Shift Length Short Breaks Meal Breaks Downtime Ideal Run Rate Total Pieces Reject Pieces Prodution Data
Shift Length Short Breaks Meal Breaks Downtime Ideal Run Rate Total Pieces Reject Pieces Prodution Data
Shift Length
Short Breaks
Meal Breaks
Downtime
Ideal Run Rate
Total Pieces
Reject Pieces
minutes
minutes
minutes
minutes
pieces per minutes
pieces
pieces
Support Variable
Planned Production Time
Operating Time
Good Pieces
Calculation
Shift Length - Breaks
Planned Production Time - Downtime
Total pieces - reject Pieces
Calculated Data
480 - 60 minutes
420 - 47 minutes
19,271 - 423 pieces
Results
420 minutes
373 minutes
18,848 pieces
OEE Factor
Availability
Performance
Quality
Overall OEE
Calculation
Operating Time/Planned Production Time
(Total Pieces/Operating Time) / Ideal Run Rate
Good Pieces / Total Pieces
Availability x Performance x Quality
Calculated Data
373 / 420 minutes
(19,271 pieces / 373 minutes) / 60 pieces per minute
18,848 / 19,271 pieces
0,8881 x 0,8611 x 0,978
OEE (%)
Action
Planned Downtime