DQ Challenges and Considerations
DQ Challenges and Considerations
This article
discusses some
of the
challenges,
execution
methods, and
potential
opportunities of
Design
Qualification
(DQ).
Reprinted from
PHARMACEUTICAL ENGINEERING
Why DQ?
Design Qualification
Specification Resource
There is a group in ISPE that focuses on GAMP in the
Americas. A subgroup of that group was formed called
the Joint Equipment Transition Team or JETT.
The group defines themselves on the JETT homepage
at http://www.jettconsortium.com as the following.
JETT is a consortium of pharmaceutical users (manufacturers), equipment suppliers, and consultants seeking to improve communications between users and
suppliers to more effectively meet the validation
requirements of the pharmaceutical industry.
This consortium has produced URS templates for
various pieces of equipment that are available for
download free of charge from the site. These templates
have been created based on the GAMP 4 methodologies.
In addition to the many URS templates available,
sample design and functional specification are included
on the site.
A matrix on the sample documents Web page
provides the status of current and future documents
the JETT is working on.
Specifications
Specifications are an important part of what defines the
design of a system or piece of equipment. Companies within
the pharmaceutical industry frequently use common terms
for specifications that unfortunately may have different meanings, interpretations, and impacts.
For example, the User Requirement Specification (URS)
as described in GAMP 4 is to be used for describing what a
system is supposed to do.4 This entire guide was written for
2
Design Qualification
dures. At a minimum, when a documented design review is
performed on systems or components that are to be qualified,
the review should be performed as a DQ.
Validation Plan
A validation plan is needed early in the project to determine
how facilities, systems, and equipment will be validated. The
validation plan should be shared with the project team,
particularly with those that will be performing the design.
The validation plan should address an impact assessment
and qualification rationale.7 The plan determines what will
be qualified; part of this qualification may be DQ. For example, the plan may state that all elements of a design that
have been determined to have a potential to impact product
quality shall be qualified during a DQ.
If applicable, the intent to perform DQs on a project should
be decided before a Request for Proposal (RFP) goes out for
bid to design firms.
DQ Execution
The pharmaceutical manufacturer or their designee must
provide a specific document that defines the users requirements to meet the intended purpose of the system or equip-
System User
Designer of the System
Validation
Quality Assurance
Project Management
Design Qualification
requirements or scope should be explained in the DQ document. Changes also should be submitted to the appropriate
party to update the users requirement or scope document.
The timing of the execution of a DQ is important to the
schedule of a project. The final DQ on a system should be late
enough so that all of the design documents have been completed, but early enough so that the fabrication or construction is not delayed. Project management should be aware that
any fabrication or construction on a system that is to be
qualified would be at risk if performed before a DQ had been
completed on the proposed design.
Design Qualification
outs, etc.) and a 20% estimate was developed for capital cost
approval. The estimate exceeded what XYZ Inc. had expected
the cost to be. A value engineering exercise was then
performed to reduce the scope and cost of the project. Once the
estimate was within XYZ Inc.s budgeted amount, the early
design documents were revised to reflect the value-engineered scope of the project.
The documents were then used by XYZ Inc. to group
portions of the project into systems. XYZ Inc.s Quality
Assurance group then had a Validation Master Plan (VMP)
created. The VMP had a list of systems and whether they
were to be considered a direct impact system. The VMP also
stated that a DQ would be carried out on direct impact design
elements only.
XYZ Inc. uses a document they call a User Requirement
Document (URD) to convey their needs for the project. The
document also designates which of those needs their process
operations and validation groups feel could have an impact on
the quality of the product on direct impact systems.
XYZ Inc.s VMP states that a DQ will be performed on
direct impact systems and equipment before design documents are approved for fabrication or issued for construction.
Once a direct impact system has successfully passed a DQ,
the design documents for that system can be approved for
fabrication or issued for construction. These same documents
then become controlled documents under XYZ Inc.s Quality
Assurance program. Updates or revisions to these documents
then require a QA/Validation evaluation as to whether they
constitute a change to the executed DQ.
XYZ Inc. had required a DQ before construction of each
design; however, the team would also be required to perform
a design review at regular intervals during design to check
that URD points for all systems are being met by the design.
The design team members were sent copies of the User
Requirements document, URD-123589-4 Rev. A, that had
been written earlier in the project in advance of the time set
for the DQ of the Cyclization Reactor. See Figure 1 for an
example page of the URD-123589-4 Rev. A document. A list
of the design and design history documents that would be
used in the DQ was also sent to the disciplines responsible for
the documents.
During the execution of the DQ, the team members examined each of the design documents listed on DQ-123589-4
(Figure 2) and verified that the design documents will meet
the requirements that may have an impact on product quality
as listed in URD-123589-4 Rev. A.
A review of the pump calculations was required for requirement URD-23859-4-3 to determine that the right pipe
and pump size had been specified.
The piping and layout drawings showed the quench tank
T-402 as being in the same room as the reactor. Yet the
requirement URD-23859-4-3 stated that the quench tank
was to be in the isolation room. This turned out to be the only
deviation so the meeting was adjourned and an investigation
of the deviation was requested.
A review of meeting minutes was performed to determine
why the location had been changed. The design team was
Copyright ISPE 2005
Summary
Pharmaceutical manufacturers may or may not have systems in place for performing DQ. The DQ procedures and
expectations will vary from company to company. Design
firms, vendors, and other support resources for pharmaceutical manufacturers need to understand the clients DQ needs
and have systems and methods adaptable to those needs.
A clear agreement on the expectations for how facilities,
systems, and equipment will be specified and which elements
will require DQ is required by the entire design team. This
should be addressed for each type of system. In particular, the
client should be aware of the typical methodologies within
each discipline of a design team.
DQ practices can improve the control of a project. The
execution of a DQ should clearly identify:
Design Qualification
the document that established the intended purpose of
the proposed design
the documents that define the design
the documents that were used to develop the design
The purpose of this article was to provide concepts, considerations, and examples that pharmaceutical industry professionals can use to help create or improve procedures for
dealing with DQ. Remember, DQ, as stated by the ICH Q7A,
is the documented verification that the proposed design of
the facilities, systems, and equipment is suitable for the
intended purpose.
References
1. FDA Presentation ICH Q7A GMP Guidance for APIs and
its Use During Inspections, http://www.fda.gov/cder/meeting/ICH_Q7A/index.htm, 2002.
2. Commission of the European Communities. The Rules
Governing Medicinal Products in the EC, Vol. IV, Good
Manufacturing Practice for Medicinal Products, Annex
15 Qualification and Validation, Luxemburg Office for
Official Publications of the EC, ISBN 92-828-2029-X,
1998.
3. Code of Federal Regulation, Title 21, Volume 8, CITE:
21CFR820.30, revised as of April 1, 2004.
4. GAMP 4 Guide for Validation of Automated Systems,
ISPE, Appendix D1, page 1, 2001.
5. GAMP 4 Guide for Validation of Automated Systems,
ISPE, Section 9.5.1, page 53, 2001.
6. ISPE Baseline Pharmaceutical Engineering Guide, Volume 5, Commissioning and Qualification, page 75, First
Edition, March 2001.
7. ISPE Baseline Pharmaceutical Engineering Guide, Volume 5, Commissioning and Qualification, page 65, First
Edition, March 2001.
8. GAMP 4 Guide for Validation of Automated Systems,
ISPE, Appendix M5, page 3, 2001.