The flow chart outlines the process for roof top net metering with a solar panel installation in three key steps:
1) Downloading and submitting an application form along with payment to register for technical feasibility assessment.
2) Upon approval, the consumer selects an empaneled supplier to install a solar panel and submits payment to receive an order.
3) After installation, the consumer submits a work completion report to replace the old meter with a net meter and close out the work order for billing.
The flow chart outlines the process for roof top net metering with a solar panel installation in three key steps:
1) Downloading and submitting an application form along with payment to register for technical feasibility assessment.
2) Upon approval, the consumer selects an empaneled supplier to install a solar panel and submits payment to receive an order.
3) After installation, the consumer submits a work completion report to replace the old meter with a net meter and close out the work order for billing.
Download application form from www.tssouthernpower/Solar
Rooftop Netmetring/Application Form
Obtain DD of Rs. 1000/- from any Scheduled bank in favor of TSSPDCL
Fill the application & submit at concern CSC/ICSC center along with DD, 2 Nos self-addressed stamped envelope and latest electricity bill
Obtain the Acknowledgment from CSC operator with unique
registration number for further reference
Application automatically forward to ADE/op login for technical
feasibility
Technical feasibility report should be approved by ADE/Op with in
10 days from the date of registration after site inspection
Data will flow to SAP for preparation of
estimation
SMS Alert and email will be
received by consumer about Technical feasibility
ADE prepares estimate & approve in SAP
with in 5 days Consumer can approach empaneled suppliers for installation of solar panel available in www.tssouthernpower.com/ www.nedcap.gov.in website
Amount to be paid by consumer will sent
to CSC from SAP
Consumer will get SMS alert about
Amount to be paid
Consumer should Obtain DD from
scheduled bank and submit at CSC/ICSC Payments will sent to SAP after entry of DD details in CSC Order will be released after receipt of payment from CSC
After completion of site work,
consumer should submit work completion report and agreement (Available at TSSPDCL website) at CSC/ICSC center and obtain acknowledgment
release of order with in 5 days SMS Alert will sent to consumer about meter drawl ADE Should inspect the site and replace the old meter with NETMETER and update the test report/ Meter change report in CSC login with in 5 days