Cost Controlling Using Earned Value Analysis in Construction
Cost Controlling Using Earned Value Analysis in Construction
I. INTRODUCTION
Earned Value analysis is a method of performance
measurement. Earned Value is a program management
technique that uses work in progress to indicate what will
happen to work in the future. Earned Value is an
enhancement over traditional accounting progress measures.
Traditional methods focus on planned accomplishment
(expenditure) and actual costs. Earned Value goes one step
further and examines actual accomplishment. This gives
managers greater insight into potential risk areas. With
clearer picture, managers can create risk mitigation plans
based on actual cost, schedule and technical progress of the
work. It is an early warning program/project management
tool that enables managers to identify and control problems
before they become insurmountable.
It allows projects to be managed better on time, on
budget. Earned Value Management System is not a specific
system or tool set, but rather, a set of guidelines that guide a
companys management control system. In the case of cost
overrun, project management team may execute a value
engineering program for cost reduction either reducing
scope and quality in some sections of project or providing
additional budget to cover overrun cost. Similarly, for time
overrun case, the may plan some program such as fast
tracking or time crashing for time reduction. Therefore, the
role of EVM as well as correct and on time forecasting is
very important to achieve project goals. This research
includes implementation and improvement on EV to achieve
a forecasting EAC based on statistical and econometrics
techniques and traditional EV indexes as well. This paper
discusses effectiveness of developed software of Earned
Value Analysis with MS Project and Primavera P6.
Planned Value
Earned Value
Actual Value
As noted, there are many ways to calculate the EV, PV
and AC of work packages that are in progress. Comparison
of those figures can serve to identify specific work packages
in which performance and progress is inadequate or
advanced, which will hopefully lead to remedial action by
the project manager and team. Cost and schedule
performance should be measured and analyzed as feasible
with regularity and intensity consistent with project
management need including the magnitude of performance
risk. Analysis should be progressive and should follow the
principle of management by exception. Variance thresholds
should be established in the planning phase and should be
used to guide the examination of performance [2].
324
ISSN: 2277-3754
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 1, Issue 4, April 2012
Name
EV AC
EV PV
EV / AC
EV / PV
Estimate At Completion(EAC)
BAC / CPI
AC + ETC
EAC AC
BAC EAC
325
ISSN: 2277-3754
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 1, Issue 4, April 2012
Fig 2 Scheduling activity, relationship SS, FS, FF, SF, Start Date, Finish Date
326
ISSN: 2277-3754
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 1, Issue 4, April 2012
327
ISSN: 2277-3754
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 1, Issue 4, April 2012
328
ISSN: 2277-3754
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 1, Issue 4, April 2012
329
ISSN: 2277-3754
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 1, Issue 4, April 2012
C. EARNED VALUE ANALYSIS IN DEVELOPED SOFTWARE
Fig 10 Scheduling Activity, Relationship SS, FS, FF, SF, Start Date, Finish Date
330
ISSN: 2277-3754
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 1, Issue 4, April 2012
V. RESULTS
In this study 8 parameters where consider for
effectiveness of Developed Software, for this purpose
comparison was done between M.S Project, Primavera
TITLE
PARAMETER
MS PROJECT
PRIMAVERA P6
Case Study
Mahindra Tech
Planed Duration
159 days
159 days
DEVELOP
SOFTWARE
159 days
Actual Duration
166 days
166 days
166 days
PV
Rs.15,47,600
Rs.15,47,600
Rs.15,47,600
AC
EV
CV
Rs.16,24,400
Rs.15,47,600
0.93
Rs.16,24,400
Rs.15,47,600
0.93
Rs.16,24,400
Rs.15,47,600
0.93
CPI
Rs.76,800
Rs.76,800
Rs.76,800
SV(t)
8 days
[PV - Planned Value, AC - Actual Value, EV - Earned Value, CV - Cost Variance, CPI - Cost Performance Index, PD Planned Duration, AD - Actual Duration, SV(t) - Schedule Variance respect to time.]
contractors involved in the wide range of construction
industries.
VI. CONCLUSION
Although EVA(Earned Value Analysis) may be most
The two Projects were analysed using the developed
easily associated with the monitoring and evaluation of software (in C#, .Net & SQL server) and MS Project 2007
project cost that are undertaken within an organization, it and Primavera P6 based on Earned Value Analysis Method.
can also be readily applied, with some adjustment, to the CPI, PD, AD, CV, PV, AC, EV variable were selected. The
control of project cost that are performed by contractors and result shows a strong relation between each software. The
vendors. In those circumstances, however, it must be final result gives more than 99.5% accuracy. A new
recognized that the client and contractor will have differing parameter SV (t) (Schedule Variances respect to time) is
perspectives on actual and budgeted costs. This study also identified and incorporated in developed software which is
indicated that EVA has significant value and presents not in MS Project 2007 and Primavera 6. The final result
unique features that can benefit clients, consultants and gives almost 100% accuracy.
331
ISSN: 2277-3754
International Journal of Engineering and Innovative Technology (IJEIT)
Volume 1, Issue 4, April 2012
REFERENCES
[1] ANSI/EIA-748-1998.
[2] A Guide to the project management body of knowledge
(PMBOK Guide)- Fourth Edition.
[3] Anbari, F. T (2003). Earned Value Project Management
Method and Extensions. Project Management journal, 34(4),
12-23
[4] Carles I. Budd, Charlene S. Budd IInd Edition A Practical
Guide to Earn Value Project Management.
[5] EunHong Kim, William G. Wells Jr, Michael R. Duffey
(2003). A Model for Effective Implementation of Earn Value
Management Methodology International Journal Of Project
Management 21 375-382.
[6] FRANK T. ANBARI, PH.D., P.E., PMP The Earned Value
Analysis Method: Extensions and Simplifications The
George Washington university.
[7] G Jagannathan Third reprint 1997 Getting More At Less
Cost The Value Engineering Way Tata McGraw-Hill
Publication
[8] ImanAttarzadeh, OwSiewHock (2009). Implementation and
Evaluation of Earned Value Index to Achieve an Accurate
Project Time and Cost Estimation and Improve Earned Value
Management System. International Conference on
Information Management and Engineering.
[9] Krishan K Chitkara Tenth reprints 2006 Construction Project
Management Tata McGraw-Hill Publication.
[10] Larry W. Zimmerman, Glen D. Hart Ist Edition Value
Engineering a practical approach for owner, designers and
contractors CBS Publication.
[11] Mario Vanhoucke and Stephan Vandevoorde (2009).
Forecasting a Projects Duration under Various Topological
Structures. The Measurable News ES
[12] Javier Pajares, Adolfo Lopez-parades (2010). An extension
of the EVM analysis for project monitoring: The Cost Control
Index and the Schedule Control Index Science Direct
International Journal Of Project Management.
[13] Jose Angelo Valle, Carlos Alberto Pereira Soares. The use of
Value Analysis (EVA) in the construction Projects. Federal
University Fluminense, Brazil, IBEC, Brazil.
[14] Paul Bowen, Peter Edwards, Keith Cattell, Ian Jay (2010).
The awareness and practice of value management by South
African consulting engineers: Preliminary Research survey
findings Science Direct International Journal of Project
Management 28 285-295.
[15] Stephan Vandevoorde, Mario Vanhoucke (2006). A
Comparison of different project duration forecasting methods
using Earned Value Metrics Science Direct International
Journal of Project Management 24 289-302.
[16] The Measurable News.(PMI,Project management institute)
[17] Walt Lipke (2006). Stastical Methods Applied to EVM
the Next Frontier The Measurable News ES.
[18] Walt Lipke (2009). The To Complete Performance Index An
Expanded View The Measurable News ES.
332