Project Management Project Management: Chapter-6
Project Management Project Management: Chapter-6
Project Management
Chapter-6
Developing a Project Plan
Chapter-6
Developing a Project Plan
Worth Doing?
Chapter-6
Developing a Project Plan
Chapter-6
Developing a Project Plan
Duration is in
Weeks
Chapter-6
Developing a Project Plan
Terminology
An activity is an element in the project that consumes time. It
is represented as a node (box).
Merge activities have more than one activity
immediately preceding it. M is a merge activity.
Burst activities has more than one activity
immediately following it. X is a bust activity.
Parallel activities can take place at the same
time but do not have to take place at the same
time. In this case, J-K-L are shown as parallel
activities.
Chapter-6
Developing a Project Plan
Terminology
Network path is a sequence of connected dependent
activities. In this example, activities A-C-F-G make up one
network path. How many others are there?
Chapter-6
Developing a Project Plan
Terminology
Critical path is the network path with the longest duration.
When an activity on the critical path is delayed, the project is
delayed that same amount of time. Given the example below,
identify the critical path.
20
20
18
30
Chapter-6
Developing a Project Plan
Chapter-6
Developing a Project Plan
Chapter-6
Developing a Project Plan
Chapter-6
Developing a Project Plan
Chapter-6
Developing a Project Plan
Chapter-6
Developing a Project Plan
20
20
18
30
A-B-E-H
A-B-F-G-H
A-C-E-H
A-C-F-G-H
A-D-F-G-H
48
35
50
47
59*
Chapter-6
Developing a Project Plan
Activity-6 as
free slack of 15
time units.
Activity-4 has
free slack of 18
time units.
Chapter-6
Developing a Project Plan
Chapter-6
Developing a Project Plan
Laddering
1. Stated earlier, a finish-to-start relationship states that the activity
must be 100% completed before advancing to the next activity.
If that activity has a long duration and if that activity has a delay,
that activity can be broken down into segments using laddering
so that the following activity can begin sooner without delaying
work.
2. Laying pipe requires that the trench must be dug, pipe laid, and
the trench refilled. If the pipeline is 1-mile long, it is not
necessary to dig on mile of trench before pipe laying can begin.
3. It is also true that once the pipe is in place, refilling the trench
can also begin.
Chapter-6
Developing a Project Plan
Laddering
Chapter-6
Developing a Project Plan
Use of Lags
When an long duration activity delays the start of finish of the next
(or successor) activity, the network normally breaks the activity into
smaller activities to avoid the long delay of the successor activity.
Using lags can avoid such delays and reduce the network detail.
Lags can be used to constrain the start and finish of an activity.
During this lag, no work can occur or be charged
to account code.
The project manager normally must justify lags.
Chapter-6
Developing a Project Plan
Chapter-6
Developing a Project Plan
Chapter-6
Developing a Project Plan
Beta Testing
Chapter-6
Developing a Project Plan
Hammock Activities
1. Hammock activities derives its name because this activity spans
over a segment of a project. They are used to identify fixed
resources or costs over a segment of a project.
2. Hammock activities are very useful in assigning and controlling
indirect project costs.
3. Hammock activities are determined after the network plan is
drawn. See Snapshot from Practice pg. 183.
Chapter-6
Developing a Project Plan
8
Start
7
F
Finish
D
6
Chapter-6
Developing a Project Plan
Start
17
15
11
13
14
Finish
Chapter-6
Developing a Project Plan
15
17
Start
Finish
22
E
12
F
Chapter-6
Developing a Project Plan
C
4
D
1
E
3
B
6
I
2
F
1
G
5
H
1
Chapter-6
Developing a Project Plan
Activity, 161
Activity-on-Node, 160
Sensitivity, 170