Arrow Diagram Example - Benchmarking Project: 0 5 3 8 Latest Start

This arrow diagram shows the critical path for a benchmarking project with 14 tasks. The critical path has a total duration of 56 days from earliest start to latest finish. Key tasks on the critical path include developing a detailed plan, training the team, collecting data, analyzing data, developing a new process, and getting approval for implementation.

Uploaded by

Prabu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views

Arrow Diagram Example - Benchmarking Project: 0 5 3 8 Latest Start

This arrow diagram shows the critical path for a benchmarking project with 14 tasks. The critical path has a total duration of 56 days from earliest start to latest finish. Key tasks on the critical path include developing a detailed plan, training the team, collecting data, analyzing data, developing a new process, and getting approval for implementation.

Uploaded by

Prabu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 4

Arrow Diagram example - Benchmarking project

Earliest finish

Earliest start

Number of days

0
3

5 Develop broad plan

Latest finish

5
8

Latest start

2
5 7
8 10

Get approval

3
7 17
10 20

Identify team

10

4
2
19 21
24 26

Develop detailed plan


2

5
4

17 19
20 22

Train team

Conduct research

19 23
22 26

7
Identify key practices

23 26
28 31

23 38
27 42

Identify partners
15

10

23 33
26 36

Collect data

Critical path
0

2
Develop
questions

Identify current
state

11

26 37
31 42

26 28
40 42

10

9
Critical path
6
Analyze data

0
39 45
48 54

12

11

Visit partners 6
12

Develop new process

33 39
36 42

39 51
42 54

13
2

Finalize new process

51 53
54 56

Critical path

Critical path

54 56

14
Get approval for implementation

4
15

53 57
56 60

Latest finish

Critical path

Critical path

Critical path

Critical path