Case Study PM
Case Study PM
of the required tasks for commissioning the new master depots and for closing the
existing depots. Next, IPM led the team through an optimization process that
reduced the schedule to the desired 18 months without jeopardizing customer
service or production operations.IPM trained the clients newly hired project
manager to take over the responsibility for the remaining implementation
activities.
4. Illustrate the flow of the project.
Ans: Annual operating savings: $16M
Capital investment reduction: $20M
Order fill rate: greater than 99% (improved from 96%)
18 months, a 40% reduction from the original plan
In addition to realizing the above results, the modified DSD network gives the
company additional flexibility to expand their product distribution, therefore
improving customer satisfaction and their own revenue