Comparison of Cartridge-Anfo-Emulsion Charging Methods
Comparison of Cartridge-Anfo-Emulsion Charging Methods
NORMET
COMPARISION OF
CARTRIDGE- , ANFO- &
EMULSION CHARGING METHODS
J Lehto
Drilling
Tunnel A = 58 m2
Tunnel width 7,5 m
Tunnel height 8,7 m
Drilling length 6,3 m (22)
Pull out length 5,8 m
Parallel cut
Opening holes 3 x 102 mm
Blasting holes 123 x 51 mm
Initiating
Non-electric detonators
Cartridge charging
ANFO charging
Emulsion charging
Cartridge -charging
ANFO -charging
50 % less
Charging time:
111 holes x 4 min/hole = 444 min
Charging time:
61 holes x 4 min/hole
50 holes x 1 min/hole =
Total
= 244 min
= 50 min
= 294 min
35 % less
6
Cartridge -charging
Emulsion -charging
60 % less !
Charging time:
111 holes x 4 min/hole = 444 min
Charging time:
111 holes x 1 min/hole = 111 min
75 % less !
7