Weekly Status Report 01

Raghu Prakash submitted a weekly progress report to Joseph Ravi covering September 13-19, 2014. During this period, Raghu completed revised reports for Sinopec and L&T projects, visited sites for Azizia Bridge and RCC Sinoma projects, and conducted lab tests. Activities still in process included resolving issues on additional Sinopec and L&T reports, retrieving a PO for Azizia Bridge, ongoing permeability and structural tests, and following up on inspections. Long term projects consisted of RE wall activities for Azizia Bridge.

Uploaded by

Raghu Prakash A
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
68 views

Weekly Status Report 01

Raghu Prakash submitted a weekly progress report to Joseph Ravi covering September 13-19, 2014. During this period, Raghu completed revised reports for Sinopec and L&T projects, visited sites for Azizia Bridge and RCC Sinoma projects, and conducted lab tests. Activities still in process included resolving issues on additional Sinopec and L&T reports, retrieving a PO for Azizia Bridge, ongoing permeability and structural tests, and following up on inspections. Long term projects consisted of RE wall activities for Azizia Bridge.

Uploaded by

Raghu Prakash A
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Page 1 of 1

WEEKLY PROGRESS REPORT


To:
Engr. Joseph Ravi
From:
Engr. Raghu Prakash
Period: September 13, 2014 to September 19, 2014

ACTIVITIES COMPLETED THIS WEEK
Completed Deliverables:
Sinopec Revised Method Statement
Sinopec Revised Report for KP0 to KP6
L & T Report for Tower # 108 to 126
Site visit and meetings with AYC for Azizia Bridge Project
L & T lab test reports for Access Road works
Site visit for RCC Sinoma
Schedule of lab test works for L & T tower works
Training and supervision of Permeability test for Schlumberger
Structural inspection for ABANA building in Mecca Road

ACTIVITIES IN PROCESS
Sinopec report for KP7 to KP60 Elevation for Survey department is pending
Sinopec report for PK4 to PK37 Additional ERT issues to be resolved
Retrieval of PO for AYC for Azizia Bridge Project
Permeability test for Schlumberger
L & T Report for Turbah Towers
Al Fahd report revision for ADA comments
Qassim Branch Road Report on process
Site inspection report for RCC Sinoma
Structural inspection for ABANA building in Mecca Road Follow up
Contract deliverance for MEPS

LONG TERM PROJECTS
RE wall activities for Azizia Bridge Project