CIVL 392 - Chapter ddd2 - Earthmoving Materials and Operations
CIVL 392 - Chapter ddd2 - Earthmoving Materials and Operations
AND OPERATIONS
Introduction to Earthmoving
Equipment Selection
The major criterion in selecting an equipment
is the ability of equipment to do the job. This
can be specified as:
Production of Earthmoving
Equipments
Production
In calculating the job efficiency for cycles per hour
there are two methods:
Good
Fair
Poor
Excellent
0.84
0.81
0.76
0.70
Good
0.78
0.75
0.71
0.65
Fair
0.72
0.69
0.65
0.60
Poor
0.63
0.61
0.57
0.52
Job conditions
Job conditions are the physical conditions of a
job that they affect production rate (not
including the type of material involved). They
include:
Soil Conditions
There are three conditions that the soil may exist:
Swell
Weight/bank volume
Swell (%) (
1) 100
Weight/loose volume
Example
Solution :
Swell (
2800
1) 100 = 40%
2000
Shrinkage
Weight/bank volume
Shrinkage (%) = (1 ) 100
Weight/Compacted volume
1
Load Factor =
1 + Swell
Example
Problem: A Soil Weighs 1163kg/Lm3,
1661kg/Bm3 and 2077kg/Cm3,
a) Find load factor and shrinkage factor.
b) How many bank Bm3 and compacted
Cm3 are contained in 593,300
Lm3 of
this soil.
Solution
a)
Load Factor =
1163
= 0.70
1661
1661
Shrinkage Factor =
= 080
.
2077
Example
A soil weighs 1471 kg/m3 loose, 1839 kg/m3 in place
and 2090 kg/m3 compacted.
Solution
a-
Swell (%) (
Weight/bank volume
1) 100
Weight/loose volume
1839
Swell (%) (
1) 100 25%
1471
Shrinkage (%) = (1 -
Weight/bank volume
) 100
Weight/Compacted volume
1839
) 100 12%
2090
Solution
Load Factor =
Load Factor =
1
1 + Swell
1
0.80
1 + 0.25
Solution
Compacted volume = (bank volume x shrinkage factor)
Bank Volume =
5227272Bm 3
Shrinkage_ factor
0.88
BankVolume 5227272
Losse _ Volume
6534091Lm 3
LoadFactor
0.80
Spoil Banks
In earthwork planning it may be necessary to
determine the size of the pile of soil that will be
created by excavation. If the pile of material is long in
relation to its width, it is referred to as spoil bank. If
the material is dumped from a fixed position, a soil
pile is created which has a conical shape. To
determine the dimensions of spoil banks or piles, it is
first necessary to convert the volume of excavation
from in-place to loose conditions. Angle of repose of
soil is the angle that the sides of a spoil bank or pile
naturally form with the horizontal surface when the
excavated soil is dumped onto the pile.
B tanR
H=
2
Where:
B: base width (m)
H: pile height (m)
L: pile length (m)
R: angle of repose (deg)
V: pile volume (m3)
D
H = tan R
2
Material
Clay
35
32
37
Gravel
35
Sand, dry
25
Sand, moist
37
Example
Problem:
Find the base width and height of a
triangular spoil bank containing 76.5 Bm3
if the pile is 9.14m, the soils angle of
repose is 37, and its swell is 25 %.
Solution
Loose volume=76.5 x 1.25=95.6m3
4V
B=(
)1/2
L tanR
B tanR
H=
2
4 95.6
1/2
Base width = (
)
= 7.45m
9.14 tan 37
7.45
Height =
tan 37 = 2.80m
2
Example
Problem:
Find the base diameter and height of a
conical spoil pile that will contain 76.5
Bm3 of excavation if the soils angle of
repose is 32 and its swell is 12%.
Solution
Loose volume=76.5 x 1.12=87.5m3
7.64V 1/ 3
D=(
)
tan R
D
H = tan R
2
7.64 85.7 1 / 3
Base diameter = (
) 10.16m
tan 32
Height =
10.16
tan 32 3.17m
2
Example
Solution
B(
4V 1/ 2
4 section _ area L 1/ 2
4 section _ area 1/ 2
) (
) (
)
L tan R
L tan R
tan R
4 3.12
B
tan 35
1/ 2
4.22m
1.478m
2
2
Sand: material smaller than gravel but larger than 0.07 mm (No. 200
sieve).
Silt: particles passing No. 200 sieve but larger than 0.002 mm.