Appendix D: Engineering Standards Manual ISD 341-2
Appendix D: Engineering Standards Manual ISD 341-2
Chapter 8 I&C
Rev. 1, 10/27/06
APPENDIX D
INSTALLATION AND CALIBRATION OF INSTRUMENTS GUIDANCE
(PROGRAMMATIC AND FACILITY)
TABLE OF CONTENTS
1.0
PURPOSE .................................................................................................................................... 3
2.0
SCOPE ........................................................................................................................................ 3
3.0
4.0
MATERIALS................................................................................................................................ 5
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
13.0
LEVEL CONSIDERATIONS......................................................................................................... 14
14.0
15.0
16.0
17.0
CALIBRATION .......................................................................................................................... 16
Page 1 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
RECORD OF REVISIONS
Rev
Date
11/17/03
10/27/06
Description
Initial issue.
POC
Mel Burnett,
Gurinder Grewal,
FWO-DECS
FWO-DO
Mike Clemmons,
Kirk Christensen,
FM&E-DES
CENG
Page 2 of 17
OIC
Chapter 8 I&C
Rev. 1, 10/27/06
1.0
PURPOSE
This appendix provides guidance for the mechanical installation and initial calibration of field
installed instrumentation, equipment supports, and associated tubing systems.
2.0
SCOPE
This appendix applies to all I&C systems and devices and may be supplemented with specific
installation and initial calibration requirements provided on design drawings or by other project
specific documents.
2.1
Included
-
2.2
Not Included
-
Installation and/or furnishing electrical raceway, conduit, cable and electrical terminations
Periodic calibration
Installation inspection and documentation of vendor installed instruments
Installation of in-line mounted instruments
Installation of control valves
3.0
3.1
ACRONYMS
ANSI - American National Standards Institute
ASME - American Society of Mechanical Engineers
HVAC - Heating, Ventilation and Air Conditioning
HP - High Pressure
ISA The Instrumentation, Systems, and Automation Society
LP - Low Pressure
P&ID - Process and Instrumentation Diagram
RTD - Resistance Temperature Detector
Page 3 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
3.2
DEFINITIONS
Calibration The systematic process performed to determine outputs of a device corresponding
to a series of values of the variable which the device is to measure, receive or transmit for the
purpose of determining the error of the device compared against a standard and /or adjusting the
device to bring it to the desired value, within a specified tolerance.
Cold Bend Shaping tubing or piping by bending, drawing, stretching, or other stamping
operations without the application of heat.
Design Agency The organization performing the detailed design and analysis of a project or
modification.
Design Authority The person or group responsible for the final acceptability of and changes to
the design of a system or component and its technical baseline (typically the manager of
engineering).
Flaring Increasing the diameter at the end of pipe or tube to form a conical section.
Gauge Glass A glass or plastic tube for measuring liquid level in a tank or pressure vessel,
usually by direct sight.
Impulse Line The line, tubing or pipe, that connects the process to the primary measuring
element of the instrument loop and is part of the process pressure boundary and containment.
Sensing lines and impulse lines are the same.
In-Line Instrument/Device Instrument/device installed in the process piping system (e.g,
control valves, orifice plates, thermowell).
Installation Detail Installation documentation in the form of standards, specifications,
procedures, drawings, and quality inspection plans.
Instrumentation A mechanical, electrical, pneumatic or hydraulic item
(device/component/equipment) which is used for process monitoring or control. This also
includes items such as sample probes and thermowells, which support instrumentation functions.
Line Mounted Instrument Instrument installed in a connection attached to the process piping
system (e.g., temperature indicators, temperature elements, temperature switches).
Local Mounted Instrument Instrument installed locally on a wall, column, floor stand, etc.
(e.g., transmitters, switches, indicators).
Pigtail A 270 or 360 loop in pipe or tubing to form a trap for vapor condensate. Used to
prevent high temperature vapors form reaching the instrument.
Root Valve The first valve located in a sample line after it taps off the process. It is typically
located in close proximity to the sample tap.
Seal Pot Enlarged pipe sections in measurement impulse lines to provide a) a high area to
volume displacement ratio to minimize error from hydrostatic head difference when using large
volume displacement measuring elements, and b) to prevent loss of seal fluid by displacement
into the process. A section of pipe (4 in. diameter) installed horizontally at the orifice flange
union to provide a large area surge surface for movement of the impulse line fluid with
instrument element position change to reduce measurement error from hydrostatic head
difference in the impulse lines.
Page 4 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
Snug Tight Snug tight is a solid connection obtained using standard tools where bolting
hardware has been sufficiently tightened to bring contacting surfaces of the bolted assembly into
solid contact without damaging or distorting the assembly or hardware
Standpipe A vertical tube filled with a liquid.
Thermowell A pressure tight receptacle adapted to receive a temperature sensing element and
provided with external threads or other means for pressure tight attachment to a vessel.
Wet-Leg A liquid filled sensing line in a differential pressure level measuring system.
4.0
MATERIALS
A. Before fabrication all materials should be visually examined for defects.
B. Material should be controlled during construction at all times to ensure that it is identifiable
as acceptable material.
C. Tubing, fittings and valve ends should be sealed to prevent moisture, dirt and foreign matter
from entering the tubing/valves during storage.
D. Material should be compatible with the environment in which it is located. If contact is made
with the process, the material should also be compatible with the measured medium at the
specified operating conditions. Consideration should be given to the affects of corrosion,
abrasion, contamination, and degradation due to excessive pressure or temperature.
5.0
PROCESS TAPS
A. The general location of the process tap with respect to other taps/branches should be shown
on a P&ID. The exact location of process connections may be shown on area piping
composite drawings, piping isometric drawings, HVAC drawings, or the equipment vendor
drawings.
B. The placement of the tap on the process pipe should take into consideration instrument
operability concerns, such as required number of pipe diameters up or downstream of a fitting
/ sensing device. If the tap can perform its function in a number of locations, choose the one
nearest the sensing device.
C. During the placement of the tap, strive for maintenance accessibility of root valves and a
vertical stem installation.
D. The process tap should be located near a pipe support to minimize vibration.
6.0
Page 5 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
Liquid
Gas
H. Instruments should be located such that the sensing lines are as short as practical to minimize
slope requirement problems. Instruments that cannot be connected with proper slope should
be provided with vent or drain points.
Page 6 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
7.0
Sensing lines should have continuous slope to promote their being kept either full or free of
fluid (unless noted otherwise). The preferred slope is 8.3 cm/m (1 inch per foot), however,
2.1 cm/m (1/4 inch per foot) is acceptable. For instruments sensing steam at pressures up to
138 kilo pascals absolute (20 psia), the instrument lines should slope a minimum of 16.7
cm/m (2 inches per foot). Minimum slope will begin after the root valve and terminate at the
instrument valve inlet. The sensing lines may be level through and on each side of a valve
manifold or instrument connection shut off valve for a distance of up to 10 cm (4 inches).
Instrument sensing lines may be level through and on each horizontal leg of a vertically
oriented tee or cross connection for a distance of up to 10 cm (4 inches), and through a
penetration for a total cumulative length of 30 cm (12 inches) outside the ends of each
penetration.
Page 7 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
J.
Bends, rather than tube or pipe fittings, should be used to change the direction of sensing
lines. The cold bending method is advised for all bends. A minimum bend radius of at least
two and one quarter (2 1/4) times the tubing outside diameter should be employed for bends
in stainless steel tubing and copper tubing. The minimum bend radius for capillary tubing,
aluminum, and plastic tubing should be per manufacturer recommendations. Refer to the
LANL Engineering Standards Manual, Mechanical Chapter, for tube bending requirements
and the determination of wall thinning effects.
K. Where fittings must be used and an installation detail document specifies the size and type of
fitting, a combination of fittings of other sizes may be substituted if the specified part is
unavailable or it is more convenient to use the combination. The fittings must, however, be
of the same equivalent type and produce the same or better overall effect. A weld fitting may
replace a threaded or flareless joint; however, a threaded or flareless connection should not be
used if welded fittings are required. Flareless fittings should be installed using the
manufacturers assembly instructions. For compression fittings, refer to LANL Master
Specification 40 0511, Compression Fittings on Copper and Stainless Steel Tubing.
L. For threaded connections of stainless steel to stainless steel, lubrication should be applied to
prevent seizing and galling. Low or no chloride content lubricants should be used with
stainless steel. Although Teflon tape is allowed in many applications, it should not be used as
a sealant or lubricant on threaded instrument connections. The use of compound or lubricant
on threads should consider the potential reaction with either the service fluid or the piping
material.
M. Sensing lines should be blown clear of any foreign material with clean, oil free, dry air or
nitrogen before the system is placed in operation. Demineralized water may be used to flush
tubing, provided the process system to which the tubing is connected will also be flushed or
hydro-tested with water in accordance with applicable construction procedures. Open lines,
fittings or valves should be sealed after being blown clear. Instrument tubing between the
manifold valve and the instrument is not required to be blown down or flushed if visual
inspection is performed prior to final connection and tightening of fittings.
N. Capillary tubes sealed to the instrument by the manufacturer should not be opened or cut
during or after installation unless specifically required by the installation drawing or
manufacturers instruction. Slope requirements do not apply to capillary tubing.
Manufacturers installation requirements, including those relating to minimum bend radius,
should be followed. Excess lengths of capillary tubing should be neatly coiled in protected
enclosures. The maximum amount of unprotected capillary should be no more than 15 cm (6
inches) at any one location, except at capillary enclosures, process connections, instrument
connections, and penetrations. At the entrance and exit of capillary enclosures, process
connections and instrument connections, the maximum unprotected capillary should be 45 cm
(18 inches). Capillaries in trays should be tied down or clamped every three feet. At the
entrance and exit of penetrations, the maximum unprotected capillary should be 30 cm (12
inches).
O. Primary sensing lines at local panels and racks should be neatly arranged with easy access to
test, drain, and vent connections, instruments valves, and manifold. Primary tubing between
the instrument valve or manifold and the instrument should be arranged in accordance with
the vendors instruction and with adequate flexibility to avoid undue strain to the instruments.
Page 8 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
8.0
9.0
Material
Wall
Thickness
All
91 cm (3 ft.)
3/8
All
1.5 m (5 ft.)
1/2
All
1.5 m (5 ft)
3/4
All
1.8 m (6 ft.)
All
2.1 m (7 ft.)
Capillary
Tubing
All
Page 9 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
F. Anchors, consisting of connections to root valves, instrument valves, or any type of clamp
that when fastened to tubing prevents axial movement of the tube, should be placed in each
straight run of tubing that requires a support. The connection to the instrument is not
considered an anchor point for this purpose.
G. Sensing lines should be supported with guides wherever a longitudinal movement along the
line axis is involved due to temperature, vibration, and related ambient conditions. When two
or more tubes are attached to a single support, each line should be guided so that it can move
axially independent of the others, unless the support is designed specifically as an anchor. It
will always be assumed that each tube expands and contracts individually and independent of
all others.
H. For portions of a sensing line run which may be subjected to temperatures greater than 60C,
the following limitations apply:
1. Anchors should be used only where the axial movement cannot be controlled easily
by other means.
2. Every effort should be made to support vertical runs and to control end movement of
horizontal runs by thoughtful placement of guides near turns and offsets
I.
All fasteners should be at least snug tight. Bolted Fasteners, as a minimum, should have the
end of a bolt to be at least flush with the outer surface of the nut. In the event that vendor
instruction, design drawings or specification specify torque requirements, the vendor
instruction shall take precedence. The torque values below should be used in the absence of
specified values.
Bolt Diameter
Required Torque
Less than
Snug Tight
1/4
5/16
3/8
1/2
5/8
3/4
7/8
* Nm = Newton Meter
Chapter 8 I&C
Rev. 1, 10/27/06
2. As a minimum, high point vents in liquid service sensing lines should be accessible
by means of a portable ladder. Vent and drain valves in systems with normal
operating temperatures greater than 49C (120F) should be labeled with an
appropriate warning tag. Hazardous fluid systems, including cryogenics, should also
be labeled with an appropriate warning.
3. All high points in liquid service sensing lines should have a valve vent connection
located outside high radiation zones at an accessible elevation (if necessary at
elevations accessible by means of a ladder). Vent valves should be located such that
they are at the high point of the instrument line.
4. The use of hot blowdown for instrument lines should be avoided. Vents should be
used for releasing trapped air, back flushing, or pre-filling of tubing systems. Vents
should not be used for blowdowns. Lines subjected to temperatures above 93C
(200F) should be designed for thermal expansion.
5. All vent and drain valves should be capped, plugged or have short pieces of tubing
installed on the downstream side, unless specifically routed to a drain point. All drip
legs should be a minimum of 61 cm (24 inches).
6. An accessible calibration connection should be provided between the instrument and
its nearest isolation valve. The connection should be easily accessed for in-situ
instrument calibration and servicing. This connection may be a vent or drain point
provided that isolation from the process is acceptable. All such connections should
be capped or plugged when not in use.
B. Root Valves
1. I&C design responsibility should begin at the outlet of the root valve.
2. When a root valve is located in a high radioactive or hazardous area, an accessible
isolation valve should be provided.
3. The root valve should be installed clear of main line insulation in a horizontal or
vertical orientation as required by specific conditions. Process connections and root
valves should be located so that they are accessible.
4. For adapting stainless steel to main line class piping, socket welding should not be
performed when the service temperature at a dissimilar weld is greater than 100C
(212F). The methods of welding dissimilar materials in services above 100C
(212F) should be provided by the Design Authority.
C. Isolation Valves
1. The instrument isolation valve is defined as the valve nearest the instrument.
2. A higher rated valve may be substituted for a lower rated valve of the same type (i.e.,
gate, globe, ball, etc).
Page 11 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
3. An instrument line with a remote mounted instrument should have at least two valves
between the process tap and the instrument. The root valve and instrument isolation
valve will suffice, with the instrument isolation valve within reach of the instrument.
For rack or panel-mounted instruments, the panel valve located at the panel process
tap and the isolation valve located at the bulkhead will suffice. For locally mounted
instruments, with the root valve within reach of the instrument, an additional
isolation valve is not required.
4. Isolation valves should be located just beyond a penetration on the non-radioactive
side of a shield wall. This will allow instrument maintenance during plant operation
when the root valve is inaccessible.
D. All instrument valves (manifolds, vents, drains, isolations, etc.) in instrument process and
sample tubing installations should be supported and considered a 3-directional anchor.
Page 12 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
Page 13 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
2. Condensate chambers, also known as seal pots, should be installed to ensure the
instrument sensing lines are filled with liquid. Water or other coolants can be applied
to the seal pots to speed the condensing process. The pipe from a process connection
to a seal pot should be insulated for process fluids hotter than 121C (250F).
3. The sensing lines to differential-pressure instruments should be installed to maintain
the condensate legs at an equal height. A pair of seal pots should be at the same
elevation 0.6 cm (1/4 inches) and as high or higher than the highest process
connection.
4. A pigtail or wet-leg should be considered to protect an instrument that may be subject
to high process temperatures. The pigtail should be located close to the instrument.
A wet-leg should have a filling connection, usually at the top.
5. If there is a concern of moisture freezing in the sensing line, a diaphragm seal and
low-temperature compatible fill fluid should be considered.
E. Pressure calibration/test points should be accessible. If the root valve is not accessible
(accessible defined as not over 1.8 m (6 feet) from floor, grating, or platforms), tubing and an
instrument valve should be installed at a convenient remote location.
Page 14 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
Page 15 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
C. Tubing leaks in low-pressure systems may not be detectable through pressure tests.
Additional leak tests should be considered for such systems.
D. The instrument impulse tubing should always be tested to the same pressure as the process
pipe system unless otherwise noted in the design specification. Test pressures can only be
revised/waived by the Design Authority. Instrument air supply tubing should be tested at the
same test pressure as the headers test pressure.
E. The following attributes should be either inspected or functionally tested, and documented as
appropriate for fabrication and installation. The responsible technical and quality personnel
must determine the required detail and oversight that is necessary based on the safety
classification of the I&C equipment / system.
1. Verification of documentation from Construction Engineering
2. Sensing Line Protection
3. Sensing Line Slope
4. Drain Connections
5. Connection Lubricant
6. Condensate Pot Elevation
7. Stilling Well Location
8. Mounted Panel & Racks
9. Thermowell Installation
10. Bends in Sample Lines
11. Instrument Location
12. Instrument Orientation
13. Sample Tubing Supports
14. Material Identification
15. Instrument Tubing Supports
16. Panels & Racks Location
17. Blowdown / Flushing
18. Pressure Testing
17.0 CALIBRATION
A. Initial calibrations should be performed in accordance with the Laboratory Calibration
Program.
B. As part of the initial calibration, the instrument details (i.e. manufacturer, model number,
size, material of construction, range, etc.) should be verified to be in agreement with the
design specification.
Page 16 of 17
Chapter 8 I&C
Rev. 1, 10/27/06
C. The component under calibration should be subject to input variations at a number of test
points ascending and descending to sufficiently verify its response over the full span. The
following test points should be used when no other specific direction is given in the
applicable procedure or work document.
1. Switches Trip and reset. Switches for which no reset value is specified or which
have fixed dead band, the reset value should be documented on the calibration record
for reference.
2. Valves Full open/Full closed; modulating valves should also be verified at midtravel (50%)
3. Mechanical and Electrical Indicator and/or Transmitter at or near (within 10%) 0,
20, 40, 60, 80, and at or near 100% of span or reading increasing and 80, 60, 40, 20
and at or near 0% of span or reading decreasing.
Page 17 of 17