Installation of Interconnecting Walkway With Stairs Between Inlet Separators V-0701 A/B/C at Fdp-1

The contractor Al-Jalhami will install an interconnecting walkway with stairs between three inlet separators (V-0701 A/B/C) at FDP-1 under contract HT 003 SS11. The scope of work includes excavation and foundations, fabrication and galvanization of structural members, on-site erection by bolting and welding, inspection and approval by ESD, MSS and OND, and final site restoration upon handover to OND.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
129 views

Installation of Interconnecting Walkway With Stairs Between Inlet Separators V-0701 A/B/C at Fdp-1

The contractor Al-Jalhami will install an interconnecting walkway with stairs between three inlet separators (V-0701 A/B/C) at FDP-1 under contract HT 003 SS11. The scope of work includes excavation and foundations, fabrication and galvanization of structural members, on-site erection by bolting and welding, inspection and approval by ESD, MSS and OND, and final site restoration upon handover to OND.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

INSTALLATION OF INTERCONNECTING WALKWAY WITH STAIRS

BETWEEN INLET SEPARATORS V-0701 A/B/C AT FDP-1

Contract no.: HT 003 SS11

Contractor: Al-Jalhami

SCOPE OF WORK:

1. Marking and Excavation for laying up the civil foundation. The activities includes
cutting of existing floor slab, backfilling, compaction and restoration same as original.
2. Inspection and approval by ESD upon every activity.
3. Pouring of reinforced concrete foundations and footing as per drawing provided by
OND.
4. Inspection of protective coating on concrete structures by ESD.
5. Procurement of structural materials for initializing fabrication work.
6. Inspection of procured materials by ESD.
7. Shop fabrication of structural members as per drawing provided by OND.
8. All structural members after fabrication will be sent for Galvanization.
9. Inspection of galvanized structures by ESD.
10. On Site erection of structures by bolting and welding as per drawing.
11. Final paint touch up work on welded areas.
12. Final inspection and approval of erected structure by ESD, MSS, and OND.
13. Handing over the completed structure to OND.
14. Site restoration and De-mobilization.