Art Montemayor
Air Separation
expanders motor generator is unlocked and the circuit is activated. All lubrication
systems are confirmed.
The air compressor is started up by activating the electrical starter to the
compressors motor and the unit is allowed to free-wheel, blowing air through
the interstage drains and the discharge vent. After confirming that the compressor
is operating properly and there are no problems with lubrication and instruments,
the drains are slowly closed one-by-one in the order of increasing stages. The
discharge vent valve is the last to be slowly closed and the compressors discharge
is allowed to enter the adsorption purification system while the entire discharge
system increases up to operating pressure. The discharge pressure is kept at the
operating level using the expansion valve on the HP column.
After ensuring that the air compressor is operating normally and feeding the
purification system and the HP column in a controlled, steady state, the turbo
expander is put on stream by slowly opening the suction block valve while also
throttling the HP column expansion valve to keep the compressor discharge
pressure steady at the operating level. After ensuring that the turbo expander is
running OK and its discharge temperature is slowly decreasing, the majority of the
compressors discharge is sent to the expander by throttling on the HP column
expansion valve. This is done for accelerating the cool down and efficient buildup
of crude oxygen liquid level in the HP column.
The above procedure step is maintained until the liquid level in the sump of the HP
column reaches maximum design level and the expansion valve on the LP column
is slowly opened to allow the crude oxygen from the HP column to cool down the
LP column. This procedure is continued until there is a liquid level built up in the
sump of the LP pressure column, at which time the feed to the turbo expander is
reduced while opening the HP expansion valve. Purity samples are taken routinely
during this time to confirm the established stream purities especially the purities
of the crude and pure oxygen.
As soon as established purities are confirmed the argon side column is put on
stream by opening the feed valve off of the LP column to the argon column.
Stream purity samples are continuously taken and the regeneration of the idle
adsorption bed is carried out during this time. Adsorbent regeneration can
commence as soon as there is 99% waste nitrogen gas available from the column.
Once design stream purities are established and liquid levels are controlled and
held to a constant level, the transfer of product oxygen, nitrogen, and argon can
proceed on to their respective storage tanks.