Technological University of The Philippines

This document contains calculations for concrete and steel works for a construction project. It provides details of the estimated quantities of cement, sand, gravel and steel bars needed for the footings, columns, beams, slab, stairs and total works. The footings will require 40 bags of cement, 78 bags for the columns, 109 bags for the beams, 245 bags for the slab and 7 bags for the stairs, for a total of 479 bags. The estimated steel bars needed are 34 pieces for the footings, 110 pieces for the columns, 23 pieces for the beams and 22 pieces plus 19 pieces for lateral column and beam ties, for a total of 208 pieces.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
136 views

Technological University of The Philippines

This document contains calculations for concrete and steel works for a construction project. It provides details of the estimated quantities of cement, sand, gravel and steel bars needed for the footings, columns, beams, slab, stairs and total works. The footings will require 40 bags of cement, 78 bags for the columns, 109 bags for the beams, 245 bags for the slab and 7 bags for the stairs, for a total of 479 bags. The estimated steel bars needed are 34 pieces for the footings, 110 pieces for the columns, 23 pieces for the beams and 22 pieces plus 19 pieces for lateral column and beam ties, for a total of 208 pieces.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES

Ayala Blvd., Ermita, Manila


COLLEGE OF ENGINEERING
Civil Engineering Department

PROJECT TITLE: CONCRETE WORKS


OWNER/S: MR. & MRS. RESTITUTO S. PARAISO
LOCATION: 3160 ABUCAY STREET MANUGUIT TONDO, MANILA CITY
PREPARED BY: BEAS, NOWIE T.
Item to be
Estimated

FOOTINGS

CALCULATIONSCEMENT
FOOTING1 = (1.2m)(1.2m)(0.3m)(1.10m)(6) = 2.8512 m3
FOOTING2 = (1.2m)(1.2m)(0.3m)(1.10m)(6) = 2.8512 m3
TOTAL VOLUME FOR FOOTING = 5.7024 m3

SAND

GRAVEL

40 bags

2.8512 m3

5.7024 m3

78 bags

5.544 m3

11.088 m3

109 bags

9.081535 m3

11.088 m3

20.3740152
m3

40.7480304
m3

CEMENT: 5.7024 m3 x 7.0 = 39.9168 ; 40 bags


SAND: 5.7024 m3 x 0.50 = 2.8512 m3
GRAVEL: 5.7024 m3 X 1 = 5.7024 m3
COLUMN1 = (0.3m)(0.4m)(0.7m)(1.10)(6) = 0.5544 m3
COLUMN2 = (0.3m)(0.4m)(0.7m)(1.10)(6) = 0.5544 m3
COLUMN3 = (0.3m)(0.4m)(6.6m)(1.05)(6) = 4.9896 m3
COLUMN4 = (0.3m)(0.4m)(6.6m)(1.05)(6) = 4.9896 m3
COLUMNS
TOTAL VOLUME FOR COLUMN = 11.088 m

BEAMS

CEMENT: 11.088 m3 x 6.0 = 77.616 ; 78 bags


SAND: 11.088 m3 x 0.50 = 5.544 m3
GRAVEL: 11.088 m3 x 1 = 11.088 m3
BEAM1 = (0.4m)(0.25m)[9m+3.760m(4)+3.823m(2)+
3.474m(4)+3.1m(3)+5.026m(2)](1.05) = 6.81807 m3
BEAM2 = (0.4m)(0.25m)[10.52m(2)+6.574m(4)](1.05)
= 4.97028 m3
BEAM3 = (0.4m)(0.25m)(10.52m)(1.10)(2) = 2.3144 m3
BEAM4 = (0.4m)(0.25m)(3)(1.10) = 0.33 m3
BEAM5 = (0.4m)(0.25m)(3.76m)(1.10) = 0.4136 m3
BEAM6 = (0.4m)(0.25m)(6.575m)(1.10)(2) = 1.4465 m3
BEAM7 = (0.4m)(0.25m)(8.501m)(1.10)(2) = 1.87022 m3
TOTAL VOLUME FOR BEAMS = 18.16307 m3
CEMENT: 18.16307 m3 x 6.0 = 108.97842 ; 109 bags
SAND: 18.16307 m3 x 0.50 = 9.081535 m3
GRAVEL: 18.16307 m3 x 1 = 11.088 m3
SLAB1 = (5.975m)(2.4m)(0.6m)+(6.92m)(5.964m)(0.6m)
(1.05) = 35.0348544 m3
SLAB2 = [(2.874m)(2.4m)+(2.874m)(3.16m)+
(2.874m)(3.16m)+(2.5m)(2.4m)(2)+(4.426m)(3.92m)]
(1.05)(0.1m) = 5.713176 m3

SLAB

245 bags
TOTAL VOLUME FOR SLAB = 40.7480304 m3

CEMENT: 40.7480304 m3 x 6.0 = 244.488 ; 245 bags


SAND: 40.7480304 m3 x 0.50 = 20.3740152 m3
GRAVEL: 40.7480304 m3 x 1 = 40.7480304 m3

Item to be
Estimated

STAIRS

CALCULATIONSCEMENT
TOTAL VOLUME FOR STAIRS
= {[(0.09m2)(7)+(0.045m2)(6)](0.3m)(1.05)(2)}+(0.85)
(2)(0.3)(1.05)(2)
= 1.022175 m3
7 bags

SAND

GRAVEL

0.5110875 m3

1.022175 m3

38.3618377
m3

76.7236754
m3

CEMENT: 1.022175 m3 x 6.0 = 6.13305 ; 7 bags


SAND: 1.022175 m3 x 0.50 = 0.5110875 m3
GRAVEL: 1.022175 m3 X 1 = 1.022175 m3
TOTAL VOLUME:
TOTAL

479 bags
76.7236754 m3

Submitted to:
_ENGR. MARJUN B. MACASILHIG_
INSTRUCTOR

TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES


Ayala Blvd., Ermita, Manila
COLLEGE OF ENGINEERING
Civil Engineering Department

PROJECT TITLE: STEEL WORKS


OWNER/S: MR. & MRS. RESTITUTO S. PARAISO
LOCATION: 3160 ABUCAY STREET MANUGUIT TONDO, MANILA CITY
PREPARED BY: BEAS, NOWIE T.
Item to be
Estimated

FOOTINGS

CALCULATIONS
(1.2m/8)(2) = 0.3 m -> to be subtracted to 1.2
FOOTING1(6 sets)
PER PIECE:
0.9m+2[9(0.016)] = 1.188 m
1.188m x 14 = 16.632 m
PER SET:
16.632m x 6 sets = 99.792 m
99.792m / 6 = 16.632 ; 17pcs.-6m-16mm
FOOTING2(6 sets)
PER PIECE:
0.9m+2[9(0.016)] = 1.188 m
1.188m x 14 = 16.632 m
PER SET:
16.632m x 6 sets = 99.792 m
99.792m / 6 = 16.632 ; 17pcs.-6m-16mm

STEEL BARS

34 pcs.-6m-16mm

TOTAL LENGTH FOR FOOTING = 199.584 m

COLUMNS

TOTAL NUMBER OF STEEL BARS:


34 pcs.-6m-16mm
COLUMN1&3 (6 set) h = 6.6 m , 8 bars
LT = (6.6m)(8)(6) = 316.80 m
316.80m x 1.05 = 332.64 m
332.64m / 6 = 55.44 ; 55pcs.-6m-16mm
COLUMN2&4 (6 set) h = 6.6 m , 8 bars
LT = (6.6m)(8)(6) = 316.80 m
316.80m x 1.05 = 332.64 m
332.64m / 6 = 55.44 ; 55pcs.-6m-16mm
TOTAL LENGTH FOR COLUMNS = 665.28 m

110 pcs.-6m-16mm

TOTAL NUMBER OF STEEL BARS:


110 pcs.-6m-16mm

Item to be
Estimated

LATERAL
TIES
(COLUMNS)

CALCULATIONS
LTIES:
(0.4m)(2)+(0.3m)(2)+(20)(0.01m) = 1.6 m
1(0.001)+3(0.03)+5(0.05)+6(0.1) = 0.95(4 pieces)->15ties
2.6 / 0.2 = 13 ties
1.1 / 0.2 = 5.5 ; 6 ties

STEEL BARS

22 pcs-6m-10mm

TOTAL: 79 ties
LT = (1.6m)(79 ) = 126.4 m
126.4m / 6 = 21.07 ; 22 pcs-6m-10mm

TIE WIRES

BEAMS

Number of intersection:
7 x 7 = 49 int.
LTIE WIRES = 0.3 m
LT = (0.3m)(49) = 14.7 m
14.7m / 53 = 0.28 mg
(0.28kg)(10) = 2.8 kg no. 16 G.I. wire

BEAMS1&3 (4 set) d = 3.6 m , 4 bars


LT = (3.6m)(4)(4) = 57.60 m
57.60m x 1.05 = 60.48 m
60.48m / 6 = 10.08 ; 11pcs.-6m-16mm
BEAMS2&4 (6 set) d = 4 m , 4 bars
LT = (4m)(4)(4) = 64 m
64m x 1.05 = 67.2 m
67.2m / 6 = 11.2 ; 12pcs.-6m-16mm

2.8 kg no. 16 G.I. wire

23 pcs.-6m-16mm

TOTAL LENGTH FOR BEAMS = 127.68 m

LATERAL
TIES
(BEAMS)

TOTAL NUMBER OF STEEL BARS:


23 pcs.-6m-16mm
LTIES:
(0.4m)(2)+(0.2m)(2)+(20)(0.01m) = 1.4 m
1(0.001)+3(0.03)+5(0.05)+6(0.1) = 0.95(4 pieces)->15ties
2.6 / 0.2 = 13 ties
1.1 / 0.2 = 5.5 ; 6 ties
TOTAL: 79 ties
LT = (1.4m)(79 ) = 110.6 m
110.6m / 6 = 18.43 ; 19 pcs-6m-10mm

19 pcs-6m-10mm

Submitted to:
_ENGR. MARJUN B. MACASILHIG_
INSTRUCTOR