Monthly Work UPDates

Monthly Work UPDates

Uploaded by

acidrisamuel2656
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Monthly Progress Report (activities of the month)

(1) Abutment A1 -Excavation Works (60%)


First stage Excavation works (100%). Second Stage Excavation (20%)
(2) Pylon P1 -Excavation Works (0%)
First stage Excavation works (0%). Second Stage Excavation (0%)
(3) Pylon P2 Excavation Works (50%)
Clearing and Grubbing (100%)
First stage Excavation works (100%). Second Stage Excavation (0%)
(4)
No.
No.
No.

A1, P1
of piles
of piles
of piles

and P2 Piles works (21%)


at A1 are 8 Design (100%) & 1 Test Pile (100%)
at P1 are 18 Design, excavated and casted (0%),
at P2 are 21 Design (4%) & 1 Test Pile (100%).

(5) Oil and silt fence (100%)


Anchor block placement (100%), Oil/silt fence connection (100%).
(4) Temporary Jetty (26%)
Percentage of work completed at jetty (26%) and the remaining work is (74%).
(5) Fuel Station (65%)
Excavation work for diesel and gasoline tanks (100%), for drainage pipes (100%)
Masonry work for the fuel pumps (100%), for pipe lines (100%), Ground Levelling for the slabs (45%), Concrete casting; to the bottom slab (0%)
(6) Clearing and Grubbing -Stockpile area, Jinja Side (Chainage 0+440-0+580) (100%)
Clearing and Grubbing (100%).
(7) Electrical and optic fiber cable (100%)
Excavation of pits for poles and stay loads (100%), pole erection & stay loads (100%), placement of conductors and accessories (100%) Tensioning of Stays (100),
Alignment of Structures (100), Re-sagging of Conductors (100).
(8) Temporary road- Njeru side (90%)
Setting out and other works (90%), Drainage Works (0%).
(10) Temporary Site Toilets (100%)
Both Jinja and Njeru Concrete work (100%), Masonry work (100%), Roofing work (100%)
(11) Engineers Offices (99%)
Jinja side office: Levelling works (100%), ceiling (100%), floor tiles (100%), IT and Electrical Installations (100%), septic tank (100%).
Njeru side: Prefab frame (100%), ceiling (100%), floor tiles (100%), IT and Electrical Installations (100%). Plumbing work (100%), Furniture & accessories (70%)