Third Party Re Pack Production Process - Manual
Third Party Re Pack Production Process - Manual
Process Flow
CS01
Creation of BOM
CA01
Creation of Routing for Re
pack material
CO01
Create Production Order
C011N
Production Order
Confirmation
MB1A
Enter Goods Issue against a
Production Order
MB31
Enter Goods Receipt against
production orders
KO88
Order Settlement
Put the Finished material code and plant along with BOM usage.
Press enter
Put item category as (L) and component along with the quantity required.
Lick on Item 0010
Press Enter
Put the Re Pack material code, Productio plant and select order type ZP04 (Re
Packing Production Order)
Press Enter
Note- For each Re pack materials goods receipt Accounting Entry will be
generated, as its treated as valuated with the value of activity cost and any
own packing material used in production.