Plate House
Plate House
2014
ITEM NO.
ACTIVITIES
COST
% COST
7-Jul
I.
II.
III.
PRELIMINARIES:
1.1 Stake out & Survey Works
1.2 Secure Bonds, Clearances and Misc. Permits.
FOOTING & EARTH WORKS:
2.1 Excavation Works
VII.
VIII.
IX.
0.200%
2.130%
0.369%
1.900%
4-Aug
0.300%
1.900%
0.245%
0.850%
1.52%
0.260%
0.260%
39,452.00
1.34%
0.220%
0.200%
48,215.00
1.64%
28,041.00
0.95%
1,436,430.00
48.72%
57,911.00
1.96%
126,742.00
4.30%
56,834.00
1.93%
23,566.00
0.80%
28,346.00
0.96%
49,853.00
1.69%
18,464.00
0.63%
25,679.00
123,234.00
33,457.00
0.87%
4.18%
1.13%
22,346.00
0.76%
74,600.00
2.53%
55,339.00
22,456.00
1.88%
0.76%
62,836.00
68,853.00
2.13%
2.34%
61,643.00
2.09%
23,526.00
0.80%
55,633.00
1.89%
2,948,045.00
100.00%
0.270%
CONCRETE WORKS:
VI.
0.381%
28-Jul
44,666.00
V.
3.18%
9.03%
AUGUST
21-Jul
IV.
93,800.00
266,123.00
JULY
14-Jul
7.470%
9.940%
7.750%
0.160%
0.200%
0.230%
MECHANICAL WORKS:
7.1 Installation of Air Conditioning Units
7.2 Installation of Mechanical Fixtures
PAINTING WORKS:
8.1 Exterior Areas
8.2 Interior Areas
MISCELLENEOUS WORKS:
TOTAL:
0.38%
MONTHLY PERCENTAGE:
WEEKLY COMMULATIVE:
MONTHLY COMMULATIVE:
2.33%
9.74%
12.78%
10.01%
25.23%
0.38%
2.71%
25.23%
21.95%
12.45%
25.23%
35.23%
47.18%
25-Aug
1-Sep
SEPTEMBER
8-Sep
15-Sep
22-Sep
0.255%
0.245%
0.225%
0.250%
0.250%
0.250%
0.250%
0.200%
0.180%
0.180%
0.180%
0.180%
0.250%
0.250%
0.205%
0.205%
0.160%
0.150%
0.150%
0.050%
0.050%
0.070%
0.070%
0.070%
0.070%
4.000%
3.300%
0.400%
0.160%
0.160%
0.200%
0.070%
0.230%
0.230%
0.450%
0.200%
0.200%
7.400%
6-Oct
OCTOBER
13-Oct
20-Oct
27-Oct
3-Nov
NOVEMBER
10-Nov
17-Nov
0.080%
0.080%
0.080%
0.080%
0.070%
0.080%
0.080%
0.080%
0.070%
0.080%
0.080%
0.160%
0.060%
0.060%
0.030%
0.040%
0.020%
0.150%
0.150%
0.200%
0.260%
0.360%
0.150%
0.150%
0.200%
0.390%
0.160%
0.160%
0.160%
0.145%
0.145%
0.145%
0.145%
2.060%
0.070%
9.04%
1.37%
1.54%
5.11%
21.95%
44.27%
47.18%
3.98%
0.44%
0.45%
0.60%
9.98%
45.63%
47.17%
52.28%
56.26%
57.15%
0.74%
0.74%
0.44%
0.33%
2.52%
56.70%
57.15%
57.75%
58.49%
59.67%
0.39%
2.69%
6.28%
59.23%
59.66%
59.99%
60.37%
65.95%
63.06%
ER
24-Nov
1-Dec
DECEMBER
8-Dec
15-Dec
0.080%
2.400%
22-Dec
5-Jan
JANUARY
12-Jan
19-Jan
0.080%
0.080%
0.080%
26-Jan
2-Feb
FEBRUARY
9-Feb
16-Feb
MAR
23-Feb
0.080%
0.080%
2-Mar
0.080%
2.200%
2.200%
0.210%
0.370%
0.170%
0.145%
0.145%
0.075%
0.070%
0.145%
0.145%
0.145%
0.070%
0.065%
0.030%
0.035%
0.070%
0.065%
0.065%
0.065%
0.065%
0.065%
0.065%
0.070%
0.050%
0.050%
0.025%
0.025%
0.050%
0.087%
0.087%
0.087%
0.087%
0.087%
0.087%
0.087%
0.087%
0.690%
0.500%
0.500%
0.130%
0.100%
0.100%
0.100%
0.200%
0.170%
0.170%
0.388%
0.170%
0.390%
0.160%
0.290%
0.250%
0.348%
0.170%
0.348%
0.190%
0.345%
0.110%
0.345%
0.130%
0.095%
0.070%
0.060%
0.010%
0.200%
0.530%
2.89%
3.03%
3.40%
0.81%
0.00%
1.15%
7.24%
65.94%
68.97%
72.37%
73.19%
0.65%
0.86%
0.71%
0.85%
3.36%
73.18%
73.18%
74.33%
74.98%
76.54%
0.67%
0.87%
0.76%
1.23%
3.15%
75.83%
76.54%
77.40%
78.07%
79.69%
4.9
78.93%
79.69%
80.92%
84.6
TION SCHEDULE
MARCH
9-Mar
16-Mar
23-Mar
6-Apr
APRIL
13-Apr
20-Apr
27-Apr
0.080%
0.550%
0.450%
0.500%
0.750%
0.130%
100.00%
80.00%
0.064%
Axis Title
GENE
60.00%
40.00%
0.341%
0.100%
0.357%
0.090%
0.310%
0.090%
0.330%
0.378%
0.075%
0.075%
0.045%
0.095%
0.245%
0.300%
0.220%
0.200%
0.210%
0.250%
0.00%
0.300%
0.520%
0.750%
0.180%
0.750%
0.180%
0.180%
0.200%
0.200%
0.200%
0.355%
0.355%
0.370%
0.370%
0.390%
0.390%
0.400%
0.510%
0.550%
0.540%
0.500%
0.500%
0.250%
0.350%
0.200%
0.990%
0.900%
3.93%
4.31%
0.260%
0.360%
0.96%
1.36%
0.355%
0.355%
1.36%
3.38%
4.91%
81.88%
84.60%
3.78%
20.00%
10-Jun
30-Jul
15.40%
83.25%
84.60%
87.98%
91.76%
100.00%
95.69%
100.00%
18-Sep
7-Nov
Axis Title
27-Dec
15-Feb
6-Apr
26-May
HEDULE
pr
26-May
2014
EQUIPMENT
QUANTITY
JULY
7-Jul
BACKHOE (Tracked)
BACKHOE (Wheeled)
PAYLOADER
DUMP TRUCK
MOBILE CRANE
PUMPCRETE
SHOTCRETE PUMP
VIBRATOR
PNEUMATIC COMPACTOR
WELDING MACHINE
GENERATOR SET
COMPACT CONCRETE MIXER
1
1
1
1
1
1
2
2
2
2
1
1
14-Jul
AUGUST
21-Jul
28-Jul
4-Aug
4
AUGUST
11-Aug
SEPTEMBER
18-Aug
25-Aug
1-Sep
8-Sep
15-Sep
OCTOBER
22-Sep
6-Oct
EQUIPMENT SCHEDULE
2014
OCTOBER
13-Oct
NOVEMBER
20-Oct
27-Oct
3-Nov
10-Nov
17-Nov
DECEMBER
24-Nov
1-Dec
TIAL BUILDING
LE
DECEMBER
8-Dec
15-Dec
JANUARY
22-Dec
5-Jan
12-Jan
FEBRUARY
19-Jan
26-Jan
2-Feb
2015
FEBRUARY
9-Feb
MARCH
16-Feb
23-Feb
2-Mar
9-Mar
APRIL
16-Mar
23-Mar
6-Apr
ALZADA
APRIL
13-Apr
20-Apr
27-Apr
2.0
3.0
SITE WORKS
Clearing and Grabbing
Excavation
Backfilling and Compaction
Gravel Fill
Soil Poisoning
Subtotal 02
CIVIL WORKS
Concreting , Rebar and Formwors
FOOTING
Concrete
Rebar
Formworks
COLUMN
sq.m
cu.m
cu.m
cu.m
sq.m
199.00
36.49
298.50
30.71
199.00
150.00
1,150.00
75.00
cu.m
kg
sq.m
10.17
1,252.82
32.24
4,000.00
48.00
475.00
cu.m
kg
sq.m
5.52
1,379.70
83.70
4,000.00
48.00
475.00
cu.m
kg
sq.m
27.72
2,217.60
4.83
4,000.00
48.00
475.00
cu.m
kg
sq.m
1.04
125.37
11.28
4,000.00
48.00
475.00
150.00
895.00
300.00
870.00
###
###
###
###
-
###
###
###
###
###
###
### 1,100.00
###
16.00
###
550.00
###
###
###
###
###
###
### 1,100.00
###
16.00
###
550.00
6,070.68
###
###
###
###
###
###
###
###
### 1,100.00
###
16.00
2,294.25
550.00
###
###
###
###
2,656.50 4,950.75
4,179.00
6,017.76
5,356.58
1,149.23
2,005.92
6,202.35
1,100.00
16.00
550.00
5,328.23
8,023.68
###
###