Optimization of Blasting Parameters in Opencast Mines 06
Optimization of Blasting Parameters in Opencast Mines 06
IN OPENCAST MINES
A THESIS SUBMITTED IN PARTIAL FULFILLMENT OF THE
REQUIREMENTS FOR THE DEGREE OF
BACHELOR OF TECHNOLOGY
IN
MINING ENGINEERING
BY
MANMIT ROUT
&
CHINMAY KUMAR PARIDA
By
MANMIT ROUT
&
CHINMAY KUMAR PARIDA
Under the Guidance of
DR. H. B. SAHU
CERTIFICATE
This is to certify that the thesis entitled Optimization of Blasting Parameters in Opencast
Mines submitted by Sri Manmit Rout (Roll. No.: 10305019) and Sri Chinmay Kumar Parida
(Roll. No.: 10305017), in fulfillment of the requirements for the award of Bachelor of
Technology Degree in Mining Engineering at the National Institute of Technology, Rourkela
(Deemed University) is an authentic work carried out by him under my supervision and
guidance.
To the best of my knowledge, the matter embodied in the thesis has not been submitted to any
other University/ Institute for the award of any Degree or Diploma.
Date:
(Dr. H. B. Sahu)
Asst. Professor
Department of Mining Engineering
National Institute of Technology
Rourkela
ACKNOWLEDGEMENT
Date:
Manmit Rout
CONTENTS
Page No.
CHAPTER 1:
INTRODUCTION
1-3
CHAPTER 2:
LITERATURE REVIEW
4-8
CHAPTER 3:
CHAPTER 4:
CHAPTER 5:
CHAPTER 6:
CHAPTER 7:
9-22
3.2 Blasting
23-29
30-40
41-45
45-48
52-54
54-55
55-58
59
60
61
65-66
6.2 Conclusion
67
68
REFERENCES
69-71
ABSTRACT
Drilling and blasting are the major unit operations in opencast mining. Inspite of the best
efforts to introduce mechanization in the opencast mines, blasting continue to dominate the
production. Therefore to cut down the cost of production optimal fragmentation from properly
designed blasting pattern has to be achieved. Proper adoption of drilling and blasting can
contribute significantly towards profitability and therefore optimization of these parameters is
essential.
Introduction
Rock breaking by drilling and blasting is the first phase of the production cycle in
most of the mining operations. Optimization of this operation is very important as the
fragmentation obtained thereby affects the cost of the entire gamut of interrelated mining
activities, such as drilling, blasting, loading, hauling, crushing and to some extent grinding.
Optimization of rock breaking by drilling and blasting is sometimes understood to mean
minimum cost in the implementation of these two individual operations. However, a
minimum cost for breaking rock may not be in the best interest of the overall mining system.
A little more money spent in the rock-breaking operation can be recovered later from the
system and the aim of the coordinator of the mining work should be to achieve a minimum
combined cost of drilling, blasting, loading, hauling, crushing and grinding. Only a balance
sheet of total cost of the full gamut of mining operations vis--vis production achieved can
establish whether the very first phase- rock breaking- was optimum financially; leaving
aside factors of human safety.
An optimum blast is also associated with the most efficient utilization of blasting energy
in the rock-breaking process, reducing blasting cost through less explosive consumption and
less wastage of explosive energy in blasting, less throw of materials, and reduction of blast
vibration resulting in greater degrees of safety and stability to the nearby structures.
Development of a Blast Optimization Model
Selection of proper explosive in any blasting round is an important aspect of optimum blast
design. Basic parameters include VOD of explosive (m/s), Density (g/cc), Characteristic
impedance, Energy output (cal/gm), and Explosive type (ANFO, Slurry, Emulsion etc.).
However, all these parameters can not be taken for optimizing the blasting method
successfully. Some of the parameters are taken for minimizing the blasting cost. These cost
reduction and optimum blast design parameter will give an economical result. The parameters
are
i.
ii.
iii.
iv.
Methodology
The study of the various parameters of blasting suggests that the powder factor should be
constant as per the requirement. The number of holes desired as per the explosive, the drill
i
hole diameter as available and the cost of explosive are kept as input. The spacing, bench
height, burden, charge per hole as depending on the previous parameters can be calculated.
From the different input and calculated parameters the total cost of the method is calculated
and the least expensive method is selected as the optimized model.
Blasting related information were collected from three different mines of Mahanadi Coalfields
Ltd.(MCL) for implementation of the optimization model. A program was designed using
visual basic on .net platform taking the above parameters into consideration to select the
optimized model. It was observed that the program gives satisfactory results. A sample
output of the program is as presented below:
Conclusion
The blast optimization model has been developed with simple methodologies which can be
adopted by the mining industry to compare the explosive costs and achieve better blasting
results and. The model developed is a user friendly one, since by keeping the powder factor
and number of choices of explosives available as constant and by varying the parameters like
drill hole diameter, number of holes and cost of explosives one can compare the explosive
performance and accordingly take a decision to select the proper type of explosives for
blasting.
It may be noted, that the model has been developed based on case studies of three different
mines of MCL, and it can be modified with collection of information from a large number of
mines.
References
Nanda, N.K. (2003), Optimization of mine production system through operation research
techniques, 19th World Mining Congress,New Delhi, November, pp.583-595.
Pal Roy, P. (2005), Terms and parameters influencing mine and ground excavations, Rock
blasting effects and operations, pp. 17-22,
ii
LIST OF FIGURES
Figure No.
Page No
3.1
Drag Bit
13
3.2
14
3.3
Button Bit
15
3.4
17
3.5
Blast-hole Drill
18
3.6
20
3.7
27
3.8(a) :
28
3.8(b) :
28
3.9
29
3.10
29
3.11
29
3.12
35
5.1
51
LIST OF TABLES
Table No.
Title
Page No
5.1
55-56
5.2
56-57
5.3
58
iii
CHAPTER 1
INTRODUCTION
CHAPTER - 1
INTRODUCTION
Mining industry is the backbone for the development of any nation. In mining the basic aim is to
achieve maximum extraction of minerals keeping in view the environmental, economic and lease
constraints. With the advancement of civilization, the requirement of different minerals has
increased manifold to meet this demand. There is an upsurge in interest and action in opencast
mining because of the improved productivity, recovery and safety of mining operation.
Improvement in production has been achieved with the help of large capacity opencast
machineries, continuous mining system with improved design, development of modern
generation, explosives and accessories, process innovations and application of information
technologies and increased adoption of computerized mine planning and control.
Drilling and blasting are the major unit operations in opencast mining. Inspite of the best
efforts to introduce mechanization in the opencast mines, blasting continue to dominate the
production. Explosives contribute currently about 5% of the direct cost of production and if the
aggregate cost of drilling and blasting is taken together, this may go as high as 30% of direct cost
of production. Therefore to cut down the cost of production optimal fragmentation from properly
designed blasting pattern has to be achieved. Fragmentation of rock represents one of the key
problems in maximizing economic efficiency for exploitation of mineral deposits. Large
fragments adversely affect the loading and hauling equipments and increase the frequency of
sorting of oversize boulders and secondary blasting, thereby increasing the cost of mining. Fines
are also undesirable as indicates excessive explosive consumption. It is therefore desirable to
have a uniform fragment distribution, avoiding both fines and oversized fragments to overall cost
of mining to optimum level.
Drilling and blasting cost in any project can be as high as 25% of the total production
cost. Inspite of this the design and implementation of a blast is not given that much priority in
our country. Proper adoption of drilling and blasting can contribute significantly towards
profitability and therefore optimizations of these parameters are essential.
Optimization means achieving the best i.e. to achieve maximum or minimum value of the
operating parameters. Optimization of blast is dependent on a host of complex factors related to
the rock, explosive, initiation, drill-hole parameters and their layout. The present work is a step
in the direction of developing a suitable blast model, with simple methodologies which can be
adapted by the mining industry to achieve better blasting results.
CHAPTER 2
LITERATURE REVIEW
CHAPTER - 2
LITERATURE REVIEW
Verma (1993) advocated that performance rating of explosives has become a primary need
because of the growing requirement and competition. In experiments, the usually accessed
parameters are the strength though there is no such parameter still to compare the performance
index of the explosives. At present, the only way out is to compare the lab results and the
company or manufacturers claimed results about the explosive properties. The ratio must be 1
but due to factors it must be close to it, if not equal. By the ratio the explosives can be classified
into different categories.
Biran (1994) observed that many empirical formulas have been used over 200 years for selection
of proper charge size and other parameters for good fragmentation. But for blasting efficiency
and uniform fragmentation, there should be uniform distribution of explosives in holes. The
blasted material heap should have more throw for loaders and hydraulic shovels and more heave
for rope shovels and loaders. For good economic blasting the holes should not be deviated from
the plan. It requires meticulous planning on the use of site mixed slurry explosives, stemming of
holes with mechanical means and blasting after pilot blasting of holes to access various details.
Adhikari and Venkatesh (1995) suggested that drilling and blasting cost in any project can be
as high as 25% of the total production cost. So the design and implementation of a blast must be
given some priority. By the blast design parameters optimization the profitability would increase.
For this the study of the existing practice was done followed by pre-blast, in-blast, and post-blast
survey. Then the data were analyzed and a model was interpreted. All the parameters were then
compared and worked on for the best suiting result. They observed that to achieve a certain
degree of refinement in blast design, scientific and systematic approach is needed. With
instruments like VOD probes, laser profiling system, etc the monitoring becomes easier, efficient
and cost effective.
Singh and Dhillon (1996) pointed out that to optimize the cost in an opencast mine, there is a
need to optimize the drilling and blasting parameters. Incase of blasting operations; for
optimization of explosives, the first step is to optimize the booster cartridges and cast boosters
5
along with column explosives. The booster for initiation of the whole column of the explosive
must be reduced by experimentation. It saves a large share of expenditure. By the use of a total
top initiation system instead of a down the hole for bottom initiation reduces the use of
detonating fuse. By use of air decks, the explosive cost can be saved to some extent. By
introduction of top-initiation system and non-electric initiation the desensitization effect has been
completely eliminated, thus enabling optimum utilization of explosive energy.
Uttarwar and Mozumdar (1996) studied the blast casting technique that utilizes explosive
energy to fragment the rock mass and cast a long portion of it directly into previously worked out
pits. The technique depends on factors like bench height and helps in efficient trajectory of
thrown rock and so in the height to width ratio. This technique is most effective with explosives
that maximize ratio of heave energy to strain energy. Higher powder factor supports the
technique. Optimal blast-hole diameter and inclination, stemming and decking method used, the
burden to spacing ratio, delay intervals and initiation practices help in effective blasting.
Thote and Singh (1997) observed that the blasting results of fragmentation are influenced by
various factors. For example, rock strength decreases the fragmentation, it is also affected by the
blastability index, porosity and the geological disturbances. In case of discontinuities, the shock
wave gets reflected causing higher attenuation at a smaller area. This leads to boulder formation.
All these factors need a detailed study and in-field experiments to judge the blasting parameters
and decide the quantity of explosives to be used to avoid boulder formation or enable good
fragmentation.
Karyampudi and Reddy (1999) observed that the toe formation has always been a drawback in
the opencast mines. There are certain factors that result in toe formation like the burden and
spacing, size of drill block, condition of drill holes and condition of face before blasting;
charging of blast holes and the type of initiation are the factors that can be avoided. But the strata
variation, fractured strata and watery holes are unavoidable. So it should be tried to achieve a
drill block where the unavoidable factors are non-existent. It is marked with crest, burden,
spacing. They were of the view that blast holes must be charged as per proper charging pattern
with appropriate percentage of booster, base and column and holes by charging from bottom
initiation leads to toe-less blasting.
Pal and Ghosh (2002) studied the optimization of blasting pattern implemented at Sonepur
Bazari opencast project for control of ground vibration, noise or air over pressure and fly rock
with improved production and productivity. Their study revealed that by proper design of blast
parameters the desired results in fragmentation, vibration were achieved where as fly rock
needed good supervision. They recommended use of non-electric initiation system instead of
detonating fuse; this increased the cost but gave back in productivity reducing chances of
misfire, fly rock and achieved proper fragmentation with reduced sub-grade drilling. The
direction of invitation was also important. They suggested a blast design for proper balance
between environmental aspects and productivity criteria.
Pradhan (2002) studied the trend of blasting in Indian opencast mines and observed that it has
been changing with requirements. There are new explosives, use of electronic delay detonators
for accurate delays, blast design as per physico-mechanical properties of rock, initiation of shock
tubes, air-deck system, blast performance monitoring, cost-effective explosive formulations, etc.
Now-a-days GPS is also used for blast planning. He pointed out that inspite of optimum blasting
pattern and scientifically choosen explosives, still a lot has to be done for blast management and
control.
Nanda (2003) advocated that operation research facilitates in describing the behaviour of the
systems, analyzing the behaviour by constructing appropriate models and predicting future
behaviour by using these models. They studied the Queuing, Markov and Reliability models and
concluded that with the help of operations research an appropriate mathematical model for
situations, processes and systems can be developed. The model can then be tested and operated
by changing the variable values to implement optimization of parameters. They were also of the
view that in the present era optimal use of resources are essential and operation research can
facilitate to take proactive decisions to make the system profitable and competitive.
Konari et al (2004) observed that blast casting is the most recent innovation on blasting for
overburden removal in opencast mines. It is implemented in due regard of the growing demand
in coal due to rise of power sector needs. It can be implemented by considering some aims like
increase of production levels, reduce capital outlay, improving productivity, equipment
replacement. The parameters to be considered for blast casting are the overburden rock
characteristics, blast geometry, spacing to burden ratio, delay interval, stemming and decking,
7
bench height to width ratio, explosive used etc. They were of the opinion that by improvement in
all these parameters, blast casting has a good future in India keeping in view the increasing depth
of opencast coal mines. It has high potential to equipment productivity, safety and overall
operational economics.
Sethi and Dey (2004) studied the blast designs in Indian mines and found that most of the
designs are based on trial and error to a large extent. They pointed out that utilizing
computerized blast designing method, the disadvantages of the previous used ones can be
eliminated. After studying all the parameters related to blasting, they observed their share of
weightage and found that parameters like the fragmentation size and hole diameter are more
significant on powder factor where as charge per hole has negligible impact on overall
performance. The hole length and bench height has equal weightage. Similar are the spacing and
burden. They pointed out that calculating and manipulating the extent of significance of all the
factors, software can be designed to provide an appropriate solution to the blast design.
Bhandari (2004) developed a blast information management system (BIMS) where all the data
in the mining operation are stored, analyzed, audited, documented and managed. These can be
used to optimize the whole process. They observed that use of software for blasting operation i.e.
BIMS makes the job simpler. It is easy to use, user friendly, data entry, reliable storage and
analysis and can be customized easily. It saves time and cost to get the impact of a particular
design. It helps to train and assess the effects of a certain drill and blast design for people and
organizations that use blasting.
Kumar et al (2004) tried to evaluate the potential of bulk explosive due to increase in rock
excavation targets. They studied performance of the explosive in Nigahi and Jayant mines, and
observed that with increase in tensile strength of rock there is decrease in the powder factor.
They observed that by increase in blastability index, there is increase in density and p-wave
velocity, and the fragmentation decreases with powder factor. They were of the opinion that the
explosive consumption should be taken care of to get proper fragmentation size. They pointed
out that more efforts should be put on assessing the VOD of the explosive as it increases the
shock energy and more studies are needed to justify the results from the work done.
Chapter 3
CHAPTER - 2
Percussive Drilling
10
ii)
Rotary Drilling
iii)
Rotary-percussive Drilling
ii)
ii)
iii)
hole sizes are in the 63 to 150mm (2.5 to 6 in.) range. The larger machines are crawler-mounted
and self contained. Drill towers permit single pass drilling from 7.6 to 15.2m with hole sizes in
the range of 120 to 229mm. These larger machines are almost exclusively operated using down
the hole hammers. For many years these machines were exclusively operated using pneumatic
hammers. But in the last 20 years hydraulic machines have been introduced in the smaller size
range.
3.1.3 Rotary Drilling
As the name suggests, the boring tools used in this method are rotated and they crush, cut or
abrade the rock. The rate of drilling depends on
Nature of the rock
Pressure exerted by drilling bits and rods
The rpm of the bit
Type of drilling bit
The simplest form is the hand augur. These are attached to rods and rotated by means of a
simple cross bar. In this method hollow drill rods of steel or aluminum are used. These are
thread connected and transmit torque and feed pressure to the drilling bit or drilling tool, which
is attached at the end of column of the drill rods. Rotation of the drill rods is through gearing
driven by a prime mover at the surface. The drill bit attacks the rock with energy supplied to it
by a rotating drill rod, while a thrust is applied to it by a pull down mechanism using upto 65%
of the weight of the machine, forcing the bit into the rock. As the rods rotate, the drilling tool/bit
breaks the rock (by either a ploughing-scrapping action in soft rock, or a crushing-chipping
action in hard rock, or by combination of the two) and the cuttings are cleared by pumping water
under pressure or compressed air down the hole through the hollow drill rods. The air both cools
the bit and provides a medium for flushing the cuttings from the hole.The water or air, along
with the cuttings, comes to the surface through the space between the drill rods and the sides of
the drill hole.
The bit moves forward by the effect of torque and thrust simultaneously applied to the
rock surface. The mechanism of penetration rate are related to shearing and friction processes.
The shearing action of the leading edge of the cutting component produces chipping, whereas
friction creates wear of the bit-rock interface.
12
Blast hole sizes produced by rotary machines vary in the size range of 100 to 445mm
diameter with the most common sizes being 200, 250, 311, and 381mm in diameter. These drills
usually operate in the vertical position although many types can drill up to 25 or 300 off the
vertical. To achieve high drilling speeds, and to drill holes to greater depths, three power driven
rotary methods are available viz., hydraulic rotary drilling, diamond drilling, and chillied shot
drilling
3.1.4 Rotary Percussion Drilling
This is a hybrid form of drilling. In a rotary- percussive machine the advantages of both rotary
and percussive principles are used for making the hole. Here blows are imparted and the tool is
also rotated during drilling action. Generally, percussion bits (with buttons or asymmetric
wings) or sometimes roller bits are used. The superimposing of percussion on a rotary system
means that higher impact forces are realized than in straight rotary drilling, but thrust and torqueinduced forces are still operative. In rotary-percussion drilling, rock failure occurs by crushing
and chipping, the proportion being a function of the drilling action.
3.1.5 Drill Bits
A bit is the applier of energy in the system, attacking rock mechanically to achieve penetration.
The common drilling bits being used in large opencast mines are Drag bit, Carset bit, Tricone
rock roll, Button bit.
Drag bit: they have three or four
cutting wings tipped with carbide
inserts and usually an A.P.I. regular
threaded pin connection. Blade bits
have a similar cutting action, except that the blades
can
be
replaced.
Carset bit: The drill bit in this case is essentially a cross bit tipped with tungsten carbide and it
is an integral part of the unit called a carset bit. It has five air holes (one at the center and four on
the sides). The drill bit is usually fitted in a 1.5 m long pipe like device known as hammer. This
hammer contains a piston and valve arrangement. During operation, compressed air passes down
13
the hollow drill rods through filipper valves and experts pressure on the piston, which in turn
strikes the bit. Air then enters the bottom of the piston through a passage way around the cylinder
when it is at the ends of its down stroke, and lifts the piston up. In this piston the passage way is
cleared and the entrapped air below is released through the carset bit and there by cleared again.
The piston is then struck by an air stream at its top and this forces it down and thus the process of
up and down movement of the piston gets going.
In pneumatically operated drilling machines, the piston strikes the carset bit about 1000
times/minute at full air pressure. The drilling action in such cases, that is, movement of the drill
down hole, takes place on account of atomization of rock due to constant pounding on it by the
carset bit. Theses bits have line contact with the rock and constant impact while breaking and
atomizing wears out the contacts. The cutting edge as well as the periphery needs grinding for
further use.
Tricone Rock Roller Bit: In rotary
drilling
machines,
which
are
pneumatic
and
hydraulic
14
depends on the volumetric output of the compressor and its operation pressure capacity. The
nozzle size should be such that it only clears but also cools the equipment. Rotary speed varies
from 60 to 120 rpm for a steel- toothed bit and 50 to 80 rpm tungsten carbide bits. The normal
life of such a bit is about 2500 m. this bit is not repairable and has to be disposed of after use for
2500 m.
Button Bit: Button bits have cylindrical bodies with a larger diameter head on the top and the
stem is spline shaped. The head is chamfered on
the sides. A number of hard metal balls in the
shaped of a hemisphere are sintered on the head
and on the side to flush cutting from the drill
holes. There are certain vertical slots at the side
to provide a passage for the cutting to come out
of the holes. Rotational speed varies from 10 to
20 rpm. The bodies are made of alloy steel and
heat treated. The hole diameter varies from 100
to 210 m.
Figure 3.3: Button bit
3.1.6 Feed Mechanism
The pressure acting on the bit into the rock is controlled by an arrangement known as
feed mechanism. The feed mechanism is hydraulic for deep holes, but may be replaced by a
screw feed for shallow holes. Beyond a depth of nearly 60m, the weight of the rods keeps the bit
pressed against the rocks and the feed mechanism may not be necessary. At greater depths the
feed mechanism is operated in such a way that the weight on the drill bit is not excessive.
Three types of such mechanisms are used in drilling machines. They are:
1. Pneumatically operated mechanism
2. Hydraulic operated mechanism
3. Rope pulley operated mechanism
Pneumatically operated mechanism: This consists of an air motor, transmission system and
chain drive. The air motor is driven by compressed air, drives the sprocket chain arrangement
15
through a gear box or a belt pulley system. The rotary head is placed on a chain which
reciprocates during the raising and lowering of the chain.
Hydraulic operated mechanism:
of hydraulic rams only, (b) by the use of hydraulic rams in combination with a rope pulley
arrangement. The first is consisting of a hydraulic tank, a hydraulic pump, a two-way valve, a
feed control valve, a hydraulic cylinder, a cross head, and pipelines.
The hydraulic pumps is a vane type variable delivery unit which discharges the hydraulic
fluid either at the top of the cylinder or at the bottom of the cylinder through a two way valve,
there by extending or retraction the piston cylinder assembly, which finally provides the feeding
action of the machine. There are two return lines, one form the pumps and the other form the
two-way valve so that excess oil may be allowed to come back to the tank. This two-way valve is
equipped with built-in relief valve of a differential plunger design to ensure accurate and uniform
maintenance of pressure. The oil pressure gauge on the oil pump line indicates the oil pressure in
the system. There is a feed control valve in the piping, leading form the bottom of the cylinder. It
is adjusted to regulate or stop the advance of the bit.
The second method is usually used in electrically driven drilling machines. The pistons of
the hydraulic cylinder actuate the hydraulic motor through a rope pulley arrangement as shown
in the figure.
Rope pulley mechanism: A rope pulley operated system uses purely mechanical components.
Here the rotary head is allowed to move on a guided path. The top of the head is connected to a
rope and this rope allows to pass over the auxiliary reel at the top and then around a bull reel in
the middle. Finally, the rope is connected to the bottom of the rotary head structure after passing
over the bottom reel. The middle reel, that is the bull reel, is powered by a prime mover. When
the bull reel rotates in a clockwise direction the rotary head is raised and as the reel is rotated in a
counter in a counter-clockwise direction the rotary head is lowered, providing feed for the drill
rod.
3. 1.7 Power Transmission System
Transmission of power in drilling machines is of two types:
(a) In combination with pneumatic and mechanical means.
(b) Electric, pneumatic and mechanical means
16
pump which raises the mast form the horizontal to the vertical position. At the rear there are two
spikes which help to hold the machine during drilling action.
Blast hole drills
Bigger drilling machines, which produce holes to be blasted in order to facilitate higher capacity
excavators, are termed as blast hole drilling machines. In fact, all drilling machines which make
holes for blasting purposes should be termed as blast hole drills. However, it is a common
practice to refer only to bigger capacity machines as such. The hole diameter varies form 100 to
300 mm up to depth of 60 m with a drilling speed varying form 1.8 to 24 m/hours.
This machine usually consists of a
prime mover (either a diesel or an
electric motor) which drives the air
compressor, the hydraulics pumps, the
rotary
head
and
other
auxiliary
compressor
is
to
supply
For
pneumatically
also
to
operate
the
feed
Figure 3.5: Blast hole drill
cuttings. All other main functions such as drill rod rotation and feed mechanism movement are
performed by a hydraulic motor run by hydraulic pumps which are in turn operated by electric
motors. The third type of machine, which is electrically driven in combination with pneumatic
and hydraulic system, uses an electric motor for drill rod rotation while a hydraulic motor run by
the hydraulic system operates the feed mechanism in addition to the removal of cuttings by
compressed airs previously.
18
Drill bit: There are three types of drill bits used in the above type of drilling machine. They are
a) Carset but
c) Button bit
Mast assembly
This is vertical structural frame work with feed mechanism that is either a chain or
hydraulic type. The rotary head (air motor/hydraulic motor/electric motor) is placed at the top
and is capable of traveling along the feed mechanism, downward or upward. Drill rods are
attached to the rotary head through a coupling and gear box. The whole of this frame work is
held in position by means of hydraulic piston cylinder arrangement and is capable of swiveling
the mast in vertical plane.
Drill Rod
Blast hole drills use a heavier type of hollow steel called rod or pipe that is designed to
convey torque rather than impact. It uses America Petroleum Institute (API) steeply tapered
threads, male type at one end female type at the other. They are made of medium carbon.
It has got three parallel paths for performing three different functions. The AC induction
motor is used to drive a screw type air compressor and the air is stored in a tank. This air is
allowed to pass through a separator for removing moisture and fairly dry air is forced through the
drill rods and bit to remove the cuttings form the hole.
There is a blower fan run by a motor, which is placed near the drill hole. As the cuttings are
lifted form the hole, this blower fan laterally throws the cuttings some distance away form the
hole by the air stream. The AC supply is used to drive the rotary DC motor after passing through
a rectifier. This DC motor drives the drill rod and bit through the gear box and tyre coupling.
Undercarriage unit: This unit is mounted on both a tyred wheel system and a crawler
mechanism. A structural framework mounted on three wheels is the common feature of the
former type while the latter type consists of two crawler mechanisms on which the whole
19
machine rests. Each mechanism is provided with a separate driving sprocket, driven wheel and
an endless chain run by the driven sprocket. The tension adjustment arrangement for each
mechanism is provided to adjust the tension as required for the purpose. There are certain carrier
rollers, which guide and carry the endless chain. The undercarriage unit is also provided with
hydraulic jacks over which the whole machines rest during action. Each crawler unit has a
separate framework and they are rigidly connected to form a single unit.
A pneumatically operated machine uses compressed air to remove cuttings for the drilled
holes, for operation of drill rods and for forcing/withdrawing the drill rods from the hole. A
hydraulically operated machine, on the other hand, uses compressed air for removing cuttings
only. The drill rod rotation and the up and down movement of the drill rod are done
hydraulically.
An electrically operated machine in combination with hydraulic and pneumatic systems
also uses compressed air for removing cuttings only. The drill rod operation is done electrically,
while the raising and lowering of the drill rod is performed hydraulically.
JACK HAMMER DRILL
This is the best example of a percussive type drilling machine and is a familiar equipment
to mine workers and civil construction labourers. This is a hand held and unmounted drill used to
bore vertically down ward holes. The weight of the machine varies for 15 to 25 kg and is capable
of making drill holes up to a depth of 3 m with hole diameters generally between 25 and 37 mm.
It is a compressed air
operated drilling machine
to which air is supplied
from
external
compressor(s)
through
Suitably
1.flushing hole 2.water or air tube 3.Air tube 4.piston 5.air channel for extra
blowing 6.cylinder chamber 7.rocker valve 8.air inlet valve 9.air outlet valve
10.drill steel 11. front cylinder chamber
20
the shank and the other end is so shaped as to form a nondetachable single chisel bit with a
tungsten carbide insert. It may also be used for drilling inclined holes.
This machine consists of the following mechanisms:
i) Percussive mechanisms
Operation
Figure 3.6 shows the cut-away view of a jack hammer. The compressed air enters the
machine thought the air inlet valve at point 8 and flows via the channel past the disc shaped
rockeer valve (7) into the rear cylinder chamber (6) Here compressed air actuates the piston (4)
so that the piston moves in a forward direction. The air outlet (9) in the cylinder wall is
uncovered due to the forward movement of the piston, allowing the air in the rear cylinder
chamber to flow out freely. The piston continues to move forward and strikes the drill steel. Due
to the uncovering of the air outlet the pressure of air causes the rocker valve to be reversed.
Compressed air now flows to the front of the cylinder chamber (11) and forces the piston (4) in a
backward direction during the backward movement of the piston; the air outlet is again
uncovered, resulting in the expulsion of air from the front cylinder chamber. Owing to the
uncovering of the air outlet, the pressure of air causes the rocker valve to be reversed. The whole
working cycle is repeated.
Flushing the drill hole: This is done in two ways, (i) with water under pressure, and (ii) with
compressed air. In the first method, the drill hole is flushed with water under pressure conducted
throught the water tube (2) in the rock drill and the flushing hole (1) in the drill steel. In the
second method, compressed air is fed to the drill via the tube of the tool and the flushing hole in
the drill steel. This eliminates the need for tube (3)
Rotation of drill bit: The rifle bar is splined and slightly twisted. Four pawls are attached to its
upper end, which allow the rifle bar to rotate in one direction that is in the direction of twist. The
21
rifle nut placed on the top of the piston has matchine splines. As the piston moves up, the rifle
nut splines exert twisting force on both the rifle bar and the piston. The rifle bar is held by the
ratchet, so the piston turns. On the return stroke, the rifle bar turns having less rotational
resistance than the piston, which drives the rod straight down.
Comparison of pneumatic, hydraulic and electrically operated drilling machines.
Pneumatic
Hydraulic
Electric
It is more compact,
precise control is
possible, low noise level,
High rate of penetration
Possibility of pollution in
case of leakage in oil line.
They required greater
maintenance.
22
3.2 BLASTING
3.2.1 Explosives
The basic objective of drilling and blasting program is to achieve optimum
fragmentation. Blasting in Overburden is mainly done either to fragment and shatter the rock or
to displace the rock in the mine area by casting of Overburden.
According to explosive rules the explosives and their accessories are classified into eight
classes. These are:
Class1 : Gunpowder
Class5 : Fluminate,
Class6 : Ammunition
etc.
Class7 : Fireworks,
The commonly used explosives in the opencast mines of our country are:
Ammonium Nitrate: It is very high explosive and having a good oxidizing and cooling agent
and very safe to handle. AN is mixed with a sensitizers (fuel oil or NG or Trinitrotoluene) to
form an explosive. It is hygroscopic in nature. It is having low temperature of detonation and less
power as compared to NG. It is cheap, safe to handle and give better fragmentation. Prilled AN
of fertilizer grade mixed with diesel oil is used for larger diameter hole in opencast mines.
23
Ammonium Nitrate and Fuel Oil: It is a mixture of prilled AN and fuel oil, at the nearly
oxygen balanced ratio of 94/6 AN/FO. Both sensitivity and performance depend upon prill
properties. It does not detonate ideally and its performance properties depend upon charge
diameter and confinement. For dry hole condition it is excellent, and also it should be initiated as
soon as it is loaded. It is initiated by small quantity of O.C.G. or booster.
Slurry Explosive: This type of explosive incorporate besides oxidizer (AN, sodium Nitrate etc.)
water, sensitizer hydrophilic colloid which results in viscosity build up of the matrix. Water
resistance is due to the cross-linking agent forms a network of bonds involving the polyvalent
metal ion and hydrated gum molecules. Proper density control is crucial for maximizing the
shock sensitivity of theses explosives. These are the safest of all explosives as they are not
ignited easily and insensitive to the type of shock, bullet, impact and friction. It has good fume
properties, water resistant. Slurry automation is accomplished by pump truck method. It led to
the successful field implementation of SMS (site mixed slurry) concept. It gives a high loading
rate (150-300 kg/min) and minimizes the blasting efficiency.
Site Mixed Slurry: These explosives are used for blasting on a large scale in an opencast mine.
It involves specially designed pump trucks for transport to the blasting site ingredients required
for SMS system. It basically comprises a mother support plant where intermediate non-explosive
slurry is, initially, prepared for its application. This intermediate slurry subsequently, is
transferred to a 10 tonne capacity stainless steel tank.
Emulsion Explosive: It is a mixture of oxidizer and fuel which are both in liquid form. With the
help of emulsifying agent an intimate mix of oil and water is possible. Delivery rate of 200-300
kg/min can be achieved. Load cells/digital meters indicate amount explosive being loaded into
boreholes. Straight emulsion explosive has high bulk strength. Emulsion matrix can be carried in
support tankers of 10-12 tones capacity or more which is transferred at site thus saving time. It
ensures uninterrupted charging. It is recommended that 500 gm Pentolite boosters are used for
boosting. Manpower savings are obtained with less deployment of van drivers or helper, blasting
crew and magazine staff. Full borehole coupling expanded burden/spacing parameters on
blasting efficiency. It does not give explosive pilferage.
24
Heavy ANFO: It is latest development of 1980s had been use of emulsion slurry mixed with
different proportion of ANFO. The ratio of emulsion to ANFO is 20:80 to 50:50 depending on
the severity of water conditions and need of stronger blast energy. It is of low cost with higher
density, higher energy and better water resistance than ANFO and AN. Its concentrate system
allows expansion of drilling pattern, thereby reducing drilling cost.
The comparative VOD of ANFO, Slurry and emulsion are 2000 to 4800 m/s, 3300 m/s
and 5000 to 6000 m/s.
3.2.2 Accessories
Detonator: High explosives are initiated by detonator or detonating fuses. It is a small cupper or
aluminum tube containing a small auxiliary charge of special explosive. Due to chemical
reaction initiated by flame or electric current in the special explosives, an explosion of sufficient
intensity result throughout the high explosive enclosing the detonator. It is of plain ordinary
electric detonators. It is having a rd with A.S.A. composition and P.E.T.N. No.6 detonator is
suitable for normal requirement of mining work. No.8 is more power full than No.6. The current
of 0.5amp is required for ignition of fuse-head so single detonator can blasted with minimum
voltage of 3.5 volt. Delay detonator is used for more efficient blasting due to supply of
immediate free face for multi-row blasting.
Booster: For effective detonation of slurry explosives and ANFO mixture such as GN-1, use of
high detonation velocity booster is necessary. It is water resistant and VOD of 7000 m/s, wet
strength 82 and can be detonated by detonating fuse or detonator. Cast booster is not substitute
for explosive charge. It is a very power full detonator of large size and is preferred for deep large
diameter, blast hole in opencast mines.
Safety fuse: It looks like a cord consists of core of fine grained gunpowder warped with layer of
a tape or textile yarn and water proof coating. The burning speed is 100-120sec/m. it carries a
flame of uniform rate of ignition to detonate an ordinary detonator.
Detonating fuse: For shallow depth (<3m), and for small number of holes, a detonator is
inserted in the cartridge itself and detonated and detonated by ignition of safety fuse or incase of
electric detonator, by an exploder. It contains core of PETN enclosed in a tap wrapped with
cloth. It looks like a plastic cord. Its diameter is 5 mm external and weight about 20 g/m length.
25
It has a VOD of 6500 m/s. A large number of shots connected with detonating fuse can be
blasted by a single detonator. Nonel is non-electric detonator.
Detonating Relays: In opencast working; it use detonating fuse for initiation provide a nonelectric delay firing system. It avoids electrical connection which are required when using delay
detonators. A detonating relay is an assembly of two open ended delay detonator coupled
together with flexible neoprene tubing in an Aluminum sleeve. The delay interval for each
detonating relay varies from 15-45 milliseconds. In use, the main or branch line of detonating
fuse cut at required point of delay and detonating relay is crimped between two cut ends of the
line. Cord relays manufactured by IDL chemicals.
Circuit Tester: The blasting circuit is tested by circuit tester because to avoid accidental
explosion of detonator. Blastomer is manufactured by IDL chemical. It is an electronic solid
circuit tester.
Crimper: A crimper is a paid of pliers to crimp or press the end of the detonator tube on safety
fuse so that fuse cannot come out from the detonator.
Shot firing cables: During electric shot firing the leads for the detonator are connected to long
shot firing cables to fire the shots from safe distance.
Exploder:
The portable apparatus which provide the current necessary for firing electric
detonator is called exploder. There are three types of exploder used in Indian mines i.e. Magneto
(or Dynamo) Exploder, Battery condenser Exploder and Condenser dynamo Exploder.
3.2.3 Blasting Pattern Followed in Opencast Mines
In opencast mines both vertical and inclined holes parallel with bench face is practiced.
Row of the holes may be in single or multiple. So there are mainly two types of blasting pattern
followed in opencast mines. These are:
a) Single Row blasting pattern
b) Multi-row blasting pattern.
26
3.2.3.1 Single row firing pattern: In single row blasting the fragmentation is low and specific
explosive consumption is more than multi-row blasting, so multi-row blasting pattern is
preferred.
In this the following patterns are used:
a) The alternate delay pattern (used for softer rocks),
b) Consecutive shot delay pattern (rock with medium hardness),
c) Short delay firing with a cut (used for hard rocks).
Detonating
Relay
S
7
Blast hole
B = Burden
S = Spacing
Blast hole
S
1
Detonating fuse
Detonator
Safety fuse
B
Figure 3.7 Sequence of initiation in single row blasting
3.2.3.2 Multi Row firing pattern: The Multi Row Firing pattern is of mainly five types:
a). Square grid in-line initiation (spacing(S) = effective burden (B)).
b). Square grid V pattern (S = B; SE =2.BE).
c). Square grid V1 pattern (S = B; SE = 5.BE).
d). Staggered grid V pattern (S = B; SE = 1.25BE).
e). Staggered grid V1 pattern (S = B; SE = 3.25BE).
27
28
Beside cut pattern other pattern of blasting in multi row of firing are as given below:
Transverse cut pattern: They are used where smaller width of muck pile is desired.
Wedge or trapezoidal blasting pattern: They are used when the rocks are medium hard
and hard one. Due to the motion in opposite direction in this case the big boulders are
broken by supplementary collision.
7
2
3
2
Delay detonator
Figure 3.10: Wedge blasting Pattern
Diagonal blasting pattern: With this it is possible to blast the rock towards the least
resistance and improve the fragmentation of rock.
4
3
2
1
29
10
sensitive explosives.
Application Flexibility: Composition boosters are available in standard, cord-sensitive, slider
and stinger configurations to make them easy to use with all types of initiation systems.
High Visibility: Fluorescent color packaging reduces the possibility of losing or misplacing
charges.
Unlimited Shelf Life: Shelf life is unlimited and freeze/thaw cycles are no problem.
30
3.3.2 Nonel
NONEL Initiation System
The invention of NONEL by Dyno Nobel's Swedish organization in the 1970's
revolutionized the blasting industry. Instead of electric wires, a hollow plastic shock tube
delivers the firing impulse to the detonator, making it immune to most of the hazards associated
with stray electrical current. NONEL shock tube is a small diameter, three-layer plastic tube
coated on the innermost wall with a reactive explosive compound, which, when initiated,
propagates a low energy signal, similar to a dust explosion, at approximately 6,500 ft/sec (2,000
m/sec) along the length of the tubing with minimal disturbance outside of the tube. The design of
NONEL detonators incorporates patented technology, including the Cushion Disk (CD) and
Delay Ignition Buffer (DIB) to provide reliability and accuracy in all blasting applications.
NONEL MS:
detonator crimped to a length of shock tube, and are used in open pit mining, quarrying,
construction and underground mining. NONEL MS units are available in firing times ranging
from 0 to 1000 milliseconds.
NONEL LP: It is a non-electric delay detonators are precise in-hole delay detonators used
extensively in underground mining, tunneling, shaft sinking and special construction
applications. NONEL LP units consist of a high-strength detonator crimped to a length of shock
tube, available in 19 delay periods from 0 to 8000 milliseconds.
NONEL SL: These are non electric delay detonators comprising of 30 inch lengths of shock
tube with a precise in-hole delay detonator on one end and a loop of shock tube on the other, to
be used in conjunction with low-energy detonating cord down lines. When used in a slider
configuration, they provide independent deck initiation from a single down line. NONEL SL
units are available in firing times ranging from 0 to 1000 milliseconds.
NONEL TD: These delay detonators provide precise, reliable surface delay times, lengths and
hardware suited for initiating detonating cord or shock tube down lines in various surface
applications such as open pit mining, quarrying and construction. They consist of a precise
31
surface delay detonator housed in a plastic bunch block on a length of shock tube, and are
available in delay times ranging from 9 to 109 milliseconds.
NONEL EZ DET: This non-electric blast initiation system was developed for a variety of
blasting applications, including construction, surface and underground blasting. They eliminate
the need to inventory various in-hole delays and provide fast, simple hook-ups while allowing an
unlimited number of holes to be shot with independent hole initiation. An EZ DET unit consists
of a surface delay detonator housed in a plastic connector and a precise in-hole delay detonator,
linked by a length of shock tube. They are available in a variety of lengths and delay times.
NONEL EZTL: These non-electric trunk-line delay detonators are precise, reliable millisecond
delays, with delay times and hardware suited for use as trunk-lines in open pit mining, quarrying,
construction and underground mining. EZTL units consist of a precise in-hole delay detonator
housed in a connector block and crimped to a length of shock tube. They are available in various
lengths and delay times.
NONEL EZ DRIFTER: These non-electric blast initiation systems are used extensively in
underground mining. An EZ DRIFTER unit consists of a surface delay detonator housed in a
plastic connector and a precise high strength in-hole delay detonator, linked by a length of shock
tube. They are available in various lengths, with a delay time of 200/5400 milliseconds.
NONEL STARTER: It is a non-electric delay detonators are used as the primary initiator for
mining, quarrying and construction blasts. They consist of a spool of non-electric shock tube
factory-assembled to a detonator that is housed in a plastic bunch block. NONEL STARTER is
available in various spooled lengths for easy application and deployment.
NONEL LEAD LINE: This is NONEL shock tube spooled at the factory in 2,500 ft (763 m)
lengths for easy application and deployment. NONEL LEAD LINE provides maximum
flexibility to the blaster in choosing a position of safety from which to initiate non-electric blast
rounds in either underground or surface applications.
NONEL TWINPLEX: These delay detonators are designed to provide two independent paths
of initiation between boreholes and/or rows of boreholes (twin-path applications) in open pit
mining, quarrying, construction and underground applications. TWINPLEX units consist of two
precise millisecond delay detonators of the same delay, with individual yellow shock tube leads,
32
33
over bottom initiation of the holes a suitable combination of bottom and top detonator delay
times is chosen.
If the top and bottom detonators in a hole are located at a distance greater than 25 meters
apart it is recommended to increase the difference in delay time between the detonators, due to
the additional time taken for the signal to travel the length of the NONEL tube (1 millisecond for
every 2 meters of tube).
3.3.3 Digital blasting using electronic detonators(E-Blast)
Improving contour blasting and decreasing the need for rock support
34
Thus the increasing disadvantages and the environmentally disturbing results with
ordinary electric and shock tube detonators and the great potential in the use of electronic
detonators highlights the need for the digital blasting system.
Components of digital blasting system
The components of a digital blasting system are the same as that of an ordinary blasting
system. Only the type of blasting machines and the detonators used change. The components of a
digital blasting system are listed below
Electronic detonator
Connecting wires
The preparatory work for a blasting operation includes determining the delay time for
each blast hole in the round and charging the holes with detonators with detonators with suitably
chosen period numbers. The blasting machines time memory is then programmed with the
necessary time information adapted to the period number chosen.
Electronic detonators
Blasting machine
Connecting box
Electronic detonator
From the exterior, the electronic detonator looks exactly like a conventional electric
detonator. In principle, the detonator consists of an electronic delay unit in combination with an
instantaneous detonator. Electronic detonators utilize stored electrical energy inside the detonator
as a means of providing the timing delay and initiation energy. All other detonator technologies,
including shock tube, electric or safety fuse initiated, utilize pyrotechnic energy as a means of
delay and initiation.
35
An integrated circuit on a microchip constitutes the heart of the detonator. In addition the
detonator has a capacitor for energy storage, and separate safety circuits on the input side in
order to protect against various forms of electric overload. Thus fuse head for initiating the
primary charge is specially developed to provide a short initiation time with minimal time
scatter.
Programmable electronic detonators contain a tiny circuit board that enables the
detonator to store a blast sequence number in its on- board memory. It also can perform a selfcheck of its functionality when connected to a hand-held programming unit or digital blasting
machine. Depending on the brand used, delay periods of 1 to several thousands milliseconds, in
1-ms increments, can be programmed into the detonators. This level of precision eclipses the
minimum 25-ms delay capabilities found in most pyrotechnic based detonators.
The most striking characteristic of an electronic detonator is its flexibility. Period
numbers, which are marked on the detonators, do not state the delay time but the order in which
the detonators will go off. Each detonator has its own time reference but the final delay time is
determined through interaction between the detonator and the basting machine immediately
before initiation.
Typical characteristics of an electronic detonator are.
The detonator initially has no initiation energy of its own
The detonator cannot be made to detonate without a unique activation code
The detonator receives its initiation energy and activation code from the blasting machine
The detonator is equipped with over voltage protection. Low excess loads are dissipated via
internal safety circuits and higher voltages limited by means of a spark plug
The initiation systems operate with low voltages, which is a great advantage
considering
36
The controls for initiation appear as simple as possible in spite of the advanced internal
design of the machine. A panel with lamps indicates what is happening and gives the go-ahead
signal when the shot is to be fired.
Delay time allocation to the detonators is carried out by uniquely coded signals to
eliminate any possibility of error. The detonator responds to the code only from the blasting
machine and thus eliminates any risk of initiation from external energy sources. The blasting
machine also performs an operation status control, which is done automatically by the machine.
System characteristics
The typical characteristics of digital blasting system are
The shortest delay time between two adjacent delay period can be as low as 1 ms.
A detonator with a lower period number cannot be given a longer delay time than a
detonator with a higher period number.
Detonators with different period numbers cannot be closer to each other than the difference
in their period numbers.
can be used. Thus for a successful blast, a user requires only a sufficient number of detonators
with different period numbers in stock.
Mode of operation
The preparatory operations for a blast includes determining the delay time for each blast
hole in the round and charging the holes with detonators with suitably chosen period numbers.
An outline of a round using this system is given in the figure. The detonators in the round are
connected in parallel with arbitrary polarity. This is done by connecting the detonators to a twowire bus cable via a terminal block, using special pliers. Finally the bus cable is connected to the
blasting machine via terminal box and a firing cable. After getting the go-ahead sign, energy is
supplied to the detonators from the blasting machine, which in turn initiates the explosives.
Advantages of digital blasting system
The digital blasting system has a number of advantages over the one, which uses
pyrotechnic delay. Vibrations resulting from blasting are one of the major problems of
37
pyrotechnic delay. Of the three components of ground vibrationpeak particle velocity (PPV),
duration and frequencyfrequency is the most important when it comes to human reaction from
blast effects. The geology of the area surrounding the blasting site influences the transmission of
vibrations. Once the influence of the geology is understood, blast can be configured to disrupt
rather than reinforce the natural frequency of the site t5hrough the use of millisecond delays.
High precision timing obtained using the electric detonator and the reduction in the time of delay
intervals has the advantages of decreasing the charge per delay thus leading to reduce levels of
vibration. Apart from reduction in the vibration, there is also an increase in the frequency thus
avoiding structure resonance.
Use of the digital blasting system also to helps achieve a higher fragmentation of the rock
being blasted and better throw of the blasted material. Increased fragmentation and good throw
can result in better loading conditions. Boulder formation can be greatly avoided with a well
designed blast thus eliminating the need for secondary blasting. Drilling costs are reducing since
there is not a need for deck holes and in turn the explosives cost. Since a large number of holes
can be blasted without any worry about vibrations, and overall frequency of the blasting
operations can be greatly increased, thus bringing down the time taken for blasting per tonne of
rock. This will lead to minimum suspension in operations such as loading and drilling. Hall these
factors will influence a higher productivity. Increase in output of the mine means an increase in
profit for the mine owner.
From the advantages summarized above, the potential applications of digital blasting can
be listed as follows:
Complex blasts, difficult to design with standard pyrotechnic detonators and delay
imings
38
3.3.4
Digital Drilling
Computerized drills and MWD systems are two technologies that can provide feedback on
important aspects of the drilling function:
automate the drilling process, which can increase machine utilization, and to improve drilling
accuracy, which helps optimize blasting and improve safety. The company developed
computerized control systems for its jumbo drills in the early 1990s and more recently
introduced the technology to surface crawler drills.
The Atlas Copco ROC D7 C top-hammer drill uses a CAN-bus system-Controller Area
Network comprising a number of small on-board computers linked by a single cable. All
hydraulics has been removed from the cab and a color monitor replaces traditional dials and
gauges.
A Rig Control System (RCS) senses variations in rock conditions and adjusts drilling
functions to optimize drill penetration and accuracy and to minimize consumption of drill tools,
the company says. RCS works in conjunction with ROC Manager software for monitoring
drilling operations. Drill plans can be designed in the office and uploaded to the drill rig. While
drilling, the system logs deviations and other parameters for later analysis, which can reveal
geologic or hole conditions that can impact explosives loading or other blasting plans. MWD
parameters include penetration rate, percussion pressure, feeder pressure, damper pressure,
rotation speed, rotation pressure, and flush air pressure.
The ROC D7 C automatically adds rods to the drill string to a preset hole depth, allowing
drilling to continue during operator breaks and between shifts, Atlas Copco says. Rig utilization
through using the automated functions can increase 10 to 15 percent, according to the
manufacturer.
The modular design of the RCS allows future expansion or upgrading of the system by
adding control modules. Options under development include the use of a Global Positioning
System (GPS) for accurately positioning the rig to drill holes according to the blast design
without surveying or staking.
39
GPS and MWD systems developed by several companies currently are available as
retrofit components for drill rigs. Thunderbird Mining Systems Drill NAV Plus is a blasthole
drill monitoring and navigation system that allows operators to get within approximately 8 in. of
the designed hole location without staking, according to the company. A color VGA display
shows the operator where every hole should be drilled as well as the location of previously
drilled holes. As the drill moves around the drill pattern, the map moves on the operators display
to allow quick navigation between holes and a visual lock ring function indicates when the drill
is positioned within tolerance of the design location of a hole. Map data is transferred to and
from the drill via spread spectrum-radio.
The system also indicates the elevation above sea level of the drill bit as the hole is
drilled. Consequently, the target bottom of each hole can be specified as an elevation, rather than
a depth, to reduce under- and over-drilling, eliminate hard-digging toes, and create level benches.
Drill NAV Plus also provides drill monitoring by measuring, displaying and recording feet or
meters drilled; penetration rate; drilling, non-drilling, and tramming time; and hole, pattern, and
drill bit numbers.
Aquila Mining Systems, a Caterpillar company, offers drill monitoring systems for
mining applications. Its DM products, based on the AMP computer hardware and QNX
operating system software, are available factory installed on new drills or retrofitted to older
drills. Six stand-alone products allow operators to upgrade drill-monitoring capabilities as
needed The DM-1 Production Monitoring System provides feedback to the operator on drilling
productivity and performance. DM-2 Material Recognition System uses a vibration sensor and
pattern recognition software to analyze drill variables and determine hole geology while drilling.
The DM-5 Guidance System for vertical drilling uses RTK GPS receivers to allow the
operator to spot the hole within centimeters of the target location without surveying or staking,
according to the company. Once the drill is leveled and the hole started, the DM-5 automatically
determines collar elevation and calculates the required drilling depth. Blasthole position
information is stored and transmitted to the mine office for use in blast design. The DM-6
Guidance System is for inclined drilling.
40
CHAPTER 4
41
CHAPTER - 4
Safety aspects
Design drilling patterns to maximize drilling efficiency while lowering overall, operation
cost.
Simplify the control, which decreases training time required for drilling function.
Calculate and optimize drilling costs for any given blasting pattern.
42
Geology: Rock density, tensile and compressive strength of rock, youngs modules of
rocks, and Poissons ratio. Strike and dip value, joint structure and frequency.
Equipment: Feed thrust, impact frequency, piston strike, Impact pressure, rotation rate.
Type of drill rig, type of bit.
Site factors: Dimensions of the face, Diameter of hole ratio of spacing and burden,
length of hole, inclination of hole, number of rows, wet or dry holes, drilling sequence.
Cost factor: Cost of drilling equipment and depreciation cost, number of operators,
wages and efficiency factor, the unit cost of drill rods, blast hole bit and consumables,
the cost of power and lubrication oil.
Pit geometry which refers to bench height, pit width and the ratio of these two
parameters.
Capacity of striping
43
Density,
Porosity,
(iii)
(iv)
Fly Rocks: It can be controlled by giving proper attention to blast design layout,
drilling and loading of explosive.
SYSTEM
THROUGH
Optimization means achieving the best that is to achieve maximum or minimum value of the
operating parameters. Operations Research uses suitable techniques or tools available to achieve
the goal. The techniques like linear program, waiting line theory, game theory, inventory control
models and non-liner programming, integer programming, dynamic programming sequencing
theory, Markov process, network scheduling PERT and CPM, Symbolic logic, information
theory and utility/ value theory are popular (Nanda, 2003).
The different optimization techniques being utilized for the purpose are:
1. Queuing Model: used for optimization dumper shovel combination.
2. Markov model: used for production potential prediction.
3. Reliability model: used for assessing reliability of mine production system.
4. Cargo-loading model: can be used for selection of explosives.
5. work force size model:
4.2.1 Queuing Model
It was introduced by A.K. Erlang. There are a specified number of dumpers allotted to a
particular shovel for operation. If the number of dumper is not matching perfectly then either
dumper or shoved will be idle, so optimum number of dumpers to be allotted for economically
viable operation.
Time study is to be conducted to obtain the following parameters
45
P0 =
1/
Where:
n=m
n=0
M! . (/)n
(M - N)!
Operating state,
Repair state.
Application: By using Markov Model the transition probabilities of different states can be
obtained.
Series System: The machines are kept in series and at least, drill machines are in operation. It
means that if one machine goes under breakdown there want be any more failure. In this
situation the transition matrix for three machines with different values of & , can be solved.
P0 =
1+
i=1
( i / i)
and P0 + P1 + P2 . + Pn =1
Where:
P1 = P0 ((
i / i)
P0 is transition probability of initial state and is number of components in the system.
46
Parallel System: Instead of keeping all the three M/C in series for operation (two are operation
and one as stand by). In such case assumptions are,
1) Two components in parallel are required to keep the system operating.
2) Upon failure of one on-line component the stand by unit is brought to operation mode.
3) Repair work starts when ever a component transits to failure mode and each component has
its own failure rate and repair rate.
4) If the failed component is repaired and is ready for operation before the stand by unit
completes its schedule, work, the repaired M/C becomes a stand by.
5) No failure is possible when the M/C is off the line.
The steady state reliability of each m/c is calculated by derivation of Markov process for steady
state reliability i.e. R(t) = /+ where, = repair rate, = failure rate.
4.2.3 Reliability Model
Probability of success is a measure of reliability and the probability of failure is the measure of
unreliability.
To provide a quantitative basis for evaluation of reliability, there is some well-known
time to failure distributions in standard use. The important role in evaluating them is time
between failures of system. The distributions are commonly used in failure and repair analyses
are
1) Exponential distribution
2) Weibull distribution
3) Log-normal distribution
4) Gamma distribution
5) Poisson distribution.
Exponential distribution : The distribution has no memory i.e. if a unit has survived (t) hours
then the probability of its surviving an additional h hours is exactly the same as the probability
of surviving h hours of a new item.
If items under study are replaced or renewed like as good as new after failure, the time
periods between failures are independent and identically distributed. It is widely new for
representing operating and repair times.
47
I=1, 2,, n
48
CHAPTER 5
49
CHAPTER - 5
50
Controllable variables are those, which can be manipulated or changed by trial and error
depending on the characteristics of ground vibration. On the other, non-controllable variables are
those, over which the blasting engineer has no control. Non-controllable variables are:
(i)
(ii)
(iii)
Wind
Type of explosive
Delay interval
Most of these variables are interrelated. A change in one variable in the operating system
can change the others. The net change in the magnitude, frequency and duration of ground
movement is the combined influence of all variables rather than anyone of them independently.
It is of course a very difficult task to quantify the measures or extent of the effect of each
variable individually. Basic parameters involved in the process of optimum blasting may be
classified as follows:
Blast Geometry
Rock mass
Parameters
Explosive
Properties
Basic
Parameters
Initiation
Pattern
Fig 5.1: Classification of basic parameters
51
ii.
Density (g/cc)
iii.
Characteristic impedance
iv.
v.
52
ii.
iii.
iv.
v.
vi.
vii.
RQD
viii.
ix.
Spacing (m)
ii.
Burden (m)
iii.
iv.
v.
vi.
vii.
viii.
(ii)
Although it is unlikely that all of the above-listed parameters can be accounted for in
detail by means of simple closed-form expressions, it is probable that better predictability can be
achieved by explicitly incorporating those parameters, which predominantly govern the blasting
operation.
vi.
vii.
Cost of explosive,
viii.
Drill hole diameter: The drill hole diameter are taken as fixed parameter because the bit size
available in the market is limited. The hole diameter is also vary as the geology condition of the
strata. From the drill hole diameter other information required to design a blast geometry.
Powder factor: The powder factor for a particular mine is fixed as to give a continuous product
size and also avoiding the oversize and under sized product.
Cost of explosive: This is a parameter where the value depends on the explosive strength and
type of the explosive used.
Numbers of hole required to blast: It depends on the production of the mine. More the hole
required to be blasted when the demand is more. These parameters are generally decided from
54
the other parameters also. These are density of explosive and energy output from explosives.
More hole for blasting at a time means the strength of explosive should be more so, the density
will be high and the energy released from explosive should be more.
Parameters
Specifications
1.
Strike length
1.5km
2.
Number of seam
3.
Average thickness
4.
Dip
5.
Type of coal
D to E and F grade
6.
Total reserve
36.76 MT
7.
Stripping ratio
0.78
8.
OMS
20 T/ manshift
9.
Production
10.
11.
1m 6m
12.
100mm, 160mm
13.
Burden
14.
Spacing
55
15.
16.
Explosives used
Slurry Explosive
17.
O/B5.5m3, Coal5.6m3
18.
Stemming height
19.
Cuttings
20.
PrimeRs.17.25/kg,
(column)
ColumnRs.13.92/kg
21.
Same as Coal
22.
Rs.2.21/m
23.
Rs.17.25/kg
24.
30kg/m
25.
Delay used
25ms, 17ms
26.
Density of coal
1.6
27.
28.
Not available
29.
Not available
Table 5.2: Blasting and other related information for Ananta OCP
Sl.
No.
Parameters
Specifications
1.
Strike length
2.
Number of seam
3.
Average thickness
4.
Dip
1 in 18 to 12
5.
Type of coal
E and F grade
6.
Total reserve
148.48 MT
7.
Stripping ratio
1:0.52
8.
OMS
27.91 T/ manshift
56
9.
Production
10.
Square grid
11.
12.
13.
Burden
6m(O/B), 5m(Coal)
14.
Spacing
6.5m(O/B), 5m(Coal)
15.
16.
Explosives used
17.
O/B2.6m3, Coal4.9m3
18.
Stemming height
19.
Cuttings
20.
Rs. 14/kg
21.
Density of explosive
22.
Same as Coal
23.
Rs.8/m
24.
Rs.2 Lakh/T
25.
26.
Delay used
25ms
27.
Density of coal
28.
E675/T, F441/T
29.
Not available
30.
Not available
57
Table 5.3: Blasting and other related information for Bharatpur OCP
Sl.
No.
1.
Strike length
2.
Number of seam
3.
Average thickness
4.
Dip
1 in 14 to 10
5.
Type of coal
E and F grade
6.
Total reserve
118.39 MT
7.
Stripping ratio
0.84
8.
OMS
24.91
9.
Production
5.341 MT / year
10.
Square grid
11.
8 to 12m
12.
160mm
13.
Burden
4.5m
14.
Spacing
4.5m
15.
16.
Explosives used
17.
O/B2.2m3, Coal4.6m3
18.
Stemming height
Not available
19.
Cuttings
20.
Rs. 14/kg
21.
Density of explosive
22.
Same as Coal
23.
Rs.8/m
24.
Rs.2 Lakh/T
25.
60 65kg
26.
Delay used
25ms
27.
Density of coal
28.
E675/T, F441/T
29.
Not available
30.
Not available
Parameters
Specifications
58
59
Is
select< (1/t)
YES
select=1/t,
NO
sel=count
Count=count+1
YES
Is
count<=n
NO
STOP
60
61
62
63
64
CHAPTER 7
Discussion
Conclusion
Scope for Further Study
65
CHAPTER - 6
Blast
output
and
productivity
RESULTS
EXECUTION
PLANNING
Rock
mass
characterization
Conditions
at the
blasting
site
Drilling
pattern
and blast
design
6.2 CONCLUSION
Efficiency of drilling and blasting operations can be defined in many ways, but the bottom line
is that they must contribute to the best overall economic result for the total mining operation.
Thus decisions on drilling and blasting operations need to be considered in the overall context,
and should not generally be based on short term economic factors. Drilling and blasting costs are
always a significant part of the overall operating costs for surface coal mines. The cost of
explosives may vary from 4.0% to 12% of the total operating costs and out of this about 20% of
the costs are controlled by mine site management, and thus there should be a strong emphasis on
reducing the explosive consumption without sacrificing performance.
In the present work a blast optimization model has been developed with simple methodologies
which can be adopted by the mining industry to compare the explosive costs and achieve better
blasting results and. The model takes into account the common explosives being utilized by large
opencast mine at the moment which in turn is decided by the rock characteristics, density and
other related parameters.
The model developed is a user friendly one, since by keeping the powder factor and number of
choices of explosives available as constant and by varying the parameters like drill hole
diameter, number of holes and cost of explosives one can compare the explosive performance
and accordingly take a decision to select the proper type of explosives for blasting.
It may be noted here that the model has been developed based on case studies of three different
mines of MCL, and it can be modified with collection of information from a large number of
mines.
The model will definitely give some relief to the mine operators and blasting engineers to
achieve a better output with a low cost of mining. By reducing the cost of explosives a
considerable amount of expenditure can be saved, since modern mines require very large
quantities of explosives throughout the life of the mine.
67
optimization of drill hole parameters can also be incorporated in the model for better blasting
results.
68
CHAPTER 7
REFERENCES
69
CHAPTER - 7
REFERENCES
Adhikari, G.R. and Venkatesh, H.S. (1995), An approach for optimizing a blast design for
surface mines, The Indian Mining & Engineering Journal, February, pp.25-28.
Bhandari, A. (2004), Indian mining industry: need for adoption of technology for better
future, The Indian Mining & Engineering Journal, December, pp.40-49.
Biran, K.K. (1994), Advancements in drilling and blasting technology, The Indian Mining &
Engineering Journal, July, pp.20-29.
Dey, A. (1995), Drilling machine, Latest development of heavy earth moving machinery,
Annapurna Publishers, pp.120-228.
Dutta, P.K., Barman, B.K and Moitra, B.C. (1973), Some problems of opencast drilling and
blasting, Seminar on Limestone and Dolomite Industry in India, Roukema, pp.150.
Jack Freymuller(2001), Whats new in drilling and blasting, a special report, July,
quarrytour.rockproducts.com/ar/rock_whats_new_drilling/index.htm.
Karyampudi, P. and Reddy, A.A.K. (1999), Toe formation on blasted benches and its
elimination: a practical approach, Mining Engineers Journal, November, pp.21-27.
Konari, R., Babu, K.N., Kumar, K.S. and Rai, P. (2004), Important techno-economic
considerations for overburden casting, The Indian Mining & Engineering Journal,
January, pp.24-30.
Kumar, S., Ranjan, R., Sharma, A. and Murthy, V.M.S.R. (2004), Performance analysis of
bulk explosives in different geo-mining conditions, The Indian Mining & Engineering
Journal, December, pp.24-31.
Nanda, N.K. (2003), Optimization of mine production system through operation research
techniques, 19th World Mining Congress, New Delhi, November, pp.583-595.
Pal Roy, P. (2005), Terms and parameters influencing mine and ground excavations, Rock
blasting effects and operations, pp. 17-22, 61.
Pal, U.K. and Ghosh, N. (2002), Optimization of blast design parameters at Sonepur Bazari
opencast project, The Indian Mining & Engineering Journal, September, pp.36-41.
Pradhan, G.K. (2002), Surface mine drilling and blasting: the Indian scenario, The Indian
Mining & Engineering Journal, December, pp.23-28.
Sethi, N.N. and Dey, N.C. (2004), A stimulated studies on blast design operation in open cast
iron ore mine, The Indian Mining & Engineering Journal, January, pp.17-23.
70
Siskind, D.E. (1973), Ground and air vibrations from blasting, SME Mining Engineering
Handbook, Vol-I, New York, USA, pp.11-99.
Singh, A.K. and Dhillon, P.S. (1996), Case studies on safety and optimization of explosive in
large opencut and underground mines, Drilling and Blasting, MINTECH publications,
Bhubaneswar, India, pp.117-123.
Thote, N.R. and Singh, D.P. (1997), Necessity of blast fragmentation assessment and
correlation of rock parameters with blasting performances-a practical approach, The
Indian Mining & Engineering Journal, September, pp.19-23.
Uttarwar, M.D. and Mozumdar, B.K. (1996), Blast-casting in surface coal mines, Drilling
and Blasting, MINTECH publications, Bhubaneswar, India, pp. 124-126.
Verma, R.K. (1993), Performance ratings of explosives, The Indian Mining & Engineering
Journal, November, pp.49-52.
71