuai dokumen teknis
sesuai dokumen teknis
pipa OUTLET instalasi IPAL ke drainase kota
* Penyambungan pipa Ventilasi dari instalasi IPAL ke samping gedung
Penarikan kabel listrik
Penarikan kabel listrik dari Main Power Switch ke Instalasi IPAL
Pengisian Air
Pengisian Air kedalam tangki untuk test kebocoran tangki , pemasangan &
testing commissioning
Dikerjakan / Dipersiapkan oleh
Kontraktor Lain