MAJULINQWindow Slicing Method For Assessment of Number of Days Entitlement For EOT

This document summarizes two window slicing analyses for entitlement to extensions of time (EOT) for the completion of structural works at two zones of a building. For Zone 5, the original completion date was February 11, 2011 but works were delayed until March 13, 2011 due to earlier works at that zone. This entitled the project to 28 days of EOT. For Zone 6, revised drawings were received on October 14, 2010, delaying completion from the original date of March 2, 2011 until March 9, 2011. This entitled the project to 8 days of EOT.

Uploaded by

Jamruz Jamil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views

MAJULINQWindow Slicing Method For Assessment of Number of Days Entitlement For EOT

This document summarizes two window slicing analyses for entitlement to extensions of time (EOT) for the completion of structural works at two zones of a building. For Zone 5, the original completion date was February 11, 2011 but works were delayed until March 13, 2011 due to earlier works at that zone. This entitled the project to 28 days of EOT. For Zone 6, revised drawings were received on October 14, 2010, delaying completion from the original date of March 2, 2011 until March 9, 2011. This entitled the project to 8 days of EOT.

Uploaded by

Jamruz Jamil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Assessment for

EOT Entitlement
Window Slicing Approach with CPM Methodology

ICP804: Project Planning, Monitoring & Control

WINDOW SLICING NO. 1: EoT Entitlement for B2


at Zone 5 (Podium)

15/06/1
3

ORIGINAL Site Commencement

Revised site possession


15/08/2013
1 day
28/02/1
1
Original Float = 91 days
(TF = 0 day on
13/02/11)

22/11/1
0

13/02/1
1

EOT Entitlement =
28 Days

14 days original completion


period for B2 beams & slab
at Zone 5 (based on Original
WP)
13/03/1
1

22/03/1
1

ACTUAL B2 Beams & Slab @ Zone


5

Summary of EoT Claim for B2 at


Zone 5:

Duration = 13th Feb 2011 to 13th


Mar 2011
No. of Days
= 28 days

WINDOW SLICING NO. 2: EoT Entitlement for B2


at Zone 6 (Podium)

06/10/1
0

ORIGINAL B2 Beams & Slab @


Zone 6

9 Days

Kitchen Detail Level B2


Section A-A, B-B & C-C
14/10/1
received Status A: B2 slab
0
works at Zone 5 clear to
resume works
28/02/1
1
Original Float = 100
02/03/1
days
1
(TF = 0 day on
02/03/11)
9 days original completion
period for B2 beams & slab
at Zone 6 (based on Original
WP)

09/03/1
1

EOT Entitlement =
8 Days

04/10/1
0

ACTUAL B2 Beams & Slab @ Zone


6

30/03/1
1
(Complete
B2
Beams & Slab at
Kitchen Area)

Summary of EoT Claim for B2 at


Zone 6:

Duration = 2nd Mar 2011 to 9th


Mar 2011
No. of Days
= 8 days