Formwork Lecture1
Formwork Lecture1
CM 420
420
Temporary Structures
Formwork for Concrete
CM 420
Temporary Structures
Temporary
Structures
Formwork For
Concrete
CM
CM 420
420
Temporary Structures
CM
CM 420
420
Temporary Structures
Grading System:
CM
CM 420
420
Temporary Structures
Formwork for Concrete
CM
CM 420
420
Temporary Structures
Recommended Textbooks:
Hurd, M. K., Formwork for
Concrete. 6th edition, American
Concrete Institute, Detroit, Michigan,
1995.
Ratay, Robert T., Handbook of
Temporary Structures in
Construction. 2nd edition, McGraw
Hill, New York, 1996.
4
CM
CM 420
420
Temporary Structures
CM
CM 420
420
Temporary Structures
CM
CM 420
420
Temporary Structures
Formwork for Concrete
CM
CM 420
420
Temporary Structures
CM
CM 420
420
Temporary Structures
CM
CM 420
420
Temporary Structures
CM
CM 420
420
Temporary Structures
Formwork for Concrete
CM
CM 420
420
Temporary Structures
A 1909 construction
scene shows the
first application of
steel forms for
street paving.
10
CM
CM 420
420
Temporary Structures
11
CM
CM 420
420
Temporary Structures
CM
CM 420
420
Temporary Structures
Formwork for Concrete
CM
CM 420
420
Temporary Structures
13
CM
CM 420
420
Temporary Structures
Form w ork
m aterial
cost
Concrete,
rebar,
footings,
placem ent
CM
CM 420
420
14
Temporary Structures
15
CM
CM 420
420
Temporary Structures
Formwork for Concrete
CM
CM 420
420
Temporary Structures
Formwork collapse
causes injuries, loss
of life, property
damage, and
construction delays
16
CM
CM 420
420
Temporary Structures
17
CM
CM 420
420
Causes of Failure
Temporary Structures
CM
CM 420
420
Temporary Structures
Formwork for Concrete
CM
CM 420
420
Temporary Structures
Causes of Failure
Inadequate Bracing
CM
CM 420
420
Temporary Structures
Causes of Failure
Inadequate Bracing Use of Diagonal Bracing
High shoring with heavy load at the top is
vulnerable to eccentric or lateral loading.
CM
CM 420
420
Temporary Structures
Causes of Failure
Inadequate Bracing
The main exhibition floor of the New York Coliseum
collapsed when concrete was being placed.
Forms for the floor slab were supported on two
tiers of shores.
Case study:
New York Coliseum
Formwork collapse,
where rapid
delivery of
concrete
introduced lateral
forces at the top of
high shoring.
21
CM
CM 420
420
Temporary Structures
Formwork for Concrete
CM
CM 420
420
Temporary Structures
Causes of Failure
Inadequate Bracing Use of Diagonal Bracing
Case study: New York Coliseum
Increased diagonal bracing was added to all
remaining shoring, following partial collapse of
formwork.
22
CM
CM 420
420
Temporary Structures
Causes of Failure
Inadequate Bracing Use of Diagonal Bracing
When a failure occurs at one part, inadequate
bracing may permit the collapse to extend to a
large portion of the structure and multiply the
damage.
Suppose a worker accidentally rams or
wheelbarrow into some vertical shores and
dislodges a couple of them. This may set up a
chain of reaction that brings down the entire floor.
One major objective of bracing is to prevent such
a minor accident or failure from becoming a
disaster.
23
CM
CM 420
420
Temporary Structures
Causes of Failure
Vibration
Forms sometimes collapse when their
supporting shores or jacks are displaced by
vibration caused by:
passing traffic
movement of workers and equipment on
the formwork
the effect of vibrating concrete to
consolidate it.
Diagonal bracing can help prevent failure
due to vibration.
24
CM
CM 420
420
Temporary Structures
Formwork for Concrete
CM
CM 420
420
Temporary Structures
Causes of Failure
CM
CM 420
420
Temporary Structures
Causes of Failure
Fresh
Concrete
H
26
CM
CM 420
420
Temporary Structures
Causes of Failure
CM
CM 420
420
Temporary Structures
Formwork for Concrete
CM
CM 420
420
Temporary Structures
10