Raghu Prakash submitted a weekly progress report to Joseph Ravi covering September 13-19, 2014. During this period, Raghu completed revised reports for Sinopec and L&T projects, visited sites for Azizia Bridge and RCC Sinoma projects, and conducted lab tests. Activities still in process included resolving issues on additional Sinopec and L&T reports, retrieving a PO for Azizia Bridge, ongoing permeability and structural tests, and following up on inspections. Long term projects consisted of RE wall activities for Azizia Bridge.
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
68 views
Weekly Status Report 01
Raghu Prakash submitted a weekly progress report to Joseph Ravi covering September 13-19, 2014. During this period, Raghu completed revised reports for Sinopec and L&T projects, visited sites for Azizia Bridge and RCC Sinoma projects, and conducted lab tests. Activities still in process included resolving issues on additional Sinopec and L&T reports, retrieving a PO for Azizia Bridge, ongoing permeability and structural tests, and following up on inspections. Long term projects consisted of RE wall activities for Azizia Bridge.
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1
Page 1 of 1
WEEKLY PROGRESS REPORT
To: Engr. Joseph Ravi From: Engr. Raghu Prakash Period: September 13, 2014 to September 19, 2014
ACTIVITIES COMPLETED THIS WEEK Completed Deliverables: Sinopec Revised Method Statement Sinopec Revised Report for KP0 to KP6 L & T Report for Tower # 108 to 126 Site visit and meetings with AYC for Azizia Bridge Project L & T lab test reports for Access Road works Site visit for RCC Sinoma Schedule of lab test works for L & T tower works Training and supervision of Permeability test for Schlumberger Structural inspection for ABANA building in Mecca Road
ACTIVITIES IN PROCESS Sinopec report for KP7 to KP60 Elevation for Survey department is pending Sinopec report for PK4 to PK37 Additional ERT issues to be resolved Retrieval of PO for AYC for Azizia Bridge Project Permeability test for Schlumberger L & T Report for Turbah Towers Al Fahd report revision for ADA comments Qassim Branch Road Report on process Site inspection report for RCC Sinoma Structural inspection for ABANA building in Mecca Road Follow up Contract deliverance for MEPS
LONG TERM PROJECTS RE wall activities for Azizia Bridge Project