Shift Length Short Breaks Meal Breaks Downtime Ideal Run Rate Total Pieces Reject Pieces Prodution Data

The document contains production data from a shift including shift length, breaks, run rate, pieces produced, rejects, downtime, and OEE calculations. It shows the calculation of availability, performance, quality, and overall OEE, which was 88.81%. The standard lean OEE factors and the current OEE percentages are also displayed. The document concludes with definitions of calendar time, available time, operating time, downtime, net operating time, speed losses, valuable operating time, quality losses, and planned downtime.

Uploaded by

Mustaffa Fajra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
122 views8 pages

Shift Length Short Breaks Meal Breaks Downtime Ideal Run Rate Total Pieces Reject Pieces Prodution Data

The document contains production data from a shift including shift length, breaks, run rate, pieces produced, rejects, downtime, and OEE calculations. It shows the calculation of availability, performance, quality, and overall OEE, which was 88.81%. The standard lean OEE factors and the current OEE percentages are also displayed. The document concludes with definitions of calendar time, available time, operating time, downtime, net operating time, speed losses, valuable operating time, quality losses, and planned downtime.

Uploaded by

Mustaffa Fajra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Prodution Data

Shift Length
Short Breaks
Meal Breaks
Downtime
Ideal Run Rate
Total Pieces
Reject Pieces

minutes
minutes
minutes
minutes
pieces per minutes
pieces
pieces

Support Variable
Planned Production Time
Operating Time
Good Pieces

Calculation
Shift Length - Breaks
Planned Production Time - Downtime
Total pieces - reject Pieces

Calculated Data
480 - 60 minutes
420 - 47 minutes
19,271 - 423 pieces

Results
420 minutes
373 minutes
18,848 pieces

OEE Factor
Availability
Performance
Quality
Overall OEE

Calculation
Operating Time/Planned Production Time
(Total Pieces/Operating Time) / Ideal Run Rate
Good Pieces / Total Pieces
Availability x Performance x Quality

Calculated Data
373 / 420 minutes
(19,271 pieces / 373 minutes) / 60 pieces per minute
18,848 / 19,271 pieces
0,8881 x 0,8611 x 0,978

OEE (%)

OEE Factor Standard Lean Our Current OEE


Availability
Performance
Quality
Overall OEE

Action

Calendar Time (A)


Available Time (B)
Operating Time (C)
Unplanned Downtime
Net Operating Time (D)
Speed Losses
Valuable Operating Time (E) Quality Losses

Planned Downtime