We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 1
Monthly Progress Report (activities of the month)
(1) Abutment A1 -Excavation Works (60%)
First stage Excavation works (100%). Second Stage Excavation (20%) (2) Pylon P1 -Excavation Works (0%) First stage Excavation works (0%). Second Stage Excavation (0%) (3) Pylon P2 Excavation Works (50%) Clearing and Grubbing (100%) First stage Excavation works (100%). Second Stage Excavation (0%) (4) No. No. No.
A1, P1 of piles of piles of piles
and P2 Piles works (21%)
at A1 are 8 Design (100%) & 1 Test Pile (100%) at P1 are 18 Design, excavated and casted (0%), at P2 are 21 Design (4%) & 1 Test Pile (100%).
(5) Oil and silt fence (100%)
Anchor block placement (100%), Oil/silt fence connection (100%). (4) Temporary Jetty (26%) Percentage of work completed at jetty (26%) and the remaining work is (74%). (5) Fuel Station (65%) Excavation work for diesel and gasoline tanks (100%), for drainage pipes (100%) Masonry work for the fuel pumps (100%), for pipe lines (100%), Ground Levelling for the slabs (45%), Concrete casting; to the bottom slab (0%) (6) Clearing and Grubbing -Stockpile area, Jinja Side (Chainage 0+440-0+580) (100%) Clearing and Grubbing (100%). (7) Electrical and optic fiber cable (100%) Excavation of pits for poles and stay loads (100%), pole erection & stay loads (100%), placement of conductors and accessories (100%) Tensioning of Stays (100), Alignment of Structures (100), Re-sagging of Conductors (100). (8) Temporary road- Njeru side (90%) Setting out and other works (90%), Drainage Works (0%). (10) Temporary Site Toilets (100%) Both Jinja and Njeru Concrete work (100%), Masonry work (100%), Roofing work (100%) (11) Engineers Offices (99%) Jinja side office: Levelling works (100%), ceiling (100%), floor tiles (100%), IT and Electrical Installations (100%), septic tank (100%). Njeru side: Prefab frame (100%), ceiling (100%), floor tiles (100%), IT and Electrical Installations (100%). Plumbing work (100%), Furniture & accessories (70%)