Use of Integration PM-PS For Effective Long-Term Planning: Joseph Layani
Use of Integration PM-PS For Effective Long-Term Planning: Joseph Layani
Long-Term Planning
Joseph Layani, PMP
Socit de Transport de Montral
Montreal Transit Commission
Produced by:
Supported by:
Journey to Success
Integration Process and Achievements
Project
Planning
Based on engineers
estimates
In a third party
software by projects
coordinators (Eng.
Dept.)
Project execution
Project Closing
Slide 5
External : PO to
contractors in MM-SRV
and Serv. entry
Internal : PM work orders
by maintenance planners
Maintenance
Planning
In SAP-PM
Based on
Maint. Plans simulation,
breakdown estimate
& projects
Use of Maintenance Work Centers
Infrastructure
Projects planners
Estimated
projects work
hours for
internal
resources
Preventive
maintenance
backlog
(hours/WC)
Preventive
maintenance
( hours / work
centers)
Overall
needed
working
hours
PM task
lists
Infrastructure
Maintenance planners
Corrective
maintenance
(hours /WC)
based on
historic data
Infrastructure
Maintenance Manager
PM work
orders
Trigger points
Engineering
Maintenance vs. Engineering
Lack of integration : Maintenance
Impossible to compare project estimates, made in the
third party software, with the planning made in PM
High level work area vs. PM work centers
o Annual Maint. team capacity allotted to projects : imprecise
o
Key challenges
Simplify the projects planning process
Productivity improvement for the Eng. Group
Kick-off
October 2011
Support & BI
deployment
Blueprint
(PS & BI)
May 2012
(6 months)
Realization
and tests
September 2012
(5months)
Conversion &
user training
November 2012
(2 months)
December
3rd 2012
Important Considerations
Change management
Technical considerations
Use of PM-PS integration points
performed
Project activities for internal resources are planned with a
control key that allows capacity requirement
PM order affectation to projects leads to an automatic
replacement of the activity control key (no capacity req.)
Work Centers usage must be changed from Maintenance
usage to All task list types usage
Results
Business process integration
Infrastructure Maintenance planners
Functional Location
Project
WBS
Network Activity
(Internal labor)
Link
Maintenance Order
for projects
Work Centers
Results
Business process integration
Project
Functional
Location
WBS
Network Activity
(Internal labor)
Capacity requirement is disabled
for project activity
Work
Centers
Maintenance Order
for projects
Short term planning
PM/
BW
Backlog for
preventive
maintenance
(hours/WC)
Calculated PM
work hours for
preventive
maintenance
Estimated
projects work
hours for internal
work centers
PS
Total work
hours
(Planned)
BO
Estimated
corrective work
hours /WC
based on
historic data
PM
Maintenance planners
Are able to react to change of project timeframe
o
Slide 17
Configuration point
Slide 18
Thank you
Questions
Slide 21