Pushing The Envelope With Coil Tubing Drilling: AADE-07-NTCE-31
Pushing The Envelope With Coil Tubing Drilling: AADE-07-NTCE-31
Abstract
Coil tubing drilling in the western Canadian sedimentary
basin has revolutionized the shallow gas drilling market.
Although coil tubing drilling has brought significant
improvements to this area, there are limitations. These
limitations include depth of penetration, vertical control in
problematic deviation areas, and directional drilling. With
increased pressure to reduce drilling cost, coil tubing drilling can
be an economic advantage for both directional wells and drill
depths over 1500m.
With emerging advances in coil tubing drilling rig depth
capacity, these typical shallow gas depths can be pushed past
1500m. Pushing coil tubing drill depths past 1500m has specific
challenges with regard to directional control and directional
drilling. For a large infield development well program, economic
advantages can be achieved with coiled tubing drilling if the
correct geological properties exist.
Directional drilling with coil tubing is not a new technology,
but has typically been limited in open hole size. When applying
coil tubing drilling and rotary steerable technology, open hole
advantages include an increase in hole size and a reduction in the
overall tortuosity of the well bore. Development fields with both
oil and gas wells require a larger open hole size for an effective
completion program.
This paper presents the challenges encountered in the
project from the basic conceptual design, through the detailed
engineering phase, to the execution of applying coil tubing
drilling with rotary steerable technology for both directional
drilling and directional control. The project objectives
incorporate an overall decrease in rig operation days. The
primary factors incorporated to achieve this are: mobilization, rig
up and down operations, drilling while surveying, tool
communication while drilling, and elimination of slide drilling.
Introduction
The western Canadian energy market has been subjected
to an increasing cost environment. Maintaining a constant well
cost or reducing well costs are a continual challenge. Coil
Tubing Drilling (CTD) using Hybrid Rigs has been a major
factor in controlling drilling costs for shallow oil and gas
AADE-07-NTCE-31
AADE-07-NTCE-31
AADE-07-NTCE-31
AADE-07-NTCE-31
CTD operations in the area of this study. The bit selected had
very few deviation problems with coil tubing drilling while
maintaining high ROP. The bit nozzle configuration had five
fixed nozzles and three adjustable nozzles. The total flow area
was too high to optimize hydraulics, and nozzle selection was
not designed for hydraulic optimization.
The first survey was taken 50m below the shoe. The
inclination had climbed to 3.25 and within 100m had climbed
to 4.5. The approach used to solve this problem was to utilize
drop bit technology. The drilling parameters with this bit
require a slow RPM (80-100 rpm) and increased WOB (8,000
daN-12,000 daN). In order to meet these drilling parameters a
low speed high torque motor was required. A thin/even-walled
motor was utilized for this particular application. During
drilling operations differential pressure was used as an
indicator of weight transmitted to the bit. When drilling
resumed, the deviation began to drop immediately and
corrected back to 1 inclination by 770m.
High WOB was maintained by maximizing the differential
pressure to the point of motor stall. When maximizing the
differential pressure, too much weight on bit was applied and
eliminated the corrective measure of the drop bit. There
appears to be a threshold where a high WOB is required to
maintain the BHA to drill vertical, although excess WOB
would tend to increase deviation.
The well was TD at 1866m and the wiper trip performed
did not require any back reaming. Only minor reaming was
required when running in the well to condition the wellbore
for logging operations. Open hole logging operations made
two attempts, both of which bridged off immediately under the
shoe. The two primary factors, which resulted in failed open
hole logging attempts were; not achieving desired mud
conditions and the reduced hole size had tighter tolerances
between the tools and the wellbore. After the second logging
attempt, the decision was made to case the well and perform
cased hole logs.
Discussion BRC HTR V 8-4
The offset well research did not indicate deviation
problems, although immediately after drilling 100m into
formation the wellbore deviation increased to 3.25
inclination. The increase in deviation proves that coiled tubing
drilling does have an inherently higher chance of deviation
than rotary drilling even when the CTD BHA is designed to
maintain the coil tubing in tension.
Once deviation had occurred, drop bit technology was
capable of both correcting deviation and controlling deviation
during the drilling operation of the well. The drop bit drilling
parameters required a high torque and low speed motor for
correct operation. The thin/even-walled motor sourced for this
AADE-07-NTCE-31
compressive strength would require at least one bit run and the
use of tri-cone diamond insert bits. Recommendations from bit
supply companies were not conclusive whether the Turner
Valley formation was drillable with PDC bit technology. In
the likely event that a PDC bit could not drill the Turner
Valley, a bit trip was programmed at ~2000m to change for a
tri-cone diamond insert bit.
Operational Review CoP 100 V 9-21
The wellbore geometry along with the casing scheme was
changed for this well. The change was made to mirror the
drilling wellbore geometry that proved successful for logging
operations with the conventional drilling rigs operated in the
area. The production hole size was increased to 200mm which
required a 171.5mm rotary steerable BHA size. The BHA
configuration was changed and an additional stabilizer was
added, as shown in figure 10. The stabilizer was added in an
attempt to increase the rigidity of the RSS BHA. The drilling
assembly was run in the well and built to an inclination of 4.4
in 80 m. The RSS BHA was pulled out of the hole and two
stabilizers were removed from the BHA, as shown in figure
11. The BHA was tripped in hole and it immediately began to
drop inclination and successfully maintained deviation below
1 inclination.
When drilling reached 1780m, the decision was made to
trip the directional control BHA out hole and continue drilling
with a slick BHA. Hole problems occurred during drilling
operations which required two additional bit trips. Offset well
information did not encounter similar problems.
When the Turner Valley formation was encountered the
PDC could not drill into the formation and a bit trip was made.
When the PDC bit was inspected on surface, severe damage to
the cutting structure was observed. The tri-cone bit selected to
drill into the Turner Valley, drilled 63m in 24hrs and was
tripped to surface because of a reduction in ROP. The bit was
inspected on surface and had severe damage and wear. At a
depth of 2140m the well was called TD.
While logging out hole the caliper arms had to be closed
several times to get through collapsed sections of the wellbore.
At 706m the caliper arms mechanically failed and would not
retract, resulting in stuck logging tool. The tools were
successfully retrieved out of the wellbore with a side entry sub
and fishing equipment. The casing was run and cemented
without incident.
Discussion CoP 100 V 9-21
Drilling 200mm open hole size had a significant reduction
in ROP when compared to 156mm. Such a dramatic drop of
ROP has not previously been experienced with coiled tubing
drilling in other areas. The mud system was also changed from
a Polymer to a Gel-Chem system. The previous two wells did
not have conclusive evidence that the Polymer Mud system
AADE-07-NTCE-31
References
1.Shafer, R.S.: Step Change in Remote Exploration, SPE/IADC
105051, SPE/IADC Drilling Conference, Amsterdam, The
Netherlands, February 20-22, 2007.
2.Bourgoyne A.T., Chenevert M.E., Millheim K.K., Young F.S.:
Applied Drilling Engineering.: SPE Testbook Series Vol.2,
Society of Petroleum Engineers, Ninth Printing 2003.
3.Steve Devereux: Practical Well Planning, PenWell Publishing
Company, 1998, ISBN 0-87814-696-2.
4.Gilles Gabolde, Jean-Paul Nguyen, Drilling Data Handbook,
Eight Edition, Editions Technip, 2006.
5.C. Pratten, Rotary Steerable Systems in the Gulf of Mexico - A
Step Change in Drilling Performance, AADE 01-NC-HO-22,
AADE 2001 National Drilling Conference, Houston, Texas,
March 27 - 29, 2001.
6.F. J. Schuh, P. Herbert, J. Harrell, The New Generation of Rotary
Systems May be Closer Than You Think, AADE-03-NTCE02, AADE 2003 National Drilling Conference and Exhibition,
Houston, Texas, April 1-3, 2003.
7.C. Sidwell, J. Jares, M. Durant, Rotary Steerable in 6 hole Key to
AADE-07-NTCE-31
E+00 = cm
E+01 = m
E+00 = N
E+01 = Kg
E+00 = kPa
AADE-07-NTCE-31
Appendix
Appendix
10
AADE-07-NTCE-31
140
120
Effective ROP
100
80
60
40
20
0
0
20
40
60
80
100
On Bottom ROP
120
140
AADE-07-NTCE-31
Appendix
11
0
0
0.5
1.5
-200
Depth (m)
-400
-600
-800
-1000
-1200
-50
0
-150
Depth (m)
-250
0.1
0.2
0.3
0.4
0.5
0.6
0.7
-350
-450
-550
-650
-750
0.8
12
AADE-07-NTCE-31
120
Proposed TD
Basal Belly River
Projection to TD
100
Tie-In
80
60
40
20
Tangent Section 13.23
Surface Casing (177.8mm)
0
50
100
-20
Casing at 86 m
-100
-80
-60
-40
-20
20
40
60
150
Critical Points
MD
INCL
AZIM
TVD
VSEC
N(+) / S(-)
E(+) / W(-)
DLS
Casing at 86 m
86.00
1.20
270.00
86.00
-0.16
-0.23
-0.10
1.49
Projection to TD
738.00
16.00
321.00
720.58
128.06
109.76
-66.61
0.67
Critical Point
200
250
300
350
True
Grid
Mag
400
450
Belly River
True North
Tot Corr (M->T +15.7660)
Mag Dec (+15.766)
500
550
Grid Conv ()
Taber Coal
600
650
McKay Coal
700
Lea Park
Proposed TD
750
-100
-50
50
100
150
200
250
300
350
Vertical Section (m ) Azim = 332.86, Scale = 1(cm ):50(m ) Origin = 0 N/-S, 0 E/-W
AADE-07-NTCE-31
Appendix
13
14
Figure 10: Vertical Control BHA Design 1 for COP 100 V 9-21
Figure 11: Vertical Control BHA Design 2 for COP 100 V 9-21
AADE-07-NTCE-31
AADE-07-NTCE-31
Appendix
-500
0.5
1.5
15
2.5
3.5
-700
Depth (m)
-900
-1100
-1300
-1500
-1700
-1900
-2100
Days From Drilling Out of Surface Casing
-500
-700
0.5
1.5
2.5
3.5
-900
Field Average
Depth (m)
-1100
-1300
-1500
-1700
-1900
-2100
Days From Drilling Out of Surface Casing
16
-500
-700
0.5
1.5
2.5
3
3.5
4
Coil Tubing Rig 2: 09-21-15-26W4
Conventional Rig 2: 05-11-15-27W4
Field Average
-900
Depth (m)
-1100
-1300
-1500
-1700
-1900
-2100
Days From Drilling Out of Surface Casing
AADE-07-NTCE-31
AADE-07-NTCE-31
Appendix
250
250
17
Surface
Casing
500
500
750
750
Form. 1
1000
TVD (m)
Form. 2
1250
1250
Form. 3
CoP 100 V 6-21
CoP 100 V 9-21
BRC HTR 8-4
1500
1500
Form. 4
1750
1750
Form. 5
2000
2000
2250
2250
0
-50
Inclination (Deg)
50
100
ROP (m/h)
150
200