Delay Report
Delay Report
Activity Name
Adibatla - SEZ
2 Phase I
3 Statutory Approvals
4 Fire Authority Approval
5 Preparation of Documents for Submission by Consultant
5 Preparation of Drgs for Submission by Consultant
5 Submission of Documents/Drgs to Authority & Review
5 Approval from Fire Authority Approval
4 HMDA Approvals
5 Preparation of Documents for Submission by Consultant
5 Preparation of Drgs for Submission by Consultant
5 Submission of Documents/Drgs to Authority & Review
5 Approval from HMDA
4 AAI Approval
5 Preparation of Drgs for Submission by Consultant
5 Submission of Documents/Drgs to Authority & Review
5 Approval from AAI
4 MoEF Approval
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
1009058
1
2
3
A27280
A27290
A27310
A27320
4
A27330
A27340
A27360
A27370
2
A27240
A27260
A27270
1
13-Feb-2012
13-Feb-2012
16-Mar-2012
16-Mar-2012
22-Mar-2012
16-Mar-2012
31-May-2012
18-Jun-2012
16-Mar-2012
16-Mar-2012
16-Mar-2012
25-May-2012
13-Aug-2012
16-Mar-2012
16-Mar-2012
31-May-2012
18-Jun-2012
09-May-2012
21-Feb-2014
21-Feb-2014
20-Aug-2012
25-Jun-2012
12-May-2012
07-May-2012
16-Jun-2012
25-Jun-2012
20-Aug-2012
07-May-2012
07-May-2012
11-Jun-2012
20-Aug-2012
25-Jun-2012
07-May-2012
16-Jun-2012
25-Jun-2012
11-Aug-2012
11-Feb-2012A
11-Feb-2012A
19-Mar-2012A
19-Mar-2012A
22-MAR-12A
19-MAR-12A
04-JUN-12A
21-JUN-12A
19-Mar-2012A
19-MAR-12A
19-MAR-12A
25-MAY-12A
13-AUG-12A
20-Mar-2012A
20-MAR-12A
04-JUN-12A
28-JUN-12A
10-May-2012A
11-May-2015
11-May-2015
31-May-2013
31-May-2013
16-MAY-12A
10-MAY-12A
20-JUN-12A
31-MAY-13
31-May-2013
10-MAY-12A
11-MAY-12A
14-JUN-12A
31-MAY-13
31-May-2013
23-MAY-12A
27-JUN-12A
31-MAY-13
31-May-2013
-380d
-380d
-244d
-292d
-2d
-2d
-2d
-291d
-244d
-2d
-3d
-2d
-244d
-292d
-13d
-8d
-291d
-251d
Page 1 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A27190
A27200
A27210
A27220
3
A
10
1
A28400
A28410
6
1
A28290
A28300
A28310
A28320
4
A29320
09-May-2012
30-Jun-2012
18-Jul-2012
04-Aug-2012
13-Feb-2012
20-Apr-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
29-Jun-2012
17-Jul-2012
03-Aug-2012
11-Aug-2012
28-Feb-2013
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
10-MAY-12A
30-JUN-12A
18-JUL-12A
31-AUG-12A
11-Feb-2012A
07-Aug-2012A
10-Jan-2013A
10-Jan-2013A
10-JAN-13A
10-JAN-13A
12-Oct-2012A
17-Oct-2012A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
12-Oct-2012A
12-OCT-12A
11-JUL-12A
31-JUL-12A
31-AUG-12A
31-MAY-13
31-May-2013
31-May-2013
31-May-2013
31-May-2013
10-JAN-13A
10-JAN-13A
31-May-2013
31-May-2013
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
31-May-2013
12-OCT-12A
-9d
-11d
-23d
-250d
-65d
-269d
-269d
-269d
-169d
-169d
-269d
-269d
-112d
-112d
-112d
-112d
-282d
-122d
Page 2 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
7 SECTIONS B-B
7 DETAILS
7 RAMP DETAILS
6 U1 Block
7 SECTION -3 & SECTION 4
7 SECTIONS C-C & D-D
7 SECTION E-E / SECTION 1 / SECTION 2
7 WALL SECTIONS & SHAFT TERMINATION DETAILS
7 SECTIONS A-A & B-B / EQUIPMENT HATCH DETAILS
6 S2 Block
7 SECTIONS A-A ,B-B & C-C
7 SECTIONS D-D & ELEVATIOS D-D
7 WALL / FACADE SECTIONS
7 WALL / FACADE SECTIONS
6 K1 Block
7 SECTIONS & DETAILS
7 BUILDING SECTIONS
5 General Drgs
A29330
A29340
A29350
3
A29080
A29050
A29060
A29070
A29040
2
A28710
A28720
A28730
A28740
8
A29540
A29580
1
20-Apr-2012
20-Apr-2012
20-Apr-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
12-OCT-12A
27-FEB-13A
12-OCT-12A
17-Oct-2012A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
12-Oct-2012A
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
25-Mar-2013A
25-MAR-13A
25-MAR-13A
07-Aug-2012A
12-OCT-12A
27-FEB-13A
12-OCT-12A
31-May-2013
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
31-May-2013
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
31-May-2013
25-MAR-13A
25-MAR-13A
31-May-2013
-122d
-216d
-122d
-269d
-112d
-112d
-112d
-112d
-112d
-270d
-110d
-110d
-110d
-110d
-270d
-222d
-222d
-269d
Page 3 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 S1 Block
7 SITE PLAN - (Architectural )
7 SITE PLAN - ( Main Services Tunnel Layout )
7 SITE PLAN - Main Services Tunnel - Overall Setting-out Plan
7 Tunnel - Setting-out Detail Plan
7 Tunnel - Detail Sections
7 Tunnel - Detail Sections
7 Tunnel - Setting-out Detail Plan
5 Others
6 REVISED LEVEL FOR SERVICE ELEVATOR PIT DEPTH
6 REVISED LEVEL FOR SERVICE ELEVATOR PIT DEPTH
6 REVISED LEVEL FOR SERVICE ELEVATOR PIT DEPTH & DRAIN SUMPS
6 REVISED LEVEL FOR SERVICE ELEVATOR PIT DEPTH & DRAIN SUMPS
6 REVISED LEVEL FOR SERVICE ELEVATOR PIT DEPTH & DRAIN SUMPS
6 REVISED INVERT LEVEL FOR DRAIN SUMP
6 REVISED INVERT LEVEL FOR DRAIN SUMP
6 REVISED INVERT LEVEL FOR DRAIN SUMP
6 TYPICAL FLOORS NAHANI LOCATION SETTING OUT PLAN
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
1
A27930
A27940
A27950
A27960
A27970
A27980
A27990
11
A29600
A29610
A29620
A29630
A29640
A29650
A29660
A29670
A29690
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
07-Aug-2012A
07-AUG-12A
27-SEP-12A
26-SEP-12A
26-SEP-12A
26-SEP-12A
26-SEP-12A
22-OCT-12A
19-Oct-2012A
19-OCT-12A
19-OCT-12A
19-OCT-12A
19-OCT-12A
19-OCT-12A
19-OCT-12A
19-OCT-12A
19-OCT-12A
08-JAN-13A
31-May-2013
07-AUG-12A
27-SEP-12A
26-SEP-12A
26-SEP-12A
26-SEP-12A
26-SEP-12A
22-OCT-12A
31-May-2013
19-OCT-12A
19-OCT-12A
19-OCT-12A
19-OCT-12A
19-OCT-12A
19-OCT-12A
19-OCT-12A
19-OCT-12A
08-JAN-13A
-269d
-62d
-98d
-97d
-97d
-97d
-97d
-115d
-270d
-115d
-115d
-115d
-115d
-115d
-115d
-115d
-115d
-168d
Page 4 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A29700
A29710
A29720
A29730
2
1
A28000
A28010
A28020
A28030
A28040
A28050
A28060
A28070
A28080
4
A29130
A29140
08-May-2012
08-May-2012
08-May-2012
08-May-2012
20-Apr-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
08-JAN-13A
08-JAN-13A
08-JAN-13A
11-JAN-13A
20-Sep-2012A
20-Sep-2012A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-Sep-2012A
20-SEP-12A
20-SEP-12A
08-JAN-13A
08-JAN-13A
08-JAN-13A
11-JAN-13A
31-May-2013
31-May-2013
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
31-May-2013
20-SEP-12A
20-SEP-12A
-168d
-168d
-168d
-171d
-269d
-269d
-93d
-93d
-93d
-93d
-93d
-93d
-93d
-93d
-93d
-282d
-106d
-106d
Page 5 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A29150
A29160
A29170
2
A28420
A28430
A28440
A28450
A28460
A28470
A28480
A28490
A28500
3
A28820
A28830
A28840
A28850
20-Apr-2012
20-Apr-2012
20-Apr-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-SEP-12A
20-SEP-12A
28-MAR-13A
20-Sep-2012A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-Sep-2012A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
28-MAR-13A
31-May-2013
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
31-May-2013
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
-106d
-106d
-237d
-270d
-94d
-94d
-94d
-94d
-94d
-94d
-94d
-94d
-95d
-269d
-93d
-93d
-93d
-93d
Page 6 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A28860
A28870
A28880
7
A29500
6
A29460
5
A29420
8
A29560
8
2
A28790
A28800
4
A29380
A29400
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
20-SEP-12A
20-SEP-12A
17-OCT-12A
28-Mar-2013A
28-MAR-13A
28-Mar-2013A
28-MAR-13A
28-Mar-2013A
28-MAR-13A
25-Mar-2013A
25-MAR-13A
12-Oct-2012A
12-Oct-2012A
12-OCT-12A
04-JAN-13A
12-Oct-2012A
12-OCT-12A
12-OCT-12A
20-SEP-12A
20-SEP-12A
17-OCT-12A
31-May-2013
28-MAR-13A
31-May-2013
28-MAR-13A
31-May-2013
28-MAR-13A
31-May-2013
25-MAR-13A
31-May-2013
31-May-2013
12-OCT-12A
04-JAN-13A
31-May-2013
12-OCT-12A
12-OCT-12A
-93d
-93d
-112d
-270d
-225d
-270d
-225d
-270d
-225d
-270d
-222d
-269d
-270d
-110d
-166d
-269d
-109d
-109d
Page 7 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 S1 Block
7 PASENGOR ELEVATOR (1-16) / SERVICE ELE DETAILS
7 ESCALATOR DETAILS
5 Centre Line Plans
6 U1 Block
7 BASEMENT FLOOR
7 BASEMENT TANK SLEEVE SETTING OUT
7 BASEMENT TANK TOP LEVEL @ +96.75M LVL
7 GROUND FLOOR
7 MEZZANINE FLOOR PLAN
7 FIRST FLOOR PLAN
7 TERRACE FLOOR PLAN
6 P1 Block
7 LOWER BASEMENT FLOOR PLAN
7 UPPER BASEMENT FLOOR PLAN
7 GROUND FLOOR PLAN
7 FIRST FLOOR PLAN
7 TERRACE FLOOR PLAN
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
1
A28370
A28380
3
3
A28890
A28900
A28910
A28920
A28930
A28940
A28950
4
A29180
A29190
A29200
A29210
A29220
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
17-Oct-2012A
17-OCT-12A
04-JAN-13A
20-Sep-2012A
20-Sep-2012A
20-SEP-12A
27-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-Sep-2012A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
31-May-2013
17-OCT-12A
04-JAN-13A
31-May-2013
31-May-2013
20-SEP-12A
27-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
31-May-2013
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
-269d
-112d
-165d
-269d
-269d
-93d
-98d
-93d
-93d
-93d
-93d
-93d
-282d
-106d
-106d
-106d
-106d
-106d
Page 8 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 K1 Block
7 CENTRELINE,LAYOUT PLAN & ELEVATIONS
7 FIRST FLOOR CENTRELINE PLAN
6 S1 Block
7 GROUND FLOOR
7 MEZZANINE FLOOR
7 FIRST FLOOR PLAN
7 SECOND FLOOR PLAN
7 THIRD FLOOR PLAN
7 FOURTH FLOOR PLAN
7 FIFTH FLOOR PLAN
7 SIXTH FLOOR PLAN
7 TERRACE FLOOR PLAN
6 S2 Block
7 GROUND FLOOR
7 MEZZANINE FLOOR
7 FIRST FLOOR PLAN
7 SECOND FLOOR PLAN
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
8
A29530
A29550
1
A28090
A28100
A28110
A28120
A28130
A28140
A28150
A28160
A28170
2
A28510
A28520
A28530
A28540
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
10-Feb-2013A
10-FEB-13A
25-MAR-13A
20-Sep-2012A
20-SEP-12A
04-DEC-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-Sep-2012A
20-SEP-12A
03-DEC-12A
20-SEP-12A
20-SEP-12A
31-May-2013
10-FEB-13A
25-MAR-13A
31-May-2013
20-SEP-12A
04-DEC-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
31-May-2013
20-SEP-12A
03-DEC-12A
20-SEP-12A
20-SEP-12A
-270d
-192d
-222d
-269d
-93d
-144d
-93d
-93d
-93d
-93d
-93d
-93d
-93d
-270d
-94d
-144d
-94d
-94d
Page 9 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A28550
A28560
A28570
A28580
A28590
7
3
A29090
A29100
A29110
A29120
4
A29360
A29370
2
A28750
A28760
A28770
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
20-Apr-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
12-Oct-2012A
17-Oct-2012A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
12-Oct-2012A
12-OCT-12A
12-OCT-12A
12-Oct-2012A
12-OCT-12A
12-OCT-12A
12-OCT-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
20-SEP-12A
31-May-2013
31-May-2013
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
31-May-2013
12-OCT-12A
12-OCT-12A
31-May-2013
12-OCT-12A
12-OCT-12A
12-OCT-12A
-94d
-94d
-94d
-94d
-95d
-269d
-269d
-112d
-112d
-112d
-112d
-282d
-122d
-122d
-270d
-110d
-110d
-110d
Page 10 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 STAIRCASE-08
6 S1 Block
7 STAIRCASE-01/02/03/04
7 STAIRCASE-05
7 STAIRCASE- 06
7 STAIRCASE-08
5 Exterior Elevations
6 P1 Block
7 NORTH ELEVATION
7 SOUTH ELEVATION
7 WEST & EAST ELEVATION
6 K1 Block
7 BUILDING ELEVATIONS
6 S2 Block
7 ELEVATIONS A & B
7 ELEVATION C
6 S1 Block
7 ELEVATIONS A & B
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A28780
1
A28330
A28340
A28350
A28360
5
4
A29290
A29300
A29310
8
A29590
2
A28690
A28700
1
A28270
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
12-OCT-12A
17-Oct-2012A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
12-Oct-2012A
12-Oct-2012A
12-OCT-12A
12-OCT-12A
12-OCT-12A
25-Mar-2013A
25-MAR-13A
12-Oct-2012A
12-OCT-12A
12-OCT-12A
17-Oct-2012A
17-OCT-12A
12-OCT-12A
31-May-2013
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
31-May-2013
31-May-2013
12-OCT-12A
12-OCT-12A
12-OCT-12A
31-May-2013
25-MAR-13A
31-May-2013
12-OCT-12A
12-OCT-12A
31-May-2013
17-OCT-12A
-110d
-269d
-112d
-112d
-112d
-112d
-269d
-282d
-122d
-122d
-122d
-270d
-222d
-270d
-110d
-110d
-269d
-112d
Page 11 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 ELEVATION C
6 U1 Block
7 ELEVATIONS A & C
7 ELEVATIONS A & C (FAADE)
7 ELEVATIONS B & D
7 ELEVATIONS B & D (FAADE)
5 Misc Details
6 S2 Block
7 SHAFT TERMINATION AT TERRACE LEVEL DETAILS & FACADE BLOW-UP DETAILS
6 P1 Block
7 SHAFT TERMINATION DETAILS
6 S1 Block
7 SHAFT TERMINATION AT TERRACE LEVEL DETAILS & FACADE BLOW-UP DETAILS
5 Walling Plans
6 S1 Block
7 GROUND FLOOR
7 MEZZANINE FLOOR
7 FIRST FLOOR PLAN
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A28280
3
A29000
A29010
A29020
A29030
9
2
A28810
4
A29390
1
A28390
4
1
A28180
A28190
A28200
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
20-Apr-2012
08-May-2012
08-May-2012
20-Apr-2012
20-Apr-2012
09-May-2012
09-May-2012
20-Apr-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
20-Apr-2012
20-Apr-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
17-OCT-12A
17-Oct-2012A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
12-Oct-2012A
25-Mar-2013A
25-MAR-13A
12-Oct-2012A
12-OCT-12A
25-Mar-2013A
25-MAR-13A
12-Oct-2012A
17-Oct-2012A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
31-May-2013
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
31-May-2013
31-May-2013
25-MAR-13A
31-May-2013
12-OCT-12A
31-May-2013
25-MAR-13A
31-May-2013
31-May-2013
17-OCT-12A
17-OCT-12A
17-OCT-12A
-112d
-269d
-112d
-112d
-112d
-112d
-269d
-270d
-222d
-282d
-122d
-269d
-221d
-269d
-269d
-112d
-112d
-112d
Page 12 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A28210
A28220
A28230
A28240
A28250
A28260
8
A29570
3
A28960
A28970
A28980
A28990
2
A28600
A28610
A28620
A28630
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
09-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
28-MAR-13A
25-Mar-2013A
25-MAR-13A
17-Oct-2012A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
12-Oct-2012A
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
28-MAR-13A
31-May-2013
25-MAR-13A
31-May-2013
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
31-May-2013
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
-112d
-112d
-112d
-112d
-112d
-224d
-270d
-222d
-269d
-112d
-112d
-112d
-112d
-270d
-110d
-110d
-110d
-110d
Page 13 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A28640
A28650
A28660
A28670
A28680
4
A29240
A29250
A29230
A29260
A29270
A29280
1
6
A36390
A36400
A36410
A36420
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
13-Feb-2012
13-Feb-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
13-Feb-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
08-May-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
20-Apr-2012
27-Feb-2013
27-Feb-2013
10-Aug-2012
28-Jan-2013
08-Feb-2013
04-Feb-2013
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
28-MAR-13A
12-Oct-2012A
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
11-Feb-2012A
11-Feb-2012A
10-MAR-12A
10-MAR-12A
10-MAR-12A
11-FEB-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
28-MAR-13A
31-May-2013
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
12-OCT-12A
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-110d
-110d
-110d
-110d
-225d
-282d
-122d
-122d
-122d
-122d
-122d
-122d
-66d
-66d
-203d
-87d
-78d
-82d
Page 14 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A36430
A36440
A36450
A36460
A36470
A36480
2
A36710
A36720
A36730
A36740
A36750
A36760
A36770
A36780
A36790
A36800
A36810
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
04-Feb-2013
07-Feb-2013
26-Feb-2013
01-Aug-2012
04-Feb-2013
27-Feb-2013
27-Feb-2013
07-May-2012
10-Aug-2012
28-Jan-2013
08-Feb-2013
12-Feb-2013
13-Feb-2013
11-Feb-2013
22-Feb-2013
01-Aug-2012
18-Feb-2013
27-Feb-2013
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-Mar-2012A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
28-MAR-13A
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-82d
-79d
-66d
-210d
-82d
-65d
-66d
-225d
-203d
-87d
-78d
-76d
-75d
-77d
-68d
-210d
-72d
-65d
Page 15 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 P1 Block
6 Architectural
6 Structural
6 Lighting
6 Coordinated
6 CCTV IBM
6 Fire Alarm & PA
6 FPS
6 Electrical
6 Plumbing
6 HVAC
6 Interiors
5 S1 Block
6 Architectural
6 Structural
6 Lighting
6 Coordinated
6 CCTV IBM
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A36820
A36830
A36840
A36850
A36860
A36870
A36880
A36890
A36900
A36910
A36920
1
A36050
A36060
A36070
A36080
A36090
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
13-Feb-2012
13-Feb-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
27-Feb-2013
08-May-2012
10-Aug-2012
28-Jan-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
26-Feb-2013
01-Aug-2012
05-Feb-2013
27-Feb-2013
27-Feb-2013
08-May-2012
10-Aug-2012
28-Jan-2013
28-Jan-2013
07-Feb-2013
10-Mar-2012A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
11-Feb-2012A
11-FEB-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
31-May-2013
28-MAR-13A
17-OCT-12A
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
28-MAR-13A
11-JAN-13A
31-MAY-13
31-MAY-13
31-MAY-13
-66d
-224d
-46d
-87d
-81d
-81d
-81d
-81d
-66d
-210d
-81d
-65d
-66d
-224d
-104d
-87d
-87d
-79d
Page 16 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A36100
A36110
A36120
A36130
A36140
A36150
4
A36160
A36170
A36180
A36200
A36210
A36220
A36230
A36240
A36250
A36260
I
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
12-Mar-2012
28-Feb-2013
07-Feb-2013
07-Feb-2013
26-Feb-2013
01-Aug-2012
07-Feb-2013
27-Feb-2013
27-Feb-2013
08-May-2012
10-Aug-2012
28-Jan-2013
04-Feb-2013
04-Feb-2013
04-Feb-2013
26-Feb-2013
01-Aug-2012
04-Feb-2013
27-Feb-2013
28-Feb-2013
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-Mar-2012A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
10-MAR-12A
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
17-OCT-12A
16-OCT-12A
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
-79d
-79d
-66d
-210d
-79d
-65d
-66d
-112d
-45d
-87d
-82d
-82d
-82d
-66d
-210d
-82d
-65d
-65d
Page 17 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
5
3
A32200
5
A32450
1
A30020
A30030
A30040
A30050
A30060
A30070
A30080
2
A31230
A31240
A31250
A31260
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-May-2013
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 18 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A31270
A31280
A31290
4
A32350
9
3
A32220
5
A32460
1
A30300
A30310
A30320
4
A32360
2
A31510
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 19 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A31520
A31530
7
1
A30160
A30170
A30180
A30190
A30200
A30210
A30220
4
A32320
2
A31370
A31380
A31390
A31400
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 20 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A31410
A31420
A31430
5
A32430
3
A32180
6
1
A30090
A30100
A30110
A30120
A30130
A30140
A30150
4
A32340
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 21 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 K1 Block
7 Ground Floor Plan
6 U1 Block
7 Ground Floor Plan
6 S2 Block
7 Ground Floor Plan
7 First Floor Plan
7 Second Floor Plan
7 Third Floor Plan
7 Fourth Floor Plan
7 Fifth Floor Plan
7 Sixth Floor Plan
5 Ceiling Plans
6 P1 Block
7 Ground Floor Plan
6 K1 Block
7 Ground Floor Plan
6 S2 Block
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
5
A32440
3
A32190
2
A31300
A31310
A31320
A31330
A31340
A31350
A31360
3
4
A32330
5
A32420
2
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 22 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A31090
A31100
A31110
A31120
A31130
A31140
A31150
1
A29880
A29890
A29900
A29910
A29920
A29930
A29940
3
A32170
12
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 23 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 K1 Block
7 Schedule of Finish
6 S2 Block
7 Schedule of Finish
7 Door schedule
6 U1 Block
7 Schedule of Finish
6 S1 Block
7 Schedule of Finish
7 Door schedule
6 P1 Block
7 Schedule of Finish
5 Coordinated Plans (Raceway)
6 U1 Block
7 Ground Floor Plan
6 S1 Block
7 Ground Floor Plan
7 First Floor Plan
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
5
A32500
2
A32040
A32050
3
A32280
1
A30830
A30840
4
A32400
8
3
A32210
1
A30230
A30240
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 24 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A30250
A30260
A30270
A30280
A30290
2
A31440
A31450
A31460
A31470
A31480
A31490
A31500
11
5
A32480
A32490
3
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 25 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 Door Detail
6 P1 Block
7 Door Detail
6 S2 Block
7 Reception Table Detail
7 Storage Detail
7 Column Cladding Detail
7 Door Detail
7 Discussion Pod Detail - 1
7 Discussion Pod Detail - 2
7 Discussion Pod Detail - 3
7 Discussion Pod Detail - 4
7 Discussion Pod Detail - 5
7 Discussion Pod Detail - 6
7 Jaali Detail
7 Caf Island and Bench seating Detail
7 Feature staircase Detail
6 S1 Block
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A32270
4
A32390
2
A31910
A31920
A31930
A31940
A31950
A31960
A31970
A31980
A31990
A32000
A32010
A32020
A32030
1
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 26 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A30700
A30710
A30720
A30730
A30740
A30750
A30760
A30770
A30780
A30790
A30800
A30810
A30820
1
1
A29740
A29750
A29760
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 27 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A29770
A29780
A29790
A29800
3
A32160
4
A32310
2
A30950
A30960
A30970
A30980
A30990
A31000
A31010
5
A32410
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 28 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Milliwork Details
6 U1 Block
7 Cabin Table Detail
7 Meeting Table Setail (8- Seated)
6 S1 Block
7 Cabin Table Detail (General)
7 Cabin Table Detail (Executive)
7 Discussion Table Detail
7 Meeting Table - 8 seater Detail
7 Meeting Table - 12 seater Detail
7 Executive Conference table Detail
7 Large Conference Table Detail
7 Trainee and Trainer Desk Detail
7 DC Head table Detail
7 Darbur Conference Table.
6 S2 Block
7 Cabin Table Detail (General)
7 Cabin Table Detail (Executive)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
13
3
A32290
A32300
1
A30850
A30860
A30870
A30880
A30890
A30900
A30910
A30920
A30930
A30940
2
A32060
A32070
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 29 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A32080
A32090
A32100
A32110
A32120
A32130
A32140
A32150
10
1
A30330
A30340
A30350
A30360
A30370
A30380
A30390
A30400
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 30 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A30410
A30420
A30430
A30440
A30450
A30460
A30470
A30480
A30490
A30500
A30510
A30520
A30530
A30540
A30550
A30560
A30570
A30580
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 31 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A30590
A30600
A30610
A30620
A30630
A30640
A30650
A30660
A30670
A30680
A30690
3
A32230
A32240
A32250
A32260
4
A32370
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 32 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A32380
5
A32470
2
A31540
A31550
A31560
A31570
A31580
A31590
A31600
A31610
A31620
A31630
A31640
A31650
A31660
A31670
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 33 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A31680
A31690
A31700
A31710
A31720
A31730
A31740
A31750
A31760
A31770
A31780
A31790
A31800
A31810
A31820
A31830
A31840
A31850
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 34 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 Janitor Detail
7 Vendor Reception Elevations
7 Admin Area Elevations
7 HR Area Elevations
7 Pantry / Break out -2 Elevation
5 Working Plans
6 S1 Block
7 Ground Floor Plan
7 First Floor Plan
7 Second Floor Plan
7 Third Floor Plan
7 Fourth Floor Plan
7 Fifth Floor Plan
7 Sixth Floor Plan
6 S2 Block
7 Ground Floor Plan
7 First Floor Plan
7 Second Floor Plan
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A31860
A31870
A31880
A31890
A31900
4
1
A29950
A29960
A29970
A29980
A29990
A30000
A30010
2
A31160
A31170
A31180
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 35 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A31190
A31200
A31210
A31220
2
1
A29810
A29820
A29830
A29840
A29850
A29860
A29870
2
A31020
A31030
A31040
A31050
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
-65d
Page 36 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A31060
A31070
A31080
M
H
5
A10360
A10370
A10380
A10390
A10970
A10980
1
A10490
A10510
A10520
A10530
A10540
28-Feb-2013
28-Feb-2013
28-Feb-2013
02-Aug-2012
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
27-Feb-2013
19-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
29-Nov-2012A
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-65d
-65d
-65d
-66d
-72d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-79d
-79d
-79d
-79d
-79d
-79d
Page 37 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A10550
A10560
A10570
A10580
A10590
A10600
A10610
A10620
A10630
A10640
A10650
A10660
A10670
A10680
A10690
A10700
A10500
A10710
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
Page 38 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A10720
2
A10730
A10740
A10750
A10760
A10770
A10780
A10790
A10800
A10810
A10820
A10830
A10840
A10850
A10860
A10870
A10880
08-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
08-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-79d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
Page 39 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A10890
A10900
A10910
A10920
A10930
A10940
A10950
A10960
3
A10400
A10410
A10420
A10430
A10440
A10450
4
A10460
A10470
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-72d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-81d
-81d
-81d
Page 40 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A10480
CO
5
A14330
A14340
2
A14160
A14170
A14180
A14190
A14200
A14210
A14220
A14230
1
A14150
4
A14290
06-Feb-2013
29-Jan-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
29-Jan-2013
29-Jan-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
11-Feb-2013
29-Jan-2013
29-Jan-2013
06-Feb-2013
06-Feb-2013
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
-81d
-78d
-78d
-78d
-78d
-78d
-78d
-78d
-78d
-78d
-78d
-78d
-78d
-78d
-87d
-87d
-81d
-81d
Page 41 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A14300
A14310
A14320
F
4
A13230
A13240
A13250
A13260
A13270
A13280
5
A13290
A13300
A13310
3
A13200
A13210
06-Feb-2013
06-Feb-2013
06-Feb-2013
05-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
12-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
-81d
-81d
-81d
-77d
-81d
-81d
-81d
-81d
-81d
-81d
-81d
-79d
-79d
-79d
-79d
-82d
-82d
-82d
Page 42 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A13220
2
A13110
A13120
A13130
A13140
A13150
A13160
A13170
A13180
A13190
1
A13020
A13030
A13040
A13050
A13060
A13070
05-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
05-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
12-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-82d
-77d
-77d
-77d
-77d
-77d
-77d
-77d
-77d
-77d
-77d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
Page 43 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A13080
A13090
A13100
LT
4
A14810
A14820
A14830
A14840
A14850
A14860
A14870
A14880
A14890
A14900
1
A14350
A14360
08-Feb-2013
08-Feb-2013
08-Feb-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
-79d
-79d
-79d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
Page 44 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A14370
A14380
A14390
A14400
A14410
A14420
A14430
A14440
A14450
A14460
A14470
A14480
A14490
2
A14500
A14510
A14520
A14530
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
Page 45 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A14540
A14550
A14560
A14570
A14580
A14590
A14600
A14610
A14620
A14630
A14640
3
A14650
A14660
A14670
A14680
A14690
A14700
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
Page 46 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 ROOF PLAN
7 ELEVATIONS A & C
7 ELEVATIONS A & C (FAADE)
7 ELEVATIONS B & D
7 ELEVATIONS B & D (FAADE)
7 SECTIONS A-A & B-B / EQUIPMENT HATCH DETAILS
7 SECTIONS C-C & D-D
7 SECTION E-E / SECTION 1 / SECTION 2
7 WALL SECTIONS & SHAFT TERMINATION DETAILS
7 SECTION -3 & SECTION 4
6 Others
7 DETAIL PLANTATION DRAWINGS
7 SECTION DETAIL PLANS
5 Electrical
6 S1 Block
7 LT distribution schematic (s1) (5 Sheets)
7 Main Single Line Diagram For Kitchen & Fire Emergency
7 Earthing schematic (s1)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A14710
A14720
A14730
A14740
A14750
A14760
A14770
A14780
A14790
A14800
5
A14910
A14920
E
1
A11350
A11360
A11370
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
29-Jan-2013
27-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-87d
-66d
-68d
-68d
-68d
-68d
Page 47 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A11380
A11390
A11400
A11410
A11420
A11430
A11440
A11450
A11460
A11470
A11480
A11490
A11500
A11510
A11520
A11530
A11540
A11550
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
Page 48 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A11560
A11570
A11580
A11590
A11600
A11610
A11620
A11630
A11640
A11650
A11660
A11670
A11680
A11690
A11700
A11710
A11720
A11730
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
Page 49 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A11740
A11750
A11760
A11770
A11780
A11790
A11800
A11810
A11820
A11830
A11840
A11850
A11860
A11870
A11880
A11890
A11900
A11910
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
Page 50 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A11920
A11930
A11940
A11950
A11960
A11970
2
A12060
A12070
A12080
A12090
A12100
A12110
A12120
A12130
A12140
A12150
A12160
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
Page 51 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A12170
A12180
A12190
A12200
A12210
A12220
A12230
A12240
A12050
A12250
A12260
A12270
A12280
A12290
A12300
A12310
A12320
A12330
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
Page 52 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A12340
A12350
A12360
A12370
A12380
A12390
A12400
A12410
A12420
A12430
A12440
A12450
A12460
A12470
A12480
A12490
A12500
A12510
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
Page 53 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A12520
A12530
A12540
A12550
A12560
A12000
A12010
A12020
A12030
A12040
3
A12780
A12790
A12800
A12810
A12820
A12830
A12840
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-68d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
Page 54 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A12850
A12860
A12870
A12880
A12890
A12900
A12910
A12920
A12930
A12940
5
A12970
A12980
A12990
A13000
A13010
4
A12590
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
Page 55 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A12600
A12610
A12620
A12630
A12640
A12650
A12660
A12670
A12680
A12690
A12700
A12710
A12740
A12750
FP
1
A13320
A13330
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
05-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
27-Feb-2013
14-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-66d
-75d
-79d
-79d
-79d
Page 56 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A13340
A13350
A13360
A13370
A13380
A13390
A13400
3
A13500
A13510
A13520
A13530
A13540
A13550
5
A13620
4
A13560
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
06-Feb-2013
06-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
06-Feb-2013
06-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-81d
-81d
Page 57 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A13570
A13580
A13590
A13600
A13610
2
A13410
A13420
A13430
A13440
A13450
A13460
A13470
A13480
A13490
P
2
A11120
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
02-Aug-2012
02-Aug-2012
02-Aug-2012
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
02-Aug-2012
02-Aug-2012
02-Aug-2012
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
29-Nov-2012A
19-Dec-2012A
27-FEB-13A
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
27-FEB-13A
-81d
-81d
-81d
-81d
-81d
-75d
-75d
-75d
-75d
-75d
-75d
-75d
-75d
-75d
-75d
-210d
-210d
-144d
Page 58 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A11130
A11140
A11150
A11160
A11170
A11180
A11190
A11200
A11210
A11220
1
A10990
A11000
A11010
A11020
A11030
A11040
A11050
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
21-DEC-12A
19-DEC-12A
19-DEC-12A
19-DEC-12A
19-DEC-12A
19-DEC-12A
19-DEC-12A
31-MAY-13
19-DEC-12A
31-MAY-13
29-Nov-2012A
31-MAY-13
21-DEC-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
21-DEC-12A
19-DEC-12A
19-DEC-12A
19-DEC-12A
19-DEC-12A
19-DEC-12A
19-DEC-12A
31-MAY-13
19-DEC-12A
31-MAY-13
31-May-2013
31-MAY-13
21-DEC-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
-98d
-96d
-96d
-96d
-96d
-96d
-96d
-210d
-96d
-210d
-210d
-210d
-98d
-82d
-82d
-82d
-82d
-82d
Page 59 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A11060
A11070
A11080
A11090
A11100
A11110
3
A11310
A11320
A11330
4
A11230
A11240
A11250
A11260
A11270
A11280
A11300
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
02-Aug-2012
29-NOV-12A
31-MAY-13
29-NOV-12A
29-NOV-12A
29-NOV-12A
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
18-Dec-2012A
31-MAY-13
29-DEC-12A
18-DEC-12A
18-DEC-12A
18-DEC-12A
18-DEC-12A
31-MAY-13
29-NOV-12A
31-MAY-13
29-NOV-12A
29-NOV-12A
29-NOV-12A
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
29-DEC-12A
18-DEC-12A
18-DEC-12A
18-DEC-12A
18-DEC-12A
31-MAY-13
-82d
-210d
-82d
-82d
-82d
-210d
-210d
-210d
-210d
-210d
-210d
-210d
-103d
-95d
-95d
-95d
-95d
-210d
Page 60 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A11290
5
A11340
CC
1
A13630
A13640
A13650
A13660
A13670
A13680
A13690
A13700
A13710
4
A13870
A13880
A13890
02-Aug-2012
02-Aug-2012
02-Aug-2012
05-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
02-Aug-2012
02-Aug-2012
02-Aug-2012
13-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
08-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
-210d
-210d
-210d
-76d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-79d
-81d
-81d
-81d
-81d
Page 61 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A13900
A13910
A13920
5
A13930
A13940
A13950
A13960
A13970
A13980
A13990
A14000
A14010
A14020
A14030
A14040
A14050
A14060
06-Feb-2013
06-Feb-2013
06-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-81d
-81d
-81d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
Page 62 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A14070
2
A13720
A13730
A13740
A13750
A13760
A13770
A13780
A13790
A13800
3
A13810
A13820
A13830
A13840
A13850
A13860
05-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
13-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
-82d
-76d
-76d
-76d
-76d
-76d
-76d
-76d
-76d
-76d
-76d
-82d
-82d
-82d
-82d
-82d
-82d
-82d
Page 63 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
4 Structural Details
5 Section Details
6 S2 Block
7 BRIDGE SECTION DETAILS (FIRST FLOOR)
7 Fifth Floor Slab Reinft. Section Details
7 First Floor Slab Reinft. Section Details
7 Fourth Floor Slab Reinft. Section Details
7 Second Floor Slab Reinft. Section Details
7 SECTION DETAILS (FIRST FLOOR)
7 Sixth Floor Slab Reinft. Section Details
7 Terrace Floor Slab Reinft. Section Details
7 Third Floor Slab Reinft. Section Details
7 Tie Beam Section Details
6 S1 Block
7 Fifth Floor Slab Reinft. Section Details
7 First Floor Slab Reinft. Section Details
7 Fourth Floor Slab Reinft. Section Details
7 Second Floor Slab Reinft. Section Details
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S
7
2
A34360
A34490
A34570
A34650
A34830
A34850
A34920
A35030
A35140
A35170
1
A32980
A33070
A33170
A33370
01-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
09-Aug-2012A
20-Aug-2012A
16-Oct-2012A
11-JAN-13A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
12-DEC-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-Oct-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
31-May-2013
31-May-2013
11-JAN-13A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
12-DEC-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
-203d
-206d
-206d
-107d
-48d
-48d
-48d
-48d
-87d
-48d
-48d
-48d
-48d
-206d
-48d
-48d
-48d
-48d
Page 64 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A33430
A33440
A33450
A33460
A33470
A33480
A33560
A33600
A33680
A33800
A33830
A32840
4
A9420
A9510
A9560
A9570
A35840
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
16-OCT-12A
12-DEC-12A
12-DEC-12A
12-DEC-12A
12-DEC-12A
12-DEC-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
05-NOV-12A
11-JAN-13A
20-Aug-2012A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
16-OCT-12A
12-DEC-12A
12-DEC-12A
12-DEC-12A
12-DEC-12A
12-DEC-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
05-NOV-12A
11-JAN-13A
31-May-2013
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
-48d
-87d
-87d
-87d
-87d
-87d
-48d
-48d
-48d
-48d
-62d
-107d
-206d
-8d
-8d
-8d
-8d
-8d
Page 65 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A36010
3
A35470
A35650
A35690
11
1
A33270
2
A36930
10
7
A10040
A10210
8
A10110
A10270
6
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
20-AUG-12A
20-Aug-2012A
20-AUG-12A
20-AUG-12A
20-AUG-12A
12-Dec-2012A
12-Dec-2012A
12-DEC-12A
12-Dec-2012A
12-DEC-12A
20-Aug-2012A
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
20-AUG-12A
31-May-2013
20-AUG-12A
20-AUG-12A
20-AUG-12A
31-May-2013
31-May-2013
12-DEC-12A
31-May-2013
12-DEC-12A
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
-8d
-206d
-8d
-8d
-8d
-211d
-211d
-92d
-211d
-92d
-203d
-203d
-203d
-203d
-203d
-203d
-203d
-203d
Page 66 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 Column schedule
7 Beam schedule
6 S1 Block
7 Fifth Floor Slab Beam Schedule
7 First Floor Slab Beam Schedule
7 Fourth Floor Slab Beam Schedule
7 Mezzanine Floor Slab Beam Schedule
7 Second Floor Slab Beam Schedule
7 Sixth Floor Slab Beam Schedule
7 Terrace Floor Slab Beam Schedule
7 Third Floor Slab Beam Schedule
7 Bar Bending Schedule (Beam) - 1st Floor
7 Bar Bending Schedule (Beam) - 2nd Floor
7 Bar Bending Schedule (Beam) - 3rd Floor
7 Bar Bending Schedule (Beam) - 4th Floor
7 Bar Bending Schedule (Beam) - 5th Floor
7 Bar Bending Schedule (Beam) - 6th Floor
7 Bar Bending Schedule (Beam) - Mezzanine Floor
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A9970
A10150
1
A32960
A33050
A33150
A33290
A33350
A33540
A33660
A33780
A32520
A32530
A32540
A32550
A32560
A32570
A32580
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
31-MAY-13
31-MAY-13
20-Aug-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
31-MAY-13
31-MAY-13
31-May-2013
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
-203d
-203d
-206d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-62d
-62d
-62d
-62d
-62d
-62d
-62d
Page 67 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A32590
A32600
A32610
A32620
A32630
A32640
A32650
A32660
A32670
A32860
A32880
2
A33950
A33960
A33970
A33980
A33990
A34000
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
20-AUG-12A
20-AUG-12A
26-Oct-2012A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
20-AUG-12A
20-AUG-12A
31-May-2013
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
-62d
-62d
-62d
-62d
-62d
-62d
-62d
-62d
-62d
-8d
-8d
-203d
-59d
-59d
-59d
-59d
-59d
-59d
Page 68 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A34010
A34020
A34030
A34040
A34050
A34060
A34070
A34080
A34090
A34100
A34200
A34210
A34220
A34230
A34240
A34250
A34260
A34270
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
05-NOV-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
-59d
-59d
-59d
-59d
-59d
-59d
-59d
-59d
-59d
-59d
-53d
-53d
-53d
-53d
-53d
-53d
-53d
-53d
Page 69 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A34380
3
A35440
A35450
A35480
A35510
A35560
A35600
A35720
4
A9270
A36030
A36040
A9120
A9130
A9140
A9150
A9160
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
26-OCT-12A
20-Aug-2012A
16-OCT-12A
16-OCT-12A
20-AUG-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-Oct-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
26-OCT-12A
31-May-2013
16-OCT-12A
16-OCT-12A
20-AUG-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
-53d
-206d
-48d
-48d
-8d
-48d
-48d
-48d
-48d
-203d
-45d
-45d
-45d
-45d
-45d
-45d
-45d
-45d
Page 70 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A9170
A9180
A9190
A9200
A9210
5
A9840
A9880
4
2
A34280
A34290
A34300
A34310
A34320
A34330
A34340
A34350
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
31-MAY-13
31-MAY-13
20-Aug-2012A
26-Oct-2012A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
-45d
-45d
-45d
-45d
-45d
-203d
-203d
-203d
-206d
-206d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
Page 71 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A34480
A34560
A34640
A34820
A34910
A35020
A35130
A35180
A35190
A35200
A35210
A35220
A35230
A35240
A35250
1
A32970
A33060
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
20-Aug-2012A
16-OCT-12A
16-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
31-May-2013
16-OCT-12A
16-OCT-12A
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-206d
-48d
-48d
Page 72 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A33090
A33160
A33200
A33360
A33550
A33670
A33790
A33840
A33850
A33860
A33870
A33880
A33890
A33900
A33910
A32760
A32770
A32780
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
16-OCT-12A
16-OCT-12A
20-AUG-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
20-AUG-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
-48d
-48d
-8d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
Page 73 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A32790
A32800
A32810
A32820
A32830
4
A9390
A9400
A9410
A9540
A9550
A9620
A9630
A9640
A9650
A9660
A35810
A35820
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
17-Oct-2012A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
-48d
-48d
-48d
-48d
-48d
-206d
-49d
-49d
-49d
-49d
-49d
-49d
-49d
-49d
-49d
-49d
-49d
-49d
Page 74 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A35830
A35980
A35990
A36000
5
A9830
5
7
A10010
A10200
8
A10080
A10260
1
A33000
A33100
A33210
A33300
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
11-Jan-2013A
11-JAN-13A
20-Aug-2012A
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
20-Aug-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
17-OCT-12A
31-May-2013
11-JAN-13A
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
-49d
-49d
-49d
-49d
-206d
-107d
-206d
-206d
-206d
-206d
-206d
-206d
-206d
-206d
-48d
-48d
-48d
-48d
Page 75 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A33490
A33610
A33700
A32850
A32900
2
A34370
A34410
A34510
A34590
A34690
A34770
A34860
A34970
A35050
3
A35300
A35310
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
16-OCT-12A
16-OCT-12A
16-OCT-12A
20-AUG-12A
16-OCT-12A
26-Oct-2012A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
16-Oct-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
20-AUG-12A
16-OCT-12A
31-May-2013
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
31-May-2013
16-OCT-12A
16-OCT-12A
-48d
-48d
-48d
-8d
-48d
-206d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-206d
-48d
-48d
Page 76 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A35460
A35520
A35530
A35570
A35580
A35610
A35620
A35630
A35640
A35670
A35730
A35760
4
A9340
A9350
A9360
A9520
A9530
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-Oct-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-206d
-48d
-48d
-48d
-48d
-48d
Page 77 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A9610
A35780
A35790
A35850
A35860
A35880
A35890
A35900
A35910
A35920
A9220
A9230
A9240
A9250
A9260
5
A9820
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
12-Dec-2012A
12-DEC-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
12-DEC-12A
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-206d
-87d
Page 78 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A9870
6
A9940
A10140
8
3
A35680
1
A33280
A33580
A33590
2
A34760
A34940
A34950
6
A9980
4
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
12-DEC-12A
31-May-2013
31-MAY-13
31-MAY-13
20-Aug-2012A
10-Sep-2012A
10-SEP-12A
20-Aug-2012A
27-NOV-12A
20-AUG-12A
12-NOV-12A
20-Aug-2012A
27-NOV-12A
20-AUG-12A
12-NOV-12A
31-May-2013
31-MAY-13
10-Sep-2012A
12-DEC-12A
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
10-SEP-12A
31-May-2013
27-NOV-12A
20-AUG-12A
12-NOV-12A
31-May-2013
27-NOV-12A
20-AUG-12A
12-NOV-12A
31-May-2013
31-MAY-13
31-May-2013
-88d
-206d
-206d
-206d
-203d
-203d
-19d
-203d
-73d
-5d
-64d
-203d
-73d
-5d
-64d
-203d
-203d
-203d
Page 79 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 Staircase Details
6 K1 Block
7 Staircase Details
6 G2 Block
7 Staircase Details
6 G3 Block
7 Staircase Details
5 PT Beam Reinforcement Details
6 S1 Block
7 Fifth Floor PT Beam Reinft. Details
7 First Floor PT Beam Reinft. Details
7 First Floor PT Beam Reinft. Details
7 First Floor PT Beam Reinft. Details
7 Fourth Floor PT Beam Reinft. Details
7 Fourth Floor PT Beam Reinft. Details
7 Fourth Floor PT Beam Reinft. Details
7 Lift Pit Level PT Beam Reinft. Details
7 Lift Pit Level PT Beam Reinft. Details
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A9500
5
A9850
7
A10050
8
A10120
2
1
A32950
A33020
A33030
A33040
A33120
A33130
A33140
A33240
A33250
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
10-SEP-12A
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
16-Oct-2012A
16-Oct-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
10-SEP-12A
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
-19d
-203d
-203d
-203d
-203d
-203d
-203d
-206d
-206d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
Page 80 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A33320
A33330
A33340
A33510
A33520
A33530
A33630
A33640
A33650
A33740
A33750
A33760
A33770
A32920
A32930
A32940
2
A34440
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
26-Oct-2012A
26-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
26-OCT-12A
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-206d
-56d
Page 81 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A34450
A34460
A34470
A34530
A34540
A34550
A34610
A34620
A34630
A34720
A34730
A34790
A34800
A34810
A34880
A34890
A34900
A34990
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
Page 82 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A35000
A35010
A35090
A35100
A35110
A35120
4
A9370
A9380
A35800
A35960
A35970
6
A10170
7
A10230
8
A10290
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
16-Oct-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
31-May-2013
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
-56d
-56d
-56d
-56d
-56d
-56d
-206d
-48d
-48d
-48d
-48d
-48d
-206d
-206d
-206d
-206d
-206d
-206d
Page 83 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 K1 Block
7 PT Beam tendon Layout Plan
5 Beam & Slab Framing Plans
6 S1 Block
7 Lift pit Lvl Framing Plan
7 Tie Beam Framing Plans (Ground Floor Level)
7 Beam & Slab Framing Plan (Fifth floor)
7 Beam & Slab Framing Plan (First floor)
7 Beam & Slab Framing Plan (Fourth floor)
7 Beam & Slab Framing Plan (Mezzanine)
7 Beam & Slab Framing Plan (second floor)
7 Beam & Slab Framing Plan (Sixth floor)
7 Beam & Slab Framing Plan (Terrace)
7 Beam & Slab Framing Plan (Third floor)
6 K1 Block
7 First Floor Slab And Beam Framing
6 G1 Block
7 Beam & Slab Framing Plan.
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
5
A9900
1
1
A33260
A33820
A32680
A32690
A32700
A32710
A32720
A32730
A32740
A32750
5
A9860
6
A10130
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
31-May-2013
31-MAY-13
09-Aug-2012A
09-Aug-2012A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
-206d
-206d
-206d
-206d
-1d
-1d
-1d
-1d
-1d
-1d
-1d
-1d
-1d
-1d
-206d
-206d
-206d
-206d
Page 84 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
6 S2 Block
7 Beam & Slab Framing Plan (Fifth floor)
7 Beam & Slab Framing Plan (First Floor)
7 Beam & Slab Framing Plan (Fourth floor)
7 Beam & Slab Framing Plan (Lift Pit LVL.)
7 Beam & Slab Framing Plan (Mezzanine)
7 Beam & Slab Framing Plan (second floor)
7 Beam & Slab Framing Plan (Sixth floor)
7 Beam & Slab Framing Plan (Terrace)
7 Beam & Slab Framing Plan (Third floor)
7 Tie Beam Framing Plans (Ground Floor Level)
6 U1 Block
7 1ST PT SLAB FRAMING PLAN.(GROUND FLOOR)
7 2ND PT SLAB FRAMING PLAN.(MEZZANINE FLOOR)
7 3RD PT SLAB FRAMING PLAN.(FIRST FLOOR)
7 4TH PT SLAB FRAMING PLAN.
7 FIRST FLOOR BEAM & SLAB FRAMING PLAN
7 GROUND FLOOR BEAM & SLAB FRAMING PLAN
2
A34110
A34120
A34130
A34140
A34150
A34160
A34170
A34180
A34190
A35160
3
A35290
A35340
A35350
A35420
A35500
A35550
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
20-Aug-2012A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
09-Aug-2012A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
31-May-2013
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
31-May-2013
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
-206d
-8d
-8d
-8d
-8d
-8d
-8d
-8d
-8d
-8d
-8d
-206d
-1d
-1d
-1d
-1d
-1d
-1d
Page 85 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A35590
A35700
A35740
A35750
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
-1d
-1d
-1d
-1d
4
A9300
A9310
A9320
A35770
7
A10190
8
A10250
13
A9670
A9680
A9690
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
20-Aug-2012A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
27-Sep-2012A
29-OCT-12A
27-SEP-12A
27-SEP-12A
31-May-2013
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
29-OCT-12A
27-SEP-12A
27-SEP-12A
-206d
-8d
-8d
-8d
-8d
-206d
-206d
-206d
-206d
-211d
-62d
-40d
-40d
Page 86 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A9700
A9710
A9720
A9730
A9740
A9750
A9760
A9770
A9780
A9790
A10310
A10320
A10330
A10340
A10350
12
1
A33390
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
27-SEP-12A
31-MAY-13
24-DEC-12A
12-NOV-12A
19-JAN-13A
19-JAN-13A
19-JAN-13A
19-JAN-13A
19-JAN-13A
19-JAN-13A
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-Dec-2012A
31-Dec-2012A
31-DEC-12A
27-SEP-12A
31-MAY-13
24-DEC-12A
12-NOV-12A
19-JAN-13A
19-JAN-13A
19-JAN-13A
19-JAN-13A
19-JAN-13A
19-JAN-13A
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
31-DEC-12A
-40d
-211d
-100d
-72d
-118d
-118d
-118d
-118d
-118d
-118d
-211d
-211d
-211d
-211d
-211d
-211d
-211d
-104d
Page 87 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A33400
A33410
A33420
5
A9890
6
A10160
7
A10220
8
A10280
9
5
A9800
A9810
6
A9920
A9930
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
01-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
31-DEC-12A
31-DEC-12A
31-DEC-12A
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
20-Aug-2012A
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-DEC-12A
31-DEC-12A
31-DEC-12A
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
-104d
-104d
-104d
-211d
-211d
-211d
-211d
-211d
-211d
-211d
-211d
-203d
-203d
-203d
-203d
-203d
-203d
-203d
Page 88 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A9950
A9960
7
A9990
A10000
A10020
A10030
8
A10060
A10070
A10090
A10100
1
A33190
A32870
2
A34390
A34400
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
20-Aug-2012A
20-AUG-12A
20-AUG-12A
20-Aug-2012A
20-AUG-12A
20-AUG-12A
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
20-AUG-12A
20-AUG-12A
31-May-2013
20-AUG-12A
20-AUG-12A
-203d
-203d
-203d
-203d
-203d
-203d
-203d
-203d
-203d
-203d
-203d
-203d
-206d
-8d
-8d
-203d
-5d
-5d
Page 89 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 General Notes
7 Lift & Shear Wall Details
7 M.S. 'Y' SHAPE COLUMN DETAIL (1ST TO 4TH FLOOR)
7 Standard Beam Sections
6 U1 Block
7 Excavation Plan & Details
7 General Notes
7 Shear Wall Details
7 TYPICAL BEAM ANCHORAGE DETAILS
6 P1 Block
7 Combined Footing Details
7 Excavation Plan & Details (2 Sheets)
7 General Notes
7 Ground Floor Typ. Shear Links Details.
7 Lift & Shear Wall Details
7 Raft Layout Plan & DetailS (2 Sheets)
7 Rock Anchor Layout Plan
7 First Floor Typ. Shear Links Details.
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A34670
A34680
A34750
A34960
3
A35490
A35540
A35660
A35710
4
A9280
A9290
A9330
A9460
A9470
A9480
A9490
A35870
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
13-Aug-2012
20-AUG-12A
20-AUG-12A
31-MAY-13
20-AUG-12A
20-Aug-2012A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-Aug-2012A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
31-MAY-13
20-AUG-12A
31-May-2013
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
31-May-2013
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
20-AUG-12A
-5d
-5d
-203d
-5d
-206d
-8d
-8d
-8d
-8d
-203d
-5d
-5d
-5d
-5d
-5d
-5d
-5d
-5d
Page 90 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
6
1
A32990
A33080
A33180
A33380
A33570
A33690
A33810
4
A9430
A9440
A9450
A9580
A9590
A9600
A35930
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
16-Oct-2012A
16-Oct-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-Oct-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
31-May-2013
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
-206d
-206d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-206d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
Page 91 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A35940
A35950
2
A34500
A34580
A34660
A34840
A34930
A35040
A35150
3
1
A33010
A33110
A33220
A33230
A33310
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
16-OCT-12A
16-OCT-12A
26-Oct-2012A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
16-Oct-2012A
16-Oct-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
31-May-2013
31-May-2013
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
-48d
-48d
-206d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-206d
-206d
-48d
-48d
-48d
-48d
-48d
Page 92 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A33500
A33620
A33710
A33720
A33730
A32890
A32910
2
A34420
A34430
A34520
A34600
A34700
A34710
A34780
A34870
A34980
A35060
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
26-Oct-2012A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
26-OCT-12A
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-206d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
-56d
Page 93 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A35070
A35080
3
A35260
A35270
A35280
A35320
A35330
A35360
A35370
A35380
A35390
A35400
A35410
A35430
5
A9910
6
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
26-OCT-12A
26-OCT-12A
16-Oct-2012A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
31-MAY-13
31-May-2013
26-OCT-12A
26-OCT-12A
31-May-2013
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
16-OCT-12A
31-May-2013
31-MAY-13
31-May-2013
-56d
-56d
-206d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-206d
-206d
-206d
Page 94 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A10180
7
A10240
8
A10300
6
1
P1 B-S1
P1 B-S2
P1 UTIL-U1
P1 PARK-P1
P1 GB-G1
P1 KK-K1
P1 GB-G2
P1 GB-G3
5
1
2
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Oct-2013
08-Oct-2013
10-Feb-2014
21-Feb-2014
10-Feb-2014
23-Oct-2013
10-Feb-2014
08-Oct-2013
10-Feb-2014
10-Feb-2014
09-Aug-2012
09-Aug-2012
13-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
08-Aug-2012
21-Feb-2014
21-Feb-2014
10-Feb-2014
21-Feb-2014
10-Feb-2014
23-Oct-2013
10-Feb-2014
08-Oct-2013
10-Feb-2014
10-Feb-2014
21-Feb-2014
10-Feb-2014
28-Mar-2013
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
09-Nov-2013
09-Nov-2013
28-FEB-15
06-JUN-14
09-MAY-15
09-NOV-13
09-MAY-15
30-JAN-14
09-MAY-15
09-MAY-15
09-Aug-2012A
09-Aug-2012A
11-Jan-2013A
31-MAY-13
31-May-2013
31-MAY-13
31-May-2013
31-MAY-13
09-May-2015
09-May-2015
28-FEB-15
06-JUN-14
09-MAY-15
09-NOV-13
09-MAY-15
30-JAN-14
09-MAY-15
09-MAY-15
11-May-2015
11-May-2015
18-Sep-2013
-206d
-206d
-206d
-206d
-206d
-379d
-379d
-329d
-91d
-389d
-15d
-389d
-99d
-389d
-389d
-380d
-390d
-149d
Page 95 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 FPS
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
6 HT Switchyard
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
6 Handrails
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
1
A15060
A15070
A15080
A15090
A15100
2
A15110
A15120
A15130
A15140
A15150
10
A15160
A15170
A15180
A15190
A15200
24-Aug-2012
24-Aug-2012
11-Sep-2012
17-Sep-2012
19-Sep-2012
28-Sep-2012
13-Aug-2012
13-Aug-2012
30-Aug-2012
05-Sep-2012
07-Sep-2012
17-Sep-2012
25-Jan-2013
25-Jan-2013
06-Feb-2013
12-Feb-2013
14-Feb-2013
23-Feb-2013
03-Oct-2012
10-Sep-2012
15-Sep-2012
18-Sep-2012
27-Sep-2012
03-Oct-2012
21-Sep-2012
29-Aug-2012
04-Sep-2012
06-Sep-2012
15-Sep-2012
21-Sep-2012
25-Feb-2013
05-Feb-2013
11-Feb-2013
13-Feb-2013
22-Feb-2013
25-Feb-2013
15-Jan-2013A
15-JAN-13A
16-JAN-13A
21-JAN-13A
23-JAN-13A
06-MAY-13A
05-Mar-2013A
05-MAR-13A
06-MAR-13A
11-MAR-13A
18-MAR-13A
06-MAY-13A
19-Jun-2013
19-JUN-13
01-JUL-13
06-JUL-13
09-JUL-13
18-JUL-13
15-Jun-2013
03-JUN-13
04-JUN-13
05-JUN-13
10-JUN-13
15-JUN-13
27-Jun-2013
08-JUN-13
11-JUN-13
13-JUN-13
21-JUN-13
27-JUN-13
19-Jul-2013
29-JUN-13
05-JUL-13
08-JUL-13
17-JUL-13
19-JUL-13
-219d
-228d
-224d
-222d
-218d
-218d
-239d
-243d
-240d
-240d
-239d
-239d
-124d
-124d
-124d
-124d
-124d
-124d
Page 96 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 Landscape
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
6 Signages
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
6 Elevators
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
12
A15210
A15220
A15230
A15240
A15250
13
A15260
A15270
A15280
A15290
A15300
14
A15310
A15320
A15330
A15340
A15350
09-Feb-2013
09-Feb-2013
27-Feb-2013
05-Mar-2013
07-Mar-2013
16-Mar-2013
13-Feb-2013
13-Feb-2013
02-Mar-2013
08-Mar-2013
11-Mar-2013
20-Mar-2013
02-Oct-2012
02-Oct-2012
19-Oct-2012
25-Oct-2012
27-Oct-2012
06-Nov-2012
21-Mar-2013
26-Feb-2013
04-Mar-2013
06-Mar-2013
15-Mar-2013
21-Mar-2013
25-Mar-2013
01-Mar-2013
07-Mar-2013
09-Mar-2013
19-Mar-2013
25-Mar-2013
10-Nov-2012
18-Oct-2012
24-Oct-2012
26-Oct-2012
05-Nov-2012
10-Nov-2012
09-Aug-2013
09-AUG-13
27-AUG-13
02-SEP-13
04-SEP-13
13-SEP-13
24-Jul-2013
24-JUL-13
10-AUG-13
16-AUG-13
19-AUG-13
28-AUG-13
11-Jan-2013A
14-JAN-13A
15-JAN-13A
11-JAN-13A
10-APR-13A
31-MAY-13
18-Sep-2013
26-AUG-13
31-AUG-13
03-SEP-13
12-SEP-13
18-SEP-13
02-Sep-2013
09-AUG-13
15-AUG-13
17-AUG-13
27-AUG-13
02-SEP-13
05-Jun-2013
08-MAY-13A
11-MAY-13A
14-MAY-13A
23-MAY-13A
05-JUN-13
-155d
-155d
-155d
-155d
-155d
-155d
-138d
-138d
-138d
-138d
-138d
-138d
-177d
-173d
-171d
-171d
-171d
-177d
Page 97 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 HVAC
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Final review and approval as GFC
7 Resubmission of shop drgs
6 Solar Power system
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
6 Fire Door
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A15360
A15370
A15380
A15400
A15390
15
A15760
A15770
A15780
A15790
A15800
16
A15810
A15820
A15830
A15840
A15850
04-Sep-2012
04-Sep-2012
21-Sep-2012
27-Sep-2012
09-Oct-2012
29-Sep-2012
16-Feb-2013
16-Feb-2013
06-Mar-2013
12-Mar-2013
14-Mar-2013
23-Mar-2013
23-Jan-2013
23-Jan-2013
09-Feb-2013
15-Feb-2013
18-Feb-2013
27-Feb-2013
13-Oct-2012
20-Sep-2012
26-Sep-2012
28-Sep-2012
13-Oct-2012
08-Oct-2012
28-Mar-2013
05-Mar-2013
11-Mar-2013
13-Mar-2013
22-Mar-2013
28-Mar-2013
04-Mar-2013
08-Feb-2013
14-Feb-2013
16-Feb-2013
26-Feb-2013
04-Mar-2013
15-Mar-2013A
15-MAR-13A
16-MAR-13A
12-JUN-13
24-JUN-13
14-JUN-13
25-Jul-2013
25-JUL-13
12-AUG-13
17-AUG-13
20-AUG-13
29-AUG-13
19-Jun-2013
19-JUN-13
06-JUL-13
12-JUL-13
15-JUL-13
24-JUL-13
28-Jun-2013
08-JUN-13
11-JUN-13
13-JUN-13
28-JUN-13
22-JUN-13
03-Sep-2013
10-AUG-13
16-AUG-13
19-AUG-13
28-AUG-13
03-SEP-13
29-Jul-2013
05-JUL-13
11-JUL-13
13-JUL-13
23-JUL-13
29-JUL-13
-221d
-224d
-221d
-221d
-221d
-221d
-136d
-136d
-136d
-136d
-136d
-136d
-126d
-126d
-126d
-126d
-126d
-126d
Page 98 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 STP
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
6 Internal Building Electrification
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
6 Faade
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
4
A15410
A15420
A15430
A15440
A15450
5
A15460
A15470
A15480
A15490
A15500
11
A15510
A15520
A15530
A15540
A15550
13-Sep-2012
13-Sep-2012
01-Oct-2012
06-Oct-2012
09-Oct-2012
18-Oct-2012
25-Sep-2012
25-Sep-2012
12-Oct-2012
18-Oct-2012
20-Oct-2012
30-Oct-2012
24-Oct-2012
24-Oct-2012
10-Nov-2012
16-Nov-2012
19-Nov-2012
28-Nov-2012
23-Oct-2012
29-Sep-2012
05-Oct-2012
08-Oct-2012
17-Oct-2012
23-Oct-2012
03-Nov-2012
11-Oct-2012
17-Oct-2012
19-Oct-2012
29-Oct-2012
03-Nov-2012
03-Dec-2012
09-Nov-2012
15-Nov-2012
17-Nov-2012
27-Nov-2012
03-Dec-2012
13-Jan-2013A
13-JAN-13A
14-JAN-13A
20-JAN-13A
04-FEB-13A
12-JUN-13
31-May-2013
31-MAY-13
18-JUN-13
24-JUN-13
26-JUN-13
05-JUL-13
19-Jun-2013
19-JUN-13
06-JUL-13
12-JUL-13
15-JUL-13
24-JUL-13
18-Jun-2013
04-JUN-13
05-JUN-13
06-JUN-13
12-JUN-13
18-JUN-13
10-Jul-2013
17-JUN-13
22-JUN-13
25-JUN-13
04-JUL-13
10-JUL-13
29-Jul-2013
05-JUL-13
11-JUL-13
13-JUL-13
23-JUL-13
29-JUL-13
-204d
-212d
-208d
-207d
-204d
-204d
-213d
-213d
-213d
-213d
-213d
-213d
-204d
-204d
-204d
-204d
-204d
-204d
Page 99 of 533
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
6
A15560
A15570
A15580
A15590
A15600
8
A15610
A15620
A15630
A15640
A15650
7
A15660
A15670
A15680
A15690
A15700
20-Nov-2012
20-Nov-2012
07-Dec-2012
13-Dec-2012
15-Dec-2012
25-Dec-2012
06-Nov-2012
06-Nov-2012
23-Nov-2012
29-Nov-2012
01-Dec-2012
11-Dec-2012
04-Jan-2013
04-Jan-2013
22-Jan-2013
28-Jan-2013
30-Jan-2013
08-Feb-2013
29-Dec-2012
06-Dec-2012
12-Dec-2012
14-Dec-2012
24-Dec-2012
29-Dec-2012
15-Dec-2012
22-Nov-2012
28-Nov-2012
30-Nov-2012
10-Dec-2012
15-Dec-2012
13-Feb-2013
21-Jan-2013
26-Jan-2013
29-Jan-2013
07-Feb-2013
13-Feb-2013
31-May-2013
31-MAY-13
18-JUN-13
24-JUN-13
26-JUN-13
05-JUL-13
11-Jun-2013
11-JUN-13
28-JUN-13
04-JUL-13
06-JUL-13
16-JUL-13
15-Jun-2013
15-JUN-13
03-JUL-13
09-JUL-13
11-JUL-13
20-JUL-13
10-Jul-2013
17-JUN-13
22-JUN-13
25-JUN-13
04-JUL-13
10-JUL-13
22-Jul-2013
28-JUN-13
04-JUL-13
06-JUL-13
16-JUL-13
22-JUL-13
25-Jul-2013
02-JUL-13
08-JUL-13
10-JUL-13
19-JUL-13
25-JUL-13
-165d
-165d
-165d
-165d
-165d
-165d
-187d
-186d
-186d
-186d
-186d
-186d
-139d
-139d
-139d
-139d
-139d
-139d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 IT & Networking
7 Preperation and Submission of shop drgs
7 Review of shop drawings by consultant
7 Comment on shop drgs by consultant
7 Resubmission of shop drgs
7 Final review and approval as GFC
5 Project Milestones
6 S1
7 Completion of Super Structure Works
7 Completion of Civil Finishes
7 Completion of Substructure works
7 NSC work Completion
7 Start of Substructure works
7 Start of Civil Finishes
7 Start of NSC Works
6 Kiosk 1
7 Completion of Structure Works
7 Completion of Civil Finishes
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
9
A15710
A15720
A15730
A15740
A15750
MS
S1
S1-M10
S1-M11
A53550
S1-M32
A63240
A63260
A63270
K1
K1-M10
K1-M11
02-Feb-2013
02-Feb-2013
20-Feb-2013
26-Feb-2013
28-Feb-2013
09-Mar-2013
13-Aug-2012
13-Aug-2012
07-May-2013
11-Jul-2013
10-Nov-2012
10-Feb-2014
13-Aug-2012
21-Jan-2013
06-Mar-2013
13-Aug-2012
12-Dec-2012
13-Mar-2013
14-Mar-2013
19-Feb-2013
25-Feb-2013
27-Feb-2013
08-Mar-2013
14-Mar-2013
10-Feb-2014
10-Feb-2014
07-May-2013
11-Jul-2013
10-Nov-2012
10-Feb-2014
13-Aug-2012
21-Jan-2013
06-Mar-2013
01-Apr-2013
12-Dec-2012
13-Mar-2013
31-May-2013
31-MAY-13
18-JUN-13
24-JUN-13
26-JUN-13
05-JUL-13
20-Aug-2012A
20-Aug-2012A
31-MAY-13
05-SEP-13
20-DEC-12A
28-FEB-15
20-AUG-12A
10-MAR-13A
18-MAR-13A
07-Jan-2013A
15-AUG-13
14-NOV-13
10-Jul-2013
17-JUN-13
22-JUN-13
25-JUN-13
04-JUL-13
10-JUL-13
28-Feb-2015
28-Feb-2015
31-MAY-13
05-SEP-13
20-DEC-12A
28-FEB-15
20-AUG-12A
10-MAR-13A
18-MAR-13A
03-Dec-2013
15-AUG-13
14-NOV-13
-101d
-101d
-101d
-101d
-101d
-101d
-329d
-329d
-21d
-49d
-34d
-329d
-6d
-42d
-10d
-211d
-212d
-212d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
K1-M12
K1-M20
K1-M30
K1-M40
U1
U1-M10
U1-M11
A53560
U1-M22
A63300
A63310
2
A15900
A15910
A22950
A22960
1
A15860
01-Apr-2013
13-Aug-2012
15-Dec-2012
08-Feb-2013
17-Dec-2012
01-Mar-2013
28-Jun-2013
17-Dec-2012
18-Dec-2013
07-Feb-2013
14-Mar-2013
13-Sep-2012
31-Jan-2013
28-May-2013
13-Sep-2012
30-Oct-2012
23-Aug-2012
10-Jan-2013
01-Apr-2013
13-Aug-2012
15-Dec-2012
08-Feb-2013
18-Dec-2013
01-Mar-2013
28-Jun-2013
17-Dec-2012
18-Dec-2013
07-Feb-2013
14-Mar-2013
28-May-2013
31-Jan-2013
28-May-2013
13-Sep-2012
30-Oct-2012
13-Apr-2013
10-Jan-2013
03-DEC-13
07-JAN-13A
19-AUG-13
12-OCT-13
30-Jan-2013A
31-MAY-13
11-SEP-13
30-JAN-13A
20-MAR-14
31-MAY-13
13-SEP-13
10-Dec-2012A
08-AUG-13
13-JAN-14
10-DEC-12A
18-JUN-13
25-Sep-2012A
19-AUG-13
03-DEC-13
07-JAN-13A
19-AUG-13
12-OCT-13
20-Mar-2014
31-MAY-13
11-SEP-13
30-JAN-13A
20-MAR-14
31-MAY-13
13-SEP-13
13-Jan-2014
08-AUG-13
13-JAN-14
10-DEC-12A
18-JUN-13
26-Mar-2014
19-AUG-13
-212d
-126d
-212d
-212d
-79d
-78d
-65d
-38d
-80d
-97d
-157d
-197d
-163d
-198d
-75d
-199d
-297d
-190d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A15870
A15880
A15890
A22970
A26230
A26240
A26500
3
A15920
A15930
A26530
A26540
4
A15940
A15950
A26620
A26650
5
13-Apr-2013
28-Jan-2013
13-Apr-2013
23-Aug-2012
20-Oct-2012
15-Sep-2012
18-Oct-2012
13-Sep-2012
22-Nov-2012
07-Mar-2013
13-Sep-2012
22-Nov-2012
04-Sep-2012
13-Nov-2012
20-Apr-2013
04-Sep-2012
25-Dec-2012
22-Nov-2012
13-Apr-2013
28-Jan-2013
13-Apr-2013
23-Aug-2012
20-Oct-2012
15-Sep-2012
18-Oct-2012
07-Mar-2013
22-Nov-2012
07-Mar-2013
13-Sep-2012
22-Nov-2012
20-Apr-2013
13-Nov-2012
20-Apr-2013
04-Sep-2012
25-Dec-2012
22-Nov-2013
15-NOV-13
21-DEC-13
26-MAR-14
25-SEP-12A
18-APR-13A
05-NOV-12A
31-MAY-13
31-May-2013
01-AUG-13
16-NOV-13
31-MAY-13
02-AUG-13
29-Mar-2013A
27-JUL-13
31-DEC-13
29-MAR-13A
06-SEP-13
26-Feb-2013A
15-NOV-13
21-DEC-13
26-MAR-14
25-SEP-12A
18-APR-13A
05-NOV-12A
31-MAY-13
16-Nov-2013
01-AUG-13
16-NOV-13
31-MAY-13
02-AUG-13
31-Dec-2013
27-JUL-13
31-DEC-13
29-MAR-13A
06-SEP-13
26-May-2014
-186d
-282d
-298d
-28d
-154d
-43d
-193d
-218d
-217d
-219d
-223d
-217d
-218d
-221d
-219d
-177d
-219d
-158d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A15980
A15960
A15970
A26660
A36290
A36310
Pro
NSC
A53990
A54000
A54010
A54020
A54030
A54040
A54050
A54060
A54070
A54080
24-Oct-2013
22-Nov-2013
20-Jun-2013
22-Mar-2013
22-Nov-2012
20-Apr-2013
13-Aug-2012
13-Aug-2012
23-Jan-2013
25-Jan-2013
04-Feb-2013
13-Feb-2013
16-Feb-2013
24-Oct-2012
13-Sep-2012
02-Feb-2013
04-Jan-2013
20-Nov-2012
24-Oct-2013
22-Nov-2013
20-Jun-2013
22-Mar-2013
22-Nov-2012
20-Apr-2013
10-Jun-2013
16-Feb-2013
23-Jan-2013
25-Jan-2013
04-Feb-2013
13-Feb-2013
16-Feb-2013
24-Oct-2012
13-Sep-2012
02-Feb-2013
04-Jan-2013
20-Nov-2012
26-MAY-14
15-APR-14
03-FEB-14
19-SEP-13
26-FEB-13A
07-JAN-14
28-Nov-2012A
28-Nov-2012A
24-JUL-13
18-JUN-13
20-JUL-13
23-JUL-13
24-JUL-13
03-JAN-13A
03-JAN-13A
02-MAY-13A
14-JUN-13
31-MAY-13
26-MAY-14
15-APR-14
03-FEB-14
19-SEP-13
26-FEB-13A
07-JAN-14
03-Dec-2013
14-Aug-2013
24-JUL-13
18-JUN-13
20-JUL-13
23-JUL-13
24-JUL-13
03-JAN-13A
03-JAN-13A
02-MAY-13A
14-JUN-13
31-MAY-13
-184d
-124d
-196d
-155d
-82d
-224d
-151d
-153d
-157d
-124d
-144d
-138d
-136d
-61d
-96d
-76d
-139d
-165d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 HVAC
7 FPS
7 Internal Building Electrification
7 IBMS
7 Landscape
7 Faade
7 Elevators
7 HT Switchyard
7 HT / LT Package
7 Chillers
7 Lighting fixtures
7 Kitchen Equipments
7 Workstations & Modular Furniture
7 Fire Doors
7 UPS and batteries
6 Procurement of long Lead Material
7 MEP Material Procurement
8 DGs
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A54090
A54100
A54110
A54120
A54130
A54140
A54150
A54160
A54170
A54180
A54190
A54200
A54210
A54220
A54230
Pro- Mat
1
A54240
04-Sep-2012
24-Aug-2012
25-Sep-2012
06-Nov-2012
09-Feb-2013
24-Oct-2012
02-Oct-2012
13-Aug-2012
07-Sep-2012
05-Oct-2012
11-Dec-2012
29-Dec-2012
10-Jan-2013
23-Jan-2013
21-Jan-2013
11-Sep-2012
11-Sep-2012
24-Oct-2012
04-Sep-2012
24-Aug-2012
25-Sep-2012
06-Nov-2012
09-Feb-2013
24-Oct-2012
02-Oct-2012
13-Aug-2012
07-Sep-2012
05-Oct-2012
11-Dec-2012
29-Dec-2012
10-Jan-2013
23-Jan-2013
21-Jan-2013
10-Jun-2013
10-Jun-2013
12-Mar-2013
08-MAR-13A
07-JAN-13A
18-MAR-13A
02-MAY-13A
08-AUG-13
18-JUN-13
04-JAN-13A
28-NOV-12A
07-JAN-13A
03-JAN-13A
14-AUG-13
05-JUL-13
17-JUL-13
18-JUN-13
02-MAY-13A
12-Feb-2013A
12-Feb-2013A
01-MAY-13A
08-MAR-13A
07-JAN-13A
18-MAR-13A
02-MAY-13A
08-AUG-13
18-JUN-13
04-JAN-13A
28-NOV-12A
07-JAN-13A
03-JAN-13A
14-AUG-13
05-JUL-13
17-JUL-13
18-JUN-13
02-MAY-13A
03-Dec-2013
03-Dec-2013
23-OCT-13
-159d
-116d
-149d
-152d
-155d
-204d
-82d
-92d
-104d
-77d
-212d
-162d
-162d
-126d
-87d
-151d
-151d
-193d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
8 Chillers
8 Air Cooler
8 Lifts
8 Escalators
8 HT Transformers
8 LT Transformaers
8 Electrical Panels
8 AHUs
5 Handing Over Dates
6 STP
7 STP Handing over
6 Kiosk
7 kiosk Handing over
6 Service tunnel
7 Service Tunnel handing over
6 HSD
7 HSD Handing Over
6 HT Panel & Switch Yard
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A54250
A54260
A54270
A54280
A54290
A54300
A54310
A54320
1
5
A54410
3
A54430
4
A54460
7
A54420
6
25-Oct-2012
22-Nov-2012
06-Dec-2012
16-Oct-2012
16-Oct-2012
11-Sep-2012
11-Sep-2012
11-Sep-2012
07-Mar-2013
24-Jan-2014
24-Jan-2014
07-Oct-2013
07-Oct-2013
24-Jan-2014
24-Jan-2014
07-Mar-2013
07-Mar-2013
20-Apr-2013
06-Feb-2013
06-Mar-2013
10-Jun-2013
28-Jan-2013
24-Dec-2012
19-Nov-2012
19-Nov-2012
24-Dec-2012
10-Feb-2014
24-Jan-2014
24-Jan-2014
07-Oct-2013
07-Oct-2013
24-Jan-2014
24-Jan-2014
07-Mar-2013
07-Mar-2013
20-Apr-2013
12-FEB-13A
31-MAY-13
04-MAR-13A
24-MAY-13A
25-APR-13A
03-MAY-13A
31-MAY-13
31-MAY-13
16-Nov-2013
09-May-2015
09-MAY-15
29-Jan-2014
29-JAN-14
09-May-2015
09-MAY-15
16-Nov-2013
16-NOV-13
01-Jan-2014
22-AUG-13
12-SEP-13
03-DEC-13
17-OCT-13
05-SEP-13
08-AUG-13
08-AUG-13
12-SEP-13
11-May-2015
11-May-2015
11-MAY-15
30-Jan-2014
30-JAN-14
11-May-2015
11-MAY-15
16-Nov-2013
16-NOV-13
01-Jan-2014
-169d
-163d
-151d
-225d
-219d
-225d
-225d
-225d
-390d
-404d
-403d
-99d
-99d
-404d
-403d
-218d
-219d
-219d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A54450
1
A54330
A54340
A54350
A54360
A54370
A54380
A54390
A54400
2
A54440
Des
1
A53760
A53770
A53780
A53790
20-Apr-2013
15-Oct-2013
10-Feb-2014
15-Oct-2013
04-Nov-2013
23-Nov-2013
13-Dec-2013
02-Jan-2014
22-Jan-2014
10-Feb-2014
10-Feb-2014
10-Feb-2014
13-Aug-2012
13-Aug-2012
01-Sep-2012
13-Sep-2012
11-Sep-2012
11-Sep-2012
20-Apr-2013
10-Feb-2014
10-Feb-2014
15-Oct-2013
04-Nov-2013
23-Nov-2013
13-Dec-2013
02-Jan-2014
22-Jan-2014
10-Feb-2014
10-Feb-2014
10-Feb-2014
22-Nov-2012
13-Sep-2012
01-Sep-2012
13-Sep-2012
11-Sep-2012
11-Sep-2012
01-JAN-14
20-Jan-2014
28-FEB-15
20-JAN-14
29-JAN-14
18-FEB-14
11-MAR-14
01-APR-14
21-APR-14
10-MAY-14
09-May-2015
09-MAY-15
20-Aug-2012A
20-Sep-2012A
19-OCT-12A
31-MAY-13
31-MAY-13
31-MAY-13
01-JAN-14
28-Feb-2015
28-FEB-15
20-JAN-14
29-JAN-14
18-FEB-14
11-MAR-14
01-APR-14
21-APR-14
10-MAY-14
09-May-2015
09-MAY-15
31-May-2013
31-May-2013
19-OCT-12A
31-MAY-13
31-MAY-13
31-MAY-13
-219d
-329d
-329d
-84d
-75d
-75d
-76d
-77d
-77d
-78d
-389d
-389d
-163d
-223d
-41d
-223d
-225d
-225d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A11381
A11395
A53800
2
A53950
A53960
A53970
A53980
A11431
A11441
3
A53710
A53720
A53730
A53740
A11551
A11561
4
13-Aug-2012
01-Sep-2012
11-Sep-2012
13-Aug-2012
16-Aug-2012
01-Sep-2012
01-Sep-2012
11-Sep-2012
13-Aug-2012
11-Sep-2012
13-Aug-2012
13-Aug-2012
01-Sep-2012
01-Sep-2012
11-Sep-2012
13-Aug-2012
11-Sep-2012
21-Aug-2012
13-Aug-2012
01-Sep-2012
11-Sep-2012
11-Sep-2012
16-Aug-2012
01-Sep-2012
01-Sep-2012
11-Sep-2012
13-Aug-2012
11-Sep-2012
11-Sep-2012
13-Aug-2012
01-Sep-2012
01-Sep-2012
11-Sep-2012
13-Aug-2012
11-Sep-2012
18-Oct-2012
20-SEP-12A
21-FEB-13A
31-MAY-13
20-Aug-2012A
20-AUG-12A
15-OCT-12A
31-MAY-13
31-MAY-13
24-SEP-12A
21-FEB-13A
10-Dec-2012A
10-DEC-12A
19-JAN-13A
31-MAY-13
31-MAY-13
18-JAN-13A
31-MAY-13
29-Oct-2012A
20-SEP-12A
21-FEB-13A
31-MAY-13
31-May-2013
20-AUG-12A
15-OCT-12A
31-MAY-13
31-MAY-13
24-SEP-12A
21-FEB-13A
31-May-2013
10-DEC-12A
19-JAN-13A
31-MAY-13
31-MAY-13
18-JAN-13A
31-MAY-13
31-May-2013
-33d
-148d
-225d
-225d
-3d
-37d
-233d
-225d
-36d
-140d
-225d
-102d
-120d
-233d
-225d
-136d
-225d
-193d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A53890
A53900
5
A53910
A53920
6
A53810
A53820
7
A53830
A53840
8
A53850
A53860
A53870
A53880
A14930
9
21-Aug-2012
18-Oct-2012
13-Sep-2012
13-Sep-2012
30-Oct-2012
13-Sep-2012
13-Sep-2012
10-Nov-2012
01-Sep-2012
01-Sep-2012
10-Nov-2012
18-Oct-2012
18-Oct-2012
22-Nov-2012
22-Nov-2012
22-Nov-2012
22-Nov-2012
13-Aug-2012
21-Aug-2012
18-Oct-2012
30-Oct-2012
13-Sep-2012
30-Oct-2012
10-Nov-2012
13-Sep-2012
10-Nov-2012
10-Nov-2012
01-Sep-2012
10-Nov-2012
22-Nov-2012
18-Oct-2012
22-Nov-2012
22-Nov-2012
22-Nov-2012
22-Nov-2012
13-Sep-2012
29-OCT-12A
31-MAY-13
18-Jan-2013A
18-JAN-13A
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
29-OCT-12A
31-MAY-13
31-May-2013
18-JAN-13A
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
31-May-2013
-59d
-193d
-183d
-109d
-183d
-173d
-223d
-173d
-173d
-233d
-173d
-163d
-193d
-163d
-163d
-163d
-163d
-223d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A53930
A53940
10
A14940
A14950
7
3
MOC130
1
A53580
A53590
T& C
T&C-1000
T&C-1001
Cons
S1
Fac
S1-Fac1000
13-Aug-2012
13-Sep-2012
13-Sep-2012
13-Sep-2012
01-Oct-2012
09-Aug-2012
09-Aug-2012
09-Aug-2012
09-Aug-2012
09-Aug-2012
09-Aug-2012
15-Nov-2013
15-Nov-2013
17-Jan-2014
13-Aug-2012
13-Aug-2012
04-Dec-2012
04-Dec-2012
13-Aug-2012
13-Sep-2012
01-Oct-2012
13-Sep-2012
01-Oct-2012
17-Oct-2012
24-Sep-2012
24-Sep-2012
17-Oct-2012
17-Oct-2012
17-Oct-2012
08-Feb-2014
23-Jan-2014
08-Feb-2014
08-Feb-2014
08-Feb-2014
28-Sep-2013
24-Jan-2013
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
09-Aug-2012A
09-Aug-2012A
09-AUG-12A
09-Aug-2012A
09-AUG-12A
09-AUG-12A
28-Feb-2015
28-FEB-15
16-APR-15
18-Aug-2012A
18-Aug-2012A
30-Jan-2013A
30-JAN-13A
31-MAY-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
31-May-2013
31-May-2013
10-OCT-12A
31-May-2013
20-NOV-12A
02-NOV-12A
09-May-2015
09-MAY-15
09-MAY-15
28-Feb-2015
28-Feb-2015
10-Feb-2014
19-AUG-13
-250d
-223d
-208d
-223d
-208d
-194d
-214d
-13d
-194d
-28d
-13d
-390d
-403d
-389d
-330d
-330d
-115d
-177d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S1-Fac1001
S1-Fac1020
S1-Fac1011
S1-Fac1012
S1-Fac1013
S1-Fac1014
S1-Fac1015
S1-Fac1016
3
6
2
1
A36300
A62960
A62970
3
A36510
A36520
06-May-2013
28-Sep-2013
22-May-2013
11-Jun-2013
01-Jul-2013
22-Jul-2013
10-Aug-2013
30-Aug-2013
17-Jan-2013
16-Mar-2013
16-Mar-2013
16-Mar-2013
16-Mar-2013
22-Mar-2013
27-Mar-2013
02-Apr-2013
02-Apr-2013
05-Apr-2013
30-May-2013
28-Sep-2013
19-Jun-2013
09-Jul-2013
29-Jul-2013
19-Aug-2013
07-Sep-2013
27-Sep-2013
24-Jul-2013
10-Jul-2013
08-Apr-2013
27-Mar-2013
21-Mar-2013
26-Mar-2013
27-Mar-2013
08-Apr-2013
04-Apr-2013
06-Apr-2013
18-SEP-13
10-FEB-14
04-OCT-13
24-OCT-13
13-NOV-13
05-DEC-13
25-DEC-13
13-JAN-14
06-Apr-2013A
06-Apr-2013A
06-Apr-2013A
06-Apr-2013A
06-APR-13A
10-APR-13A
17-APR-13A
19-Apr-2013A
19-APR-13A
23-APR-13A
12-OCT-13
10-FEB-14
01-NOV-13
21-NOV-13
11-DEC-13
01-JAN-14
21-JAN-14
10-FEB-14
04-Dec-2014
04-Dec-2014
24-Jun-2013
24-Jun-2013
12-APR-13A
17-APR-13A
18-APR-13A
24-Jun-2013
25-MAY-13A
28-MAY-13A
-116d
-116d
-116d
-116d
-116d
-116d
-116d
-116d
-427d
-439d
-66d
-76d
-18d
-18d
-18d
-66d
-43d
-43d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 Fourth Floor ro Fifth Floor
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A36530
2
A62980
A36490
A36500
5
1
A63000
A63010
A63020
2
A63030
A63040
A63050
3
A63060
A63070
A63080
08-Apr-2013
28-Mar-2013
28-Mar-2013
30-Mar-2013
01-Apr-2013
16-May-2013
16-May-2013
16-May-2013
20-May-2013
22-May-2013
23-May-2013
23-May-2013
25-May-2013
27-May-2013
28-May-2013
28-May-2013
31-May-2013
03-Jun-2013
08-Apr-2013
01-Apr-2013
29-Mar-2013
30-Mar-2013
01-Apr-2013
03-Jun-2013
22-May-2013
18-May-2013
21-May-2013
22-May-2013
27-May-2013
24-May-2013
25-May-2013
27-May-2013
03-Jun-2013
30-May-2013
01-Jun-2013
03-Jun-2013
29-APR-13A
06-Apr-2013A
06-APR-13A
10-APR-13A
17-APR-13A
14-Aug-2013
14-Aug-2013
14-AUG-13
03-SEP-13
20-SEP-13
07-Oct-2013
07-OCT-13
25-OCT-13
11-NOV-13
27-Nov-2013
27-NOV-13
17-DEC-13
03-JAN-14
29-MAY-13A
24-Jun-2013
12-APR-13A
17-APR-13A
18-APR-13A
20-Jan-2014
07-Oct-2013
02-SEP-13
20-SEP-13
07-OCT-13
27-Nov-2013
25-OCT-13
11-NOV-13
27-NOV-13
20-Jan-2014
17-DEC-13
03-JAN-14
20-JAN-14
-43d
-72d
-11d
-14d
-14d
-198d
-118d
-91d
-104d
-118d
-158d
-131d
-144d
-158d
-198d
-171d
-184d
-198d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
7
3
A16320
A36960
A36970
1
A63180
A63190
A63200
2
A63210
A63220
A63230
6
1
A63090
A63100
A63110
22-Jun-2013
04-Jul-2013
10-Jul-2013
04-Jul-2013
08-Jul-2013
22-Jun-2013
22-Jun-2013
26-Jun-2013
28-Jun-2013
29-Jun-2013
29-Jun-2013
02-Jul-2013
03-Jul-2013
04-Jun-2013
04-Jun-2013
04-Jun-2013
07-Jun-2013
10-Jun-2013
10-Jul-2013
10-Jul-2013
10-Jul-2013
06-Jul-2013
09-Jul-2013
28-Jun-2013
25-Jun-2013
27-Jun-2013
28-Jun-2013
03-Jul-2013
01-Jul-2013
02-Jul-2013
03-Jul-2013
21-Jun-2013
10-Jun-2013
06-Jun-2013
08-Jun-2013
10-Jun-2013
27-Jun-2014
11-Oct-2014
17-NOV-14
11-OCT-14
30-OCT-14
27-Jun-2014
27-JUN-14
17-JUL-14
04-AUG-14
21-Aug-2014
21-AUG-14
08-SEP-14
24-SEP-14
20-Jan-2014
20-Jan-2014
20-JAN-14
08-FEB-14
26-FEB-14
04-Dec-2014
04-Dec-2014
04-DEC-14
30-OCT-14
17-NOV-14
20-Aug-2014
17-JUL-14
04-AUG-14
20-AUG-14
11-Oct-2014
08-SEP-14
24-SEP-14
11-OCT-14
27-Jun-2014
14-Mar-2014
08-FEB-14
26-FEB-14
14-MAR-14
-439d
-439d
-438d
-411d
-425d
-358d
-331d
-345d
-358d
-399d
-371d
-385d
-398d
-318d
-238d
-211d
-225d
-238d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 SF to TF
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A63150
A63160
A63170
2
A63120
A63130
A63140
3
2
A36570
A36580
A36590
3
A36600
A36610
A36620
1
15-Jun-2013
15-Jun-2013
19-Jun-2013
21-Jun-2013
11-Jun-2013
11-Jun-2013
13-Jun-2013
14-Jun-2013
09-Apr-2013
16-Apr-2013
16-Apr-2013
18-Apr-2013
19-Apr-2013
20-Apr-2013
20-Apr-2013
24-Apr-2013
26-Apr-2013
09-Apr-2013
21-Jun-2013
18-Jun-2013
20-Jun-2013
21-Jun-2013
14-Jun-2013
12-Jun-2013
13-Jun-2013
14-Jun-2013
26-Apr-2013
19-Apr-2013
17-Apr-2013
18-Apr-2013
19-Apr-2013
26-Apr-2013
23-Apr-2013
25-Apr-2013
26-Apr-2013
15-Apr-2013
05-May-2014
05-MAY-14
24-MAY-14
11-JUN-14
14-Mar-2014
14-MAR-14
02-APR-14
18-APR-14
30-Apr-2013A
01-May-2013A
01-MAY-13A
04-MAY-13A
10-MAY-13A
12-May-2013A
12-MAY-13A
17-MAY-13A
23-MAY-13A
30-Apr-2013A
27-Jun-2014
24-MAY-14
11-JUN-14
27-JUN-14
05-May-2014
02-APR-14
18-APR-14
05-MAY-14
24-Jun-2013
24-Jun-2013
07-JUN-13A
08-JUN-13A
10-JUN-13A
24-Jun-2013
13-JUN-13A
15-JUN-13A
17-JUN-13A
24-Jun-2013
-318d
-291d
-305d
-318d
-278d
-251d
-265d
-278d
-50d
-56d
-43d
-43d
-43d
-50d
-43d
-43d
-43d
-60d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Reinforcement
11 Concrete
9 TF to Fourth Floor
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
8 ST 4
9 TF to Fourth Floor
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A36540
A36550
A36560
4
1
A36630
A36640
A36650
2
A36660
A36670
A36680
3
A36690
A36700
A62990
4
4
09-Apr-2013
12-Apr-2013
15-Apr-2013
27-Apr-2013
27-Apr-2013
27-Apr-2013
01-May-2013
03-May-2013
04-May-2013
04-May-2013
07-May-2013
08-May-2013
09-May-2013
09-May-2013
13-May-2013
15-May-2013
21-Feb-2013
30-Apr-2013
11-Apr-2013
13-Apr-2013
15-Apr-2013
15-May-2013
03-May-2013
30-Apr-2013
02-May-2013
03-May-2013
08-May-2013
06-May-2013
07-May-2013
08-May-2013
15-May-2013
11-May-2013
14-May-2013
15-May-2013
12-Jul-2013
17-May-2013
30-APR-13A
03-MAY-13A
09-MAY-13A
25-May-2013A
25-May-2013A
25-MAY-13A
28-MAY-13A
02-JUN-13A
25-May-2013A
25-MAY-13A
28-MAY-13A
02-JUN-13A
03-Jun-2013A
03-JUN-13A
10-JUL-13
29-JUL-13
23-Jul-2013
28-Sep-2013
01-JUN-13A
04-JUN-13A
05-JUN-13A
14-Aug-2013
24-Jun-2013
20-JUN-13A
22-JUN-13A
24-JUN-13A
28-Jun-2013A
26-JUN-13A
27-JUN-13A
28-JUN-13A
14-Aug-2013
10-JUL-13
29-JUL-13
14-AUG-13
12-Dec-2013
17-Oct-2013
-43d
-43d
-43d
-78d
-44d
-43d
-43d
-43d
-44d
-43d
-43d
-43d
-78d
-51d
-64d
-78d
-131d
-131d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 Fourth Floor ro Fifth Floor
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
2
A61990
A62000
A62010
3
A62020
A62030
A62040
1
A61960
A61970
A61980
5
2
A62080
A62090
A62100
3
07-May-2013
07-May-2013
09-May-2013
10-May-2013
11-May-2013
11-May-2013
15-May-2013
17-May-2013
30-Apr-2013
30-Apr-2013
03-May-2013
06-May-2013
18-May-2013
25-May-2013
25-May-2013
28-May-2013
29-May-2013
30-May-2013
10-May-2013
08-May-2013
09-May-2013
10-May-2013
17-May-2013
14-May-2013
16-May-2013
17-May-2013
06-May-2013
02-May-2013
04-May-2013
06-May-2013
05-Jun-2013
29-May-2013
27-May-2013
28-May-2013
29-May-2013
05-Jun-2013
05-Oct-2013
05-OCT-13
08-OCT-13
09-OCT-13
10-Oct-2013
10-OCT-13
14-OCT-13
16-OCT-13
28-Sep-2013
28-SEP-13
02-OCT-13
04-OCT-13
17-Oct-2013
24-Oct-2013
24-OCT-13
26-OCT-13
28-OCT-13
29-Oct-2013
10-Oct-2013
08-OCT-13
09-OCT-13
10-OCT-13
17-Oct-2013
14-OCT-13
16-OCT-13
17-OCT-13
05-Oct-2013
02-OCT-13
04-OCT-13
05-OCT-13
05-Nov-2013
29-Oct-2013
26-OCT-13
28-OCT-13
29-OCT-13
05-Nov-2013
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 GF to FF
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Fifth Flight
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A62110
A62120
A62130
1
A62050
A62060
A62070
1
1
A61630
A61640
A61650
2
A61660
A61670
A61680
5
A61750
30-May-2013
03-Jun-2013
05-Jun-2013
18-May-2013
18-May-2013
22-May-2013
24-May-2013
21-Feb-2013
21-Feb-2013
21-Feb-2013
23-Feb-2013
25-Feb-2013
26-Feb-2013
26-Feb-2013
01-Mar-2013
04-Mar-2013
16-Mar-2013
16-Mar-2013
01-Jun-2013
04-Jun-2013
05-Jun-2013
24-May-2013
21-May-2013
23-May-2013
24-May-2013
22-Mar-2013
25-Feb-2013
22-Feb-2013
23-Feb-2013
25-Feb-2013
04-Mar-2013
28-Feb-2013
02-Mar-2013
04-Mar-2013
22-Mar-2013
19-Mar-2013
29-OCT-13
01-NOV-13
04-NOV-13
17-Oct-2013
17-OCT-13
21-OCT-13
23-OCT-13
23-Jul-2013
23-Jul-2013
23-JUL-13
25-JUL-13
26-JUL-13
27-Jul-2013
27-JUL-13
31-JUL-13
02-AUG-13
15-Aug-2013
15-AUG-13
01-NOV-13
04-NOV-13
05-NOV-13
24-Oct-2013
21-OCT-13
23-OCT-13
24-OCT-13
22-Aug-2013
27-Jul-2013
25-JUL-13
26-JUL-13
27-JUL-13
03-Aug-2013
31-JUL-13
02-AUG-13
03-AUG-13
22-Aug-2013
19-AUG-13
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Concrete
10 Fourth Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 FF to SF
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A61760
A61770
4
A61720
A61730
A61740
3
A61690
A61700
A61710
2
1
A61780
A61790
A61800
2
A61810
A61820
20-Mar-2013
22-Mar-2013
12-Mar-2013
12-Mar-2013
14-Mar-2013
15-Mar-2013
05-Mar-2013
05-Mar-2013
08-Mar-2013
11-Mar-2013
23-Mar-2013
23-Mar-2013
23-Mar-2013
27-Mar-2013
29-Mar-2013
30-Mar-2013
30-Mar-2013
02-Apr-2013
21-Mar-2013
22-Mar-2013
15-Mar-2013
13-Mar-2013
14-Mar-2013
15-Mar-2013
11-Mar-2013
07-Mar-2013
09-Mar-2013
11-Mar-2013
10-Apr-2013
29-Mar-2013
26-Mar-2013
28-Mar-2013
29-Mar-2013
03-Apr-2013
01-Apr-2013
02-Apr-2013
19-AUG-13
21-AUG-13
10-Aug-2013
10-AUG-13
13-AUG-13
14-AUG-13
03-Aug-2013
03-AUG-13
07-AUG-13
09-AUG-13
22-Aug-2013
22-Aug-2013
22-AUG-13
26-AUG-13
28-AUG-13
29-Aug-2013
29-AUG-13
31-AUG-13
21-AUG-13
22-AUG-13
15-Aug-2013
13-AUG-13
14-AUG-13
15-AUG-13
10-Aug-2013
07-AUG-13
09-AUG-13
10-AUG-13
10-Sep-2013
29-Aug-2013
26-AUG-13
28-AUG-13
29-AUG-13
03-Sep-2013
31-AUG-13
02-SEP-13
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 Fifth Floor to Sixth Floor
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A61830
3
A61840
A61850
A61860
6
1
A62140
A62150
A62160
2
A62170
A62180
A62190
3
A62200
A62210
A62220
03-Apr-2013
04-Apr-2013
04-Apr-2013
08-Apr-2013
10-Apr-2013
06-Jun-2013
06-Jun-2013
06-Jun-2013
10-Jun-2013
12-Jun-2013
13-Jun-2013
13-Jun-2013
15-Jun-2013
17-Jun-2013
18-Jun-2013
18-Jun-2013
21-Jun-2013
24-Jun-2013
03-Apr-2013
10-Apr-2013
06-Apr-2013
09-Apr-2013
10-Apr-2013
24-Jun-2013
12-Jun-2013
08-Jun-2013
11-Jun-2013
12-Jun-2013
17-Jun-2013
14-Jun-2013
15-Jun-2013
17-Jun-2013
24-Jun-2013
20-Jun-2013
22-Jun-2013
24-Jun-2013
02-SEP-13
03-Sep-2013
03-SEP-13
06-SEP-13
09-SEP-13
05-Nov-2013
05-Nov-2013
05-NOV-13
08-NOV-13
11-NOV-13
12-Nov-2013
12-NOV-13
14-NOV-13
15-NOV-13
16-Nov-2013
16-NOV-13
20-NOV-13
22-NOV-13
03-SEP-13
10-Sep-2013
06-SEP-13
09-SEP-13
10-SEP-13
23-Nov-2013
12-Nov-2013
08-NOV-13
11-NOV-13
12-NOV-13
16-Nov-2013
14-NOV-13
15-NOV-13
16-NOV-13
23-Nov-2013
20-NOV-13
22-NOV-13
23-NOV-13
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
7
1
A62230
A62240
A62250
3
A53440
A62290
A62300
2
A62260
A62270
A62280
3
2
A61900
A61910
A61920
25-Jun-2013
25-Jun-2013
25-Jun-2013
28-Jun-2013
01-Jul-2013
06-Jul-2013
12-Jul-2013
06-Jul-2013
10-Jul-2013
02-Jul-2013
02-Jul-2013
04-Jul-2013
05-Jul-2013
11-Apr-2013
18-Apr-2013
18-Apr-2013
20-Apr-2013
22-Apr-2013
12-Jul-2013
01-Jul-2013
27-Jun-2013
29-Jun-2013
01-Jul-2013
12-Jul-2013
12-Jul-2013
09-Jul-2013
11-Jul-2013
05-Jul-2013
03-Jul-2013
04-Jul-2013
05-Jul-2013
29-Apr-2013
22-Apr-2013
19-Apr-2013
20-Apr-2013
22-Apr-2013
23-Nov-2013
23-Nov-2013
23-NOV-13
27-NOV-13
29-NOV-13
05-Dec-2013
11-DEC-13
05-DEC-13
09-DEC-13
30-Nov-2013
30-NOV-13
03-DEC-13
04-DEC-13
10-Sep-2013
17-Sep-2013
17-SEP-13
19-SEP-13
20-SEP-13
12-Dec-2013
30-Nov-2013
27-NOV-13
29-NOV-13
30-NOV-13
12-Dec-2013
12-DEC-13
09-DEC-13
11-DEC-13
05-Dec-2013
03-DEC-13
04-DEC-13
05-DEC-13
28-Sep-2013
21-Sep-2013
19-SEP-13
20-SEP-13
21-SEP-13
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
8 ST 2
9 Sixth Floor to Terrace
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A61930
A61940
A61950
1
A61870
A61880
A61890
2
7
1
A60880
A60890
A60900
2
A60910
A60920
A60930
23-Apr-2013
23-Apr-2013
26-Apr-2013
29-Apr-2013
11-Apr-2013
11-Apr-2013
15-Apr-2013
17-Apr-2013
29-Jan-2013
01-Jun-2013
01-Jun-2013
01-Jun-2013
05-Jun-2013
07-Jun-2013
08-Jun-2013
08-Jun-2013
11-Jun-2013
12-Jun-2013
29-Apr-2013
25-Apr-2013
27-Apr-2013
29-Apr-2013
17-Apr-2013
13-Apr-2013
16-Apr-2013
17-Apr-2013
19-Jun-2013
19-Jun-2013
07-Jun-2013
04-Jun-2013
06-Jun-2013
07-Jun-2013
12-Jun-2013
10-Jun-2013
11-Jun-2013
12-Jun-2013
21-Sep-2013
21-SEP-13
25-SEP-13
27-SEP-13
10-Sep-2013
10-SEP-13
13-SEP-13
16-SEP-13
29-Jun-2013
31-Oct-2013
31-Oct-2013
31-OCT-13
04-NOV-13
06-NOV-13
07-Nov-2013
07-NOV-13
09-NOV-13
11-NOV-13
28-Sep-2013
25-SEP-13
27-SEP-13
28-SEP-13
17-Sep-2013
13-SEP-13
16-SEP-13
17-SEP-13
19-Nov-2013
19-Nov-2013
07-Nov-2013
04-NOV-13
06-NOV-13
07-NOV-13
12-Nov-2013
09-NOV-13
11-NOV-13
12-NOV-13
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Third Flight
11 Concrete
11 Shuttering
11 Reinforcement
9 SF to TF
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 GF to FF
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A53420
A60940
A60950
3
2
A60580
A60590
A60600
3
A60610
A60620
A60630
1
A60550
A60560
A60570
1
13-Jun-2013
19-Jun-2013
13-Jun-2013
17-Jun-2013
19-Mar-2013
26-Mar-2013
26-Mar-2013
28-Mar-2013
29-Mar-2013
30-Mar-2013
30-Mar-2013
03-Apr-2013
05-Apr-2013
19-Mar-2013
19-Mar-2013
22-Mar-2013
25-Mar-2013
29-Jan-2013
19-Jun-2013
19-Jun-2013
15-Jun-2013
18-Jun-2013
05-Apr-2013
29-Mar-2013
27-Mar-2013
28-Mar-2013
29-Mar-2013
05-Apr-2013
02-Apr-2013
04-Apr-2013
05-Apr-2013
25-Mar-2013
21-Mar-2013
23-Mar-2013
25-Mar-2013
27-Feb-2013
12-Nov-2013
18-NOV-13
12-NOV-13
15-NOV-13
17-Aug-2013
24-Aug-2013
24-AUG-13
27-AUG-13
28-AUG-13
29-Aug-2013
29-AUG-13
02-SEP-13
04-SEP-13
17-Aug-2013
17-AUG-13
21-AUG-13
23-AUG-13
29-Jun-2013
19-Nov-2013
19-NOV-13
15-NOV-13
18-NOV-13
05-Sep-2013
29-Aug-2013
27-AUG-13
28-AUG-13
29-AUG-13
05-Sep-2013
02-SEP-13
04-SEP-13
05-SEP-13
24-Aug-2013
21-AUG-13
23-AUG-13
24-AUG-13
30-Jul-2013
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Fourth Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Fifth Flight
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
1
A60310
A60320
A60330
2
A60340
A60350
A60360
3
A60370
A60380
A60390
4
A60400
A60410
A60420
5
A60430
29-Jan-2013
29-Jan-2013
31-Jan-2013
01-Feb-2013
02-Feb-2013
02-Feb-2013
06-Feb-2013
08-Feb-2013
09-Feb-2013
09-Feb-2013
13-Feb-2013
15-Feb-2013
16-Feb-2013
16-Feb-2013
19-Feb-2013
20-Feb-2013
21-Feb-2013
21-Feb-2013
01-Feb-2013
30-Jan-2013
31-Jan-2013
01-Feb-2013
08-Feb-2013
05-Feb-2013
07-Feb-2013
08-Feb-2013
15-Feb-2013
12-Feb-2013
14-Feb-2013
15-Feb-2013
20-Feb-2013
18-Feb-2013
19-Feb-2013
20-Feb-2013
27-Feb-2013
23-Feb-2013
29-Jun-2013
29-JUN-13
02-JUL-13
03-JUL-13
04-Jul-2013
04-JUL-13
08-JUL-13
10-JUL-13
11-Jul-2013
11-JUL-13
15-JUL-13
17-JUL-13
18-Jul-2013
18-JUL-13
20-JUL-13
22-JUL-13
23-Jul-2013
23-JUL-13
04-Jul-2013
02-JUL-13
03-JUL-13
04-JUL-13
11-Jul-2013
08-JUL-13
10-JUL-13
11-JUL-13
18-Jul-2013
15-JUL-13
17-JUL-13
18-JUL-13
23-Jul-2013
20-JUL-13
22-JUL-13
23-JUL-13
30-Jul-2013
26-JUL-13
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Concrete
9 Fourth Floor ro Fifth Floor
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 TF to Fourth Floor
10 Second Flight
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A60440
A60450
5
2
A60730
A60740
A60750
1
A60700
A60710
A60720
3
A60760
A60770
A60780
4
2
A60670
25-Feb-2013
27-Feb-2013
25-Apr-2013
02-May-2013
02-May-2013
04-May-2013
06-May-2013
25-Apr-2013
25-Apr-2013
29-Apr-2013
01-May-2013
07-May-2013
07-May-2013
10-May-2013
13-May-2013
06-Apr-2013
13-Apr-2013
13-Apr-2013
26-Feb-2013
27-Feb-2013
13-May-2013
06-May-2013
03-May-2013
04-May-2013
06-May-2013
01-May-2013
27-Apr-2013
30-Apr-2013
01-May-2013
13-May-2013
09-May-2013
11-May-2013
13-May-2013
24-Apr-2013
17-Apr-2013
15-Apr-2013
26-JUL-13
29-JUL-13
24-Sep-2013
01-Oct-2013
01-OCT-13
03-OCT-13
04-OCT-13
24-Sep-2013
24-SEP-13
27-SEP-13
30-SEP-13
05-Oct-2013
05-OCT-13
09-OCT-13
11-OCT-13
05-Sep-2013
12-Sep-2013
12-SEP-13
29-JUL-13
30-JUL-13
12-Oct-2013
05-Oct-2013
03-OCT-13
04-OCT-13
05-OCT-13
01-Oct-2013
27-SEP-13
30-SEP-13
01-OCT-13
12-Oct-2013
09-OCT-13
11-OCT-13
12-OCT-13
24-Sep-2013
17-Sep-2013
14-SEP-13
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 FF to SF
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A60680
A33920
3
A33930
A33940
A60690
1
A60640
A60650
A60660
2
3
A60520
A60530
A60540
1
A60460
A60470
16-Apr-2013
17-Apr-2013
18-Apr-2013
18-Apr-2013
22-Apr-2013
24-Apr-2013
06-Apr-2013
06-Apr-2013
10-Apr-2013
12-Apr-2013
28-Feb-2013
12-Mar-2013
12-Mar-2013
15-Mar-2013
18-Mar-2013
28-Feb-2013
28-Feb-2013
04-Mar-2013
16-Apr-2013
17-Apr-2013
24-Apr-2013
20-Apr-2013
23-Apr-2013
24-Apr-2013
12-Apr-2013
09-Apr-2013
11-Apr-2013
12-Apr-2013
18-Mar-2013
18-Mar-2013
14-Mar-2013
16-Mar-2013
18-Mar-2013
06-Mar-2013
02-Mar-2013
05-Mar-2013
14-SEP-13
16-SEP-13
17-Sep-2013
17-SEP-13
20-SEP-13
23-SEP-13
05-Sep-2013
05-SEP-13
09-SEP-13
11-SEP-13
30-Jul-2013
10-Aug-2013
10-AUG-13
14-AUG-13
16-AUG-13
30-Jul-2013
30-JUL-13
02-AUG-13
16-SEP-13
17-SEP-13
24-Sep-2013
20-SEP-13
23-SEP-13
24-SEP-13
12-Sep-2013
09-SEP-13
11-SEP-13
12-SEP-13
17-Aug-2013
17-Aug-2013
14-AUG-13
16-AUG-13
17-AUG-13
06-Aug-2013
02-AUG-13
05-AUG-13
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 Fifth Floor to Sixth Floor
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A60480
2
A60490
A60500
A60510
6
1
A60790
A60800
A60810
2
A60820
A60830
A60840
3
A60850
A60860
A60870
06-Mar-2013
07-Mar-2013
07-Mar-2013
09-Mar-2013
11-Mar-2013
14-May-2013
14-May-2013
14-May-2013
17-May-2013
20-May-2013
21-May-2013
21-May-2013
23-May-2013
24-May-2013
25-May-2013
25-May-2013
29-May-2013
31-May-2013
06-Mar-2013
11-Mar-2013
08-Mar-2013
09-Mar-2013
11-Mar-2013
31-May-2013
20-May-2013
16-May-2013
18-May-2013
20-May-2013
24-May-2013
22-May-2013
23-May-2013
24-May-2013
31-May-2013
28-May-2013
30-May-2013
31-May-2013
05-AUG-13
06-Aug-2013
06-AUG-13
08-AUG-13
09-AUG-13
12-Oct-2013
12-Oct-2013
12-OCT-13
16-OCT-13
18-OCT-13
19-Oct-2013
19-OCT-13
22-OCT-13
23-OCT-13
24-Oct-2013
24-OCT-13
28-OCT-13
30-OCT-13
06-AUG-13
10-Aug-2013
08-AUG-13
09-AUG-13
10-AUG-13
31-Oct-2013
19-Oct-2013
16-OCT-13
18-OCT-13
19-OCT-13
24-Oct-2013
22-OCT-13
23-OCT-13
24-OCT-13
31-Oct-2013
28-OCT-13
30-OCT-13
31-OCT-13
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
8 ST 5
9 Fifth Floor to Sixth Floor
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 TF to Fourth Floor
10 First Flight
11 Shuttering
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
5
6
3
A62870
A62880
A62890
1
A62810
A62820
A62830
2
A62840
A62850
A62860
4
1
A62640
A62650
05-Mar-2013
18-Jun-2013
29-Jun-2013
29-Jun-2013
03-Jul-2013
05-Jul-2013
18-Jun-2013
18-Jun-2013
21-Jun-2013
24-Jun-2013
25-Jun-2013
25-Jun-2013
27-Jun-2013
28-Jun-2013
11-May-2013
11-May-2013
11-May-2013
15-May-2013
24-Jul-2013
05-Jul-2013
05-Jul-2013
02-Jul-2013
04-Jul-2013
05-Jul-2013
24-Jun-2013
20-Jun-2013
22-Jun-2013
24-Jun-2013
28-Jun-2013
26-Jun-2013
27-Jun-2013
28-Jun-2013
29-May-2013
17-May-2013
14-May-2013
16-May-2013
12-Jun-2013
25-Sep-2013
07-Oct-2013
07-OCT-13
10-OCT-13
12-OCT-13
25-Sep-2013
25-SEP-13
28-SEP-13
01-OCT-13
02-Oct-2013
02-OCT-13
04-OCT-13
05-OCT-13
19-Aug-2013
19-Aug-2013
19-AUG-13
22-AUG-13
01-Nov-2013
14-Oct-2013
14-Oct-2013
10-OCT-13
12-OCT-13
14-OCT-13
02-Oct-2013
28-SEP-13
01-OCT-13
02-OCT-13
07-Oct-2013
04-OCT-13
05-OCT-13
07-OCT-13
06-Sep-2013
26-Aug-2013
22-AUG-13
24-AUG-13
-86d
-86d
-86d
-85d
-85d
-85d
-86d
-85d
-85d
-85d
-86d
-85d
-85d
-85d
-86d
-86d
-85d
-85d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 Sixth Floor to Terrace
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A62660
2
A62670
A62680
A62690
3
A62700
A62710
A36020
7
2
A62930
A62940
A62950
1
A62900
A62910
A62920
17-May-2013
18-May-2013
18-May-2013
21-May-2013
22-May-2013
23-May-2013
23-May-2013
27-May-2013
29-May-2013
06-Jul-2013
13-Jul-2013
13-Jul-2013
16-Jul-2013
17-Jul-2013
06-Jul-2013
06-Jul-2013
10-Jul-2013
12-Jul-2013
17-May-2013
22-May-2013
20-May-2013
21-May-2013
22-May-2013
29-May-2013
25-May-2013
28-May-2013
29-May-2013
24-Jul-2013
17-Jul-2013
15-Jul-2013
16-Jul-2013
17-Jul-2013
12-Jul-2013
09-Jul-2013
11-Jul-2013
12-Jul-2013
24-AUG-13
26-Aug-2013
26-AUG-13
28-AUG-13
29-AUG-13
30-Aug-2013
30-AUG-13
03-SEP-13
05-SEP-13
14-Oct-2013
21-Oct-2013
21-OCT-13
23-OCT-13
24-OCT-13
14-Oct-2013
14-OCT-13
17-OCT-13
19-OCT-13
26-AUG-13
30-Aug-2013
28-AUG-13
29-AUG-13
30-AUG-13
06-Sep-2013
03-SEP-13
05-SEP-13
06-SEP-13
01-Nov-2013
25-Oct-2013
23-OCT-13
24-OCT-13
25-OCT-13
21-Oct-2013
17-OCT-13
19-OCT-13
21-OCT-13
-85d
-86d
-85d
-85d
-85d
-86d
-85d
-85d
-85d
-86d
-86d
-85d
-85d
-85d
-86d
-85d
-85d
-85d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Third Flight
11 Concrete
11 Shuttering
11 Reinforcement
9 FF to SF
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 SF to TF
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A53450
A36270
A36280
2
1
A62460
A62470
A62480
3
A62520
A62530
A62540
2
A62490
A62500
A62510
3
18-Jul-2013
24-Jul-2013
18-Jul-2013
22-Jul-2013
04-Apr-2013
04-Apr-2013
04-Apr-2013
08-Apr-2013
10-Apr-2013
16-Apr-2013
16-Apr-2013
19-Apr-2013
22-Apr-2013
11-Apr-2013
11-Apr-2013
13-Apr-2013
15-Apr-2013
23-Apr-2013
24-Jul-2013
24-Jul-2013
20-Jul-2013
23-Jul-2013
22-Apr-2013
10-Apr-2013
06-Apr-2013
09-Apr-2013
10-Apr-2013
22-Apr-2013
18-Apr-2013
20-Apr-2013
22-Apr-2013
15-Apr-2013
12-Apr-2013
13-Apr-2013
15-Apr-2013
10-May-2013
25-Oct-2013
31-OCT-13
25-OCT-13
29-OCT-13
12-Jul-2013
12-Jul-2013
12-JUL-13
16-JUL-13
18-JUL-13
24-Jul-2013
24-JUL-13
27-JUL-13
30-JUL-13
19-Jul-2013
19-JUL-13
22-JUL-13
23-JUL-13
31-Jul-2013
01-Nov-2013
01-NOV-13
29-OCT-13
31-OCT-13
31-Jul-2013
19-Jul-2013
16-JUL-13
18-JUL-13
19-JUL-13
31-Jul-2013
27-JUL-13
30-JUL-13
31-JUL-13
24-Jul-2013
22-JUL-13
23-JUL-13
24-JUL-13
19-Aug-2013
-86d
-85d
-85d
-85d
-86d
-86d
-85d
-85d
-85d
-86d
-85d
-85d
-85d
-86d
-85d
-85d
-85d
-86d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 Fourth Floor ro Fifth Floor
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A62610
A62620
A62630
2
A62580
A62590
A62600
1
A62550
A62560
A62570
5
3
A62780
A62790
A62800
1
04-May-2013
04-May-2013
08-May-2013
10-May-2013
30-Apr-2013
30-Apr-2013
02-May-2013
03-May-2013
23-Apr-2013
23-Apr-2013
26-Apr-2013
29-Apr-2013
30-May-2013
11-Jun-2013
11-Jun-2013
14-Jun-2013
17-Jun-2013
30-May-2013
10-May-2013
07-May-2013
09-May-2013
10-May-2013
03-May-2013
01-May-2013
02-May-2013
03-May-2013
29-Apr-2013
25-Apr-2013
27-Apr-2013
29-Apr-2013
17-Jun-2013
17-Jun-2013
13-Jun-2013
15-Jun-2013
17-Jun-2013
05-Jun-2013
12-Aug-2013
12-AUG-13
15-AUG-13
17-AUG-13
07-Aug-2013
07-AUG-13
09-AUG-13
10-AUG-13
31-Jul-2013
31-JUL-13
03-AUG-13
06-AUG-13
06-Sep-2013
18-Sep-2013
18-SEP-13
21-SEP-13
24-SEP-13
06-Sep-2013
19-Aug-2013
15-AUG-13
17-AUG-13
19-AUG-13
12-Aug-2013
09-AUG-13
10-AUG-13
12-AUG-13
07-Aug-2013
03-AUG-13
06-AUG-13
07-AUG-13
25-Sep-2013
25-Sep-2013
21-SEP-13
24-SEP-13
25-SEP-13
13-Sep-2013
-86d
-85d
-85d
-85d
-86d
-85d
-85d
-85d
-86d
-85d
-85d
-85d
-86d
-86d
-85d
-85d
-85d
-86d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 GF to FF
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A62720
A62730
A62740
2
A62750
A62760
A62770
1
2
A62340
A62350
A62360
1
A62310
A62320
A62330
3
A62370
30-May-2013
03-Jun-2013
05-Jun-2013
06-Jun-2013
06-Jun-2013
08-Jun-2013
10-Jun-2013
05-Mar-2013
09-Mar-2013
09-Mar-2013
13-Mar-2013
15-Mar-2013
05-Mar-2013
05-Mar-2013
07-Mar-2013
08-Mar-2013
16-Mar-2013
16-Mar-2013
01-Jun-2013
04-Jun-2013
05-Jun-2013
10-Jun-2013
07-Jun-2013
08-Jun-2013
10-Jun-2013
03-Apr-2013
15-Mar-2013
12-Mar-2013
14-Mar-2013
15-Mar-2013
08-Mar-2013
06-Mar-2013
07-Mar-2013
08-Mar-2013
22-Mar-2013
19-Mar-2013
06-SEP-13
10-SEP-13
12-SEP-13
13-Sep-2013
13-SEP-13
16-SEP-13
17-SEP-13
12-Jun-2013
17-Jun-2013
17-JUN-13
20-JUN-13
22-JUN-13
12-Jun-2013
12-JUN-13
14-JUN-13
15-JUN-13
24-Jun-2013
24-JUN-13
10-SEP-13
12-SEP-13
13-SEP-13
18-Sep-2013
16-SEP-13
17-SEP-13
18-SEP-13
12-Jul-2013
24-Jun-2013
20-JUN-13
22-JUN-13
24-JUN-13
17-Jun-2013
14-JUN-13
15-JUN-13
17-JUN-13
01-Jul-2013
27-JUN-13
-85d
-85d
-85d
-86d
-85d
-85d
-85d
-86d
-86d
-85d
-85d
-85d
-86d
-85d
-85d
-85d
-86d
-85d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Concrete
10 Fourth Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Fifth Flight
11 Shuttering
11 Reinforcement
11 Concrete
8 ST 8
9 GF to FF
10 Shuttering for staircase
10 Reinforcement for staircase
10 Concrete
10 Wall reinforcement
10 Wall shuttering
10 Wall Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A62380
A62390
4
A62400
A62410
A62420
5
A62430
A62440
A62450
8
2
A37140
A37150
A37160
A37280
A37290
A37300
20-Mar-2013
22-Mar-2013
23-Mar-2013
23-Mar-2013
26-Mar-2013
27-Mar-2013
28-Mar-2013
28-Mar-2013
01-Apr-2013
03-Apr-2013
17-Jan-2013
17-Jan-2013
19-Feb-2013
02-Mar-2013
13-Mar-2013
17-Jan-2013
04-Feb-2013
15-Feb-2013
21-Mar-2013
22-Mar-2013
27-Mar-2013
25-Mar-2013
26-Mar-2013
27-Mar-2013
03-Apr-2013
30-Mar-2013
02-Apr-2013
03-Apr-2013
13-Mar-2013
13-Mar-2013
01-Mar-2013
11-Mar-2013
13-Mar-2013
02-Feb-2013
14-Feb-2013
18-Feb-2013
27-JUN-13
29-JUN-13
01-Jul-2013
01-JUL-13
03-JUL-13
04-JUL-13
05-Jul-2013
05-JUL-13
09-JUL-13
11-JUL-13
12-Jun-2013
12-Jun-2013
15-JUL-13
26-JUL-13
06-AUG-13
12-JUN-13
29-JUN-13
11-JUL-13
29-JUN-13
01-JUL-13
05-Jul-2013
03-JUL-13
04-JUL-13
05-JUL-13
12-Jul-2013
09-JUL-13
11-JUL-13
12-JUL-13
07-Aug-2013
07-Aug-2013
26-JUL-13
05-AUG-13
07-AUG-13
29-JUN-13
11-JUL-13
15-JUL-13
-85d
-85d
-86d
-85d
-85d
-85d
-86d
-85d
-85d
-85d
-126d
-126d
-125d
-125d
-125d
-125d
-125d
-125d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
8 ST 3
9 GF to FF
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Fifth Flight
11 Shuttering
11 Reinforcement
11 Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
1
1
A60960
A60970
A60980
2
A60990
A61000
A61010
3
A61020
A61030
A61040
5
A61080
A61090
A61100
09-Feb-2013
09-Feb-2013
09-Feb-2013
09-Feb-2013
12-Feb-2013
13-Feb-2013
14-Feb-2013
14-Feb-2013
18-Feb-2013
20-Feb-2013
21-Feb-2013
21-Feb-2013
25-Feb-2013
27-Feb-2013
05-Mar-2013
05-Mar-2013
08-Mar-2013
11-Mar-2013
01-Jul-2013
11-Mar-2013
13-Feb-2013
11-Feb-2013
12-Feb-2013
13-Feb-2013
20-Feb-2013
16-Feb-2013
19-Feb-2013
20-Feb-2013
27-Feb-2013
23-Feb-2013
26-Feb-2013
27-Feb-2013
11-Mar-2013
07-Mar-2013
09-Mar-2013
11-Mar-2013
11-Jul-2013
11-Jul-2013
11-Jul-2013
11-JUL-13
13-JUL-13
15-JUL-13
16-Jul-2013
16-JUL-13
19-JUL-13
22-JUL-13
23-Jul-2013
23-JUL-13
26-JUL-13
29-JUL-13
03-Aug-2013
03-AUG-13
07-AUG-13
09-AUG-13
30-Nov-2013
10-Aug-2013
16-Jul-2013
13-JUL-13
15-JUL-13
16-JUL-13
23-Jul-2013
19-JUL-13
22-JUL-13
23-JUL-13
30-Jul-2013
26-JUL-13
29-JUL-13
30-JUL-13
10-Aug-2013
07-AUG-13
09-AUG-13
10-AUG-13
-131d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Fourth Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 FF to SF
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 TF to Fourth Floor
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
4
A61050
A61060
A61070
2
3
A61170
A61180
A61190
1
A61110
A61120
A61130
2
A61140
A61150
A61160
4
28-Feb-2013
28-Feb-2013
02-Mar-2013
04-Mar-2013
12-Mar-2013
23-Mar-2013
23-Mar-2013
27-Mar-2013
29-Mar-2013
12-Mar-2013
12-Mar-2013
15-Mar-2013
18-Mar-2013
19-Mar-2013
19-Mar-2013
21-Mar-2013
22-Mar-2013
18-Apr-2013
04-Mar-2013
01-Mar-2013
02-Mar-2013
04-Mar-2013
29-Mar-2013
29-Mar-2013
26-Mar-2013
28-Mar-2013
29-Mar-2013
18-Mar-2013
14-Mar-2013
16-Mar-2013
18-Mar-2013
22-Mar-2013
20-Mar-2013
21-Mar-2013
22-Mar-2013
06-May-2013
30-Jul-2013
30-JUL-13
01-AUG-13
02-AUG-13
10-Aug-2013
22-Aug-2013
22-AUG-13
26-AUG-13
28-AUG-13
10-Aug-2013
10-AUG-13
14-AUG-13
16-AUG-13
17-Aug-2013
17-AUG-13
20-AUG-13
21-AUG-13
17-Sep-2013
03-Aug-2013
01-AUG-13
02-AUG-13
03-AUG-13
29-Aug-2013
29-Aug-2013
26-AUG-13
28-AUG-13
29-AUG-13
17-Aug-2013
14-AUG-13
16-AUG-13
17-AUG-13
22-Aug-2013
20-AUG-13
21-AUG-13
22-AUG-13
05-Oct-2013
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 Sixth Floor to Terrace
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A61350
A61360
A61370
2
A61320
A61330
A61340
1
A61290
A61300
A61310
7
2
A61580
A61590
A61600
3
30-Apr-2013
30-Apr-2013
03-May-2013
06-May-2013
25-Apr-2013
25-Apr-2013
27-Apr-2013
29-Apr-2013
18-Apr-2013
18-Apr-2013
22-Apr-2013
24-Apr-2013
13-Jun-2013
20-Jun-2013
20-Jun-2013
22-Jun-2013
24-Jun-2013
25-Jun-2013
06-May-2013
02-May-2013
04-May-2013
06-May-2013
29-Apr-2013
26-Apr-2013
27-Apr-2013
29-Apr-2013
24-Apr-2013
20-Apr-2013
23-Apr-2013
24-Apr-2013
01-Jul-2013
24-Jun-2013
21-Jun-2013
22-Jun-2013
24-Jun-2013
01-Jul-2013
28-Sep-2013
28-SEP-13
02-OCT-13
04-OCT-13
24-Sep-2013
24-SEP-13
26-SEP-13
27-SEP-13
17-Sep-2013
17-SEP-13
20-SEP-13
23-SEP-13
12-Nov-2013
19-Nov-2013
19-NOV-13
21-NOV-13
22-NOV-13
23-Nov-2013
05-Oct-2013
02-OCT-13
04-OCT-13
05-OCT-13
28-Sep-2013
26-SEP-13
27-SEP-13
28-SEP-13
24-Sep-2013
20-SEP-13
23-SEP-13
24-SEP-13
30-Nov-2013
23-Nov-2013
21-NOV-13
22-NOV-13
23-NOV-13
30-Nov-2013
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concrete
11 Shuttering
11 Reinforcement
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 SF to TF
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A53430
A61610
A61620
1
A61550
A61560
A61570
3
2
A61230
A61240
A61250
3
A61260
A61270
A61280
1
A61200
01-Jul-2013
25-Jun-2013
28-Jun-2013
13-Jun-2013
13-Jun-2013
17-Jun-2013
19-Jun-2013
30-Mar-2013
06-Apr-2013
06-Apr-2013
09-Apr-2013
10-Apr-2013
11-Apr-2013
11-Apr-2013
15-Apr-2013
17-Apr-2013
30-Mar-2013
30-Mar-2013
01-Jul-2013
27-Jun-2013
29-Jun-2013
19-Jun-2013
15-Jun-2013
18-Jun-2013
19-Jun-2013
17-Apr-2013
10-Apr-2013
08-Apr-2013
09-Apr-2013
10-Apr-2013
17-Apr-2013
13-Apr-2013
16-Apr-2013
17-Apr-2013
05-Apr-2013
02-Apr-2013
29-NOV-13
23-NOV-13
27-NOV-13
12-Nov-2013
12-NOV-13
15-NOV-13
18-NOV-13
29-Aug-2013
05-Sep-2013
05-SEP-13
07-SEP-13
09-SEP-13
10-Sep-2013
10-SEP-13
13-SEP-13
16-SEP-13
29-Aug-2013
29-AUG-13
30-NOV-13
27-NOV-13
29-NOV-13
19-Nov-2013
15-NOV-13
18-NOV-13
19-NOV-13
17-Sep-2013
10-Sep-2013
07-SEP-13
09-SEP-13
10-SEP-13
17-Sep-2013
13-SEP-13
16-SEP-13
17-SEP-13
05-Sep-2013
02-SEP-13
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Concrete
9 Fourth Floor ro Fifth Floor
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 Fifth Floor to Sixth Floor
10 Third Flight
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A61210
A61220
5
3
A61440
A61450
A61460
1
A61380
A61390
A61400
2
A61410
A61420
A61430
6
3
A61520
03-Apr-2013
05-Apr-2013
07-May-2013
18-May-2013
18-May-2013
22-May-2013
24-May-2013
07-May-2013
07-May-2013
10-May-2013
13-May-2013
14-May-2013
14-May-2013
16-May-2013
17-May-2013
25-May-2013
06-Jun-2013
06-Jun-2013
04-Apr-2013
05-Apr-2013
24-May-2013
24-May-2013
21-May-2013
23-May-2013
24-May-2013
13-May-2013
09-May-2013
11-May-2013
13-May-2013
17-May-2013
15-May-2013
16-May-2013
17-May-2013
12-Jun-2013
12-Jun-2013
08-Jun-2013
02-SEP-13
04-SEP-13
05-Oct-2013
17-Oct-2013
17-OCT-13
21-OCT-13
23-OCT-13
05-Oct-2013
05-OCT-13
09-OCT-13
11-OCT-13
12-Oct-2013
12-OCT-13
15-OCT-13
16-OCT-13
24-Oct-2013
05-Nov-2013
05-NOV-13
04-SEP-13
05-SEP-13
24-Oct-2013
24-Oct-2013
21-OCT-13
23-OCT-13
24-OCT-13
12-Oct-2013
09-OCT-13
11-OCT-13
12-OCT-13
17-Oct-2013
15-OCT-13
16-OCT-13
17-OCT-13
12-Nov-2013
12-Nov-2013
08-NOV-13
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
8 ST 1
9 FF to SF
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A61530
A61540
2
A61490
A61500
A61510
1
A34740
A61470
A61480
1
2
2
A59810
A59820
A59830
3
A59840
10-Jun-2013
12-Jun-2013
01-Jun-2013
01-Jun-2013
04-Jun-2013
05-Jun-2013
25-May-2013
25-May-2013
29-May-2013
31-May-2013
17-Jan-2013
16-Feb-2013
23-Feb-2013
23-Feb-2013
26-Feb-2013
27-Feb-2013
28-Feb-2013
28-Feb-2013
11-Jun-2013
12-Jun-2013
05-Jun-2013
03-Jun-2013
04-Jun-2013
05-Jun-2013
31-May-2013
28-May-2013
30-May-2013
31-May-2013
07-Jun-2013
06-Mar-2013
27-Feb-2013
25-Feb-2013
26-Feb-2013
27-Feb-2013
06-Mar-2013
02-Mar-2013
08-NOV-13
11-NOV-13
31-Oct-2013
31-OCT-13
02-NOV-13
04-NOV-13
24-Oct-2013
24-OCT-13
28-OCT-13
30-OCT-13
18-Jun-2013
18-Jul-2013
25-Jul-2013
25-JUL-13
27-JUL-13
29-JUL-13
30-Jul-2013
30-JUL-13
11-NOV-13
12-NOV-13
05-Nov-2013
02-NOV-13
04-NOV-13
05-NOV-13
31-Oct-2013
28-OCT-13
30-OCT-13
31-OCT-13
07-Nov-2013
06-Aug-2013
30-Jul-2013
27-JUL-13
29-JUL-13
30-JUL-13
06-Aug-2013
02-AUG-13
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 GF to FF
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Fourth Flight
11 Shuttering
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A59850
A59860
1
A59780
A59790
A59800
1
1
A59630
A59640
A59650
3
A59690
A59700
A59710
4
A59720
A59730
04-Mar-2013
06-Mar-2013
16-Feb-2013
16-Feb-2013
20-Feb-2013
22-Feb-2013
17-Jan-2013
17-Jan-2013
17-Jan-2013
19-Jan-2013
21-Jan-2013
29-Jan-2013
29-Jan-2013
01-Feb-2013
04-Feb-2013
05-Feb-2013
05-Feb-2013
07-Feb-2013
05-Mar-2013
06-Mar-2013
22-Feb-2013
19-Feb-2013
21-Feb-2013
22-Feb-2013
15-Feb-2013
21-Jan-2013
18-Jan-2013
19-Jan-2013
21-Jan-2013
04-Feb-2013
31-Jan-2013
02-Feb-2013
04-Feb-2013
08-Feb-2013
06-Feb-2013
07-Feb-2013
02-AUG-13
05-AUG-13
18-Jul-2013
18-JUL-13
22-JUL-13
24-JUL-13
18-Jun-2013
18-Jun-2013
18-JUN-13
20-JUN-13
21-JUN-13
29-Jun-2013
29-JUN-13
03-JUL-13
05-JUL-13
06-Jul-2013
06-JUL-13
09-JUL-13
05-AUG-13
06-AUG-13
25-Jul-2013
22-JUL-13
24-JUL-13
25-JUL-13
18-Jul-2013
22-Jun-2013
20-JUN-13
21-JUN-13
22-JUN-13
06-Jul-2013
03-JUL-13
05-JUL-13
06-JUL-13
11-Jul-2013
09-JUL-13
10-JUL-13
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concrete
10 Fifth Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 SF to TF
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A59740
5
A59750
A59760
A59770
2
A59660
A59670
A59680
3
1
A59870
A59880
A59890
2
A59900
A59910
A59920
08-Feb-2013
09-Feb-2013
09-Feb-2013
13-Feb-2013
15-Feb-2013
22-Jan-2013
22-Jan-2013
25-Jan-2013
28-Jan-2013
07-Mar-2013
07-Mar-2013
07-Mar-2013
11-Mar-2013
13-Mar-2013
14-Mar-2013
14-Mar-2013
16-Mar-2013
18-Mar-2013
08-Feb-2013
15-Feb-2013
12-Feb-2013
14-Feb-2013
15-Feb-2013
28-Jan-2013
24-Jan-2013
26-Jan-2013
28-Jan-2013
25-Mar-2013
13-Mar-2013
09-Mar-2013
12-Mar-2013
13-Mar-2013
18-Mar-2013
15-Mar-2013
16-Mar-2013
18-Mar-2013
10-JUL-13
11-Jul-2013
11-JUL-13
15-JUL-13
17-JUL-13
22-Jun-2013
22-JUN-13
26-JUN-13
28-JUN-13
06-Aug-2013
06-Aug-2013
06-AUG-13
09-AUG-13
12-AUG-13
13-Aug-2013
13-AUG-13
15-AUG-13
16-AUG-13
11-JUL-13
18-Jul-2013
15-JUL-13
17-JUL-13
18-JUL-13
29-Jun-2013
26-JUN-13
28-JUN-13
29-JUN-13
24-Aug-2013
13-Aug-2013
09-AUG-13
12-AUG-13
13-AUG-13
17-Aug-2013
15-AUG-13
16-AUG-13
17-AUG-13
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 Fourth Floor ro Fifth Floor
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 TF to Fourth Floor
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A59930
A59940
A59950
5
1
A60050
A60060
A60070
2
A60080
A60090
A60100
3
A60110
A60120
A60130
4
19-Mar-2013
19-Mar-2013
22-Mar-2013
25-Mar-2013
13-Apr-2013
13-Apr-2013
13-Apr-2013
17-Apr-2013
19-Apr-2013
20-Apr-2013
20-Apr-2013
23-Apr-2013
24-Apr-2013
25-Apr-2013
25-Apr-2013
29-Apr-2013
01-May-2013
26-Mar-2013
25-Mar-2013
21-Mar-2013
23-Mar-2013
25-Mar-2013
01-May-2013
19-Apr-2013
16-Apr-2013
18-Apr-2013
19-Apr-2013
24-Apr-2013
22-Apr-2013
23-Apr-2013
24-Apr-2013
01-May-2013
27-Apr-2013
30-Apr-2013
01-May-2013
12-Apr-2013
17-Aug-2013
17-AUG-13
21-AUG-13
23-AUG-13
12-Sep-2013
12-Sep-2013
12-SEP-13
16-SEP-13
18-SEP-13
19-Sep-2013
19-SEP-13
21-SEP-13
23-SEP-13
24-Sep-2013
24-SEP-13
27-SEP-13
30-SEP-13
24-Aug-2013
24-Aug-2013
21-AUG-13
23-AUG-13
24-AUG-13
01-Oct-2013
19-Sep-2013
16-SEP-13
18-SEP-13
19-SEP-13
24-Sep-2013
21-SEP-13
23-SEP-13
24-SEP-13
01-Oct-2013
27-SEP-13
30-SEP-13
01-OCT-13
12-Sep-2013
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 First Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 Sixth Floor to Terrace
10 Third Flight
11 Concrete
11 Shuttering
11 Reinforcement
10 First Flight
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
1
A59960
A59970
A59980
2
A59990
A60000
A60010
3
A60020
A60030
A60040
7
3
A53410
A60290
A60300
1
26-Mar-2013
26-Mar-2013
29-Mar-2013
01-Apr-2013
02-Apr-2013
02-Apr-2013
04-Apr-2013
05-Apr-2013
06-Apr-2013
06-Apr-2013
10-Apr-2013
12-Apr-2013
21-May-2013
01-Jun-2013
07-Jun-2013
01-Jun-2013
05-Jun-2013
21-May-2013
01-Apr-2013
28-Mar-2013
30-Mar-2013
01-Apr-2013
05-Apr-2013
03-Apr-2013
04-Apr-2013
05-Apr-2013
12-Apr-2013
09-Apr-2013
11-Apr-2013
12-Apr-2013
07-Jun-2013
07-Jun-2013
07-Jun-2013
04-Jun-2013
06-Jun-2013
27-May-2013
24-Aug-2013
24-AUG-13
28-AUG-13
30-AUG-13
31-Aug-2013
31-AUG-13
03-SEP-13
04-SEP-13
05-Sep-2013
05-SEP-13
09-SEP-13
11-SEP-13
19-Oct-2013
31-Oct-2013
06-NOV-13
31-OCT-13
04-NOV-13
19-Oct-2013
31-Aug-2013
28-AUG-13
30-AUG-13
31-AUG-13
05-Sep-2013
03-SEP-13
04-SEP-13
05-SEP-13
12-Sep-2013
09-SEP-13
11-SEP-13
12-SEP-13
07-Nov-2013
07-Nov-2013
07-NOV-13
04-NOV-13
06-NOV-13
26-Oct-2013
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Reinforcement
11 Concrete
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
9 Fifth Floor to Sixth Floor
10 Second Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 Third Flight
11 Shuttering
11 Reinforcement
11 Concrete
10 First Flight
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A60230
A60240
A60250
2
A60260
A60270
A60280
6
2
A60170
A60180
A60190
3
A60200
A60210
A60220
1
A60140
21-May-2013
24-May-2013
27-May-2013
28-May-2013
28-May-2013
30-May-2013
31-May-2013
02-May-2013
09-May-2013
09-May-2013
11-May-2013
13-May-2013
14-May-2013
14-May-2013
17-May-2013
20-May-2013
02-May-2013
02-May-2013
23-May-2013
25-May-2013
27-May-2013
31-May-2013
29-May-2013
30-May-2013
31-May-2013
20-May-2013
13-May-2013
10-May-2013
11-May-2013
13-May-2013
20-May-2013
16-May-2013
18-May-2013
20-May-2013
08-May-2013
04-May-2013
19-OCT-13
23-OCT-13
25-OCT-13
26-Oct-2013
26-OCT-13
29-OCT-13
30-OCT-13
01-Oct-2013
08-Oct-2013
08-OCT-13
10-OCT-13
11-OCT-13
12-Oct-2013
12-OCT-13
16-OCT-13
18-OCT-13
01-Oct-2013
01-OCT-13
23-OCT-13
25-OCT-13
26-OCT-13
31-Oct-2013
29-OCT-13
30-OCT-13
31-OCT-13
19-Oct-2013
12-Oct-2013
10-OCT-13
11-OCT-13
12-OCT-13
19-Oct-2013
16-OCT-13
18-OCT-13
19-OCT-13
08-Oct-2013
04-OCT-13
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-131d
-130d
-130d
-130d
-131d
-130d
-130d
-130d
-131d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Concrete
8 ST 7
9 SF to TF
10 Shuttering
10 Reinforcement
10 Concrete
9 FF to SF
10 Shuttering
10 Reinforcement
10 Concrete
9 Fifth Floor to Sixth Floor
10 Concrete
10 Shuttering
10 Reinforcement
9 TF to Fourth Floor
10 Shuttering
10 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A60150
A60160
7
1
A37020
A37030
A37040
2
A36990
A37000
A37010
5
A16330
A37110
A37120
3
A37050
A37060
06-May-2013
08-May-2013
28-Mar-2013
20-Apr-2013
20-Apr-2013
02-May-2013
13-May-2013
28-Mar-2013
28-Mar-2013
09-Apr-2013
19-Apr-2013
29-Jun-2013
20-Jul-2013
29-Jun-2013
11-Jul-2013
14-May-2013
14-May-2013
25-May-2013
07-May-2013
08-May-2013
20-Jul-2013
13-May-2013
01-May-2013
10-May-2013
13-May-2013
19-Apr-2013
08-Apr-2013
17-Apr-2013
19-Apr-2013
20-Jul-2013
20-Jul-2013
10-Jul-2013
19-Jul-2013
05-Jun-2013
24-May-2013
03-Jun-2013
04-OCT-13
07-OCT-13
24-Jun-2013
17-Jul-2013
17-JUL-13
29-JUL-13
08-AUG-13
24-Jun-2013
24-JUN-13
05-JUL-13
16-JUL-13
25-Sep-2013
16-OCT-13
25-SEP-13
07-OCT-13
09-Aug-2013
09-AUG-13
21-AUG-13
07-OCT-13
08-OCT-13
17-Oct-2013
09-Aug-2013
29-JUL-13
07-AUG-13
09-AUG-13
17-Jul-2013
05-JUL-13
15-JUL-13
17-JUL-13
17-Oct-2013
17-OCT-13
07-OCT-13
16-OCT-13
02-Sep-2013
21-AUG-13
30-AUG-13
-130d
-130d
-76d
-76d
-75d
-75d
-75d
-76d
-75d
-75d
-75d
-76d
-75d
-75d
-75d
-76d
-75d
-75d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Concrete
9 Fourth Floor to Fifth Floor
10 Shuttering
10 Reinforcement
10 Concrete
7 Above terrace NSC Works
8 Solar Panel works
8 Chillers, Ahu units etc
8 BMU Works
7 Street Canopy
8 Structural Steel
8 PVC Polyester Mesh Membrane works
8 S2 Block Clearance
8 Foundation and column
7 Sub Structure
8 Zone -2 (16-21 /A-E)
9 Column
10 Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A37070
4
A37080
A37090
A37100
8
A52690
A52700
A52710
2
A13951
A13952
A13939
A13949
Sub
4
4
A23210
05-Jun-2013
06-Jun-2013
06-Jun-2013
18-Jun-2013
28-Jun-2013
28-Jun-2013
12-Aug-2013
28-Jun-2013
28-Jun-2013
13-Aug-2012
26-Apr-2013
11-Jul-2013
26-Apr-2013
13-Aug-2012
13-Aug-2012
30-Aug-2012
21-Sep-2012
24-Sep-2012
05-Jun-2013
28-Jun-2013
17-Jun-2013
26-Jun-2013
28-Jun-2013
19-Oct-2013
19-Oct-2013
10-Oct-2013
05-Sep-2013
26-Aug-2013
10-Jul-2013
26-Aug-2013
26-Apr-2013
03-Oct-2012
09-Nov-2012
07-Nov-2012
04-Oct-2012
04-Oct-2012
31-AUG-13
02-Sep-2013
02-SEP-13
13-SEP-13
24-SEP-13
25-Jul-2013
22-DEC-14
25-JUL-13
25-JUL-13
29-Apr-2013A
23-JUL-13
13-JAN-14
31-MAY-13
29-APR-13A
18-Aug-2012A
18-Aug-2012A
20-Sep-2012A
09-OCT-12A
02-SEP-13
25-Sep-2013
13-SEP-13
23-SEP-13
25-SEP-13
28-Feb-2015
28-FEB-15
29-NOV-13
25-OCT-13
27-Feb-2014
11-JAN-14
27-FEB-14
31-MAY-13
22-JUL-13
31-May-2013
31-May-2013
31-May-2013
26-OCT-12A
-75d
-76d
-75d
-75d
-75d
-426d
-425d
-42d
-42d
-159d
-159d
-159d
-30d
-250d
-174d
-176d
-205d
-18d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Reinforcement
10 Shuttering
9 Plinth Beam
10 Concrete
10 PCC
10 Reinforcement
10 Shuttering
9 Footing
10 PCC
10 Footing Shuttering
10 Footing Concrete
10 Reinforcement
9 Pedestal
10 Concrete
10 Reinforcement
10 Shuttering
9 Back filling
10 Backfilling up top of footing
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A23270
A23280
7
A23200
A23340
A23350
A23360
2
A23240
A23250
A23260
A23255
3
A23190
A23370
A23380
6
A23320
21-Sep-2012
22-Sep-2012
24-Oct-2012
27-Oct-2012
24-Oct-2012
25-Oct-2012
26-Oct-2012
11-Sep-2012
11-Sep-2012
12-Sep-2012
14-Sep-2012
13-Sep-2012
20-Sep-2012
22-Sep-2012
20-Sep-2012
21-Sep-2012
10-Oct-2012
10-Oct-2012
02-Oct-2012
03-Oct-2012
07-Nov-2012
07-Nov-2012
03-Nov-2012
05-Nov-2012
06-Nov-2012
27-Sep-2012
24-Sep-2012
25-Sep-2012
27-Sep-2012
26-Sep-2012
01-Oct-2012
01-Oct-2012
28-Sep-2012
29-Sep-2012
01-Nov-2012
20-Oct-2012
20-SEP-12A
05-OCT-12A
15-Nov-2012A
19-NOV-12A
15-NOV-12A
16-NOV-12A
18-NOV-12A
19-Aug-2012A
19-AUG-12A
21-AUG-12A
21-AUG-12A
20-AUG-12A
31-Aug-2012A
09-SEP-12A
31-AUG-12A
05-SEP-12A
22-Oct-2012A
22-OCT-12A
19-OCT-12A
24-OCT-12A
31-May-2013
25-NOV-12A
21-NOV-12A
22-NOV-12A
24-NOV-12A
31-May-2013
10-OCT-12A
10-OCT-12A
13-OCT-12A
08-OCT-12A
31-May-2013
15-OCT-12A
14-OCT-12A
15-OCT-12A
31-May-2013
25-OCT-12A
-14d
-17d
-176d
-15d
-14d
-14d
-15d
-211d
-13d
-12d
-13d
-9d
-208d
-11d
-13d
-12d
-181d
-3d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A23330
1
A23230
5
A23290
A23300
A23310
10
4
A24410
A24470
A24480
2
A24440
A24450
A24460
A24455
7
22-Oct-2012
30-Aug-2012
30-Aug-2012
28-Sep-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
30-Aug-2012
28-Sep-2012
01-Oct-2012
28-Sep-2012
29-Sep-2012
20-Sep-2012
20-Sep-2012
21-Sep-2012
24-Sep-2012
22-Sep-2012
26-Oct-2012
01-Nov-2012
10-Sep-2012
10-Sep-2012
09-Oct-2012
06-Oct-2012
08-Oct-2012
09-Oct-2012
09-Nov-2012
11-Oct-2012
11-Oct-2012
09-Oct-2012
10-Oct-2012
04-Oct-2012
01-Oct-2012
02-Oct-2012
04-Oct-2012
03-Oct-2012
09-Nov-2012
25-OCT-12A
18-Aug-2012A
18-AUG-12A
20-Sep-2012A
20-SEP-12A
05-OCT-12A
09-OCT-12A
30-Aug-2012A
04-Oct-2012A
09-OCT-12A
04-OCT-12A
07-OCT-12A
09-Sep-2012A
09-SEP-12A
15-SEP-12A
20-SEP-12A
11-SEP-12A
13-Nov-2012A
15-NOV-12A
31-May-2013
15-SEP-12A
31-May-2013
19-OCT-12A
24-OCT-12A
26-OCT-12A
31-May-2013
31-May-2013
13-NOV-12A
12-NOV-12A
12-NOV-12A
31-May-2013
27-OCT-12A
07-NOV-12A
10-NOV-12A
01-NOV-12A
31-May-2013
-11d
-226d
-4d
-201d
-10d
-13d
-14d
-174d
-199d
-27d
-28d
-27d
-205d
-22d
-30d
-31d
-24d
-174d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Concrete
10 PCC
10 Shuttering
10 Reinforcement
9 Pedestal
10 Concrete
10 Reinforcement
10 Shuttering
9 Wall
10 Reinforcement
10 Shuttering
10 Concrete
9 Back filling
10 Backfilling up top of footing
10 Back filling in Plinth
9 Excavation
10 Mass Excavation
10 Local Excavation
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A24400
A24540
A24560
A24550
3
A24390
A24570
A24580
5
A24490
A24500
A24510
6
A24520
A24530
1
A24420
A24430
30-Oct-2012
26-Oct-2012
29-Oct-2012
27-Oct-2012
27-Sep-2012
29-Sep-2012
27-Sep-2012
28-Sep-2012
05-Oct-2012
05-Oct-2012
06-Oct-2012
08-Oct-2012
17-Oct-2012
17-Oct-2012
24-Oct-2012
30-Aug-2012
30-Aug-2012
11-Sep-2012
09-Nov-2012
06-Nov-2012
08-Nov-2012
07-Nov-2012
08-Oct-2012
08-Oct-2012
05-Oct-2012
06-Oct-2012
16-Oct-2012
13-Oct-2012
15-Oct-2012
16-Oct-2012
05-Nov-2012
23-Oct-2012
05-Nov-2012
19-Sep-2012
10-Sep-2012
19-Sep-2012
25-NOV-12A
13-NOV-12A
21-NOV-12A
17-NOV-12A
24-Sep-2012A
01-OCT-12A
24-SEP-12A
28-SEP-12A
04-Oct-2012A
04-OCT-12A
06-OCT-12A
08-OCT-12A
31-Oct-2012A
31-OCT-12A
05-NOV-12A
30-Aug-2012A
30-AUG-12A
02-SEP-12A
20-DEC-12A
09-DEC-12A
16-DEC-12A
13-DEC-12A
31-May-2013
11-NOV-12A
10-NOV-12A
11-NOV-12A
31-May-2013
12-NOV-12A
12-NOV-12A
13-NOV-12A
31-May-2013
05-NOV-12A
11-NOV-12A
31-May-2013
15-SEP-12A
25-SEP-12A
-34d
-28d
-32d
-30d
-202d
-29d
-30d
-30d
-195d
-24d
-23d
-23d
-178d
-10d
-5d
-218d
-4d
-4d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
8 Zone -1 (1-7/E-J)
9 Back filling
10 Backfilling up top of footing
10 Back filling in Plinth
9 Footing
10 PCC
10 Footing Shuttering
10 Footing Concrete
10 Reinforcement
9 Pedestal
10 Reinforcement
10 Shuttering
10 Concrete
9 Wall
10 Reinforcement
10 Shuttering
10 Concrete
9 Plinth Beam
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
6
A23120
A23130
2
A23040
A23050
A23060
A23055
3
A23170
A23180
A7410
5
A23090
A23100
A23110
7
13-Aug-2012
06-Oct-2012
06-Oct-2012
13-Oct-2012
07-Sep-2012
07-Sep-2012
08-Sep-2012
11-Sep-2012
10-Sep-2012
17-Sep-2012
17-Sep-2012
18-Sep-2012
19-Sep-2012
25-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
20-Oct-2012
03-Nov-2012
29-Oct-2012
12-Oct-2012
29-Oct-2012
24-Sep-2012
20-Sep-2012
21-Sep-2012
24-Sep-2012
22-Sep-2012
27-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
05-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
03-Nov-2012
20-Aug-2012A
22-Oct-2012A
22-OCT-12A
27-OCT-12A
02-Sep-2012A
02-SEP-12A
04-SEP-12A
13-SEP-12A
11-SEP-12A
16-Sep-2012A
16-SEP-12A
18-SEP-12A
20-SEP-12A
24-Sep-2012A
24-SEP-12A
28-SEP-12A
01-OCT-12A
16-Nov-2012A
31-May-2013
31-May-2013
27-OCT-12A
10-NOV-12A
31-May-2013
30-SEP-12A
02-OCT-12A
06-OCT-12A
04-OCT-12A
31-May-2013
12-OCT-12A
14-OCT-12A
16-OCT-12A
31-May-2013
25-OCT-12A
28-OCT-12A
30-OCT-12A
31-May-2013
-179d
-184d
-12d
-10d
-214d
-8d
-8d
-10d
-9d
-211d
-14d
-15d
-15d
-204d
-18d
-20d
-20d
-179d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 PCC
10 Reinforcement
10 Shuttering
10 Concrete
9 Excavation
10 Mass Excavation
10 Local Excavation
9 Column
10 Reinforcement
10 Shuttering
10 Concrete
8 Zone -9 (3-7/D-F) Lift slab
9 Wall
10 Reinforcement
10 Shuttering
10 Concrete
9 Footing
10 Footing Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A23140
A23150
A23160
A7420
1
A23020
A23030
4
A23070
A23080
A7411
11
5
A24690
A24700
A24710
2
A24650
20-Oct-2012
22-Oct-2012
23-Oct-2012
24-Oct-2012
13-Aug-2012
13-Aug-2012
27-Aug-2012
18-Sep-2012
18-Sep-2012
19-Sep-2012
20-Sep-2012
15-Aug-2012
25-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
11-Sep-2012
11-Sep-2012
31-Oct-2012
01-Nov-2012
02-Nov-2012
03-Nov-2012
06-Sep-2012
25-Aug-2012
06-Sep-2012
01-Oct-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Nov-2012
05-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
24-Sep-2012
21-Sep-2012
16-NOV-12A
18-NOV-12A
20-NOV-12A
21-NOV-12A
20-Aug-2012A
20-AUG-12A
25-AUG-12A
24-Sep-2012A
24-SEP-12A
28-SEP-12A
01-OCT-12A
20-Aug-2012A
30-Sep-2012A
30-SEP-12A
05-OCT-12A
10-OCT-12A
09-Sep-2012A
09-SEP-12A
21-NOV-12A
23-NOV-12A
24-NOV-12A
25-NOV-12A
31-May-2013
12-SEP-12A
10-SEP-12A
31-May-2013
25-OCT-12A
28-OCT-12A
30-OCT-12A
31-May-2013
31-May-2013
21-OCT-12A
25-OCT-12A
30-OCT-12A
31-May-2013
25-SEP-12A
-17d
-18d
-18d
-18d
-229d
-14d
-2d
-208d
-22d
-24d
-24d
-180d
-204d
-15d
-17d
-20d
-214d
-2d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Footing Concrete
10 Reinforcement
9 Plinth Beam
10 Concrete
10 PCC
10 Reinforcement
10 Shuttering
9 Column
10 Concrete
10 Reinforcement
10 Shuttering
9 Excavation
10 Mass Excavation
10 Local Excavation
9 Pedestal
10 Concrete
10 Reinforcement
10 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A24660
A24645
7
A24600
A24740
A24750
A24760
4
A24610
A24670
A24680
1
A24620
A24630
3
A24590
A24770
A24780
13-Sep-2012
12-Sep-2012
22-Oct-2012
25-Oct-2012
22-Oct-2012
23-Oct-2012
24-Oct-2012
20-Sep-2012
22-Sep-2012
20-Sep-2012
21-Sep-2012
15-Aug-2012
15-Aug-2012
04-Sep-2012
19-Sep-2012
21-Sep-2012
19-Sep-2012
20-Sep-2012
24-Sep-2012
22-Sep-2012
02-Nov-2012
02-Nov-2012
30-Oct-2012
31-Oct-2012
01-Nov-2012
01-Oct-2012
01-Oct-2012
28-Sep-2012
29-Sep-2012
08-Sep-2012
25-Aug-2012
08-Sep-2012
27-Sep-2012
27-Sep-2012
25-Sep-2012
26-Sep-2012
13-SEP-12A
12-SEP-12A
21-Nov-2012A
01-DEC-12A
21-NOV-12A
25-NOV-12A
29-NOV-12A
30-Sep-2012A
10-OCT-12A
30-SEP-12A
05-OCT-12A
20-Aug-2012A
20-AUG-12A
25-AUG-12A
17-Sep-2012A
28-SEP-12A
17-SEP-12A
25-SEP-12A
03-OCT-12A
01-OCT-12A
31-May-2013
08-DEC-12A
03-DEC-12A
05-DEC-12A
07-DEC-12A
31-May-2013
30-OCT-12A
21-OCT-12A
25-OCT-12A
31-May-2013
12-SEP-12A
11-SEP-12A
31-May-2013
16-OCT-12A
11-OCT-12A
14-OCT-12A
-7d
-6d
-180d
-30d
-28d
-29d
-30d
-208d
-24d
-19d
-21d
-227d
-14d
-1d
-211d
-15d
-13d
-15d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 Back filling
10 Backfilling up top of footing
10 Back filling in Plinth
8 Zone -5 (7-11/E-J)
9 Excavation
10 Mass Excavation
10 Local Excavation
9 Wall
10 Reinforcement
10 Shuttering
10 Concrete
9 Footing
10 PCC
10 Footing Shuttering
10 Footing Concrete
10 Reinforcement
9 Back filling
10 Backfilling up top of footing
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
6
A24720
A24730
7
1
A23820
A23830
5
A23890
A23900
A23910
2
A23840
A23850
A23860
A23855
6
A23920
06-Oct-2012
06-Oct-2012
13-Oct-2012
27-Aug-2012
27-Aug-2012
27-Aug-2012
07-Sep-2012
04-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
19-Sep-2012
19-Sep-2012
20-Sep-2012
22-Sep-2012
21-Sep-2012
16-Oct-2012
16-Oct-2012
24-Oct-2012
12-Oct-2012
24-Oct-2012
09-Nov-2012
18-Sep-2012
06-Sep-2012
18-Sep-2012
15-Oct-2012
12-Oct-2012
13-Oct-2012
15-Oct-2012
03-Oct-2012
29-Sep-2012
01-Oct-2012
03-Oct-2012
02-Oct-2012
05-Nov-2012
22-Oct-2012
02-Nov-2012A
02-NOV-12A
06-NOV-12A
30-Aug-2012A
30-Aug-2012A
30-AUG-12A
04-SEP-12A
30-Sep-2012A
30-SEP-12A
05-OCT-12A
10-OCT-12A
09-Sep-2012A
09-SEP-12A
12-SEP-12A
14-SEP-12A
10-SEP-12A
05-Nov-2012A
05-NOV-12A
31-May-2013
06-NOV-12A
17-NOV-12A
31-May-2013
31-May-2013
16-SEP-12A
20-SEP-12A
31-May-2013
11-NOV-12A
12-NOV-12A
13-NOV-12A
31-May-2013
27-OCT-12A
05-NOV-12A
10-NOV-12A
01-NOV-12A
31-May-2013
10-NOV-12A
-188d
-20d
-20d
-174d
-219d
-8d
-1d
-196d
-25d
-24d
-24d
-206d
-23d
-29d
-32d
-25d
-178d
-16d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A23930
7
A23800
A23940
A23950
A23960
3
A23790
A23970
A23980
4
A23810
A23870
A23880
12
4
A24810
A24870
23-Oct-2012
26-Oct-2012
30-Oct-2012
26-Oct-2012
27-Oct-2012
29-Oct-2012
26-Sep-2012
28-Sep-2012
26-Sep-2012
27-Sep-2012
27-Sep-2012
29-Sep-2012
27-Sep-2012
28-Sep-2012
13-Sep-2012
21-Sep-2012
24-Sep-2012
21-Sep-2012
05-Nov-2012
09-Nov-2012
09-Nov-2012
06-Nov-2012
07-Nov-2012
08-Nov-2012
06-Oct-2012
06-Oct-2012
04-Oct-2012
05-Oct-2012
10-Oct-2012
10-Oct-2012
08-Oct-2012
09-Oct-2012
02-Nov-2012
02-Oct-2012
02-Oct-2012
29-Sep-2012
10-NOV-12A
29-Nov-2012A
06-DEC-12A
29-NOV-12A
01-DEC-12A
04-DEC-12A
17-Sep-2012A
27-SEP-12A
17-SEP-12A
23-SEP-12A
30-Sep-2012A
10-OCT-12A
30-SEP-12A
05-OCT-12A
24-Aug-2012A
11-Oct-2012A
12-OCT-12A
11-OCT-12A
25-NOV-12A
31-May-2013
15-DEC-12A
10-DEC-12A
12-DEC-12A
14-DEC-12A
31-May-2013
11-NOV-12A
10-NOV-12A
10-NOV-12A
31-May-2013
13-NOV-12A
11-NOV-12A
12-NOV-12A
31-May-2013
31-May-2013
26-OCT-12A
25-OCT-12A
-17d
-174d
-30d
-28d
-29d
-30d
-203d
-30d
-31d
-30d
-200d
-28d
-29d
-28d
-180d
-207d
-20d
-21d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Shuttering
9 Back filling
10 Backfilling up top of footing
10 Back filling in Plinth
9 Wall
10 Reinforcement
10 Shuttering
10 Concrete
9 Pedestal
10 Concrete
10 Reinforcement
10 Shuttering
9 Plinth Beam
10 Concrete
10 PCC
10 Reinforcement
10 Shuttering
9 Footing
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A24880
6
A24920
A24930
5
A24890
A24900
A24910
3
A24790
A24970
A24980
7
A24800
A24940
A24950
A24960
2
22-Sep-2012
05-Oct-2012
05-Oct-2012
17-Oct-2012
26-Sep-2012
26-Sep-2012
27-Sep-2012
28-Sep-2012
20-Sep-2012
22-Sep-2012
20-Sep-2012
21-Sep-2012
19-Oct-2012
23-Oct-2012
19-Oct-2012
20-Oct-2012
22-Oct-2012
13-Sep-2012
01-Oct-2012
27-Oct-2012
16-Oct-2012
27-Oct-2012
04-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
28-Sep-2012
28-Sep-2012
26-Sep-2012
27-Sep-2012
02-Nov-2012
02-Nov-2012
30-Oct-2012
31-Oct-2012
01-Nov-2012
25-Sep-2012
12-OCT-12A
30-Oct-2012A
30-OCT-12A
05-NOV-12A
11-Oct-2012A
11-OCT-12A
12-OCT-12A
12-OCT-12A
20-Sep-2012A
10-OCT-12A
20-SEP-12A
28-SEP-12A
16-Nov-2012A
03-DEC-12A
16-NOV-12A
24-NOV-12A
29-NOV-12A
24-Aug-2012A
26-OCT-12A
31-May-2013
05-NOV-12A
15-NOV-12A
31-May-2013
25-OCT-12A
26-OCT-12A
26-OCT-12A
31-May-2013
25-OCT-12A
15-OCT-12A
20-OCT-12A
31-May-2013
18-DEC-12A
06-DEC-12A
12-DEC-12A
16-DEC-12A
31-May-2013
-21d
-185d
-16d
-15d
-205d
-19d
-19d
-18d
-210d
-22d
-15d
-19d
-180d
-38d
-31d
-35d
-38d
-213d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 PCC
10 Footing Shuttering
10 Footing Concrete
10 Reinforcement
8 Zone -4 (16-21/E-J)
9 Pedestal
10 Concrete
10 Reinforcement
10 Shuttering
9 Back filling
10 Backfilling up top of footing
10 Back filling in Plinth
9 Wall
10 Reinforcement
10 Shuttering
10 Concrete
9 Footing
10 PCC
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A24840
A24850
A24860
A24855
6
3
A23590
A23770
A23780
6
A23720
A23730
5
A23690
A23700
A23710
2
A23640
13-Sep-2012
14-Sep-2012
17-Sep-2012
15-Sep-2012
10-Sep-2012
19-Sep-2012
21-Sep-2012
19-Sep-2012
20-Sep-2012
09-Oct-2012
09-Oct-2012
16-Oct-2012
27-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
10-Sep-2012
10-Sep-2012
21-Sep-2012
22-Sep-2012
25-Sep-2012
24-Sep-2012
06-Nov-2012
29-Sep-2012
29-Sep-2012
27-Sep-2012
28-Sep-2012
31-Oct-2012
15-Oct-2012
31-Oct-2012
08-Oct-2012
05-Oct-2012
06-Oct-2012
08-Oct-2012
26-Sep-2012
22-Sep-2012
24-AUG-12A
30-AUG-12A
05-SEP-12A
27-AUG-12A
24-Aug-2012A
06-Sep-2012A
09-SEP-12A
06-SEP-12A
07-SEP-12A
01-Nov-2012A
01-NOV-12A
05-NOV-12A
30-Sep-2012A
30-SEP-12A
04-OCT-12A
09-OCT-12A
24-Aug-2012A
24-AUG-12A
07-OCT-12A
12-OCT-12A
13-OCT-12A
09-OCT-12A
31-May-2013
31-May-2013
15-OCT-12A
14-OCT-12A
15-OCT-12A
31-May-2013
05-NOV-12A
15-NOV-12A
31-May-2013
19-OCT-12A
24-OCT-12A
30-OCT-12A
31-May-2013
10-OCT-12A
-13d
-16d
-15d
-12d
-177d
-209d
-12d
-14d
-13d
-182d
-17d
-12d
-202d
-11d
-14d
-18d
-212d
-14d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Footing Shuttering
10 Footing Concrete
10 Reinforcement
9 Column
10 Concrete
10 Reinforcement
10 Shuttering
9 Plinth Beam
10 Concrete
10 PCC
10 Reinforcement
10 Shuttering
8 Zone -7 (11-16/E-J)
9 Footing
10 PCC
10 Footing Shuttering
10 Footing Concrete
10 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A23650
A23660
A23655
4
A23610
A23670
A23680
7
A23600
A23740
A23750
A23760
9
2
A24240
A24250
A24260
A24255
11-Sep-2012
13-Sep-2012
12-Sep-2012
20-Sep-2012
22-Sep-2012
20-Sep-2012
21-Sep-2012
23-Oct-2012
26-Oct-2012
23-Oct-2012
24-Oct-2012
25-Oct-2012
29-Aug-2012
19-Sep-2012
19-Sep-2012
20-Sep-2012
22-Sep-2012
21-Sep-2012
24-Sep-2012
26-Sep-2012
25-Sep-2012
03-Oct-2012
03-Oct-2012
01-Oct-2012
02-Oct-2012
06-Nov-2012
06-Nov-2012
02-Nov-2012
03-Nov-2012
05-Nov-2012
09-Nov-2012
03-Oct-2012
29-Sep-2012
01-Oct-2012
03-Oct-2012
02-Oct-2012
01-SEP-12A
05-SEP-12A
27-AUG-12A
30-Sep-2012A
09-OCT-12A
30-SEP-12A
04-OCT-12A
23-Nov-2012A
29-NOV-12A
23-NOV-12A
25-NOV-12A
27-NOV-12A
27-Aug-2012A
08-Sep-2012A
08-SEP-12A
11-SEP-12A
14-SEP-12A
09-SEP-12A
12-OCT-12A
13-OCT-12A
11-OCT-12A
31-May-2013
30-OCT-12A
19-OCT-12A
24-OCT-12A
31-May-2013
18-DEC-12A
09-DEC-12A
12-DEC-12A
15-DEC-12A
31-May-2013
31-May-2013
27-OCT-12A
05-NOV-12A
10-NOV-12A
30-OCT-12A
-15d
-14d
-13d
-206d
-22d
-15d
-18d
-177d
-35d
-31d
-32d
-34d
-174d
-206d
-23d
-29d
-32d
-23d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 Excavation
10 Mass Excavation
10 Local Excavation
9 Pedestal
10 Concrete
10 Reinforcement
10 Shuttering
9 Back filling
10 Backfilling up top of footing
10 Back filling in Plinth
9 Column
10 Concrete
10 Reinforcement
10 Shuttering
9 Wall
10 Reinforcement
10 Shuttering
10 Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
1
A24220
A24230
3
A24190
A24370
A24380
6
A24320
A24330
4
A24210
A24270
A24280
5
A24290
A24300
A24310
29-Aug-2012
29-Aug-2012
10-Sep-2012
26-Sep-2012
28-Sep-2012
26-Sep-2012
27-Sep-2012
16-Oct-2012
16-Oct-2012
23-Oct-2012
27-Sep-2012
29-Sep-2012
27-Sep-2012
28-Sep-2012
04-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
18-Sep-2012
08-Sep-2012
18-Sep-2012
06-Oct-2012
06-Oct-2012
04-Oct-2012
05-Oct-2012
05-Nov-2012
22-Oct-2012
05-Nov-2012
10-Oct-2012
10-Oct-2012
08-Oct-2012
09-Oct-2012
15-Oct-2012
12-Oct-2012
13-Oct-2012
15-Oct-2012
27-Aug-2012A
27-AUG-12A
29-AUG-12A
18-Sep-2012A
27-SEP-12A
18-SEP-12A
21-SEP-12A
07-Nov-2012A
07-NOV-12A
12-NOV-12A
01-Oct-2012A
10-OCT-12A
01-OCT-12A
05-OCT-12A
01-Oct-2012A
01-OCT-12A
05-OCT-12A
10-OCT-12A
31-May-2013
15-SEP-12A
20-SEP-12A
31-May-2013
11-NOV-12A
10-NOV-12A
11-NOV-12A
31-May-2013
12-NOV-12A
28-NOV-12A
31-May-2013
13-NOV-12A
12-NOV-12A
12-NOV-12A
31-May-2013
12-NOV-12A
12-NOV-12A
13-NOV-12A
-219d
-5d
-1d
-203d
-30d
-31d
-31d
-178d
-17d
-19d
-200d
-28d
-29d
-28d
-196d
-25d
-24d
-24d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 Plinth Beam
10 Concrete
10 PCC
10 Reinforcement
10 Shuttering
8 Zone -6 (7-11/A-E)
9 Wall
10 Reinforcement
10 Shuttering
10 Concrete
9 Column
10 Concrete
10 Reinforcement
10 Shuttering
9 Excavation
10 Mass Excavation
10 Local Excavation
9 Pedestal
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
7
A24200
A24340
A24350
A24360
8
5
A24090
A24100
A24110
4
A24010
A24070
A24080
1
A24020
A24030
3
26-Oct-2012
30-Oct-2012
26-Oct-2012
27-Oct-2012
29-Oct-2012
27-Aug-2012
04-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
27-Sep-2012
29-Sep-2012
27-Sep-2012
28-Sep-2012
27-Aug-2012
27-Aug-2012
07-Sep-2012
26-Sep-2012
09-Nov-2012
09-Nov-2012
06-Nov-2012
07-Nov-2012
08-Nov-2012
09-Nov-2012
15-Oct-2012
12-Oct-2012
13-Oct-2012
15-Oct-2012
10-Oct-2012
10-Oct-2012
08-Oct-2012
09-Oct-2012
18-Sep-2012
06-Sep-2012
18-Sep-2012
06-Oct-2012
30-Nov-2012A
05-DEC-12A
30-NOV-12A
01-DEC-12A
03-DEC-12A
30-Aug-2012A
11-Oct-2012A
11-OCT-12A
15-OCT-12A
18-OCT-12A
11-Oct-2012A
18-OCT-12A
11-OCT-12A
15-OCT-12A
30-Aug-2012A
30-AUG-12A
10-SEP-12A
28-Sep-2012A
31-May-2013
16-DEC-12A
10-DEC-12A
12-DEC-12A
14-DEC-12A
31-May-2013
31-May-2013
12-NOV-12A
12-NOV-12A
13-NOV-12A
31-May-2013
13-NOV-12A
12-NOV-12A
12-NOV-12A
31-May-2013
16-SEP-12A
25-SEP-12A
31-May-2013
-174d
-31d
-28d
-29d
-30d
-174d
-196d
-25d
-24d
-24d
-200d
-28d
-29d
-28d
-219d
-8d
-5d
-203d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Concrete
10 Reinforcement
10 Shuttering
9 Footing
10 PCC
10 Footing Shuttering
10 Footing Concrete
10 Reinforcement
9 Plinth Beam
10 Concrete
10 PCC
10 Reinforcement
10 Shuttering
9 Back filling
10 Backfilling up top of footing
10 Back filling in Plinth
8 Zone -3 (1-7/A-E)
9 Wall
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A23990
A24170
A24180
2
A24040
A24050
A24060
A24055
7
A24000
A24140
A24150
A24160
6
A24120
A24130
5
5
28-Sep-2012
26-Sep-2012
27-Sep-2012
19-Sep-2012
19-Sep-2012
20-Sep-2012
22-Sep-2012
21-Sep-2012
26-Oct-2012
30-Oct-2012
26-Oct-2012
27-Oct-2012
29-Oct-2012
16-Oct-2012
16-Oct-2012
23-Oct-2012
13-Aug-2012
25-Sep-2012
06-Oct-2012
04-Oct-2012
05-Oct-2012
03-Oct-2012
29-Sep-2012
01-Oct-2012
03-Oct-2012
02-Oct-2012
09-Nov-2012
09-Nov-2012
06-Nov-2012
07-Nov-2012
08-Nov-2012
05-Nov-2012
22-Oct-2012
05-Nov-2012
03-Nov-2012
05-Oct-2012
10-OCT-12A
28-SEP-12A
04-OCT-12A
14-Sep-2012A
14-SEP-12A
17-SEP-12A
20-SEP-12A
15-SEP-12A
25-Nov-2012A
02-DEC-12A
25-NOV-12A
27-NOV-12A
30-NOV-12A
05-Nov-2012A
05-NOV-12A
10-NOV-12A
20-Aug-2012A
01-Oct-2012A
11-NOV-12A
10-NOV-12A
11-NOV-12A
31-May-2013
26-OCT-12A
07-NOV-12A
10-NOV-12A
29-OCT-12A
31-May-2013
10-DEC-12A
04-DEC-12A
06-DEC-12A
08-DEC-12A
31-May-2013
10-NOV-12A
23-NOV-12A
31-May-2013
31-May-2013
-30d
-31d
-31d
-206d
-22d
-31d
-32d
-22d
-174d
-25d
-23d
-24d
-25d
-178d
-16d
-15d
-179d
-204d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Reinforcement
10 Shuttering
10 Concrete
9 Plinth Beam
10 Concrete
10 PCC
10 Reinforcement
10 Shuttering
9 Back filling
10 Backfilling up top of footing
10 Back filling in Plinth
9 Pedestal
10 Concrete
10 Reinforcement
10 Shuttering
9 Column
10 Concrete
10 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A23490
A23500
A23510
7
A23400
A23540
A23550
A23560
6
A23520
A23530
3
A23390
A23570
A23580
4
A23410
A23470
25-Sep-2012
26-Sep-2012
27-Sep-2012
20-Oct-2012
24-Oct-2012
20-Oct-2012
22-Oct-2012
23-Oct-2012
06-Oct-2012
06-Oct-2012
13-Oct-2012
17-Sep-2012
19-Sep-2012
17-Sep-2012
18-Sep-2012
18-Sep-2012
20-Sep-2012
18-Sep-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
03-Nov-2012
03-Nov-2012
31-Oct-2012
01-Nov-2012
02-Nov-2012
29-Oct-2012
12-Oct-2012
29-Oct-2012
27-Sep-2012
27-Sep-2012
25-Sep-2012
26-Sep-2012
01-Oct-2012
01-Oct-2012
28-Sep-2012
01-OCT-12A
06-OCT-12A
10-OCT-12A
21-Nov-2012A
29-NOV-12A
21-NOV-12A
23-NOV-12A
26-NOV-12A
22-Oct-2012A
22-OCT-12A
27-OCT-12A
15-Sep-2012A
28-SEP-12A
15-SEP-12A
20-SEP-12A
01-Oct-2012A
10-OCT-12A
01-OCT-12A
20-OCT-12A
25-OCT-12A
30-OCT-12A
31-May-2013
08-DEC-12A
02-DEC-12A
04-DEC-12A
06-DEC-12A
31-May-2013
27-OCT-12A
17-NOV-12A
31-May-2013
16-OCT-12A
15-OCT-12A
16-OCT-12A
31-May-2013
30-OCT-12A
20-OCT-12A
-14d
-17d
-20d
-179d
-29d
-27d
-27d
-28d
-184d
-12d
-16d
-211d
-15d
-16d
-16d
-208d
-24d
-18d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Shuttering
9 Excavation
10 Mass Excavation
10 Local Excavation
9 Footing
10 PCC
10 Footing Shuttering
10 Footing Concrete
10 Reinforcement
7 Interior & MEP FInal Fix (NSC)
8 Third Floor
9 Plumbing final fix
9 Interior Works
9 False ceiling
9 Workstations & Modular Furniture
9 HVAC Grills/Defuser fixing
9 Electrical light fittings
9 FPS sprinklers
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A23480
1
A23420
A23430
2
A23440
A23450
A23460
A23455
16
Int6
S1-Str2153
S1-Str2134
S1-Str2133
S1-Str2143
s15090
s15100
s15110
19-Sep-2012
13-Aug-2012
13-Aug-2012
27-Aug-2012
07-Sep-2012
07-Sep-2012
08-Sep-2012
11-Sep-2012
10-Sep-2012
30-Mar-2013
14-May-2013
14-May-2013
24-Aug-2013
30-Jul-2013
30-Oct-2013
17-Sep-2013
17-Sep-2013
17-Sep-2013
29-Sep-2012
06-Sep-2012
25-Aug-2012
06-Sep-2012
24-Sep-2012
20-Sep-2012
21-Sep-2012
24-Sep-2012
22-Sep-2012
08-Feb-2014
12-Dec-2013
17-Jun-2013
01-Nov-2013
02-Sep-2013
27-Nov-2013
01-Nov-2013
01-Nov-2013
01-Nov-2013
06-OCT-12A
20-Aug-2012A
20-AUG-12A
06-SEP-12A
07-Sep-2012A
07-SEP-12A
12-SEP-12A
13-SEP-12A
09-SEP-12A
22-Jun-2013
09-Aug-2013
09-AUG-13
13-DEC-13
07-DEC-13
10-JAN-14
10-JAN-14
10-JAN-14
10-JAN-14
25-OCT-12A
31-May-2013
12-SEP-12A
20-SEP-12A
31-May-2013
12-OCT-12A
13-OCT-12A
14-OCT-12A
13-OCT-12A
10-May-2014
11-Mar-2014
12-SEP-13
19-FEB-14
09-JAN-14
07-FEB-14
25-FEB-14
25-FEB-14
25-FEB-14
-21d
-229d
-14d
-11d
-214d
-18d
-18d
-17d
-17d
-78d
-76d
-75d
-94d
-111d
-62d
-99d
-99d
-99d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
s15120
s15130
s15140
s15150
s15160
Int1
S1-Str2003
S1-Str1984
S1-Str1983
S1-Str1993
s14690
s14700
s14710
s14720
s14730
s14740
s14750
s14760
17-Sep-2013
17-Sep-2013
28-Nov-2013
07-Nov-2013
29-Nov-2013
10-Apr-2013
10-Apr-2013
15-Jul-2013
14-Jun-2013
20-Sep-2013
07-Aug-2013
07-Aug-2013
07-Aug-2013
07-Aug-2013
07-Aug-2013
19-Oct-2013
28-Sep-2013
21-Oct-2013
01-Nov-2013
01-Nov-2013
05-Dec-2013
11-Dec-2013
12-Dec-2013
02-Nov-2013
14-May-2013
21-Sep-2013
24-Jul-2013
18-Oct-2013
21-Sep-2013
21-Sep-2013
21-Sep-2013
21-Sep-2013
21-Sep-2013
26-Oct-2013
01-Nov-2013
02-Nov-2013
10-JAN-14
10-JAN-14
08-FEB-14
16-JAN-14
26-FEB-14
09-Aug-2013
09-AUG-13
28-OCT-13
22-OCT-13
02-DEC-13
02-DEC-13
02-DEC-13
02-DEC-13
02-DEC-13
02-DEC-13
31-DEC-13
02-DEC-13
16-JAN-14
25-FEB-14
25-FEB-14
15-FEB-14
19-FEB-14
11-MAR-14
29-Jan-2014
12-SEP-13
03-JAN-14
30-NOV-13
30-DEC-13
15-JAN-14
15-JAN-14
15-JAN-14
15-JAN-14
15-JAN-14
06-JAN-14
03-JAN-14
29-JAN-14
-99d
-99d
-62d
-60d
-76d
-75d
-104d
-89d
-111d
-62d
-99d
-99d
-99d
-99d
-99d
-61d
-54d
-75d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
8 Second Floor
9 Plumbing Final Fix
9 Interior Works
9 False ceiling
9 Workstations & Modular Furniture
9 HVAC Grills/Defuser fixing
9 Electrical light fittings
9 FPS sprinklers
9 Access Controle system
9 Networking
9 chairs ,Blinds & carpet etc
9 Fire door erection
9 Final Testing , Comissioning & cleanig
8 Fourth Floor
9 Plumbing Final Fix
9 Interior Works
9 False ceiling
9 Workstations & Modular Furniture
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
Int2
S1-Str2033
S1-Str2014
S1-Str2013
S1-Str2023
s14770
s14780
s14790
s14800
s14810
s14820
s14830
s14840
Int3
S1-Str2063
S1-Str2044
S1-Str2043
S1-Str2053
20-Apr-2013
20-Apr-2013
03-Aug-2013
04-Jul-2013
10-Oct-2013
27-Aug-2013
27-Aug-2013
27-Aug-2013
27-Aug-2013
27-Aug-2013
08-Nov-2013
18-Oct-2013
09-Nov-2013
08-Jun-2013
08-Jun-2013
13-Sep-2013
20-Aug-2013
19-Nov-2013
22-Nov-2013
24-May-2013
11-Oct-2013
13-Aug-2013
07-Nov-2013
11-Oct-2013
11-Oct-2013
11-Oct-2013
11-Oct-2013
11-Oct-2013
15-Nov-2013
21-Nov-2013
22-Nov-2013
01-Jan-2014
12-Jul-2013
21-Nov-2013
23-Sep-2013
17-Dec-2013
09-Aug-2013
09-AUG-13
22-NOV-13
11-NOV-13
21-DEC-13
21-DEC-13
21-DEC-13
21-DEC-13
21-DEC-13
21-DEC-13
18-JAN-14
27-DEC-13
05-FEB-14
09-Aug-2013
09-AUG-13
03-JAN-14
28-DEC-13
31-JAN-14
18-Feb-2014
12-SEP-13
29-JAN-14
20-DEC-13
17-JAN-14
04-FEB-14
04-FEB-14
04-FEB-14
04-FEB-14
04-FEB-14
25-JAN-14
29-JAN-14
18-FEB-14
01-Apr-2014
12-SEP-13
13-MAR-14
30-JAN-14
28-FEB-14
-75d
-95d
-94d
-111d
-61d
-99d
-99d
-99d
-99d
-99d
-61d
-59d
-75d
-77d
-53d
-96d
-111d
-63d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
s14850
s14860
s14870
s14880
s14890
s14900
s14910
s14920
Int
S1-Str1106
S1-Str1105
S1-Str1136
S1-Str1126
s14610
s14620
s14630
s14640
s14650
07-Oct-2013
07-Oct-2013
07-Oct-2013
07-Oct-2013
07-Oct-2013
18-Dec-2013
27-Nov-2013
19-Dec-2013
30-Mar-2013
25-Jun-2013
25-May-2013
30-Mar-2013
31-Aug-2013
18-Jul-2013
18-Jul-2013
18-Jul-2013
18-Jul-2013
18-Jul-2013
21-Nov-2013
21-Nov-2013
21-Nov-2013
21-Nov-2013
21-Nov-2013
25-Dec-2013
31-Dec-2013
01-Jan-2014
14-Oct-2013
02-Sep-2013
04-Jul-2013
03-May-2013
28-Sep-2013
02-Sep-2013
02-Sep-2013
02-Sep-2013
02-Sep-2013
02-Sep-2013
31-JAN-14
31-JAN-14
31-JAN-14
31-JAN-14
31-JAN-14
01-MAR-14
07-FEB-14
19-MAR-14
22-Jun-2013
18-OCT-13
12-OCT-13
22-JUN-13
22-NOV-13
22-NOV-13
22-NOV-13
22-NOV-13
22-NOV-13
22-NOV-13
18-MAR-14
18-MAR-14
18-MAR-14
18-MAR-14
18-MAR-14
08-MAR-14
13-MAR-14
01-APR-14
20-Jan-2014
26-DEC-13
21-NOV-13
27-JUL-13
20-DEC-13
06-JAN-14
06-JAN-14
06-JAN-14
06-JAN-14
06-JAN-14
-100d
-100d
-100d
-100d
-100d
-63d
-62d
-77d
-84d
-99d
-120d
-72d
-71d
-108d
-108d
-108d
-108d
-108d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
s14660
s14670
s14680
Int5
S1-Str2123
S1-Str2104
S1-Str2103
S1-Str2113
s15010
s15020
s15030
s15040
s15050
s15060
s15070
s15080
Int4
S1-Str2093
30-Sep-2013
09-Sep-2013
01-Oct-2013
30-Jul-2013
30-Jul-2013
23-Oct-2013
28-Sep-2013
28-Dec-2013
15-Nov-2013
15-Nov-2013
15-Nov-2013
15-Nov-2013
15-Nov-2013
27-Jan-2014
04-Jan-2014
27-Jan-2014
04-Jul-2013
04-Jul-2013
07-Oct-2013
12-Oct-2013
14-Oct-2013
08-Feb-2014
02-Sep-2013
31-Dec-2013
01-Nov-2013
25-Jan-2014
31-Dec-2013
31-Dec-2013
31-Dec-2013
31-Dec-2013
31-Dec-2013
03-Feb-2014
07-Feb-2014
08-Feb-2014
21-Jan-2014
07-Aug-2013
21-DEC-13
22-NOV-13
07-JAN-14
24-Sep-2013
24-SEP-13
11-FEB-14
05-FEB-14
12-MAR-14
12-MAR-14
12-MAR-14
12-MAR-14
12-MAR-14
12-MAR-14
10-APR-14
18-MAR-14
28-APR-14
09-Aug-2013
09-AUG-13
28-DEC-13
26-DEC-13
20-JAN-14
10-May-2014
14-NOV-13
21-APR-14
11-MAR-14
09-APR-14
26-APR-14
26-APR-14
26-APR-14
26-APR-14
26-APR-14
17-APR-14
21-APR-14
10-MAY-14
21-Apr-2014
12-SEP-13
-71d
-64d
-84d
-78d
-62d
-95d
-111d
-63d
-100d
-100d
-100d
-100d
-100d
-63d
-62d
-78d
-77d
-31d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 Interior Works
9 False ceiling
9 Workstations & Modular Furniture
9 HVAC Grills/Defuser fixing
9 Electrical light fittings
9 FPS sprinklers
9 Access Controle system
9 Networking
9 chairs ,Blinds & carpet etc
9 Fire door erection
9 Final Testing , Comissioning & cleanig
7 Wet Finishing
8 Second Floor
9 SF Clearance
9 Block Work
9 Internal Plastering
9 Painting
8 Third Floor
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S1-Str2074
S1-Str2073
S1-Str2083
s14930
s14940
s14950
s14960
s14970
s14980
s14990
s15000
Fin
3
A52720
A52730
A52740
A52750
4
03-Oct-2013
09-Sep-2013
09-Dec-2013
26-Oct-2013
26-Oct-2013
26-Oct-2013
26-Oct-2013
26-Oct-2013
07-Jan-2014
17-Dec-2013
08-Jan-2014
18-Jan-2013
06-Feb-2013
06-Feb-2013
08-Feb-2013
18-Feb-2013
06-Mar-2013
04-Mar-2013
11-Dec-2013
12-Oct-2013
06-Jan-2014
11-Dec-2013
11-Dec-2013
11-Dec-2013
11-Dec-2013
11-Dec-2013
14-Jan-2014
20-Jan-2014
21-Jan-2014
10-Jul-2013
09-Apr-2013
06-Feb-2013
08-Mar-2013
23-Mar-2013
09-Apr-2013
30-Apr-2013
22-JAN-14
16-JAN-14
20-FEB-14
20-FEB-14
20-FEB-14
20-FEB-14
20-FEB-14
20-FEB-14
21-MAR-14
26-FEB-14
08-APR-14
09-Mar-2013A
04-Apr-2013A
04-APR-13A
05-APR-13A
31-MAY-13
17-JUN-13
09-Apr-2013A
01-APR-14
19-FEB-14
20-MAR-14
07-APR-14
07-APR-14
07-APR-14
07-APR-14
07-APR-14
28-MAR-14
01-APR-14
21-APR-14
05-Sep-2013
20-Jul-2013
05-APR-13A
21-JUN-13
04-JUL-13
20-JUL-13
16-Jul-2013
-95d
-111d
-63d
-100d
-100d
-100d
-100d
-100d
-63d
-61d
-77d
-49d
-88d
-49d
-90d
-88d
-88d
-66d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 TF Clearance
9 Block Work
9 Internal Plastering
9 Painting
8 Fifth Floor
9 Fifth Floor Clearance
9 Block Work
9 Internal Plastering
9 Painting
8 Ground Floor
9 GF Clearance
9 Block Work
9 Internal Plastering
9 Painting
8 Fourth Floor
9 Block Work
9 Internal Plastering
9 Painting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A52960
A52970
A52980
A52990
6
A52800
A52810
A52820
A52830
1
A52880
A52890
A52900
A52910
5
A52850
A52860
A52870
04-Mar-2013
06-Mar-2013
15-Mar-2013
27-Mar-2013
24-Apr-2013
24-Apr-2013
26-Apr-2013
06-May-2013
14-May-2013
18-Jan-2013
18-Jan-2013
21-Jan-2013
30-Jan-2013
20-Feb-2013
29-Mar-2013
30-Mar-2013
09-Apr-2013
17-Apr-2013
04-Mar-2013
03-Apr-2013
18-Apr-2013
30-Apr-2013
11-Jun-2013
24-Apr-2013
24-May-2013
08-Jun-2013
11-Jun-2013
26-Mar-2013
18-Jan-2013
18-Feb-2013
05-Mar-2013
26-Mar-2013
21-May-2013
27-Apr-2013
13-May-2013
21-May-2013
09-APR-13A
10-APR-13A
31-MAY-13
12-JUN-13
16-May-2013A
16-MAY-13A
21-MAY-13A
31-MAY-13
08-JUN-13
09-Mar-2013A
09-MAR-13A
10-MAR-13A
13-JUN-13
04-JUL-13
06-May-2013A
10-MAY-13A
31-MAY-13
08-JUN-13
10-APR-13A
22-JUN-13
04-JUL-13
16-JUL-13
15-Jul-2013
28-MAY-13A
28-JUN-13
12-JUL-13
15-JUL-13
08-Aug-2013
05-JUN-13
03-JUL-13
18-JUL-13
08-AUG-13
12-Jul-2013
28-JUN-13
04-JUL-13
12-JUL-13
-31d
-69d
-66d
-66d
-29d
-29d
-30d
-29d
-29d
-116d
-117d
-116d
-116d
-116d
-45d
-53d
-45d
-45d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A52840
7
A52920
A52930
A52940
A52950
2
A52760
A52770
A52780
A52790
1
A52640
A52650
A52660
A52670
A52680
Sup
29-Mar-2013
20-May-2013
20-May-2013
22-May-2013
31-May-2013
12-Jun-2013
19-Jan-2013
19-Jan-2013
21-Jan-2013
30-Jan-2013
13-Feb-2013
07-May-2013
30-May-2013
07-May-2013
07-May-2013
08-Jul-2013
07-May-2013
03-Nov-2012
29-Mar-2013
10-Jul-2013
20-May-2013
19-Jun-2013
04-Jul-2013
10-Jul-2013
19-Mar-2013
19-Jan-2013
18-Feb-2013
05-Mar-2013
19-Mar-2013
10-Aug-2013
03-Jul-2013
29-May-2013
10-Jun-2013
10-Aug-2013
27-Jun-2013
06-May-2013
06-MAY-13A
13-Jun-2013
13-JUN-13
01-JUL-13
10-JUL-13
22-JUL-13
09-Mar-2013A
09-MAR-13A
10-MAR-13A
10-MAY-13A
31-MAY-13
15-Apr-2013A
26-JUN-13
31-MAY-13
02-MAY-13A
05-MAY-13A
15-APR-13A
29-Oct-2012A
08-MAY-13A
05-Sep-2013
29-JUN-13
15-AUG-13
30-AUG-13
05-SEP-13
04-Jul-2013
10-MAR-13A
17-JUN-13
04-JUL-13
04-JUL-13
22-Dec-2014
03-AUG-13
26-JUN-13
08-JUL-13
22-DEC-14
25-JUL-13
02-Jul-2013
-34d
-49d
-35d
-49d
-49d
-49d
-92d
-42d
-102d
-104d
-92d
-427d
-27d
-24d
-24d
-426d
-24d
-49d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
GF
2
A21460
A21470
A22910
A22820
A22830
5
A21520
A21530
A22880
A22890
A22940
7
A23000
A23010
A25730
A25990
06-Dec-2012
14-Dec-2012
29-Dec-2012
16-Jan-2013
14-Dec-2012
20-Dec-2012
24-Dec-2012
14-Dec-2012
29-Dec-2012
16-Jan-2013
20-Dec-2012
24-Dec-2012
14-Dec-2012
15-Dec-2012
28-Dec-2012
15-Jan-2013
21-Dec-2012
25-Dec-2012
17-Jan-2013
17-Jan-2013
15-Jan-2013
17-Jan-2013
19-Dec-2012
22-Dec-2012
26-Dec-2012
17-Jan-2013
15-Jan-2013
17-Jan-2013
22-Dec-2012
26-Dec-2012
19-Dec-2012
16-Jan-2013
14-Jan-2013
16-Jan-2013
24-Dec-2012
27-Dec-2012
09-Feb-2013A
14-Feb-2013A
19-FEB-13A
26-FEB-13A
14-FEB-13A
17-FEB-13A
17-FEB-13A
05-Mar-2013A
15-MAR-13A
13-MAR-13A
08-MAR-13A
12-MAR-13A
05-MAR-13A
18-May-2013A
25-MAY-13A
30-MAY-13A
21-MAY-13A
23-MAY-13A
02-Jul-2013
31-May-2013
19-APR-13A
19-APR-13A
15-APR-13A
15-APR-13A
16-APR-13A
12-Jun-2013
11-JUN-13
12-JUN-13
03-JUN-13
04-JUN-13
01-JUN-13
02-Jul-2013
29-JUN-13
02-JUL-13
08-JUN-13
12-JUN-13
-142d
-115d
-80d
-79d
-100d
-97d
-94d
-125d
-125d
-124d
-138d
-136d
-140d
-143d
-143d
-143d
-143d
-143d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Soling
9 Pour-2 (16-21 /A-E)
10 Reinforcement
10 Casting
10 Soling
10 Antitermite treatment
10 PCC
9 Pour -4 (16-21/E-J)
10 Reinforcement
10 Casting
10 Soling
10 Antitermite treatment
10 PCC
9 Pour -3 (1-7/A-E)
10 Reinforcement
10 Casting
10 Soling
10 Antitermite treatment
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A26200
Pour 1
A6240
A6250
A6370
A6300
A6310
1
A21440
A21450
A22900
A22800
A22810
Pour 3
A6270
A6360
A6380
A6320
15-Dec-2012
14-Dec-2012
28-Dec-2012
15-Jan-2013
14-Dec-2012
20-Dec-2012
24-Dec-2012
06-Dec-2012
28-Dec-2012
15-Jan-2013
06-Dec-2012
12-Dec-2012
15-Dec-2012
13-Dec-2012
28-Dec-2012
15-Jan-2013
13-Dec-2012
19-Dec-2012
20-Dec-2012
16-Jan-2013
14-Jan-2013
16-Jan-2013
19-Dec-2012
22-Dec-2012
26-Dec-2012
16-Jan-2013
14-Jan-2013
16-Jan-2013
11-Dec-2012
14-Dec-2012
18-Dec-2012
16-Jan-2013
14-Jan-2013
16-Jan-2013
18-Dec-2012
21-Dec-2012
18-MAY-13A
11-Apr-2013A
25-APR-13A
28-APR-13A
11-APR-13A
12-APR-13A
14-APR-13A
20-Feb-2013A
27-FEB-13A
23-MAR-13A
20-FEB-13A
23-FEB-13A
25-FEB-13A
09-Feb-2013A
11-FEB-13A
12-FEB-13A
09-FEB-13A
10-FEB-13A
05-JUN-13
19-Jun-2013
17-JUN-13
19-JUN-13
12-APR-13A
14-APR-13A
17-APR-13A
12-Jun-2013
10-JUN-13
12-JUN-13
17-APR-13A
19-APR-13A
20-APR-13A
18-Jun-2013
15-JUN-13
18-JUN-13
18-APR-13A
20-APR-13A
-143d
-132d
-132d
-132d
-97d
-96d
-95d
-126d
-126d
-125d
-109d
-107d
-106d
-131d
-131d
-130d
-104d
-102d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 PCC
9 Pour -1 (1-7/E-J)
10 Casting
10 Reinforcement
10 Soling
10 Antitermite treatment
10 PCC
9 Pour -6 (7-11/A-E)
10 Reinforcement
10 Casting
10 Antitermite Treatment
10 PCC
10 Soling
9 Pour -7 (11-16/E-J)
10 Reinforcement
10 Casting
10 Antitermite treatment
10 PCC
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A6330
Pour 2
A6350
A6260
A6340
A6280
A6290
3
A21480
A21490
A22840
A22850
A22920
4
A21500
A21510
A22860
A22870
22-Dec-2012
14-Dec-2012
07-Jan-2013
24-Dec-2012
14-Dec-2012
18-Dec-2012
20-Dec-2012
14-Dec-2012
29-Dec-2012
16-Jan-2013
20-Dec-2012
24-Dec-2012
14-Dec-2012
13-Dec-2012
28-Dec-2012
15-Jan-2013
19-Dec-2012
22-Dec-2012
25-Dec-2012
07-Jan-2013
07-Jan-2013
05-Jan-2013
17-Dec-2012
19-Dec-2012
22-Dec-2012
17-Jan-2013
15-Jan-2013
17-Jan-2013
22-Dec-2012
26-Dec-2012
19-Dec-2012
16-Jan-2013
14-Jan-2013
16-Jan-2013
21-Dec-2012
25-Dec-2012
10-FEB-13A
12-Feb-2013A
18-FEB-13A
16-FEB-13A
12-FEB-13A
13-FEB-13A
14-FEB-13A
10-Mar-2013A
20-MAR-13A
23-MAR-13A
13-MAR-13A
18-MAR-13A
10-MAR-13A
21-Feb-2013A
27-FEB-13A
28-FEB-13A
23-FEB-13A
25-FEB-13A
21-APR-13A
03-Jun-2013
03-JUN-13
03-JUN-13
15-APR-13A
15-APR-13A
16-APR-13A
07-Jun-2013
06-JUN-13
07-JUN-13
16-APR-13A
17-APR-13A
15-APR-13A
12-Jun-2013
11-JUN-13
12-JUN-13
03-JUN-13
04-JUN-13
-100d
-126d
-126d
-126d
-101d
-100d
-98d
-121d
-121d
-120d
-98d
-96d
-100d
-126d
-126d
-125d
-139d
-137d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Soling
9 Pour -9 (3-7/D-F) Lift slab
10 Reinforcement
10 Casting
10 Antitermite Treatment
10 PCC
10 Soling
8 Fifth Floor Slab
9 Pour -1 (1-7/E-J)
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -2 (16-21/A-E)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A22930
6
A22980
A22990
A25710
A25720
A26180
FF5
Pour 3
2
A19310
A19320
A19330
1
A19280
A19290
A19300
Pour 31
13-Dec-2012
15-Dec-2012
28-Dec-2012
15-Jan-2013
21-Dec-2012
25-Dec-2012
15-Dec-2012
05-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
16-Feb-2013
18-Feb-2013
14-Feb-2013
14-Feb-2013
16-Feb-2013
19-Feb-2013
18-Feb-2013
18-Dec-2012
16-Jan-2013
14-Jan-2013
16-Jan-2013
24-Dec-2012
27-Dec-2012
20-Dec-2012
14-Mar-2013
28-Feb-2013
27-Feb-2013
23-Feb-2013
26-Feb-2013
27-Feb-2013
28-Feb-2013
23-Feb-2013
26-Feb-2013
28-Feb-2013
14-Mar-2013
21-FEB-13A
13-Mar-2013A
23-MAR-13A
25-MAR-13A
15-MAR-13A
17-MAR-13A
13-MAR-13A
23-Feb-2013A
23-Feb-2013A
24-Feb-2013A
24-FEB-13A
24-FEB-13A
25-FEB-13A
23-Feb-2013A
23-FEB-13A
24-FEB-13A
25-FEB-13A
13-Mar-2013A
01-JUN-13
02-Jul-2013
29-JUN-13
02-JUL-13
08-JUN-13
12-JUN-13
05-JUN-13
31-May-2013
31-May-2013
31-May-2013
04-MAR-13A
05-MAR-13A
06-MAR-13A
31-May-2013
04-MAR-13A
05-MAR-13A
05-MAR-13A
31-May-2013
-141d
-143d
-143d
-143d
-143d
-143d
-143d
-67d
-79d
-80d
-6d
-5d
-5d
-79d
-6d
-5d
-3d
-67d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -6 (7-11/A-E)
10 Column
11 Reinforcement
11 Concreting
11 Shuttering
10 Walls
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
1
A19370
A19380
A19390
2
A19400
A19410
A19420
3
A19430
A19440
A19450
Pour 35
1
A19730
A19750
A19740
2
18-Feb-2013
18-Feb-2013
20-Feb-2013
22-Feb-2013
18-Feb-2013
18-Feb-2013
20-Feb-2013
21-Feb-2013
22-Feb-2013
22-Feb-2013
25-Feb-2013
13-Mar-2013
16-Feb-2013
16-Feb-2013
16-Feb-2013
20-Feb-2013
18-Feb-2013
16-Feb-2013
04-Mar-2013
27-Feb-2013
01-Mar-2013
04-Mar-2013
02-Mar-2013
27-Feb-2013
01-Mar-2013
02-Mar-2013
14-Mar-2013
11-Mar-2013
13-Mar-2013
14-Mar-2013
14-Mar-2013
01-Mar-2013
26-Feb-2013
01-Mar-2013
27-Feb-2013
28-Feb-2013
13-Mar-2013A
13-MAR-13A
14-MAR-13A
15-MAR-13A
14-Mar-2013A
14-MAR-13A
15-MAR-13A
17-MAR-13A
18-Mar-2013A
18-MAR-13A
25-MAR-13A
01-APR-13A
01-Mar-2013A
01-Mar-2013A
01-MAR-13A
05-MAR-13A
03-MAR-13A
01-Mar-2013A
31-May-2013
17-MAR-13A
18-MAR-13A
19-MAR-13A
31-May-2013
19-MAR-13A
20-MAR-13A
20-MAR-13A
31-May-2013
27-MAR-13A
01-APR-13A
02-APR-13A
31-May-2013
31-May-2013
05-MAR-13A
07-MAR-13A
06-MAR-13A
31-May-2013
-76d
-15d
-13d
-12d
-77d
-16d
-15d
-14d
-67d
-13d
-15d
-15d
-67d
-78d
-5d
-4d
-5d
-79d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -3 (1-7/A-E)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Concreting
11 Reinforcement
11 Shuttering
10 Column
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A19760
A19770
A19780
3
A19790
A19800
A19810
Pour 32
3
A19520
A19530
A19540
2
A19510
A19490
A19500
1
A19460
16-Feb-2013
18-Feb-2013
20-Feb-2013
25-Feb-2013
25-Feb-2013
28-Feb-2013
13-Mar-2013
05-Feb-2013
08-Feb-2013
08-Feb-2013
13-Feb-2013
28-Feb-2013
05-Feb-2013
08-Feb-2013
05-Feb-2013
07-Feb-2013
05-Feb-2013
05-Feb-2013
25-Feb-2013
27-Feb-2013
28-Feb-2013
14-Mar-2013
09-Mar-2013
12-Mar-2013
14-Mar-2013
01-Mar-2013
01-Mar-2013
25-Feb-2013
27-Feb-2013
01-Mar-2013
18-Feb-2013
18-Feb-2013
14-Feb-2013
16-Feb-2013
18-Feb-2013
14-Feb-2013
01-MAR-13A
03-MAR-13A
05-MAR-13A
06-Mar-2013A
06-MAR-13A
12-MAR-13A
16-MAR-13A
01-Mar-2013A
06-Mar-2013A
06-MAR-13A
11-MAR-13A
18-MAR-13A
01-Mar-2013A
06-MAR-13A
01-MAR-13A
02-MAR-13A
01-Mar-2013A
01-MAR-13A
05-MAR-13A
06-MAR-13A
07-MAR-13A
31-May-2013
13-MAR-13A
16-MAR-13A
17-MAR-13A
31-May-2013
31-May-2013
13-MAR-13A
18-MAR-13A
19-MAR-13A
31-May-2013
08-MAR-13A
05-MAR-13A
06-MAR-13A
31-May-2013
05-MAR-13A
-6d
-5d
-5d
-67d
-2d
-3d
-2d
-78d
-78d
-13d
-15d
-14d
-88d
-15d
-15d
-14d
-88d
-15d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Concreting
9 Pour -5 (7-11/E-J)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -8 (11-16/A-E)
10 Walls
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A19470
A19480
Pour 34
1
A19640
A19650
A19660
2
A19670
A19680
A19690
3
A19700
A19710
A19720
Pour 37
2
A19940
07-Feb-2013
08-Feb-2013
15-Feb-2013
15-Feb-2013
15-Feb-2013
16-Feb-2013
19-Feb-2013
15-Feb-2013
15-Feb-2013
16-Feb-2013
19-Feb-2013
23-Feb-2013
23-Feb-2013
27-Feb-2013
12-Mar-2013
16-Feb-2013
16-Feb-2013
16-Feb-2013
16-Feb-2013
18-Feb-2013
13-Mar-2013
01-Mar-2013
25-Feb-2013
27-Feb-2013
01-Mar-2013
28-Feb-2013
25-Feb-2013
27-Feb-2013
28-Feb-2013
13-Mar-2013
09-Mar-2013
11-Mar-2013
13-Mar-2013
14-Mar-2013
01-Mar-2013
26-Feb-2013
02-MAR-13A
03-MAR-13A
04-Mar-2013A
04-Mar-2013A
04-MAR-13A
07-MAR-13A
08-MAR-13A
04-Mar-2013A
04-MAR-13A
07-MAR-13A
08-MAR-13A
13-Mar-2013A
13-MAR-13A
18-MAR-13A
21-MAR-13A
15-Mar-2013A
15-Mar-2013A
15-MAR-13A
06-MAR-13A
07-MAR-13A
31-May-2013
31-May-2013
12-MAR-13A
14-MAR-13A
15-MAR-13A
31-May-2013
12-MAR-13A
14-MAR-13A
15-MAR-13A
31-May-2013
20-MAR-13A
21-MAR-13A
22-MAR-13A
31-May-2013
31-May-2013
18-MAR-13A
-14d
-14d
-68d
-78d
-12d
-12d
-11d
-79d
-12d
-12d
-12d
-68d
-8d
-8d
-7d
-67d
-78d
-16d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Concreting
11 Reinforcement
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -10 (16-20/D-F) Lift slab
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A19950
A19960
3
A19970
A19990
A19980
1
A19910
A19920
A19930
Pour 372
3
A22410
A22420
A22430
1
A22350
A22360
19-Feb-2013
21-Feb-2013
25-Feb-2013
25-Feb-2013
13-Mar-2013
28-Feb-2013
16-Feb-2013
16-Feb-2013
18-Feb-2013
20-Feb-2013
14-Feb-2013
22-Feb-2013
22-Feb-2013
26-Feb-2013
09-Mar-2013
14-Feb-2013
14-Feb-2013
15-Feb-2013
28-Feb-2013
01-Mar-2013
14-Mar-2013
11-Mar-2013
14-Mar-2013
12-Mar-2013
02-Mar-2013
26-Feb-2013
28-Feb-2013
02-Mar-2013
11-Mar-2013
11-Mar-2013
08-Mar-2013
09-Mar-2013
11-Mar-2013
28-Feb-2013
23-Feb-2013
26-Feb-2013
16-MAR-13A
18-MAR-13A
20-Mar-2013A
20-MAR-13A
29-MAR-13A
25-MAR-13A
15-Mar-2013A
15-MAR-13A
16-MAR-13A
18-MAR-13A
21-Mar-2013A
26-Mar-2013A
26-MAR-13A
29-MAR-13A
03-APR-13A
21-Mar-2013A
21-MAR-13A
22-MAR-13A
20-MAR-13A
22-MAR-13A
31-May-2013
26-MAR-13A
30-MAR-13A
29-MAR-13A
31-May-2013
18-MAR-13A
20-MAR-13A
22-MAR-13A
31-May-2013
31-May-2013
31-MAR-13A
02-APR-13A
03-APR-13A
31-May-2013
23-MAR-13A
24-MAR-13A
-16d
-17d
-67d
-12d
-13d
-14d
-77d
-16d
-16d
-16d
-70d
-70d
-19d
-19d
-19d
-79d
-23d
-22d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -9 (3-7/D-F) Lift slab
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A22370
2
A22380
A22390
A22400
Pour 371
3
A22320
A22330
A22340
1
A22260
A22270
A22280
2
A22290
A22300
A22310
18-Feb-2013
14-Feb-2013
14-Feb-2013
16-Feb-2013
19-Feb-2013
14-Feb-2013
22-Feb-2013
22-Feb-2013
26-Feb-2013
09-Mar-2013
14-Feb-2013
14-Feb-2013
15-Feb-2013
18-Feb-2013
14-Feb-2013
14-Feb-2013
16-Feb-2013
19-Feb-2013
28-Feb-2013
27-Feb-2013
23-Feb-2013
26-Feb-2013
27-Feb-2013
11-Mar-2013
11-Mar-2013
08-Mar-2013
09-Mar-2013
11-Mar-2013
28-Feb-2013
23-Feb-2013
26-Feb-2013
28-Feb-2013
27-Feb-2013
23-Feb-2013
26-Feb-2013
27-Feb-2013
23-MAR-13A
22-Mar-2013A
22-MAR-13A
24-MAR-13A
26-MAR-13A
04-Mar-2013A
15-Mar-2013A
15-MAR-13A
19-MAR-13A
22-MAR-13A
04-Mar-2013A
04-MAR-13A
06-MAR-13A
07-MAR-13A
05-Mar-2013A
05-MAR-13A
07-MAR-13A
09-MAR-13A
25-MAR-13A
31-May-2013
25-MAR-13A
27-MAR-13A
28-MAR-13A
31-May-2013
31-May-2013
20-MAR-13A
22-MAR-13A
22-MAR-13A
31-May-2013
07-MAR-13A
09-MAR-13A
11-MAR-13A
31-May-2013
09-MAR-13A
11-MAR-13A
16-MAR-13A
-20d
-80d
-24d
-24d
-24d
-70d
-70d
-9d
-10d
-9d
-79d
-9d
-9d
-8d
-80d
-11d
-10d
-14d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 Pour -4 (16-21/E-J)
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -7 (11-16/E-J)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
Pour 33
2
A19580
A19590
A19600
3
A19610
A19620
A19630
1
A19550
A19560
A19570
Pour 36
3
A19880
A19890
A19900
09-Feb-2013
09-Feb-2013
09-Feb-2013
12-Feb-2013
13-Feb-2013
14-Feb-2013
14-Feb-2013
18-Feb-2013
06-Mar-2013
09-Feb-2013
09-Feb-2013
11-Feb-2013
13-Feb-2013
13-Feb-2013
21-Feb-2013
21-Feb-2013
25-Feb-2013
09-Mar-2013
07-Mar-2013
22-Feb-2013
19-Feb-2013
21-Feb-2013
22-Feb-2013
07-Mar-2013
04-Mar-2013
05-Mar-2013
07-Mar-2013
22-Feb-2013
19-Feb-2013
20-Feb-2013
22-Feb-2013
11-Mar-2013
11-Mar-2013
07-Mar-2013
08-Mar-2013
11-Mar-2013
21-Mar-2013A
21-Mar-2013A
21-MAR-13A
22-MAR-13A
24-MAR-13A
27-Mar-2013A
27-MAR-13A
29-MAR-13A
04-APR-13A
21-Mar-2013A
21-MAR-13A
22-MAR-13A
23-MAR-13A
05-Mar-2013A
13-Mar-2013A
13-MAR-13A
19-MAR-13A
23-APR-13A
31-May-2013
31-May-2013
26-MAR-13A
29-MAR-13A
29-MAR-13A
31-May-2013
30-MAR-13A
03-APR-13A
04-APR-13A
31-May-2013
26-MAR-13A
27-MAR-13A
28-MAR-13A
31-May-2013
31-May-2013
15-APR-13A
23-APR-13A
24-APR-13A
-73d
-84d
-29d
-30d
-29d
-73d
-22d
-24d
-23d
-84d
-29d
-29d
-28d
-70d
-70d
-33d
-38d
-37d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
8 First Floor Slab
9 Pour -5 (7-11/E-J)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
1
A19820
A19830
A19840
2
A19850
A19860
A19870
FF
Pour 34
1
A16760
A16770
A16780
3
A16820
A16830
A16840
13-Feb-2013
13-Feb-2013
14-Feb-2013
16-Feb-2013
13-Feb-2013
13-Feb-2013
15-Feb-2013
19-Feb-2013
03-Nov-2012
10-Nov-2012
10-Nov-2012
10-Nov-2012
12-Nov-2012
14-Nov-2012
19-Nov-2012
19-Nov-2012
22-Nov-2012
04-Dec-2012
27-Feb-2013
22-Feb-2013
25-Feb-2013
27-Feb-2013
27-Feb-2013
22-Feb-2013
25-Feb-2013
27-Feb-2013
05-Dec-2012
05-Dec-2012
24-Nov-2012
20-Nov-2012
22-Nov-2012
24-Nov-2012
05-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
05-Mar-2013A
05-MAR-13A
07-MAR-13A
09-MAR-13A
05-Mar-2013A
05-MAR-13A
07-MAR-13A
09-MAR-13A
29-Oct-2012A
27-Nov-2012A
27-Nov-2012A
27-NOV-12A
29-NOV-12A
30-NOV-12A
08-Dec-2012A
08-DEC-12A
12-DEC-12A
31-DEC-12A
31-May-2013
12-MAR-13A
14-MAR-13A
15-MAR-13A
31-May-2013
12-MAR-13A
14-MAR-13A
15-MAR-13A
31-May-2013
31-May-2013
31-May-2013
10-DEC-12A
11-DEC-12A
12-DEC-12A
31-May-2013
29-DEC-12A
31-DEC-12A
01-JAN-13A
-80d
-14d
-14d
-13d
-80d
-14d
-14d
-13d
-152d
-152d
-161d
-16d
-15d
-14d
-152d
-22d
-22d
-22d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
Pour 371
1
A21540
A21550
A21560
2
A21570
A21580
A21590
3
A21600
A21610
A21620
Pour 37
2
A17060
A17070
A17080
03-Nov-2012
03-Nov-2012
03-Nov-2012
05-Nov-2012
07-Nov-2012
03-Nov-2012
03-Nov-2012
06-Nov-2012
08-Nov-2012
12-Nov-2012
12-Nov-2012
15-Nov-2012
27-Nov-2012
10-Nov-2012
10-Nov-2012
10-Nov-2012
13-Nov-2012
15-Nov-2012
28-Nov-2012
17-Nov-2012
13-Nov-2012
15-Nov-2012
17-Nov-2012
16-Nov-2012
13-Nov-2012
15-Nov-2012
16-Nov-2012
28-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
05-Dec-2012
23-Nov-2012
20-Nov-2012
22-Nov-2012
23-Nov-2012
16-Dec-2012A
16-Dec-2012A
16-DEC-12A
19-DEC-12A
21-DEC-12A
16-Dec-2012A
16-DEC-12A
19-DEC-12A
21-DEC-12A
24-Dec-2012A
24-DEC-12A
30-DEC-12A
05-JAN-13A
24-Nov-2012A
24-Nov-2012A
24-NOV-12A
26-NOV-12A
28-NOV-12A
31-May-2013
31-May-2013
22-DEC-12A
25-DEC-12A
26-DEC-12A
31-May-2013
22-DEC-12A
25-DEC-12A
26-DEC-12A
31-May-2013
02-JAN-13A
04-JAN-13A
05-JAN-13A
31-May-2013
31-May-2013
18-DEC-12A
19-DEC-12A
20-DEC-12A
-158d
-167d
-33d
-33d
-32d
-168d
-33d
-33d
-33d
-158d
-31d
-32d
-32d
-152d
-162d
-23d
-22d
-22d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A17090
A17100
A17110
1
A17030
A17040
A17050
Pour 33
3
A16730
A16740
A16750
2
A16700
A16710
A16720
1
19-Nov-2012
19-Nov-2012
22-Nov-2012
04-Dec-2012
10-Nov-2012
10-Nov-2012
12-Nov-2012
14-Nov-2012
07-Nov-2012
15-Nov-2012
15-Nov-2012
19-Nov-2012
04-Dec-2012
07-Nov-2012
07-Nov-2012
10-Nov-2012
13-Nov-2012
07-Nov-2012
05-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
24-Nov-2012
20-Nov-2012
22-Nov-2012
24-Nov-2012
05-Dec-2012
05-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
24-Nov-2012
21-Nov-2012
23-Nov-2012
24-Nov-2012
24-Nov-2012
05-Dec-2012A
05-DEC-12A
10-DEC-12A
11-JAN-13A
24-Nov-2012A
24-NOV-12A
26-NOV-12A
28-NOV-12A
21-Nov-2012A
14-Dec-2012A
14-DEC-12A
20-DEC-12A
12-JAN-13A
22-Nov-2012A
22-NOV-12A
23-NOV-12A
23-NOV-12A
21-Nov-2012A
31-May-2013
07-JAN-13A
11-JAN-13A
12-JAN-13A
31-May-2013
18-DEC-12A
19-DEC-12A
20-DEC-12A
31-May-2013
31-May-2013
10-JAN-13A
11-JAN-13A
14-JAN-13A
31-May-2013
17-DEC-12A
19-DEC-12A
20-DEC-12A
31-May-2013
-152d
-29d
-32d
-32d
-161d
-23d
-22d
-21d
-152d
-152d
-32d
-32d
-33d
-161d
-21d
-21d
-21d
-161d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -6 (7-11/A-E)
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -10 (16-20/D-F) Lift slab
10 Beams & Slab
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A16670
A16680
A16690
Pour 35
2
A16880
A16890
A16900
1
A16850
A16860
A16870
3
A16910
A16920
A16930
Pour 372
3
07-Nov-2012
08-Nov-2012
10-Nov-2012
10-Nov-2012
10-Nov-2012
10-Nov-2012
12-Nov-2012
14-Nov-2012
10-Nov-2012
10-Nov-2012
12-Nov-2012
14-Nov-2012
19-Nov-2012
19-Nov-2012
22-Nov-2012
04-Dec-2012
03-Nov-2012
12-Nov-2012
21-Nov-2012
22-Nov-2012
24-Nov-2012
05-Dec-2012
22-Nov-2012
19-Nov-2012
21-Nov-2012
22-Nov-2012
23-Nov-2012
20-Nov-2012
21-Nov-2012
23-Nov-2012
05-Dec-2012
01-Dec-2012
04-Dec-2012
05-Dec-2012
28-Nov-2012
28-Nov-2012
21-NOV-12A
23-NOV-12A
23-NOV-12A
01-Dec-2012A
01-Dec-2012A
01-DEC-12A
04-DEC-12A
05-DEC-12A
01-Dec-2012A
01-DEC-12A
04-DEC-12A
05-DEC-12A
07-Dec-2012A
07-DEC-12A
10-DEC-12A
05-JAN-13A
21-Dec-2012A
01-Jan-2013A
21-DEC-12A
22-DEC-12A
25-DEC-12A
31-May-2013
31-May-2013
18-DEC-12A
19-DEC-12A
20-DEC-12A
31-May-2013
18-DEC-12A
19-DEC-12A
20-DEC-12A
31-May-2013
03-JAN-13A
05-JAN-13A
06-JAN-13A
31-May-2013
31-May-2013
-25d
-25d
-25d
-152d
-163d
-24d
-23d
-23d
-162d
-23d
-23d
-22d
-152d
-27d
-27d
-27d
-158d
-158d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -3 (1-7/A-E)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A21690
A21700
A21710
2
A21660
A21670
A21680
1
A21630
A21640
A21650
Pour 32
1
A16580
A16590
A16600
3
A16640
12-Nov-2012
15-Nov-2012
27-Nov-2012
03-Nov-2012
03-Nov-2012
06-Nov-2012
08-Nov-2012
03-Nov-2012
03-Nov-2012
05-Nov-2012
07-Nov-2012
05-Nov-2012
05-Nov-2012
05-Nov-2012
06-Nov-2012
07-Nov-2012
14-Nov-2012
14-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
16-Nov-2012
13-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
13-Nov-2012
15-Nov-2012
17-Nov-2012
04-Dec-2012
23-Nov-2012
20-Nov-2012
22-Nov-2012
23-Nov-2012
04-Dec-2012
30-Nov-2012
01-JAN-13A
05-JAN-13A
13-JAN-13A
24-Dec-2012A
24-DEC-12A
27-DEC-12A
28-DEC-12A
21-Dec-2012A
21-DEC-12A
27-DEC-12A
28-DEC-12A
03-Nov-2012A
20-Nov-2012A
20-NOV-12A
21-NOV-12A
21-NOV-12A
10-Dec-2012A
10-DEC-12A
10-JAN-13A
13-JAN-13A
14-JAN-13A
31-May-2013
31-DEC-12A
02-JAN-13A
03-JAN-13A
31-May-2013
31-DEC-12A
02-JAN-13A
03-JAN-13A
31-May-2013
31-May-2013
06-DEC-12A
22-DEC-12A
25-DEC-12A
31-May-2013
27-DEC-12A
-38d
-40d
-39d
-168d
-40d
-40d
-40d
-167d
-40d
-40d
-39d
-153d
-162d
-13d
-25d
-26d
-153d
-22d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -2 (16-21/A-E)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A16650
A16660
2
A16610
A16620
A16630
Pour 31
1
A16490
A16500
A16510
3
A16550
A16560
A16570
2
A16520
A16530
19-Nov-2012
03-Dec-2012
05-Nov-2012
05-Nov-2012
07-Nov-2012
09-Nov-2012
08-Nov-2012
08-Nov-2012
08-Nov-2012
09-Nov-2012
12-Nov-2012
15-Nov-2012
15-Nov-2012
17-Nov-2012
04-Dec-2012
08-Nov-2012
08-Nov-2012
10-Nov-2012
03-Dec-2012
04-Dec-2012
22-Nov-2012
19-Nov-2012
21-Nov-2012
22-Nov-2012
05-Dec-2012
27-Nov-2012
22-Nov-2012
24-Nov-2012
27-Nov-2012
05-Dec-2012
01-Dec-2012
04-Dec-2012
05-Dec-2012
24-Nov-2012
21-Nov-2012
23-Nov-2012
14-DEC-12A
28-DEC-12A
03-Nov-2012A
03-NOV-12A
06-NOV-12A
08-NOV-12A
31-Oct-2012A
31-Oct-2012A
31-OCT-12A
01-NOV-12A
03-NOV-12A
05-Dec-2012A
05-DEC-12A
10-DEC-12A
31-DEC-12A
02-Nov-2012A
02-NOV-12A
05-NOV-12A
29-DEC-12A
30-DEC-12A
31-May-2013
06-DEC-12A
07-DEC-12A
11-DEC-12A
31-May-2013
31-May-2013
04-DEC-12A
05-DEC-12A
07-DEC-12A
31-May-2013
27-DEC-12A
30-DEC-12A
01-JAN-13A
31-May-2013
05-DEC-12A
07-DEC-12A
-22d
-22d
-163d
-14d
-13d
-15d
-152d
-159d
-9d
-8d
-8d
-152d
-21d
-22d
-22d
-161d
-11d
-11d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
9 Pour -1 (1-7/E-J)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -7 (11-16/E-J)
10 Column
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A16540
Pour 3
1
A16400
A16410
A16420
3
A16460
A16470
A16480
2
A16430
A16440
A16450
Pour 36
1
A16940
A16950
12-Nov-2012
05-Nov-2012
05-Nov-2012
05-Nov-2012
05-Nov-2012
07-Nov-2012
15-Nov-2012
15-Nov-2012
19-Nov-2012
04-Dec-2012
05-Nov-2012
05-Nov-2012
07-Nov-2012
09-Nov-2012
10-Nov-2012
10-Nov-2012
10-Nov-2012
12-Nov-2012
24-Nov-2012
05-Dec-2012
23-Nov-2012
19-Nov-2012
21-Nov-2012
23-Nov-2012
05-Dec-2012
01-Dec-2012
04-Dec-2012
05-Dec-2012
21-Nov-2012
17-Nov-2012
20-Nov-2012
21-Nov-2012
04-Dec-2012
23-Nov-2012
20-Nov-2012
22-Nov-2012
06-NOV-12A
29-Oct-2012A
29-Oct-2012A
29-OCT-12A
29-OCT-12A
31-OCT-12A
20-Nov-2012A
20-NOV-12A
07-DEC-12A
19-DEC-12A
31-Oct-2012A
31-OCT-12A
02-NOV-12A
05-NOV-12A
24-Nov-2012A
25-Nov-2012A
25-NOV-12A
28-NOV-12A
10-DEC-12A
31-May-2013
31-May-2013
05-DEC-12A
06-DEC-12A
08-DEC-12A
31-May-2013
15-DEC-12A
19-DEC-12A
21-DEC-12A
31-May-2013
05-DEC-12A
06-DEC-12A
07-DEC-12A
31-May-2013
31-May-2013
18-DEC-12A
19-DEC-12A
-12d
-152d
-162d
-13d
-12d
-12d
-152d
-11d
-12d
-13d
-164d
-14d
-13d
-13d
-153d
-162d
-23d
-22d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
8 Terace Slab
9 Pour -10 (16-20/D-F) Lift slab
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A16960
3
A17000
A17010
A17020
2
A16970
A16980
A16990
FF7
Pour 372
1
A22710
A22720
A22730
2
A22740
A22750
13-Nov-2012
17-Nov-2012
17-Nov-2012
21-Nov-2012
03-Dec-2012
10-Nov-2012
10-Nov-2012
13-Nov-2012
15-Nov-2012
28-Mar-2013
06-Apr-2013
06-Apr-2013
06-Apr-2013
08-Apr-2013
10-Apr-2013
06-Apr-2013
06-Apr-2013
09-Apr-2013
23-Nov-2012
04-Dec-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
23-Nov-2012
20-Nov-2012
22-Nov-2012
23-Nov-2012
06-May-2013
01-May-2013
20-Apr-2013
16-Apr-2013
18-Apr-2013
20-Apr-2013
19-Apr-2013
16-Apr-2013
18-Apr-2013
30-NOV-12A
05-Dec-2012A
05-DEC-12A
08-DEC-12A
15-JAN-13A
24-Nov-2012A
24-NOV-12A
28-NOV-12A
29-NOV-12A
06-Apr-2013A
27-Apr-2013A
27-Apr-2013A
27-APR-13A
30-APR-13A
02-MAY-13A
27-Apr-2013A
27-APR-13A
30-APR-13A
20-DEC-12A
31-May-2013
06-JAN-13A
15-JAN-13A
16-JAN-13A
31-May-2013
18-DEC-12A
19-DEC-12A
20-DEC-12A
03-Jun-2013A
31-May-2013
31-May-2013
05-MAY-13A
07-MAY-13A
08-MAY-13A
31-May-2013
05-MAY-13A
07-MAY-13A
-22d
-153d
-30d
-36d
-36d
-162d
-23d
-22d
-22d
-24d
-26d
-35d
-16d
-15d
-14d
-36d
-16d
-16d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -3 (1-7/A-E)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -9 (3-7/D-F) Lift slab
10 Beams & Slab
11 Reinforcement
11 Concreting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A22760
3
A22770
A22780
A22790
Pour 32
1
A20900
A20910
A20920
2
A20930
A20940
A20950
Pour 371
3
A22690
A22700
11-Apr-2013
15-Apr-2013
15-Apr-2013
18-Apr-2013
30-Apr-2013
28-Mar-2013
28-Mar-2013
28-Mar-2013
30-Mar-2013
01-Apr-2013
28-Mar-2013
28-Mar-2013
30-Mar-2013
02-Apr-2013
18-Apr-2013
18-Apr-2013
18-Apr-2013
30-Apr-2013
19-Apr-2013
01-May-2013
29-Apr-2013
30-Apr-2013
01-May-2013
12-Apr-2013
11-Apr-2013
08-Apr-2013
10-Apr-2013
11-Apr-2013
12-Apr-2013
08-Apr-2013
10-Apr-2013
12-Apr-2013
01-May-2013
01-May-2013
30-Apr-2013
01-May-2013
02-MAY-13A
01-May-2013A
01-MAY-13A
04-MAY-13A
13-MAY-13A
06-Apr-2013A
06-Apr-2013A
06-APR-13A
08-APR-13A
09-APR-13A
07-Apr-2013A
07-APR-13A
08-APR-13A
10-APR-13A
20-Apr-2013A
20-Apr-2013A
20-APR-13A
30-APR-13A
08-MAY-13A
31-May-2013
14-MAY-13A
15-MAY-13A
16-MAY-13A
31-May-2013
31-May-2013
12-APR-13A
13-APR-13A
13-APR-13A
31-May-2013
13-APR-13A
14-APR-13A
14-APR-13A
31-May-2013
31-May-2013
01-MAY-13A
02-MAY-13A
-16d
-26d
-13d
-13d
-13d
-42d
-43d
-3d
-2d
-1d
-42d
-4d
-3d
-1d
-26d
-26d
0d
0d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 Pour -7 (11-16/E-J)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -2 (16-21/A-E)
10 Beams & Slab
11 Reinforcement
11 Concreting
9 Pour -4 (16-21/E-J)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
Pour 36
3
A21320
A21330
A21340
1
A21260
A21270
A21280
2
A21290
A21300
A21310
Pour 31
3
A20880
A20890
Pour 33
05-Apr-2013
12-Apr-2013
12-Apr-2013
16-Apr-2013
29-Apr-2013
05-Apr-2013
05-Apr-2013
06-Apr-2013
08-Apr-2013
05-Apr-2013
05-Apr-2013
08-Apr-2013
11-Apr-2013
18-Apr-2013
18-Apr-2013
18-Apr-2013
04-May-2013
03-Apr-2013
30-Apr-2013
30-Apr-2013
26-Apr-2013
27-Apr-2013
30-Apr-2013
18-Apr-2013
15-Apr-2013
17-Apr-2013
18-Apr-2013
19-Apr-2013
15-Apr-2013
17-Apr-2013
19-Apr-2013
06-May-2013
06-May-2013
04-May-2013
06-May-2013
29-Apr-2013
07-May-2013A
09-May-2013A
09-MAY-13A
10-MAY-13A
16-MAY-13A
07-May-2013A
07-MAY-13A
08-MAY-13A
09-MAY-13A
07-May-2013A
07-MAY-13A
08-MAY-13A
09-MAY-13A
27-Apr-2013A
27-Apr-2013A
27-APR-13A
04-MAY-13A
17-Apr-2013A
03-Jun-2013A
03-Jun-2013A
30-MAY-13A
31-MAY-13A
03-JUN-13A
31-May-2013
17-MAY-13A
20-MAY-13A
21-MAY-13A
31-May-2013
20-MAY-13A
22-MAY-13A
24-MAY-13A
31-May-2013
31-May-2013
07-MAY-13A
08-MAY-13A
31-May-2013
-29d
-29d
-29d
-29d
-29d
-37d
-28d
-28d
-28d
-36d
-30d
-30d
-30d
-22d
-22d
-2d
-2d
-28d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Column
11 Reinforcement
11 Concreting
11 Shuttering
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -5 (7-11/E-J)
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
1
A20990
A21010
A21000
3
A21050
A21060
A21070
2
A21020
A21030
A21040
Pour 34
2
A21110
A21120
A21130
3
03-Apr-2013
03-Apr-2013
06-Apr-2013
04-Apr-2013
09-Apr-2013
09-Apr-2013
12-Apr-2013
27-Apr-2013
03-Apr-2013
03-Apr-2013
05-Apr-2013
06-Apr-2013
09-Apr-2013
09-Apr-2013
09-Apr-2013
10-Apr-2013
12-Apr-2013
20-Apr-2013
17-Apr-2013
13-Apr-2013
17-Apr-2013
15-Apr-2013
29-Apr-2013
26-Apr-2013
27-Apr-2013
29-Apr-2013
17-Apr-2013
13-Apr-2013
16-Apr-2013
17-Apr-2013
03-May-2013
22-Apr-2013
18-Apr-2013
20-Apr-2013
22-Apr-2013
03-May-2013
17-Apr-2013A
17-APR-13A
19-APR-13A
18-APR-13A
24-Apr-2013A
24-APR-13A
26-APR-13A
03-MAY-13A
17-Apr-2013A
17-APR-13A
18-APR-13A
19-APR-13A
15-Apr-2013A
15-Apr-2013A
15-APR-13A
16-APR-13A
17-APR-13A
26-Apr-2013A
31-May-2013
24-APR-13A
26-APR-13A
25-APR-13A
31-May-2013
02-MAY-13A
03-MAY-13A
04-MAY-13A
31-May-2013
24-APR-13A
25-APR-13A
26-APR-13A
31-May-2013
31-May-2013
22-APR-13A
23-APR-13A
24-APR-13A
31-May-2013
-38d
-8d
-7d
-8d
-28d
-5d
-5d
-5d
-38d
-8d
-7d
-7d
-24d
-34d
-2d
-1d
-1d
-24d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
8 Second Floor Slab
9 Pour -7 (11-16/E-J)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A21150
A21160
1
A21080
A21090
FF2
Pour 36
1
A17660
A17670
A17680
2
A17690
A17700
A17710
3
A17720
A17730
20-Apr-2013
02-May-2013
09-Apr-2013
09-Apr-2013
10-Apr-2013
29-Nov-2012
05-Dec-2012
05-Dec-2012
05-Dec-2012
07-Dec-2012
08-Dec-2012
05-Dec-2012
05-Dec-2012
07-Dec-2012
08-Dec-2012
08-Dec-2012
08-Dec-2012
12-Dec-2012
02-May-2013
03-May-2013
20-Apr-2013
18-Apr-2013
20-Apr-2013
26-Dec-2012
25-Dec-2012
14-Dec-2012
11-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
12-Dec-2012
14-Dec-2012
15-Dec-2012
25-Dec-2012
22-Dec-2012
24-Dec-2012
26-APR-13A
29-APR-13A
15-Apr-2013A
15-APR-13A
16-APR-13A
19-Dec-2012A
17-Jan-2013A
17-Jan-2013A
17-JAN-13A
19-JAN-13A
21-JAN-13A
17-Jan-2013A
17-JAN-13A
19-JAN-13A
21-JAN-13A
21-Jan-2013A
21-JAN-13A
24-JAN-13A
06-MAY-13A
07-MAY-13A
31-May-2013
22-APR-13A
23-APR-13A
31-May-2013
31-May-2013
31-May-2013
21-JAN-13A
22-JAN-13A
23-JAN-13A
31-May-2013
21-JAN-13A
23-JAN-13A
24-JAN-13A
31-May-2013
30-JAN-13A
01-FEB-13A
-2d
-2d
-35d
-2d
-1d
-134d
-135d
-144d
-34d
-33d
-33d
-143d
-33d
-33d
-33d
-135d
-32d
-33d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
9 Pour -9 (3-7/D-F) Lift slab
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -4 (16-21/E-J)
10 Walls
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A17740
Pour 371
2
A21750
A21760
A21770
3
A21780
A21790
A21800
1
A21720
A21730
A21740
Pour 33
2
A17420
A17430
24-Dec-2012
29-Nov-2012
29-Nov-2012
29-Nov-2012
01-Dec-2012
04-Dec-2012
07-Dec-2012
07-Dec-2012
11-Dec-2012
22-Dec-2012
29-Nov-2012
29-Nov-2012
30-Nov-2012
03-Dec-2012
30-Nov-2012
06-Dec-2012
06-Dec-2012
07-Dec-2012
25-Dec-2012
24-Dec-2012
12-Dec-2012
08-Dec-2012
11-Dec-2012
12-Dec-2012
24-Dec-2012
21-Dec-2012
22-Dec-2012
24-Dec-2012
13-Dec-2012
08-Dec-2012
11-Dec-2012
13-Dec-2012
20-Dec-2012
14-Dec-2012
12-Dec-2012
13-Dec-2012
01-FEB-13A
04-Jan-2013A
04-Jan-2013A
04-JAN-13A
07-JAN-13A
09-JAN-13A
12-Jan-2013A
12-JAN-13A
18-JAN-13A
23-JAN-13A
04-Jan-2013A
04-JAN-13A
07-JAN-13A
09-JAN-13A
17-Jan-2013A
17-Jan-2013A
17-JAN-13A
19-JAN-13A
02-FEB-13A
31-May-2013
31-May-2013
11-JAN-13A
13-JAN-13A
14-JAN-13A
31-May-2013
21-JAN-13A
23-JAN-13A
24-JAN-13A
31-May-2013
11-JAN-13A
13-JAN-13A
14-JAN-13A
31-May-2013
31-May-2013
30-JAN-13A
31-JAN-13A
-33d
-136d
-146d
-28d
-28d
-27d
-136d
-25d
-26d
-26d
-145d
-28d
-28d
-26d
-139d
-144d
-41d
-41d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -1 (1-7/E-J)
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A17440
1
A17390
A17400
A17410
3
A17450
A17460
A17470
Pour 3
2
A17150
A17160
A17170
3
A17180
A17190
A17200
08-Dec-2012
06-Dec-2012
06-Dec-2012
06-Dec-2012
07-Dec-2012
30-Nov-2012
30-Nov-2012
04-Dec-2012
19-Dec-2012
06-Dec-2012
06-Dec-2012
06-Dec-2012
08-Dec-2012
10-Dec-2012
06-Dec-2012
06-Dec-2012
10-Dec-2012
25-Dec-2012
14-Dec-2012
13-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
20-Dec-2012
18-Dec-2012
19-Dec-2012
20-Dec-2012
26-Dec-2012
15-Dec-2012
12-Dec-2012
14-Dec-2012
15-Dec-2012
26-Dec-2012
22-Dec-2012
25-Dec-2012
26-Dec-2012
21-JAN-13A
17-Jan-2013A
17-JAN-13A
19-JAN-13A
20-JAN-13A
24-Jan-2013A
24-JAN-13A
05-FEB-13A
12-FEB-13A
19-Dec-2012A
19-Dec-2012A
19-DEC-12A
20-DEC-12A
20-DEC-12A
22-Dec-2012A
22-DEC-12A
29-DEC-12A
11-JAN-13A
01-FEB-13A
31-May-2013
30-JAN-13A
31-JAN-13A
01-FEB-13A
31-May-2013
09-FEB-13A
12-FEB-13A
13-FEB-13A
31-May-2013
31-May-2013
26-DEC-12A
26-DEC-12A
27-DEC-12A
31-May-2013
10-JAN-13A
12-JAN-13A
13-JAN-13A
-41d
-145d
-42d
-42d
-42d
-139d
-45d
-46d
-46d
-134d
-143d
-11d
-9d
-9d
-134d
-15d
-15d
-15d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -10 (16-20/D-F) Lift slab
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -2 (16-21/A-E)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
1
A17120
A17130
A17140
Pour 372
1
A21810
A21820
A21830
3
A21870
A21880
A21890
2
A21840
A21850
A21860
Pour 31
06-Dec-2012
06-Dec-2012
06-Dec-2012
08-Dec-2012
29-Nov-2012
29-Nov-2012
29-Nov-2012
30-Nov-2012
03-Dec-2012
07-Dec-2012
07-Dec-2012
11-Dec-2012
22-Dec-2012
29-Nov-2012
29-Nov-2012
01-Dec-2012
04-Dec-2012
05-Dec-2012
14-Dec-2012
10-Dec-2012
12-Dec-2012
14-Dec-2012
24-Dec-2012
13-Dec-2012
08-Dec-2012
11-Dec-2012
13-Dec-2012
24-Dec-2012
21-Dec-2012
22-Dec-2012
24-Dec-2012
12-Dec-2012
08-Dec-2012
11-Dec-2012
12-Dec-2012
26-Dec-2012
19-Dec-2012A
19-DEC-12A
20-DEC-12A
20-DEC-12A
22-Jan-2013A
22-Jan-2013A
22-JAN-13A
25-JAN-13A
27-JAN-13A
03-Feb-2013A
03-FEB-13A
06-FEB-13A
12-FEB-13A
22-Jan-2013A
22-JAN-13A
25-JAN-13A
27-JAN-13A
02-Jan-2013A
31-May-2013
26-DEC-12A
26-DEC-12A
27-DEC-12A
31-May-2013
31-May-2013
01-FEB-13A
03-FEB-13A
04-FEB-13A
31-May-2013
10-FEB-13A
12-FEB-13A
13-FEB-13A
31-May-2013
01-FEB-13A
03-FEB-13A
04-FEB-13A
31-May-2013
-144d
-13d
-11d
-10d
-136d
-145d
-46d
-46d
-44d
-136d
-43d
-43d
-43d
-146d
-46d
-46d
-45d
-134d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A17270
A17280
A17290
2
A17240
A17250
A17260
1
A17210
A17220
A17230
Pour 34
2
A17510
A17520
A17530
1
05-Dec-2012
05-Dec-2012
07-Dec-2012
25-Dec-2012
06-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
06-Dec-2012
06-Dec-2012
07-Dec-2012
10-Dec-2012
06-Dec-2012
06-Dec-2012
06-Dec-2012
08-Dec-2012
10-Dec-2012
06-Dec-2012
26-Dec-2012
21-Dec-2012
24-Dec-2012
26-Dec-2012
14-Dec-2012
11-Dec-2012
13-Dec-2012
14-Dec-2012
13-Dec-2012
08-Dec-2012
11-Dec-2012
13-Dec-2012
26-Dec-2012
15-Dec-2012
12-Dec-2012
14-Dec-2012
15-Dec-2012
15-Dec-2012
06-Jan-2013A
06-JAN-13A
12-JAN-13A
27-JAN-13A
02-Jan-2013A
02-JAN-13A
03-JAN-13A
04-JAN-13A
02-Jan-2013A
02-JAN-13A
03-JAN-13A
04-JAN-13A
01-Jan-2013A
01-Jan-2013A
01-JAN-13A
02-JAN-13A
03-JAN-13A
01-Jan-2013A
31-May-2013
15-JAN-13A
25-JAN-13A
27-JAN-13A
31-May-2013
06-JAN-13A
07-JAN-13A
08-JAN-13A
31-May-2013
06-JAN-13A
07-JAN-13A
08-JAN-13A
31-May-2013
31-May-2013
07-JAN-13A
08-JAN-13A
08-JAN-13A
31-May-2013
-134d
-20d
-27d
-27d
-144d
-22d
-20d
-20d
-145d
-24d
-22d
-21d
-134d
-143d
-21d
-20d
-19d
-143d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -8 (11-16/A-E)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A17480
A17490
A17500
3
A17540
A17550
A17560
Pour 37
1
A17750
A17760
A17770
2
A17780
A17790
A17800
3
A17820
06-Dec-2012
08-Dec-2012
11-Dec-2012
10-Dec-2012
10-Dec-2012
13-Dec-2012
25-Dec-2012
06-Dec-2012
06-Dec-2012
06-Dec-2012
08-Dec-2012
11-Dec-2012
06-Dec-2012
06-Dec-2012
08-Dec-2012
10-Dec-2012
10-Dec-2012
13-Dec-2012
11-Dec-2012
13-Dec-2012
15-Dec-2012
26-Dec-2012
24-Dec-2012
25-Dec-2012
26-Dec-2012
26-Dec-2012
17-Dec-2012
12-Dec-2012
14-Dec-2012
17-Dec-2012
17-Dec-2012
13-Dec-2012
15-Dec-2012
17-Dec-2012
26-Dec-2012
25-Dec-2012
01-JAN-13A
02-JAN-13A
03-JAN-13A
07-Jan-2013A
07-JAN-13A
15-JAN-13A
24-JAN-13A
12-Jan-2013A
13-Jan-2013A
13-JAN-13A
16-JAN-13A
17-JAN-13A
12-Jan-2013A
12-JAN-13A
16-JAN-13A
17-JAN-13A
18-Jan-2013A
21-JAN-13A
07-JAN-13A
08-JAN-13A
08-JAN-13A
31-May-2013
21-JAN-13A
24-JAN-13A
25-JAN-13A
31-May-2013
31-May-2013
20-JAN-13A
21-JAN-13A
21-JAN-13A
31-May-2013
20-JAN-13A
21-JAN-13A
21-JAN-13A
31-May-2013
28-JAN-13A
-22d
-21d
-19d
-134d
-23d
-25d
-25d
-134d
-142d
-33d
-31d
-29d
-142d
-32d
-30d
-29d
-134d
-28d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
11 Shuttering
9 Pour -3 (1-7/A-E)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -6 (7-11/A-E)
10 Column
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A17830
A17810
Pour 32
1
A17300
A17310
A17320
3
A17360
A17370
A17380
2
A17330
A17340
A17350
Pour 35
1
A17570
25-Dec-2012
10-Dec-2012
05-Dec-2012
05-Dec-2012
05-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
08-Dec-2012
12-Dec-2012
20-Dec-2012
05-Dec-2012
05-Dec-2012
07-Dec-2012
08-Dec-2012
06-Dec-2012
06-Dec-2012
06-Dec-2012
26-Dec-2012
24-Dec-2012
21-Dec-2012
13-Dec-2012
10-Dec-2012
12-Dec-2012
13-Dec-2012
21-Dec-2012
19-Dec-2012
20-Dec-2012
21-Dec-2012
14-Dec-2012
11-Dec-2012
13-Dec-2012
14-Dec-2012
26-Dec-2012
14-Dec-2012
11-Dec-2012
28-JAN-13A
18-JAN-13A
01-Jan-2013A
01-Jan-2013A
01-JAN-13A
02-JAN-13A
03-JAN-13A
06-Jan-2013A
06-JAN-13A
11-JAN-13A
23-JAN-13A
01-Jan-2013A
01-JAN-13A
01-JAN-13A
06-JAN-13A
06-Jan-2013A
06-Jan-2013A
06-JAN-13A
29-JAN-13A
26-JAN-13A
31-May-2013
31-May-2013
06-JAN-13A
07-JAN-13A
08-JAN-13A
31-May-2013
15-JAN-13A
23-JAN-13A
24-JAN-13A
31-May-2013
06-JAN-13A
07-JAN-13A
12-JAN-13A
31-May-2013
31-May-2013
09-JAN-13A
-28d
-28d
-138d
-145d
-23d
-21d
-21d
-138d
-22d
-28d
-28d
-144d
-22d
-20d
-24d
-134d
-144d
-24d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
8 Fourth Floor Slab
9 Pour -2 (16-21/A-E)
10 Walls
11 Concreting
11 Reinforcement
11 Shuttering
10 Column
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A17580
A17590
3
A17630
A17640
A17650
2
A17600
A17610
A17620
FF4
Pour 31
2
A18700
A18680
A18690
1
A18650
06-Dec-2012
08-Dec-2012
10-Dec-2012
10-Dec-2012
13-Dec-2012
25-Dec-2012
06-Dec-2012
06-Dec-2012
06-Dec-2012
07-Dec-2012
12-Jan-2013
22-Jan-2013
22-Jan-2013
25-Jan-2013
22-Jan-2013
24-Jan-2013
22-Jan-2013
22-Jan-2013
12-Dec-2012
14-Dec-2012
26-Dec-2012
22-Dec-2012
25-Dec-2012
26-Dec-2012
15-Dec-2012
12-Dec-2012
14-Dec-2012
15-Dec-2012
16-Feb-2013
16-Feb-2013
02-Feb-2013
02-Feb-2013
30-Jan-2013
01-Feb-2013
04-Feb-2013
30-Jan-2013
07-JAN-13A
08-JAN-13A
10-Jan-2013A
10-JAN-13A
16-JAN-13A
24-JAN-13A
06-Jan-2013A
06-JAN-13A
07-JAN-13A
08-JAN-13A
12-Jan-2013A
21-Feb-2013A
22-Feb-2013A
25-FEB-13A
22-FEB-13A
25-FEB-13A
21-Feb-2013A
21-FEB-13A
09-JAN-13A
11-JAN-13A
31-May-2013
21-JAN-13A
24-JAN-13A
25-JAN-13A
31-May-2013
09-JAN-13A
09-JAN-13A
11-JAN-13A
31-May-2013
31-May-2013
31-May-2013
07-MAR-13A
04-MAR-13A
06-MAR-13A
31-May-2013
04-MAR-13A
-23d
-23d
-134d
-24d
-25d
-25d
-143d
-23d
-21d
-22d
-89d
-89d
-101d
-27d
-27d
-27d
-100d
-27d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -3 (1-7/A-E)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A18660
A18670
3
A18710
A18720
A18730
Pour 32
3
A18800
A18810
A18820
2
A18770
A18780
A18790
1
A18740
A18750
24-Jan-2013
26-Jan-2013
26-Jan-2013
26-Jan-2013
30-Jan-2013
15-Feb-2013
12-Jan-2013
15-Jan-2013
15-Jan-2013
19-Jan-2013
02-Feb-2013
12-Jan-2013
12-Jan-2013
15-Jan-2013
16-Jan-2013
12-Jan-2013
12-Jan-2013
15-Jan-2013
01-Feb-2013
04-Feb-2013
16-Feb-2013
12-Feb-2013
15-Feb-2013
16-Feb-2013
04-Feb-2013
04-Feb-2013
31-Jan-2013
02-Feb-2013
04-Feb-2013
24-Jan-2013
21-Jan-2013
23-Jan-2013
24-Jan-2013
24-Jan-2013
21-Jan-2013
23-Jan-2013
22-FEB-13A
24-FEB-13A
05-Mar-2013A
05-MAR-13A
08-MAR-13A
12-MAR-13A
12-Jan-2013A
15-Jan-2013A
15-JAN-13A
19-FEB-13A
27-FEB-13A
12-Jan-2013A
12-JAN-13A
15-JAN-13A
16-JAN-13A
12-Jan-2013A
12-JAN-13A
15-JAN-13A
06-MAR-13A
07-MAR-13A
31-May-2013
11-MAR-13A
12-MAR-13A
13-MAR-13A
31-May-2013
31-May-2013
24-FEB-13A
27-FEB-13A
28-FEB-13A
31-May-2013
13-FEB-13A
15-FEB-13A
16-FEB-13A
31-May-2013
13-FEB-13A
14-FEB-13A
-27d
-26d
-89d
-22d
-20d
-20d
-100d
-100d
-20d
-20d
-20d
-109d
-19d
-19d
-19d
-109d
-19d
-18d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
9 Pour -5 (7-11/E-J)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -1 (1-7/E-J)
10 Column
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A18760
Pour 34
3
A18980
A18990
A19000
1
A18920
A18930
A18940
2
A18950
A18960
A18970
Pour 3
1
A18560
A18570
16-Jan-2013
22-Jan-2013
29-Jan-2013
29-Jan-2013
01-Feb-2013
13-Feb-2013
22-Jan-2013
22-Jan-2013
24-Jan-2013
26-Jan-2013
22-Jan-2013
22-Jan-2013
24-Jan-2013
25-Jan-2013
22-Jan-2013
22-Jan-2013
22-Jan-2013
24-Jan-2013
24-Jan-2013
14-Feb-2013
14-Feb-2013
12-Feb-2013
13-Feb-2013
14-Feb-2013
04-Feb-2013
30-Jan-2013
01-Feb-2013
04-Feb-2013
02-Feb-2013
30-Jan-2013
01-Feb-2013
02-Feb-2013
13-Feb-2013
04-Feb-2013
30-Jan-2013
01-Feb-2013
16-JAN-13A
22-Jan-2013A
20-Feb-2013A
20-FEB-13A
24-FEB-13A
02-MAR-13A
22-Jan-2013A
22-JAN-13A
24-JAN-13A
26-JAN-13A
22-Jan-2013A
22-JAN-13A
24-JAN-13A
25-JAN-13A
22-Jan-2013A
22-Jan-2013A
22-JAN-13A
24-JAN-13A
15-FEB-13A
31-May-2013
31-May-2013
26-FEB-13A
02-MAR-13A
03-MAR-13A
31-May-2013
19-FEB-13A
21-FEB-13A
22-FEB-13A
31-May-2013
19-FEB-13A
21-FEB-13A
22-FEB-13A
31-May-2013
31-May-2013
07-FEB-13A
08-FEB-13A
-18d
-91d
-91d
-11d
-14d
-14d
-100d
-16d
-16d
-15d
-101d
-16d
-16d
-16d
-92d
-100d
-6d
-5d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -6 (7-11/A-E)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A18580
3
A18620
A18630
A18640
2
A18590
A18600
A18610
Pour 35
3
A19070
A19080
A19090
1
A19010
A19020
A19030
26-Jan-2013
24-Jan-2013
24-Jan-2013
28-Jan-2013
12-Feb-2013
22-Jan-2013
22-Jan-2013
24-Jan-2013
25-Jan-2013
22-Jan-2013
30-Jan-2013
30-Jan-2013
02-Feb-2013
14-Feb-2013
22-Jan-2013
22-Jan-2013
23-Jan-2013
25-Jan-2013
04-Feb-2013
13-Feb-2013
09-Feb-2013
12-Feb-2013
13-Feb-2013
02-Feb-2013
30-Jan-2013
01-Feb-2013
02-Feb-2013
15-Feb-2013
15-Feb-2013
12-Feb-2013
14-Feb-2013
15-Feb-2013
04-Feb-2013
31-Jan-2013
01-Feb-2013
04-Feb-2013
26-JAN-13A
28-Jan-2013A
07-FEB-13A
28-JAN-13A
12-FEB-13A
22-Jan-2013A
22-JAN-13A
24-JAN-13A
25-JAN-13A
22-Jan-2013A
30-Jan-2013A
30-JAN-13A
20-FEB-13A
26-FEB-13A
22-Jan-2013A
22-JAN-13A
23-JAN-13A
25-JAN-13A
08-FEB-13A
31-May-2013
16-FEB-13A
22-FEB-13A
23-FEB-13A
31-May-2013
09-FEB-13A
11-FEB-13A
12-FEB-13A
31-May-2013
31-May-2013
22-FEB-13A
26-FEB-13A
27-FEB-13A
31-May-2013
16-FEB-13A
17-FEB-13A
18-FEB-13A
-3d
-92d
-5d
-8d
-8d
-101d
-8d
-7d
-7d
-90d
-90d
-8d
-9d
-9d
-100d
-13d
-13d
-11d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -10 (16-20/D-F) Lift slab
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -7 (11-16/E-J)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
2
A19040
A19050
A19060
Pour 372
1
A22170
A22180
A22190
3
A22230
A22240
A22250
2
A22200
A22210
A22220
Pour 36
22-Jan-2013
22-Jan-2013
23-Jan-2013
25-Jan-2013
19-Jan-2013
19-Jan-2013
19-Jan-2013
21-Jan-2013
23-Jan-2013
28-Jan-2013
28-Jan-2013
31-Jan-2013
12-Feb-2013
19-Jan-2013
19-Jan-2013
22-Jan-2013
24-Jan-2013
19-Jan-2013
02-Feb-2013
30-Jan-2013
01-Feb-2013
02-Feb-2013
13-Feb-2013
02-Feb-2013
29-Jan-2013
31-Jan-2013
02-Feb-2013
13-Feb-2013
11-Feb-2013
12-Feb-2013
13-Feb-2013
01-Feb-2013
29-Jan-2013
31-Jan-2013
01-Feb-2013
12-Feb-2013
22-Jan-2013A
22-JAN-13A
23-JAN-13A
25-JAN-13A
26-Feb-2013A
26-Feb-2013A
26-FEB-13A
28-FEB-13A
01-MAR-13A
12-Mar-2013A
12-MAR-13A
17-MAR-13A
21-MAR-13A
27-Feb-2013A
27-FEB-13A
02-MAR-13A
05-MAR-13A
19-Jan-2013A
31-May-2013
16-FEB-13A
17-FEB-13A
18-FEB-13A
31-May-2013
31-May-2013
06-MAR-13A
13-MAR-13A
14-MAR-13A
31-May-2013
18-MAR-13A
21-MAR-13A
22-MAR-13A
31-May-2013
12-MAR-13A
16-MAR-13A
18-MAR-13A
31-May-2013
-101d
-14d
-13d
-12d
-92d
-101d
-30d
-34d
-33d
-92d
-29d
-31d
-32d
-102d
-35d
-37d
-37d
-93d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -4 (16-21/E-J)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
2
A19130
A19140
A19150
3
A19160
A19170
A19180
1
A19100
A19110
A19120
Pour 33
1
A18830
A18840
A18850
2
19-Jan-2013
19-Jan-2013
22-Jan-2013
24-Jan-2013
26-Jan-2013
26-Jan-2013
30-Jan-2013
11-Feb-2013
19-Jan-2013
19-Jan-2013
21-Jan-2013
22-Jan-2013
16-Jan-2013
16-Jan-2013
16-Jan-2013
17-Jan-2013
19-Jan-2013
16-Jan-2013
01-Feb-2013
29-Jan-2013
31-Jan-2013
01-Feb-2013
12-Feb-2013
09-Feb-2013
11-Feb-2013
12-Feb-2013
01-Feb-2013
29-Jan-2013
31-Jan-2013
01-Feb-2013
08-Feb-2013
28-Jan-2013
24-Jan-2013
25-Jan-2013
28-Jan-2013
28-Jan-2013
19-Jan-2013A
19-JAN-13A
22-JAN-13A
24-JAN-13A
21-Feb-2013A
21-FEB-13A
26-FEB-13A
04-MAR-13A
19-Jan-2013A
19-JAN-13A
21-JAN-13A
22-JAN-13A
03-Mar-2013A
03-Mar-2013A
03-MAR-13A
05-MAR-13A
06-MAR-13A
03-Mar-2013A
31-May-2013
20-FEB-13A
21-FEB-13A
22-FEB-13A
31-May-2013
27-FEB-13A
03-MAR-13A
04-MAR-13A
31-May-2013
20-FEB-13A
21-FEB-13A
22-FEB-13A
31-May-2013
31-May-2013
06-MAR-13A
08-MAR-13A
14-MAR-13A
31-May-2013
-102d
-18d
-17d
-17d
-93d
-14d
-17d
-16d
-102d
-18d
-17d
-17d
-96d
-106d
-34d
-35d
-38d
-106d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -8 (11-16/A-E)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A18860
A18870
A18880
3
A18890
A18900
A18910
Pour 37
3
A19250
A19260
A19270
1
A19190
A19200
A19210
2
A19220
16-Jan-2013
18-Jan-2013
19-Jan-2013
19-Jan-2013
19-Jan-2013
23-Jan-2013
07-Feb-2013
22-Jan-2013
30-Jan-2013
30-Jan-2013
02-Feb-2013
14-Feb-2013
22-Jan-2013
22-Jan-2013
23-Jan-2013
25-Jan-2013
22-Jan-2013
22-Jan-2013
24-Jan-2013
26-Jan-2013
28-Jan-2013
08-Feb-2013
06-Feb-2013
07-Feb-2013
08-Feb-2013
15-Feb-2013
15-Feb-2013
13-Feb-2013
14-Feb-2013
15-Feb-2013
05-Feb-2013
31-Jan-2013
02-Feb-2013
05-Feb-2013
04-Feb-2013
31-Jan-2013
03-MAR-13A
05-MAR-13A
07-MAR-13A
07-Mar-2013A
07-MAR-13A
12-MAR-13A
20-MAR-13A
26-Feb-2013A
05-Mar-2013A
05-MAR-13A
08-MAR-13A
13-MAR-13A
26-Feb-2013A
26-FEB-13A
28-FEB-13A
01-MAR-13A
27-Feb-2013A
27-FEB-13A
06-MAR-13A
08-MAR-13A
15-MAR-13A
31-May-2013
15-MAR-13A
20-MAR-13A
21-MAR-13A
31-May-2013
31-May-2013
09-MAR-13A
13-MAR-13A
14-MAR-13A
31-May-2013
04-MAR-13A
05-MAR-13A
06-MAR-13A
31-May-2013
04-MAR-13A
-34d
-34d
-39d
-96d
-31d
-34d
-34d
-90d
-90d
-20d
-22d
-22d
-99d
-26d
-25d
-24d
-100d
-26d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Concreting
9 Pour -9 (3-7/D-F) Lift slab
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
8 Third Floor Slab
9 Pour -8 (11-16/A-E)
10 Walls
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A19230
A19240
Pour 371
1
A22080
A22090
A22100
3
A22140
A22150
A22160
2
A22110
A22120
A22130
FF3
Pour 37
2
24-Jan-2013
26-Jan-2013
19-Jan-2013
19-Jan-2013
19-Jan-2013
21-Jan-2013
23-Jan-2013
28-Jan-2013
28-Jan-2013
31-Jan-2013
12-Feb-2013
19-Jan-2013
19-Jan-2013
22-Jan-2013
24-Jan-2013
19-Dec-2012
27-Dec-2012
27-Dec-2012
02-Feb-2013
04-Feb-2013
13-Feb-2013
02-Feb-2013
29-Jan-2013
31-Jan-2013
02-Feb-2013
13-Feb-2013
11-Feb-2013
12-Feb-2013
13-Feb-2013
01-Feb-2013
29-Jan-2013
31-Jan-2013
01-Feb-2013
21-Jan-2013
21-Jan-2013
09-Jan-2013
28-FEB-13A
02-MAR-13A
10-Feb-2013A
10-Feb-2013A
10-FEB-13A
12-FEB-13A
15-FEB-13A
20-Feb-2013A
20-FEB-13A
25-FEB-13A
03-MAR-13A
12-Feb-2013A
12-FEB-13A
14-FEB-13A
20-FEB-13A
14-Jan-2013A
30-Jan-2013A
31-Jan-2013A
06-MAR-13A
07-MAR-13A
31-May-2013
31-May-2013
15-FEB-13A
17-FEB-13A
20-FEB-13A
31-May-2013
26-FEB-13A
02-MAR-13A
03-MAR-13A
31-May-2013
18-FEB-13A
21-FEB-13A
22-FEB-13A
31-May-2013
31-May-2013
31-May-2013
-26d
-26d
-92d
-101d
-14d
-14d
-14d
-92d
-12d
-15d
-15d
-102d
-16d
-17d
-17d
-112d
-112d
-122d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -2 (16-21/A-E)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A18500
A18510
A18520
3
A18530
A18540
A18550
1
A18470
A18480
A18490
Pour 31
3
A17990
A18000
A18010
2
A17960
27-Dec-2012
29-Dec-2012
01-Jan-2013
04-Jan-2013
04-Jan-2013
08-Jan-2013
19-Jan-2013
27-Dec-2012
27-Dec-2012
28-Dec-2012
31-Dec-2012
27-Dec-2012
01-Jan-2013
01-Jan-2013
05-Jan-2013
19-Jan-2013
27-Dec-2012
27-Dec-2012
05-Jan-2013
08-Jan-2013
09-Jan-2013
21-Jan-2013
18-Jan-2013
19-Jan-2013
21-Jan-2013
10-Jan-2013
05-Jan-2013
08-Jan-2013
10-Jan-2013
21-Jan-2013
21-Jan-2013
17-Jan-2013
19-Jan-2013
21-Jan-2013
12-Jan-2013
09-Jan-2013
31-JAN-13A
01-FEB-13A
02-FEB-13A
03-Feb-2013A
03-FEB-13A
09-FEB-13A
24-FEB-13A
30-Jan-2013A
30-JAN-13A
01-FEB-13A
02-FEB-13A
27-Jan-2013A
02-Feb-2013A
02-FEB-13A
10-FEB-13A
19-FEB-13A
27-Jan-2013A
27-JAN-13A
03-FEB-13A
04-FEB-13A
05-FEB-13A
31-May-2013
11-FEB-13A
23-FEB-13A
25-FEB-13A
31-May-2013
03-FEB-13A
04-FEB-13A
05-FEB-13A
31-May-2013
31-May-2013
11-FEB-13A
19-FEB-13A
20-FEB-13A
31-May-2013
03-FEB-13A
-24d
-22d
-22d
-112d
-19d
-29d
-29d
-121d
-24d
-22d
-21d
-112d
-112d
-20d
-25d
-25d
-119d
-21d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -3 (1-7/A-E)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A17970
A17980
1
A17930
A17940
A17950
Pour 32
1
A18020
A18030
A18040
3
A18080
A18090
A18100
2
A18050
A18060
29-Dec-2012
31-Dec-2012
27-Dec-2012
27-Dec-2012
27-Dec-2012
29-Dec-2012
19-Dec-2012
19-Dec-2012
22-Dec-2012
19-Dec-2012
20-Dec-2012
22-Dec-2012
22-Dec-2012
27-Dec-2012
10-Jan-2013
19-Dec-2012
22-Dec-2012
19-Dec-2012
11-Jan-2013
12-Jan-2013
12-Jan-2013
09-Jan-2013
10-Jan-2013
12-Jan-2013
11-Jan-2013
03-Jan-2013
31-Dec-2012
02-Jan-2013
03-Jan-2013
11-Jan-2013
08-Jan-2013
10-Jan-2013
11-Jan-2013
03-Jan-2013
31-Dec-2012
02-Jan-2013
29-JAN-13A
31-JAN-13A
27-Jan-2013A
27-JAN-13A
28-JAN-13A
30-JAN-13A
24-Jan-2013A
24-Jan-2013A
24-JAN-13A
25-JAN-13A
25-JAN-13A
29-Jan-2013A
29-JAN-13A
03-FEB-13A
10-FEB-13A
24-Jan-2013A
24-JAN-13A
25-JAN-13A
04-FEB-13A
05-FEB-13A
31-May-2013
03-FEB-13A
03-FEB-13A
04-FEB-13A
31-May-2013
31-May-2013
30-JAN-13A
31-JAN-13A
01-FEB-13A
31-May-2013
04-FEB-13A
09-FEB-13A
11-FEB-13A
31-May-2013
30-JAN-13A
31-JAN-13A
-19d
-19d
-119d
-21d
-20d
-18d
-120d
-127d
-25d
-24d
-24d
-120d
-22d
-25d
-25d
-127d
-25d
-24d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
9 Pour -4 (16-21/E-J)
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -6 (7-11/A-E)
10 Walls
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A18070
Pour 33
2
A18140
A18150
A18160
1
A18110
A18120
A18130
3
A18170
A18180
A18190
Pour 35
2
A18320
A18330
21-Dec-2012
21-Dec-2012
21-Dec-2012
21-Dec-2012
25-Dec-2012
27-Dec-2012
21-Dec-2012
21-Dec-2012
22-Dec-2012
25-Dec-2012
27-Dec-2012
27-Dec-2012
31-Dec-2012
14-Jan-2013
27-Dec-2012
27-Dec-2012
27-Dec-2012
28-Dec-2012
03-Jan-2013
15-Jan-2013
08-Jan-2013
04-Jan-2013
07-Jan-2013
08-Jan-2013
08-Jan-2013
04-Jan-2013
05-Jan-2013
08-Jan-2013
15-Jan-2013
12-Jan-2013
14-Jan-2013
15-Jan-2013
21-Jan-2013
08-Jan-2013
04-Jan-2013
07-Jan-2013
26-JAN-13A
13-Feb-2013A
13-Feb-2013A
13-FEB-13A
14-FEB-13A
15-FEB-13A
13-Feb-2013A
13-FEB-13A
14-FEB-13A
15-FEB-13A
18-Feb-2013A
18-FEB-13A
22-FEB-13A
01-MAR-13A
26-Jan-2013A
27-Jan-2013A
27-JAN-13A
28-JAN-13A
01-FEB-13A
31-May-2013
31-May-2013
16-FEB-13A
18-FEB-13A
19-FEB-13A
31-May-2013
18-FEB-13A
20-FEB-13A
20-FEB-13A
31-May-2013
25-FEB-13A
01-MAR-13A
02-MAR-13A
31-May-2013
31-May-2013
31-JAN-13A
01-FEB-13A
-24d
-117d
-123d
-36d
-35d
-35d
-123d
-37d
-38d
-36d
-117d
-36d
-39d
-39d
-112d
-123d
-22d
-21d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -7 (11-16/E-J)
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A18340
1
A18290
A18300
A18310
3
A18350
A18360
A18370
Pour 36
1
A18380
A18390
A18400
2
A18410
A18420
A18430
31-Dec-2012
27-Dec-2012
27-Dec-2012
28-Dec-2012
31-Dec-2012
04-Jan-2013
04-Jan-2013
08-Jan-2013
19-Jan-2013
26-Dec-2012
26-Dec-2012
26-Dec-2012
27-Dec-2012
28-Dec-2012
26-Dec-2012
26-Dec-2012
28-Dec-2012
31-Dec-2012
08-Jan-2013
09-Jan-2013
05-Jan-2013
07-Jan-2013
09-Jan-2013
21-Jan-2013
17-Jan-2013
19-Jan-2013
21-Jan-2013
18-Jan-2013
08-Jan-2013
04-Jan-2013
07-Jan-2013
08-Jan-2013
08-Jan-2013
04-Jan-2013
07-Jan-2013
08-Jan-2013
29-JAN-13A
26-Jan-2013A
26-JAN-13A
27-JAN-13A
28-JAN-13A
31-Jan-2013A
31-JAN-13A
05-FEB-13A
09-FEB-13A
02-Feb-2013A
02-Feb-2013A
02-FEB-13A
02-FEB-13A
03-FEB-13A
02-Feb-2013A
02-FEB-13A
03-FEB-13A
04-FEB-13A
02-FEB-13A
31-May-2013
31-JAN-13A
01-FEB-13A
02-FEB-13A
31-May-2013
07-FEB-13A
09-FEB-13A
10-FEB-13A
31-May-2013
31-May-2013
05-FEB-13A
06-FEB-13A
06-FEB-13A
31-May-2013
05-FEB-13A
06-FEB-13A
06-FEB-13A
-21d
-122d
-21d
-21d
-20d
-112d
-17d
-17d
-17d
-114d
-123d
-26d
-25d
-24d
-123d
-26d
-25d
-24d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A18440
A18450
A18460
Pour 3
2
A17870
A17880
A17890
3
A17900
A17910
A17920
1
A17840
A17850
A17860
Pour 34
02-Jan-2013
02-Jan-2013
05-Jan-2013
17-Jan-2013
27-Dec-2012
27-Dec-2012
27-Dec-2012
29-Dec-2012
31-Dec-2012
09-Jan-2013
09-Jan-2013
09-Jan-2013
19-Jan-2013
27-Dec-2012
27-Dec-2012
29-Dec-2012
01-Jan-2013
27-Dec-2012
18-Jan-2013
16-Jan-2013
17-Jan-2013
18-Jan-2013
21-Jan-2013
08-Jan-2013
04-Jan-2013
07-Jan-2013
08-Jan-2013
21-Jan-2013
17-Jan-2013
19-Jan-2013
21-Jan-2013
09-Jan-2013
04-Jan-2013
07-Jan-2013
09-Jan-2013
21-Jan-2013
05-Feb-2013A
05-FEB-13A
10-FEB-13A
16-FEB-13A
14-Jan-2013A
14-Jan-2013A
14-JAN-13A
16-JAN-13A
17-JAN-13A
21-Jan-2013A
21-JAN-13A
24-JAN-13A
03-FEB-13A
14-Jan-2013A
14-JAN-13A
16-JAN-13A
17-JAN-13A
26-Jan-2013A
31-May-2013
12-FEB-13A
16-FEB-13A
17-FEB-13A
31-May-2013
31-May-2013
20-JAN-13A
21-JAN-13A
22-JAN-13A
31-May-2013
31-JAN-13A
02-FEB-13A
04-FEB-13A
31-May-2013
20-JAN-13A
21-JAN-13A
22-JAN-13A
31-May-2013
-114d
-22d
-25d
-25d
-112d
-123d
-13d
-11d
-11d
-112d
-11d
-11d
-11d
-122d
-13d
-11d
-10d
-112d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -9 (3-7/D-F) Lift slab
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
2
A18230
A18240
A18250
1
A18200
A18210
A18220
3
A18260
A18270
A18280
Pour 371
1
A21900
A21910
A21920
2
27-Dec-2012
27-Dec-2012
28-Dec-2012
31-Dec-2012
27-Dec-2012
27-Dec-2012
28-Dec-2012
31-Dec-2012
04-Jan-2013
04-Jan-2013
08-Jan-2013
19-Jan-2013
25-Dec-2012
25-Dec-2012
25-Dec-2012
26-Dec-2012
28-Dec-2012
25-Dec-2012
09-Jan-2013
05-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
05-Jan-2013
08-Jan-2013
10-Jan-2013
21-Jan-2013
18-Jan-2013
19-Jan-2013
21-Jan-2013
18-Jan-2013
08-Jan-2013
03-Jan-2013
05-Jan-2013
08-Jan-2013
07-Jan-2013
27-Jan-2013A
27-JAN-13A
28-JAN-13A
29-JAN-13A
26-Jan-2013A
26-JAN-13A
27-JAN-13A
28-JAN-13A
30-Jan-2013A
30-JAN-13A
07-FEB-13A
12-FEB-13A
26-Jan-2013A
26-Jan-2013A
26-JAN-13A
28-JAN-13A
29-JAN-13A
26-Jan-2013A
31-May-2013
01-FEB-13A
02-FEB-13A
02-FEB-13A
31-May-2013
01-FEB-13A
02-FEB-13A
02-FEB-13A
31-May-2013
10-FEB-13A
12-FEB-13A
13-FEB-13A
31-May-2013
31-May-2013
01-FEB-13A
02-FEB-13A
03-FEB-13A
31-May-2013
-122d
-22d
-21d
-20d
-121d
-22d
-21d
-19d
-112d
-19d
-19d
-19d
-114d
-123d
-24d
-23d
-22d
-124d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -10 (16-20/D-F) Lift slab
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A21930
A21940
A21950
3
A21960
A21970
A21980
Pour 372
2
A22020
A22030
A22040
3
A22050
A22060
A22070
1
A21990
25-Dec-2012
27-Dec-2012
29-Dec-2012
02-Jan-2013
02-Jan-2013
05-Jan-2013
17-Jan-2013
25-Dec-2012
25-Dec-2012
25-Dec-2012
27-Dec-2012
29-Dec-2012
02-Jan-2013
02-Jan-2013
05-Jan-2013
17-Jan-2013
25-Dec-2012
25-Dec-2012
03-Jan-2013
05-Jan-2013
07-Jan-2013
18-Jan-2013
16-Jan-2013
17-Jan-2013
18-Jan-2013
18-Jan-2013
07-Jan-2013
03-Jan-2013
05-Jan-2013
07-Jan-2013
18-Jan-2013
16-Jan-2013
17-Jan-2013
18-Jan-2013
08-Jan-2013
03-Jan-2013
26-JAN-13A
28-JAN-13A
29-JAN-13A
02-Feb-2013A
02-FEB-13A
05-FEB-13A
10-FEB-13A
08-Feb-2013A
08-Feb-2013A
08-FEB-13A
10-FEB-13A
12-FEB-13A
16-Feb-2013A
16-FEB-13A
19-FEB-13A
24-FEB-13A
08-Feb-2013A
08-FEB-13A
01-FEB-13A
02-FEB-13A
03-FEB-13A
31-May-2013
08-FEB-13A
10-FEB-13A
11-FEB-13A
31-May-2013
31-May-2013
14-FEB-13A
16-FEB-13A
17-FEB-13A
31-May-2013
22-FEB-13A
24-FEB-13A
25-FEB-13A
31-May-2013
14-FEB-13A
-24d
-23d
-23d
-114d
-19d
-20d
-19d
-114d
-124d
-35d
-35d
-35d
-114d
-31d
-32d
-31d
-123d
-35d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Concreting
8 Sixth Floor Slab
9 Pour -9 (3-7/D-F) Lift slab
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Column
11 Reinforcement
9 Pour -4 (16-21/E-J)
10 Column
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A22000
A22010
FF6
Pour 371
3
A22500
A22510
A22520
2
A22470
A22480
A22490
1
A22440
Pour 33
1
A20270
A20280
26-Dec-2012
28-Dec-2012
02-Mar-2013
12-Mar-2013
20-Mar-2013
20-Mar-2013
23-Mar-2013
04-Apr-2013
12-Mar-2013
12-Mar-2013
14-Mar-2013
16-Mar-2013
12-Mar-2013
12-Mar-2013
08-Mar-2013
08-Mar-2013
08-Mar-2013
09-Mar-2013
05-Jan-2013
08-Jan-2013
09-Apr-2013
05-Apr-2013
05-Apr-2013
03-Apr-2013
04-Apr-2013
05-Apr-2013
25-Mar-2013
21-Mar-2013
23-Mar-2013
25-Mar-2013
21-Mar-2013
21-Mar-2013
02-Apr-2013
21-Mar-2013
18-Mar-2013
19-Mar-2013
10-FEB-13A
12-FEB-13A
20-Mar-2013A
22-Mar-2013A
02-Apr-2013A
02-APR-13A
05-APR-13A
08-APR-13A
23-Mar-2013A
23-MAR-13A
26-MAR-13A
28-MAR-13A
22-Mar-2013A
22-MAR-13A
04-Apr-2013A
04-Apr-2013A
04-APR-13A
05-APR-13A
16-FEB-13A
17-FEB-13A
31-May-2013
31-May-2013
31-May-2013
06-APR-13A
08-APR-13A
09-APR-13A
31-May-2013
31-MAR-13A
02-APR-13A
03-APR-13A
31-May-2013
23-MAR-13A
31-May-2013
31-May-2013
08-APR-13A
09-APR-13A
-35d
-34d
-45d
-48d
-48d
-2d
-2d
-2d
-58d
-8d
-7d
-7d
-61d
-1d
-51d
-61d
-17d
-17d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
10 Walls
11 Concreting
11 Reinforcement
11 Shuttering
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -5 (7-11/E-J)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
10 Walls
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A20290
2
A20320
A20300
A20310
3
A20330
A20340
A20350
Pour 34
3
A20420
A20430
A20440
1
A20360
A20370
2
12-Mar-2013
08-Mar-2013
12-Mar-2013
08-Mar-2013
11-Mar-2013
13-Mar-2013
13-Mar-2013
16-Mar-2013
01-Apr-2013
14-Mar-2013
22-Mar-2013
22-Mar-2013
26-Mar-2013
06-Apr-2013
14-Mar-2013
14-Mar-2013
15-Mar-2013
14-Mar-2013
21-Mar-2013
21-Mar-2013
21-Mar-2013
18-Mar-2013
20-Mar-2013
02-Apr-2013
30-Mar-2013
01-Apr-2013
02-Apr-2013
08-Apr-2013
08-Apr-2013
05-Apr-2013
06-Apr-2013
08-Apr-2013
26-Mar-2013
23-Mar-2013
26-Mar-2013
27-Mar-2013
05-APR-13A
05-Apr-2013A
07-APR-13A
05-APR-13A
06-APR-13A
09-Apr-2013A
09-APR-13A
12-APR-13A
15-APR-13A
23-Mar-2013A
28-Mar-2013A
28-MAR-13A
08-APR-13A
13-APR-13A
23-Mar-2013A
23-MAR-13A
24-MAR-13A
23-Mar-2013A
10-APR-13A
31-May-2013
12-APR-13A
09-APR-13A
10-APR-13A
31-May-2013
13-APR-13A
15-APR-13A
16-APR-13A
31-May-2013
31-May-2013
10-APR-13A
13-APR-13A
14-APR-13A
31-May-2013
27-MAR-13A
28-MAR-13A
31-May-2013
-16d
-61d
-18d
-18d
-17d
-51d
-11d
-11d
-11d
-46d
-46d
-3d
-5d
-5d
-57d
-2d
-1d
-56d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -7 (11-16/E-J)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Column
11 Shuttering
11 Concreting
11 Reinforcement
9 Pour -8 (11-16/A-E)
10 Column
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A20390
A20400
A20410
Pour 36
3
A20600
A20610
A20620
2
A20570
A20580
A20590
1
A20550
A20560
A20540
Pour 37
1
14-Mar-2013
15-Mar-2013
18-Mar-2013
12-Mar-2013
19-Mar-2013
19-Mar-2013
22-Mar-2013
03-Apr-2013
12-Mar-2013
12-Mar-2013
14-Mar-2013
16-Mar-2013
12-Mar-2013
13-Mar-2013
14-Mar-2013
12-Mar-2013
15-Mar-2013
15-Mar-2013
23-Mar-2013
26-Mar-2013
27-Mar-2013
04-Apr-2013
04-Apr-2013
02-Apr-2013
03-Apr-2013
04-Apr-2013
25-Mar-2013
21-Mar-2013
23-Mar-2013
25-Mar-2013
25-Mar-2013
23-Mar-2013
25-Mar-2013
21-Mar-2013
09-Apr-2013
29-Mar-2013
23-MAR-13A
24-MAR-13A
25-MAR-13A
25-Apr-2013A
26-Apr-2013A
26-APR-13A
30-APR-13A
06-MAY-13A
25-Apr-2013A
25-APR-13A
26-APR-13A
26-APR-13A
25-Apr-2013A
26-APR-13A
26-APR-13A
25-APR-13A
01-Apr-2013A
01-Apr-2013A
27-MAR-13A
28-MAR-13A
29-MAR-13A
31-May-2013
31-May-2013
10-MAY-13A
11-MAY-13A
13-MAY-13A
31-May-2013
26-APR-13A
27-APR-13A
27-APR-13A
31-May-2013
27-APR-13A
27-APR-13A
26-APR-13A
31-May-2013
31-May-2013
-2d
-1d
-1d
-49d
-49d
-33d
-33d
-33d
-58d
-30d
-29d
-28d
-58d
-29d
-28d
-30d
-45d
-54d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
9 Pour -3 (1-7/A-E)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Walls
11 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A20630
A20640
A20650
2
A20660
A20670
A20680
3
A20690
A20700
A20710
Pour 32
3
A20240
A20250
A20260
2
A20210
15-Mar-2013
16-Mar-2013
19-Mar-2013
15-Mar-2013
15-Mar-2013
18-Mar-2013
20-Mar-2013
23-Mar-2013
23-Mar-2013
27-Mar-2013
08-Apr-2013
02-Mar-2013
06-Mar-2013
06-Mar-2013
11-Mar-2013
26-Mar-2013
02-Mar-2013
02-Mar-2013
25-Mar-2013
27-Mar-2013
29-Mar-2013
28-Mar-2013
25-Mar-2013
27-Mar-2013
28-Mar-2013
09-Apr-2013
06-Apr-2013
08-Apr-2013
09-Apr-2013
27-Mar-2013
27-Mar-2013
22-Mar-2013
25-Mar-2013
27-Mar-2013
15-Mar-2013
12-Mar-2013
01-APR-13A
02-APR-13A
03-APR-13A
01-Apr-2013A
01-APR-13A
02-APR-13A
03-APR-13A
05-Apr-2013A
05-APR-13A
08-APR-13A
12-APR-13A
20-Mar-2013A
24-Mar-2013A
24-MAR-13A
30-MAR-13A
04-APR-13A
20-Mar-2013A
20-MAR-13A
05-APR-13A
06-APR-13A
06-APR-13A
31-May-2013
05-APR-13A
06-APR-13A
06-APR-13A
31-May-2013
10-APR-13A
12-APR-13A
13-APR-13A
31-May-2013
31-May-2013
02-APR-13A
04-APR-13A
05-APR-13A
31-May-2013
23-MAR-13A
-9d
-8d
-6d
-55d
-9d
-8d
-7d
-45d
-2d
-3d
-3d
-56d
-56d
-8d
-8d
-7d
-66d
-9d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
9 Pour -2 (16-21/A-E)
10 Beams & Slab
11 Shuttering
11 Reinforcement
11 Concreting
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
10 Walls
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A20220
A20230
1
A20180
A20190
A20200
Pour 31
3
A20150
A20160
A20170
1
A20090
A20100
A20110
2
A20120
A20130
05-Mar-2013
06-Mar-2013
02-Mar-2013
02-Mar-2013
05-Mar-2013
06-Mar-2013
15-Mar-2013
20-Mar-2013
20-Mar-2013
22-Mar-2013
08-Apr-2013
15-Mar-2013
15-Mar-2013
18-Mar-2013
20-Mar-2013
15-Mar-2013
15-Mar-2013
18-Mar-2013
14-Mar-2013
15-Mar-2013
15-Mar-2013
12-Mar-2013
14-Mar-2013
15-Mar-2013
09-Apr-2013
09-Apr-2013
05-Apr-2013
08-Apr-2013
09-Apr-2013
29-Mar-2013
25-Mar-2013
27-Mar-2013
29-Mar-2013
28-Mar-2013
25-Mar-2013
27-Mar-2013
21-MAR-13A
22-MAR-13A
20-Mar-2013A
20-MAR-13A
20-MAR-13A
21-MAR-13A
03-Apr-2013A
06-Apr-2013A
06-APR-13A
10-APR-13A
16-APR-13A
03-Apr-2013A
03-APR-13A
04-APR-13A
05-APR-13A
04-Apr-2013A
04-APR-13A
05-APR-13A
24-MAR-13A
25-MAR-13A
31-May-2013
22-MAR-13A
23-MAR-13A
23-MAR-13A
31-May-2013
31-May-2013
11-APR-13A
15-APR-13A
17-APR-13A
31-May-2013
06-APR-13A
07-APR-13A
08-APR-13A
31-May-2013
07-APR-13A
08-APR-13A
-8d
-7d
-66d
-8d
-7d
-6d
-45d
-45d
-4d
-5d
-6d
-54d
-10d
-9d
-7d
-55d
-11d
-9d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting
9 Pour -10 (16-20/D-F) Lift slab
10 Walls
11 Reinforcement
11 Shuttering
11 Concreting
10 Beams & Slab
11 Concreting
11 Shuttering
11 Reinforcement
10 Column
11 Reinforcement
11 Shuttering
11 Concreting
7 Escalators & Lifts
8 Installation of Lifts (1-7)-2 Nos
8 Testing of Escalators & Lifts
8 Installation of Lifts (16-21)-2 Nos
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A20140
Pour 372
2
A22560
A22570
A22580
3
A22610
A22590
A22600
1
A22530
A22540
A22550
Elv & Esc
S1-Ele1163
S1-Ele1210
S1-Ele1183
19-Mar-2013
12-Mar-2013
12-Mar-2013
12-Mar-2013
14-Mar-2013
16-Mar-2013
20-Mar-2013
04-Apr-2013
20-Mar-2013
23-Mar-2013
12-Mar-2013
12-Mar-2013
13-Mar-2013
15-Mar-2013
16-Feb-2013
11-Jun-2013
12-Sep-2013
04-Jul-2013
28-Mar-2013
05-Apr-2013
25-Mar-2013
21-Mar-2013
23-Mar-2013
25-Mar-2013
05-Apr-2013
05-Apr-2013
03-Apr-2013
04-Apr-2013
26-Mar-2013
21-Mar-2013
23-Mar-2013
26-Mar-2013
16-Oct-2013
26-Jul-2013
16-Oct-2013
19-Aug-2013
06-APR-13A
03-Apr-2013A
04-Apr-2013A
04-APR-13A
08-APR-13A
09-APR-13A
12-Apr-2013A
25-APR-13A
12-APR-13A
20-APR-13A
03-Apr-2013A
03-APR-13A
04-APR-13A
04-APR-13A
18-Oct-2013
04-DEC-13
06-MAR-14
27-DEC-13
10-APR-13A
31-May-2013
31-May-2013
09-APR-13A
25-APR-13A
26-APR-13A
31-May-2013
26-APR-13A
23-APR-13A
25-APR-13A
31-May-2013
08-APR-13A
09-APR-13A
09-APR-13A
14-Apr-2014
23-JAN-14
14-APR-14
14-FEB-14
-10d
-48d
-58d
-15d
-27d
-27d
-48d
-17d
-16d
-17d
-57d
-14d
-13d
-11d
-154d
-155d
-154d
-154d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
8 Balance lifts
8 Escalators
7 MEP 1st & 2nd Fixes (NSC)
8 Fourth floor
9 Plumbing works
9 Hand rail
9 False ceiling Marking
9 HVAC Support & Ducting
9 Cable Tray and cabeling
9 FPS Supports and piping
9 Access Controle system
9 Networking
9 Race ways
9 Screed & Tiling (L&T Scope)
8 Ground Floor
9 Plumbing Works
9 False ceiling Marking
9 HVAC Support & Ducting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S1-Ele1193
S1-Ele1203
NSC
13
A16290
A16370
A53060
A53070
A53080
A53090
A53100
A53110
A14388
A14389
1
A16130
A14093
A53180
16-Jul-2013
16-Feb-2013
19-Jan-2013
30-Mar-2013
30-Mar-2013
29-Apr-2013
01-May-2013
16-May-2013
16-May-2013
16-May-2013
16-May-2013
16-May-2013
30-Mar-2013
20-Apr-2013
19-Jan-2013
19-Jan-2013
02-Mar-2013
06-Mar-2013
23-Sep-2013
31-May-2013
02-Sep-2013
12-Jul-2013
07-Jun-2013
15-May-2013
14-May-2013
12-Jul-2013
12-Jul-2013
12-Jul-2013
12-Jul-2013
12-Jul-2013
27-Apr-2013
13-May-2013
03-May-2013
29-Mar-2013
15-Mar-2013
02-May-2013
08-JAN-14
18-OCT-13
06-Mar-2013A
31-May-2013
31-MAY-13
03-SEP-13
05-SEP-13
20-SEP-13
20-SEP-13
20-SEP-13
20-SEP-13
20-SEP-13
05-AUG-13
26-AUG-13
06-Mar-2013A
06-MAR-13A
10-AUG-13
14-AUG-13
21-MAR-14
29-JAN-14
09-Dec-2013
16-Nov-2013
08-AUG-13
19-SEP-13
18-SEP-13
16-NOV-13
16-NOV-13
16-NOV-13
16-NOV-13
16-NOV-13
02-SEP-13
17-SEP-13
11-Oct-2013
22-JUN-13
23-AUG-13
10-OCT-13
-154d
-208d
-84d
-109d
-53d
-109d
-109d
-109d
-109d
-109d
-109d
-109d
-109d
-109d
-138d
-72d
-138d
-138d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A53190
A53200
A53210
A53220
A14091
A14092
11
A16190
A16350
A53000
A53010
A53020
A53030
A53040
A53050
A14228
A14229
10
06-Mar-2013
07-Mar-2013
07-Mar-2013
15-Mar-2013
21-Jan-2013
11-Feb-2013
09-Feb-2013
09-Feb-2013
18-Mar-2013
20-Mar-2013
03-Apr-2013
03-Apr-2013
03-Apr-2013
03-Apr-2013
03-Apr-2013
16-Feb-2013
09-Mar-2013
30-Jan-2013
02-May-2013
03-May-2013
03-May-2013
23-Apr-2013
18-Feb-2013
05-Mar-2013
30-May-2013
19-Apr-2013
03-Apr-2013
02-Apr-2013
30-May-2013
30-May-2013
30-May-2013
30-May-2013
30-May-2013
16-Mar-2013
01-Apr-2013
14-May-2013
14-AUG-13
15-AUG-13
15-AUG-13
17-AUG-13
01-JUL-13
22-JUL-13
15-May-2013A
31-MAY-13
10-AUG-13
13-AUG-13
20-MAY-13A
31-MAY-13
15-MAY-13A
31-MAY-13
31-MAY-13
31-MAY-13A
02-AUG-13
18-Mar-2013A
10-OCT-13
11-OCT-13
11-OCT-13
25-SEP-13
29-JUL-13
13-AUG-13
27-Aug-2013
08-AUG-13
27-AUG-13
26-AUG-13
27-JUL-13
27-JUL-13
27-JUL-13
27-JUL-13
27-JUL-13
09-AUG-13
24-AUG-13
12-Aug-2013
-138d
-138d
-138d
-133d
-138d
-138d
-76d
-95d
-125d
-125d
-50d
-50d
-50d
-50d
-50d
-125d
-125d
-77d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 Plumbing works
9 Hand Rail
9 False ceiling Marking
9 HVAC Support & Ducting
9 Cable Tray and cabeling
9 FPS Supports and piping
9 Access Controle system
9 Networking
9 Race ways
9 Screed & Tiling (L&T Scope)
8 Fifth floor
9 Plumbing works
9 Hand Rails
9 False ceiling Marking
9 HVAC Support & Ducting
9 Cable Tray and cabeling
9 FPS Supports and piping
9 Access Controle system
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A16140
A16340
A53290
A53300
A53310
A53320
A53330
A53340
A14148
A14149
14
A16300
A16380
A53350
A53360
A53370
A53380
A53390
30-Jan-2013
28-Feb-2013
02-Mar-2013
16-Mar-2013
16-Mar-2013
18-Mar-2013
18-Mar-2013
18-Mar-2013
30-Jan-2013
20-Feb-2013
25-Apr-2013
25-Apr-2013
25-May-2013
28-May-2013
11-Jun-2013
11-Jun-2013
11-Jun-2013
11-Jun-2013
09-Apr-2013
16-Mar-2013
15-Mar-2013
13-May-2013
13-May-2013
14-May-2013
14-May-2013
14-May-2013
27-Feb-2013
14-Mar-2013
07-Aug-2013
03-Jul-2013
11-Jun-2013
10-Jun-2013
07-Aug-2013
07-Aug-2013
07-Aug-2013
07-Aug-2013
31-MAY-13
26-JUL-13
29-JUL-13
15-APR-13A
31-MAY-13A
18-MAR-13A
31-MAY-13
31-MAY-13
20-MAY-13A
18-JUL-13
31-May-2013
31-MAY-13
14-SEP-13
17-SEP-13
01-OCT-13
01-OCT-13
01-OCT-13
01-OCT-13
08-AUG-13
12-AUG-13
10-AUG-13
22-JUL-13
27-JUL-13
08-JUL-13
27-JUL-13
27-JUL-13
29-JUL-13
09-AUG-13
27-Nov-2013
08-AUG-13
01-OCT-13
30-SEP-13
27-NOV-13
27-NOV-13
27-NOV-13
27-NOV-13
-104d
-127d
-127d
-60d
-65d
-47d
-64d
-64d
-130d
-127d
-96d
-31d
-96d
-96d
-96d
-96d
-96d
-96d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 Networking
9 Race ways
9 Screed & Tiling (L&T Scope)
8 Third Floor
9 Plumbing Work
9 Hand rail
9 False ceiling Marking
9 HVAC Support & Ducting
9 Cable Tray and cabeling
9 FPS Supports and piping
9 Access Controle system
9 Networking
9 Race ways
9 Screed & Tiling (L&T Scope)
8 Sixth floor
9 Hand Rails
9 False ceiling Marking
9 HVAC Support & Ducting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A53400
A14468
A14469
12
A16280
A16360
A53120
A53130
A53140
A53150
A53160
A53170
A14308
A14309
15
A16390
A53230
A53240
11-Jun-2013
26-Apr-2013
17-May-2013
05-Mar-2013
05-Mar-2013
04-Apr-2013
06-Apr-2013
20-Apr-2013
20-Apr-2013
20-Apr-2013
20-Apr-2013
20-Apr-2013
06-Mar-2013
27-Mar-2013
21-May-2013
20-Jun-2013
22-Jun-2013
06-Jul-2013
07-Aug-2013
24-May-2013
08-Jun-2013
17-Jun-2013
13-May-2013
20-Apr-2013
19-Apr-2013
17-Jun-2013
17-Jun-2013
17-Jun-2013
17-Jun-2013
17-Jun-2013
03-Apr-2013
18-Apr-2013
02-Sep-2013
06-Jul-2013
05-Jul-2013
02-Sep-2013
01-OCT-13
16-AUG-13
06-SEP-13
06-May-2013A
31-MAY-13
22-AUG-13
24-AUG-13
31-MAY-13A
07-SEP-13
06-MAY-13A
07-SEP-13
07-SEP-13
24-JUL-13
14-AUG-13
29-Jun-2013
26-SEP-13
28-SEP-13
12-OCT-13
27-NOV-13
13-SEP-13
28-SEP-13
04-Nov-2013
08-AUG-13
07-SEP-13
06-SEP-13
04-NOV-13
04-NOV-13
04-NOV-13
04-NOV-13
04-NOV-13
21-AUG-13
05-SEP-13
09-Dec-2013
12-OCT-13
11-OCT-13
09-DEC-13
-96d
-96d
-96d
-120d
-75d
-120d
-120d
-120d
-120d
-120d
-120d
-120d
-120d
-120d
-84d
-84d
-84d
-84d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A53250
A53260
A53270
A53280
A14548
A14549
A16310
1
2
36
35
A57630
A57640
A57650
A57660
A57670
A57680
A57690
06-Jul-2013
06-Jul-2013
06-Jul-2013
06-Jul-2013
22-May-2013
12-Jun-2013
21-May-2013
23-Aug-2012
23-Aug-2012
23-Aug-2012
16-Nov-2012
16-Nov-2012
26-Nov-2012
05-Dec-2012
05-Dec-2012
10-Dec-2012
14-Dec-2012
21-Dec-2012
02-Sep-2013
02-Sep-2013
02-Sep-2013
02-Sep-2013
19-Jun-2013
04-Jul-2013
29-Jul-2013
12-Apr-2013
26-Jan-2013
07-Jan-2013
07-Jan-2013
24-Nov-2012
04-Dec-2012
06-Dec-2012
13-Dec-2012
18-Dec-2012
22-Dec-2012
29-Dec-2012
12-OCT-13
12-OCT-13
12-OCT-13
12-OCT-13
28-AUG-13
18-SEP-13
29-JUN-13
20-Sep-2012A
20-Sep-2012A
20-Sep-2012A
10-Mar-2013A
10-MAR-13A
15-MAR-13A
20-MAR-13A
05-JUN-13
10-JUN-13
14-JUN-13
21-JUN-13
09-DEC-13
09-DEC-13
09-DEC-13
09-DEC-13
25-SEP-13
10-OCT-13
24-SEP-13
26-Mar-2014
21-Dec-2013
14-Aug-2013
08-Jul-2013
13-MAR-13A
04-JUN-13
05-JUN-13
13-JUN-13
18-JUN-13
22-JUN-13
29-JUN-13
-84d
-84d
-84d
-84d
-84d
-84d
-49d
-298d
-282d
-188d
-156d
-92d
-156d
-155d
-156d
-156d
-156d
-156d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -11
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -15
10 Soling
10 PCC
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A57700
A57710
29
A56880
A56890
A56900
A56910
A56920
A56930
A56940
A56950
A56960
A56970
A56980
A56990
33
A57370
A57380
28-Dec-2012
05-Jan-2013
12-Oct-2012
12-Oct-2012
24-Oct-2012
02-Nov-2012
05-Nov-2012
14-Nov-2012
23-Nov-2012
23-Nov-2012
28-Nov-2012
03-Dec-2012
10-Dec-2012
17-Dec-2012
25-Dec-2012
12-Oct-2012
12-Oct-2012
22-Oct-2012
03-Jan-2013
07-Jan-2013
26-Dec-2012
23-Oct-2012
01-Nov-2012
03-Nov-2012
13-Nov-2012
22-Nov-2012
24-Nov-2012
01-Dec-2012
06-Dec-2012
11-Dec-2012
18-Dec-2012
22-Dec-2012
26-Dec-2012
14-Dec-2012
20-Oct-2012
23-Oct-2012
28-JUN-13
06-JUL-13
10-Nov-2012A
10-NOV-12A
25-NOV-12A
05-DEC-12A
15-FEB-13A
16-FEB-13A
20-FEB-13A
17-FEB-13A
15-MAR-13A
22-MAR-13A
01-APR-13A
08-APR-13A
20-APR-13A
25-Oct-2012A
25-OCT-12A
11-NOV-12A
04-JUL-13
08-JUL-13
14-Aug-2013
20-NOV-12A
02-DEC-12A
12-DEC-12A
17-FEB-13A
20-FEB-13A
21-FEB-13A
27-FEB-13A
22-MAR-13A
29-MAR-13A
14-APR-13A
19-APR-13A
20-APR-13A
10-Jun-2013
10-NOV-12A
15-NOV-12A
-156d
-156d
-198d
-23d
-26d
-32d
-82d
-76d
-75d
-74d
-90d
-92d
-100d
-100d
-98d
-152d
-17d
-19d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -9
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A57390
A57400
A57410
A57420
A57430
A57440
A57450
A57460
A57470
27
A56640
A56650
A56660
A56670
A56680
A56690
A56700
A56710
24-Oct-2012
02-Nov-2012
12-Nov-2012
12-Nov-2012
16-Nov-2012
21-Nov-2012
28-Nov-2012
05-Dec-2012
13-Dec-2012
19-Sep-2012
19-Sep-2012
01-Oct-2012
10-Oct-2012
12-Oct-2012
22-Oct-2012
31-Oct-2012
31-Oct-2012
05-Nov-2012
01-Nov-2012
10-Nov-2012
13-Nov-2012
20-Nov-2012
24-Nov-2012
29-Nov-2012
06-Dec-2012
11-Dec-2012
14-Dec-2012
03-Dec-2012
29-Sep-2012
09-Oct-2012
11-Oct-2012
20-Oct-2012
30-Oct-2012
01-Nov-2012
08-Nov-2012
13-Nov-2012
23-NOV-12A
25-NOV-12A
02-DEC-12A
26-NOV-12A
12-JAN-13A
20-JAN-13A
06-FEB-13A
20-FEB-13A
04-MAR-13A
12-Mar-2013A
12-MAR-13A
18-MAR-13A
29-APR-13A
01-MAY-13A
17-MAY-13A
10-JUN-13
10-JUN-13
14-JUN-13
27-NOV-12A
02-DEC-12A
03-DEC-12A
05-DEC-12A
19-JAN-13A
25-JAN-13A
19-FEB-13A
02-MAR-13A
05-MAR-13A
12-Jul-2013
15-MAR-13A
25-MAR-13A
11-MAY-13A
18-MAY-13A
08-JUN-13
11-JUN-13
18-JUN-13
22-JUN-13
-21d
-18d
-16d
-12d
-47d
-48d
-63d
-69d
-68d
-190d
-142d
-142d
-181d
-179d
-190d
-190d
-190d
-190d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -3
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -1
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A56720
A56730
A56740
A56750
21
A55930
A55940
A55950
A55960
A55970
A55980
A55990
A56000
A56010
A56020
A56030
A56040
19
09-Nov-2012
16-Nov-2012
23-Nov-2012
01-Dec-2012
15-Sep-2012
15-Sep-2012
27-Sep-2012
06-Oct-2012
09-Oct-2012
18-Oct-2012
27-Oct-2012
27-Oct-2012
01-Nov-2012
06-Nov-2012
13-Nov-2012
20-Nov-2012
28-Nov-2012
23-Aug-2012
17-Nov-2012
24-Nov-2012
29-Nov-2012
03-Dec-2012
29-Nov-2012
26-Sep-2012
05-Oct-2012
08-Oct-2012
17-Oct-2012
26-Oct-2012
29-Oct-2012
05-Nov-2012
09-Nov-2012
14-Nov-2012
21-Nov-2012
26-Nov-2012
29-Nov-2012
06-Nov-2012
19-JUN-13
26-JUN-13
03-JUL-13
11-JUL-13
10-Feb-2013A
10-FEB-13A
26-FEB-13A
05-MAR-13A
07-MAR-13A
08-MAR-13A
10-MAR-13A
11-MAR-13A
20-MAR-13A
29-MAR-13A
05-APR-13A
08-APR-13A
17-APR-13A
10-Feb-2013A
27-JUN-13
04-JUL-13
09-JUL-13
12-JUL-13
07-Jun-2013
25-FEB-13A
05-MAR-13A
06-MAR-13A
08-MAR-13A
10-MAR-13A
11-MAR-13A
19-MAR-13A
28-MAR-13A
04-APR-13A
11-APR-13A
16-APR-13A
17-APR-13A
07-Jun-2013
-190d
-190d
-190d
-190d
-163d
-129d
-128d
-127d
-121d
-115d
-113d
-114d
-118d
-120d
-120d
-120d
-118d
-183d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -8
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A55690
A55700
A55710
A55720
A55730
A55740
A55750
A55760
A55770
A55780
A55790
A55800
26
A56540
A56550
A56560
A56570
A56580
23-Aug-2012
04-Sep-2012
13-Sep-2012
15-Sep-2012
25-Sep-2012
04-Oct-2012
04-Oct-2012
09-Oct-2012
13-Oct-2012
20-Oct-2012
27-Oct-2012
05-Nov-2012
07-Sep-2012
28-Sep-2012
01-Oct-2012
10-Oct-2012
19-Oct-2012
19-Oct-2012
03-Sep-2012
12-Sep-2012
14-Sep-2012
24-Sep-2012
03-Oct-2012
05-Oct-2012
12-Oct-2012
17-Oct-2012
22-Oct-2012
29-Oct-2012
02-Nov-2012
06-Nov-2012
21-Nov-2012
29-Sep-2012
09-Oct-2012
18-Oct-2012
20-Oct-2012
27-Oct-2012
10-FEB-13A
12-FEB-13A
05-MAR-13A
09-MAR-13A
10-MAR-13A
13-MAR-13A
12-MAR-13A
22-MAR-13A
31-MAR-13A
05-APR-13A
10-APR-13A
17-APR-13A
15-Feb-2013A
10-MAR-13A
15-MAR-13A
16-MAR-13A
20-MAR-13A
18-MAR-13A
12-FEB-13A
14-FEB-13A
06-MAR-13A
10-MAR-13A
13-MAR-13A
14-MAR-13A
20-MAR-13A
30-MAR-13A
04-APR-13A
31-MAY-13
05-JUN-13
07-JUN-13
28-Jun-2013
13-MAR-13A
17-MAR-13A
19-MAR-13A
20-MAR-13A
01-JUN-13
-138d
-132d
-147d
-143d
-137d
-136d
-135d
-140d
-140d
-184d
-184d
-182d
-188d
-140d
-136d
-129d
-128d
-186d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
10 Excavation
10 Soling
9 Secondary Tunnel -16
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A56590
A56600
A56610
A56620
A56630
A56520
A56530
34
A57490
A57500
A57510
A57520
A57530
A57540
A57550
A57560
A57570
A57580
24-Oct-2012
29-Oct-2012
05-Nov-2012
12-Nov-2012
20-Nov-2012
07-Sep-2012
19-Sep-2012
24-Oct-2012
24-Oct-2012
02-Nov-2012
05-Nov-2012
14-Nov-2012
23-Nov-2012
23-Nov-2012
28-Nov-2012
03-Dec-2012
10-Dec-2012
17-Dec-2012
01-Nov-2012
06-Nov-2012
13-Nov-2012
17-Nov-2012
21-Nov-2012
18-Sep-2012
27-Sep-2012
26-Dec-2012
01-Nov-2012
03-Nov-2012
13-Nov-2012
22-Nov-2012
24-Nov-2012
01-Dec-2012
06-Dec-2012
11-Dec-2012
18-Dec-2012
22-Dec-2012
04-MAY-13A
09-MAY-13A
12-JUN-13
19-JUN-13
27-JUN-13
15-FEB-13A
02-MAR-13A
24-Oct-2012A
24-OCT-12A
12-NOV-12A
20-NOV-12A
23-NOV-12A
02-DEC-12A
25-NOV-12A
15-MAR-13A
26-MAR-13A
15-APR-13A
21-APR-13A
08-JUN-13
13-JUN-13
20-JUN-13
25-JUN-13
28-JUN-13
28-FEB-13A
08-MAR-13A
10-Jun-2013
08-NOV-12A
15-NOV-12A
25-NOV-12A
02-DEC-12A
03-DEC-12A
10-DEC-12A
25-MAR-13A
26-MAR-13A
09-MAY-13A
14-MAY-13A
-188d
-188d
-188d
-188d
-188d
-139d
-138d
-142d
-5d
-9d
-10d
-8d
-6d
-6d
-92d
-89d
-122d
-122d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Slab Concrete
9 Secondary Tunnel -6
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -12
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A57590
24
A56300
A56310
A56320
A56330
A56340
A56350
A56360
A56370
A56380
A56390
A56400
30
A57000
A57010
A57020
A57030
25-Dec-2012
01-Nov-2012
01-Nov-2012
10-Nov-2012
13-Nov-2012
22-Nov-2012
01-Dec-2012
01-Dec-2012
06-Dec-2012
11-Dec-2012
18-Dec-2012
25-Dec-2012
02-Jan-2013
24-Oct-2012
24-Oct-2012
05-Nov-2012
14-Nov-2012
16-Nov-2012
26-Dec-2012
03-Jan-2013
09-Nov-2012
12-Nov-2012
21-Nov-2012
30-Nov-2012
03-Dec-2012
10-Dec-2012
14-Dec-2012
19-Dec-2012
26-Dec-2012
31-Dec-2012
03-Jan-2013
07-Jan-2013
03-Nov-2012
13-Nov-2012
15-Nov-2012
24-Nov-2012
08-MAY-13A
10-Nov-2012A
10-NOV-12A
18-DEC-12A
23-DEC-12A
25-DEC-12A
04-JAN-13A
03-JAN-13A
01-MAR-13A
06-MAR-13A
20-MAR-13A
15-APR-13A
25-APR-13A
12-Nov-2012A
12-NOV-12A
27-NOV-12A
06-DEC-12A
15-DEC-12A
17-MAY-13A
08-Jun-2013
24-NOV-12A
22-DEC-12A
27-DEC-12A
04-JAN-13A
05-JAN-13A
15-JAN-13A
06-MAR-13A
15-MAR-13A
18-MAY-13A
22-MAY-13A
23-MAY-13A
14-Aug-2013
22-NOV-12A
04-DEC-12A
13-DEC-12A
20-DEC-12A
-122d
-134d
-12d
-34d
-30d
-29d
-28d
-30d
-69d
-73d
-122d
-121d
-119d
-188d
-15d
-17d
-23d
-21d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -4
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A57040
A57050
A57060
A57070
A57080
A57090
A57100
A57110
22
A56050
A56060
A56070
A56080
A56090
A56100
A56110
A56120
A56130
26-Nov-2012
05-Dec-2012
05-Dec-2012
10-Dec-2012
14-Dec-2012
21-Dec-2012
28-Dec-2012
05-Jan-2013
27-Sep-2012
27-Sep-2012
09-Oct-2012
18-Oct-2012
20-Oct-2012
30-Oct-2012
08-Nov-2012
08-Nov-2012
13-Nov-2012
17-Nov-2012
04-Dec-2012
06-Dec-2012
13-Dec-2012
18-Dec-2012
22-Dec-2012
29-Dec-2012
03-Jan-2013
07-Jan-2013
11-Dec-2012
08-Oct-2012
17-Oct-2012
19-Oct-2012
29-Oct-2012
07-Nov-2012
09-Nov-2012
16-Nov-2012
21-Nov-2012
26-Nov-2012
18-DEC-12A
04-JAN-13A
04-JAN-13A
02-MAR-13A
15-MAR-13A
24-MAR-13A
01-APR-13A
20-APR-13A
10-Feb-2013A
10-FEB-13A
26-FEB-13A
05-MAR-13A
07-MAR-13A
08-MAR-13A
10-MAR-13A
11-MAR-13A
19-MAR-13A
28-MAR-13A
04-JAN-13A
05-JAN-13A
15-JAN-13A
14-MAR-13A
22-MAR-13A
12-APR-13A
19-APR-13A
20-APR-13A
08-Jun-2013
25-FEB-13A
05-MAR-13A
06-MAR-13A
08-MAR-13A
10-MAR-13A
11-MAR-13A
18-MAR-13A
27-MAR-13A
03-APR-13A
-26d
-25d
-27d
-73d
-76d
-88d
-90d
-88d
-154d
-119d
-118d
-117d
-111d
-105d
-103d
-103d
-107d
-109d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -5
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -7
10 Excavation
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A56140
A56150
A56160
23
A56170
A56180
A56190
A56200
A56210
A56220
A56230
A56240
A56250
A56260
A56270
A56280
25
A56410
24-Nov-2012
01-Dec-2012
10-Dec-2012
09-Oct-2012
09-Oct-2012
20-Oct-2012
30-Oct-2012
01-Nov-2012
10-Nov-2012
20-Nov-2012
20-Nov-2012
24-Nov-2012
29-Nov-2012
06-Dec-2012
13-Dec-2012
21-Dec-2012
27-Aug-2012
27-Aug-2012
03-Dec-2012
07-Dec-2012
11-Dec-2012
22-Dec-2012
19-Oct-2012
29-Oct-2012
31-Oct-2012
09-Nov-2012
19-Nov-2012
21-Nov-2012
28-Nov-2012
03-Dec-2012
07-Dec-2012
14-Dec-2012
19-Dec-2012
22-Dec-2012
09-Nov-2012
06-Sep-2012
04-APR-13A
08-APR-13A
25-APR-13A
02-Oct-2012A
02-OCT-12A
07-NOV-12A
15-DEC-12A
20-DEC-12A
22-DEC-12A
27-DEC-12A
28-DEC-12A
15-FEB-13A
28-FEB-13A
15-MAR-13A
25-MAR-13A
25-APR-13A
02-Oct-2012A
02-OCT-12A
10-APR-13A
06-JUN-13
08-JUN-13
08-Jun-2013
25-OCT-12A
21-NOV-12A
19-DEC-12A
23-DEC-12A
28-DEC-12A
02-JAN-13A
10-JAN-13A
28-FEB-13A
05-MAR-13A
15-APR-13A
24-APR-13A
25-APR-13A
10-Jun-2013
10-NOV-12A
-109d
-155d
-154d
-144d
-4d
-19d
-41d
-37d
-33d
-35d
-36d
-74d
-74d
-103d
-107d
-105d
-182d
-55d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -14
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A56420
A56430
A56440
A56450
A56460
A56470
A29680
A56480
A56490
A56500
A56510
32
A57240
A57250
A57260
A57270
A57280
A57290
07-Sep-2012
17-Sep-2012
19-Sep-2012
28-Sep-2012
08-Oct-2012
08-Oct-2012
12-Oct-2012
17-Oct-2012
24-Oct-2012
31-Oct-2012
08-Nov-2012
19-Sep-2012
19-Sep-2012
01-Oct-2012
10-Oct-2012
12-Oct-2012
22-Oct-2012
31-Oct-2012
15-Sep-2012
18-Sep-2012
27-Sep-2012
06-Oct-2012
09-Oct-2012
16-Oct-2012
20-Oct-2012
25-Oct-2012
01-Nov-2012
06-Nov-2012
09-Nov-2012
03-Dec-2012
29-Sep-2012
09-Oct-2012
11-Oct-2012
20-Oct-2012
30-Oct-2012
01-Nov-2012
15-NOV-12A
30-JAN-13A
04-FEB-13A
06-FEB-13A
15-FEB-13A
16-FEB-13A
01-MAR-13A
06-MAR-13A
30-MAR-13A
10-MAY-13A
23-MAY-13A
20-Sep-2012A
20-SEP-12A
25-OCT-12A
15-NOV-12A
03-DEC-12A
05-DEC-12A
23-DEC-12A
30-NOV-12A
01-FEB-13A
07-FEB-13A
16-FEB-13A
23-FEB-13A
25-FEB-13A
07-MAR-13A
15-MAR-13A
13-MAY-13A
06-JUN-13
10-JUN-13
10-Jun-2013
10-OCT-12A
10-NOV-12A
20-NOV-12A
07-DEC-12A
23-DEC-12A
25-DEC-12A
-64d
-116d
-113d
-113d
-117d
-112d
-117d
-120d
-164d
-182d
-182d
-162d
-8d
-27d
-33d
-40d
-46d
-45d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -13
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A57300
A57310
A57320
A57330
A57340
A57350
31
A57120
A57130
A57140
A57150
A57160
A57170
A57180
A57190
A57200
A57210
A57220
31-Oct-2012
05-Nov-2012
09-Nov-2012
16-Nov-2012
23-Nov-2012
01-Dec-2012
07-Sep-2012
07-Sep-2012
19-Sep-2012
28-Sep-2012
01-Oct-2012
10-Oct-2012
19-Oct-2012
19-Oct-2012
24-Oct-2012
29-Oct-2012
05-Nov-2012
12-Nov-2012
08-Nov-2012
13-Nov-2012
17-Nov-2012
24-Nov-2012
29-Nov-2012
03-Dec-2012
21-Nov-2012
18-Sep-2012
27-Sep-2012
29-Sep-2012
09-Oct-2012
18-Oct-2012
20-Oct-2012
27-Oct-2012
01-Nov-2012
06-Nov-2012
13-Nov-2012
17-Nov-2012
07-DEC-12A
10-JAN-13A
18-FEB-13A
22-FEB-13A
27-FEB-13A
04-MAR-13A
25-Sep-2012A
25-SEP-12A
30-OCT-12A
05-DEC-12A
14-DEC-12A
15-DEC-12A
20-DEC-12A
20-DEC-12A
01-MAR-13A
10-MAR-13A
18-MAR-13A
25-MAR-13A
05-JAN-13A
20-JAN-13A
19-FEB-13A
28-FEB-13A
04-MAR-13A
05-MAR-13A
10-Jun-2013
15-OCT-12A
15-NOV-12A
12-DEC-12A
15-DEC-12A
20-DEC-12A
21-DEC-12A
28-DEC-12A
09-MAR-13A
15-MAR-13A
01-JUN-13
06-JUN-13
-49d
-58d
-79d
-81d
-80d
-78d
-172d
-22d
-41d
-62d
-57d
-53d
-52d
-52d
-109d
-110d
-172d
-172d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Slab Concrete
9 Secondary Tunnel -10
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Secondary Tunnel -2
10 Excavation
10 Soling
10 PCC
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A57230
28
A56760
A56770
A56780
A56790
A56800
A56810
A56820
A56830
A56840
A56850
A56860
A56870
20
A55810
A55820
A55830
20-Nov-2012
01-Oct-2012
01-Oct-2012
12-Oct-2012
22-Oct-2012
24-Oct-2012
02-Nov-2012
12-Nov-2012
12-Nov-2012
16-Nov-2012
21-Nov-2012
28-Nov-2012
05-Dec-2012
13-Dec-2012
04-Sep-2012
04-Sep-2012
15-Sep-2012
25-Sep-2012
21-Nov-2012
14-Dec-2012
11-Oct-2012
20-Oct-2012
23-Oct-2012
01-Nov-2012
10-Nov-2012
13-Nov-2012
20-Nov-2012
24-Nov-2012
29-Nov-2012
06-Dec-2012
11-Dec-2012
14-Dec-2012
17-Nov-2012
14-Sep-2012
24-Sep-2012
26-Sep-2012
08-JUN-13
31-May-2013
31-MAY-13
12-JUN-13
21-JUN-13
24-JUN-13
03-JUL-13
12-JUL-13
12-JUL-13
17-JUL-13
22-JUL-13
29-JUL-13
05-AUG-13
13-AUG-13
10-Feb-2013A
10-FEB-13A
26-FEB-13A
05-MAR-13A
10-JUN-13
14-Aug-2013
11-JUN-13
20-JUN-13
22-JUN-13
02-JUL-13
11-JUL-13
13-JUL-13
20-JUL-13
25-JUL-13
30-JUL-13
06-AUG-13
10-AUG-13
14-AUG-13
07-Jun-2013
25-FEB-13A
05-MAR-13A
06-MAR-13A
-172d
-208d
-208d
-208d
-208d
-208d
-208d
-208d
-208d
-208d
-208d
-208d
-208d
-208d
-173d
-139d
-138d
-137d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
8 Branch Tunnel
9 BT 11
10 Filling
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A55840
A55850
A55860
A55870
A55880
A55890
A55900
A55910
A55920
2
7
A58560
A58570
A58580
A58590
A58600
A58610
A58620
27-Sep-2012
06-Oct-2012
16-Oct-2012
16-Oct-2012
20-Oct-2012
25-Oct-2012
01-Nov-2012
08-Nov-2012
16-Nov-2012
15-Sep-2012
15-Sep-2012
15-Sep-2012
22-Sep-2012
26-Sep-2012
27-Sep-2012
29-Sep-2012
02-Oct-2012
28-Sep-2012
05-Oct-2012
15-Oct-2012
17-Oct-2012
24-Oct-2012
29-Oct-2012
02-Nov-2012
09-Nov-2012
14-Nov-2012
17-Nov-2012
26-Jan-2013
19-Oct-2012
21-Sep-2012
25-Sep-2012
26-Sep-2012
28-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
07-MAR-13A
08-MAR-13A
10-MAR-13A
11-MAR-13A
20-MAR-13A
30-MAR-13A
05-APR-13A
09-APR-13A
17-APR-13A
01-Nov-2012A
01-Nov-2012A
01-NOV-12A
04-NOV-12A
07-NOV-12A
10-NOV-12A
11-NOV-12A
14-NOV-12A
13-NOV-12A
08-MAR-13A
10-MAR-13A
11-MAR-13A
19-MAR-13A
29-MAR-13A
04-APR-13A
12-APR-13A
16-APR-13A
17-APR-13A
21-Dec-2013
31-May-2013
04-NOV-12A
06-NOV-12A
10-NOV-12A
12-NOV-12A
14-NOV-12A
15-NOV-12A
18-NOV-12A
-131d
-125d
-123d
-124d
-129d
-130d
-131d
-130d
-128d
-282d
-192d
-37d
-35d
-38d
-37d
-37d
-37d
-39d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 5
10 Filling
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A58630
A58640
A58650
A58660
A58670
4
A58200
A58210
A58220
A58230
A58240
A58250
A58260
A58270
A58280
A58290
A58300
A58310
02-Oct-2012
05-Oct-2012
11-Oct-2012
17-Oct-2012
19-Oct-2012
15-Sep-2012
15-Sep-2012
22-Sep-2012
26-Sep-2012
27-Sep-2012
29-Sep-2012
02-Oct-2012
28-Sep-2012
02-Oct-2012
05-Oct-2012
11-Oct-2012
17-Oct-2012
19-Oct-2012
06-Oct-2012
10-Oct-2012
16-Oct-2012
18-Oct-2012
19-Oct-2012
19-Oct-2012
21-Sep-2012
25-Sep-2012
26-Sep-2012
28-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
06-Oct-2012
10-Oct-2012
16-Oct-2012
18-Oct-2012
19-Oct-2012
15-NOV-12A
20-NOV-12A
19-NOV-12A
21-NOV-12A
24-NOV-12A
05-Nov-2012A
05-NOV-12A
08-NOV-12A
11-NOV-12A
14-NOV-12A
15-NOV-12A
16-NOV-12A
17-NOV-12A
20-NOV-12A
26-NOV-12A
26-NOV-12A
27-NOV-12A
30-NOV-12A
20-NOV-12A
21-NOV-12A
22-NOV-12A
23-NOV-12A
24-NOV-12A
31-May-2013
08-NOV-12A
10-NOV-12A
14-NOV-12A
15-NOV-12A
16-NOV-12A
16-NOV-12A
24-NOV-12A
26-NOV-12A
27-NOV-12A
28-NOV-12A
30-NOV-12A
01-DEC-12A
-37d
-35d
-31d
-30d
-30d
-192d
-40d
-39d
-41d
-40d
-39d
-38d
-44d
-42d
-40d
-36d
-36d
-36d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 BT 12
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 1
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
9
A58800
A58810
A58820
A58830
A58840
A58850
A58860
A58870
A58880
A58890
A58900
A58910
35
A57720
A57730
A57740
A57750
24-Dec-2012
24-Dec-2012
31-Dec-2012
03-Jan-2013
04-Jan-2013
07-Jan-2013
09-Jan-2013
05-Jan-2013
09-Jan-2013
12-Jan-2013
18-Jan-2013
24-Jan-2013
26-Jan-2013
24-Dec-2012
24-Dec-2012
27-Dec-2012
31-Dec-2012
01-Jan-2013
26-Jan-2013
29-Dec-2012
02-Jan-2013
03-Jan-2013
05-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
14-Jan-2013
17-Jan-2013
23-Jan-2013
25-Jan-2013
26-Jan-2013
23-Jan-2013
26-Dec-2012
29-Dec-2012
31-Dec-2012
02-Jan-2013
12-Jul-2013
12-JUL-13
19-JUL-13
23-JUL-13
24-JUL-13
26-JUL-13
29-JUL-13
25-JUL-13
29-JUL-13
01-AUG-13
07-AUG-13
13-AUG-13
15-AUG-13
31-May-2013
31-MAY-13
22-JUN-13
15-JUL-13
03-AUG-13
15-Aug-2013
18-JUL-13
22-JUL-13
23-JUL-13
25-JUL-13
27-JUL-13
29-JUL-13
30-JUL-13
02-AUG-13
06-AUG-13
12-AUG-13
14-AUG-13
15-AUG-13
29-Nov-2013
22-JUN-13
15-JUL-13
03-AUG-13
24-AUG-13
-172d
-172d
-172d
-172d
-172d
-172d
-172d
-172d
-172d
-172d
-172d
-172d
-172d
-266d
-152d
-168d
-185d
-201d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 4
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A57760
A57770
A57780
A57790
A57800
A57810
A57820
A57830
3
A58080
A58090
A58100
A58110
A58120
A58130
A58140
A58150
A58160
03-Jan-2013
05-Jan-2013
02-Jan-2013
05-Jan-2013
09-Jan-2013
15-Jan-2013
21-Jan-2013
23-Jan-2013
27-Dec-2012
27-Dec-2012
31-Dec-2012
03-Jan-2013
04-Jan-2013
07-Jan-2013
09-Jan-2013
05-Jan-2013
09-Jan-2013
12-Jan-2013
04-Jan-2013
05-Jan-2013
07-Jan-2013
10-Jan-2013
14-Jan-2013
19-Jan-2013
22-Jan-2013
23-Jan-2013
26-Jan-2013
29-Dec-2012
02-Jan-2013
03-Jan-2013
05-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
14-Jan-2013
17-Jan-2013
24-AUG-13
16-SEP-13
23-AUG-13
27-AUG-13
30-AUG-13
25-SEP-13
19-OCT-13
09-NOV-13
13-Jun-2013
13-JUN-13
26-JUN-13
09-JUL-13
19-JUL-13
01-AUG-13
13-AUG-13
31-JUL-13
03-AUG-13
07-AUG-13
14-SEP-13
05-OCT-13
17-SEP-13
20-SEP-13
24-SEP-13
19-OCT-13
09-NOV-13
29-NOV-13
28-Sep-2013
26-JUN-13
09-JUL-13
19-JUL-13
31-JUL-13
13-AUG-13
23-AUG-13
15-AUG-13
19-AUG-13
22-AUG-13
-217d
-233d
-217d
-217d
-217d
-233d
-249d
-266d
-210d
-152d
-161d
-169d
-177d
-185d
-193d
-185d
-185d
-185d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 6
10 Filling
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 17
10 Excavation
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A58170
A58180
A58190
5
A58320
A58330
A58340
A58350
A58360
A58370
A58380
A58390
A58400
A58410
A58420
A58430
10
A58920
18-Jan-2013
24-Jan-2013
26-Jan-2013
15-Sep-2012
15-Sep-2012
22-Sep-2012
26-Sep-2012
27-Sep-2012
29-Sep-2012
02-Oct-2012
28-Sep-2012
02-Oct-2012
05-Oct-2012
11-Oct-2012
17-Oct-2012
19-Oct-2012
24-Dec-2012
24-Dec-2012
23-Jan-2013
25-Jan-2013
26-Jan-2013
19-Oct-2012
21-Sep-2012
25-Sep-2012
26-Sep-2012
28-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
06-Oct-2012
10-Oct-2012
16-Oct-2012
18-Oct-2012
19-Oct-2012
26-Jan-2013
29-Dec-2012
22-AUG-13
06-SEP-13
18-SEP-13
05-Nov-2012A
05-NOV-12A
08-NOV-12A
11-NOV-12A
14-NOV-12A
15-NOV-12A
16-NOV-12A
17-NOV-12A
20-NOV-12A
26-NOV-12A
27-NOV-12A
28-NOV-12A
30-NOV-12A
09-Aug-2013
09-AUG-13
06-SEP-13
18-SEP-13
28-SEP-13
31-May-2013
08-NOV-12A
10-NOV-12A
14-NOV-12A
15-NOV-12A
16-NOV-12A
16-NOV-12A
24-NOV-12A
26-NOV-12A
27-NOV-12A
28-NOV-12A
30-NOV-12A
01-DEC-12A
12-Sep-2013
15-AUG-13
-193d
-202d
-210d
-192d
-40d
-39d
-41d
-40d
-39d
-38d
-44d
-42d
-40d
-36d
-36d
-36d
-196d
-196d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 16
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A58930
A58940
A58950
A58960
A58970
A58980
A58990
A59000
A59010
A59020
A59030
12
A59160
A59170
A59180
A59190
A59200
A59210
31-Dec-2012
03-Jan-2013
04-Jan-2013
07-Jan-2013
09-Jan-2013
05-Jan-2013
09-Jan-2013
12-Jan-2013
18-Jan-2013
24-Jan-2013
26-Jan-2013
27-Dec-2012
27-Dec-2012
31-Dec-2012
03-Jan-2013
04-Jan-2013
07-Jan-2013
09-Jan-2013
02-Jan-2013
03-Jan-2013
05-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
14-Jan-2013
17-Jan-2013
23-Jan-2013
25-Jan-2013
26-Jan-2013
26-Jan-2013
29-Dec-2012
02-Jan-2013
03-Jan-2013
05-Jan-2013
08-Jan-2013
09-Jan-2013
16-AUG-13
20-AUG-13
21-AUG-13
23-AUG-13
26-AUG-13
22-AUG-13
26-AUG-13
29-AUG-13
04-SEP-13
10-SEP-13
12-SEP-13
21-Apr-2013A
21-APR-13A
22-APR-13A
24-APR-13A
26-APR-13A
26-APR-13A
29-APR-13A
19-AUG-13
20-AUG-13
22-AUG-13
24-AUG-13
26-AUG-13
27-AUG-13
30-AUG-13
03-SEP-13
09-SEP-13
11-SEP-13
12-SEP-13
08-Aug-2013
22-APR-13A
23-APR-13A
24-APR-13A
08-JUL-13A
10-JUL-13A
11-JUL-13A
-196d
-196d
-196d
-196d
-196d
-196d
-196d
-196d
-196d
-196d
-196d
-166d
-96d
-94d
-94d
-157d
-157d
-157d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 20
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A59220
A59230
A59240
A59250
A59260
A59270
14
A59390
A59400
A59410
A59420
A59430
A59440
A59450
A59460
A59470
A59480
A59490
05-Jan-2013
09-Jan-2013
12-Jan-2013
18-Jan-2013
24-Jan-2013
26-Jan-2013
27-Dec-2012
27-Dec-2012
31-Dec-2012
03-Jan-2013
04-Jan-2013
07-Jan-2013
09-Jan-2013
05-Jan-2013
09-Jan-2013
12-Jan-2013
18-Jan-2013
24-Jan-2013
10-Jan-2013
14-Jan-2013
17-Jan-2013
23-Jan-2013
25-Jan-2013
26-Jan-2013
26-Jan-2013
29-Dec-2012
02-Jan-2013
03-Jan-2013
05-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
14-Jan-2013
17-Jan-2013
23-Jan-2013
25-Jan-2013
28-APR-13A
05-MAY-13A
08-MAY-13A
10-MAY-13A
12-MAY-13A
15-MAY-13A
29-Mar-2013A
29-MAR-13A
02-APR-13A
05-APR-13A
07-APR-13A
09-APR-13A
18-APR-13A
18-APR-13A
19-APR-13A
22-APR-13A
23-APR-13A
01-MAY-13A
12-JUL-13A
16-JUL-13A
19-JUL-13A
25-JUL-13A
27-JUL-13A
29-JUL-13A
31-May-2013
02-APR-13A
04-APR-13A
05-APR-13A
08-APR-13A
17-APR-13A
18-APR-13A
20-APR-13A
21-APR-13A
22-APR-13A
06-MAY-13A
12-MAY-13A
-157d
-157d
-157d
-157d
-157d
-157d
-107d
-79d
-78d
-78d
-78d
-84d
-84d
-85d
-83d
-80d
-87d
-91d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Slab Concrete
9 BT 15
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 21
10 Excavation
10 Soling
10 PCC
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A59500
11
A59040
A59050
A59060
A59070
A59080
A59090
A59100
A59110
A59120
A59130
A59140
A59150
15
A59510
A59520
A59530
26-Jan-2013
24-Dec-2012
24-Dec-2012
27-Dec-2012
31-Dec-2012
01-Jan-2013
03-Jan-2013
05-Jan-2013
02-Jan-2013
05-Jan-2013
09-Jan-2013
15-Jan-2013
21-Jan-2013
23-Jan-2013
24-Dec-2012
24-Dec-2012
27-Dec-2012
31-Dec-2012
26-Jan-2013
23-Jan-2013
26-Dec-2012
29-Dec-2012
31-Dec-2012
02-Jan-2013
04-Jan-2013
05-Jan-2013
07-Jan-2013
10-Jan-2013
14-Jan-2013
19-Jan-2013
22-Jan-2013
23-Jan-2013
23-Jan-2013
26-Dec-2012
29-Dec-2012
31-Dec-2012
03-MAY-13A
21-Apr-2013A
21-APR-13A
22-APR-13A
24-APR-13A
26-APR-13A
26-APR-13A
29-APR-13A
28-APR-13A
05-MAY-13A
08-MAY-13A
10-MAY-13A
12-MAY-13A
15-MAY-13A
29-Mar-2013A
29-MAR-13A
02-APR-13A
05-APR-13A
17-MAY-13A
08-Aug-2013
22-APR-13A
23-APR-13A
24-APR-13A
08-JUL-13A
10-JUL-13A
11-JUL-13A
12-JUL-13A
16-JUL-13A
19-JUL-13A
25-JUL-13A
27-JUL-13A
29-JUL-13A
31-May-2013
02-APR-13A
04-APR-13A
05-APR-13A
-94d
-169d
-99d
-97d
-97d
-160d
-160d
-160d
-160d
-160d
-160d
-160d
-160d
-160d
-110d
-82d
-81d
-81d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 22
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A59540
A59550
A59560
A59570
A59580
A59590
A59600
A59610
A59620
13
A59280
A59290
A32510
A59300
A59310
A59320
A59330
A59340
01-Jan-2013
03-Jan-2013
05-Jan-2013
02-Jan-2013
05-Jan-2013
09-Jan-2013
15-Jan-2013
21-Jan-2013
23-Jan-2013
24-Dec-2012
24-Dec-2012
31-Dec-2012
03-Jan-2013
04-Jan-2013
07-Jan-2013
09-Jan-2013
05-Jan-2013
09-Jan-2013
02-Jan-2013
04-Jan-2013
05-Jan-2013
07-Jan-2013
10-Jan-2013
14-Jan-2013
19-Jan-2013
22-Jan-2013
23-Jan-2013
26-Jan-2013
29-Dec-2012
02-Jan-2013
03-Jan-2013
05-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
14-Jan-2013
07-APR-13A
09-APR-13A
18-APR-13A
18-APR-13A
19-APR-13A
22-APR-13A
23-APR-13A
01-MAY-13A
03-MAY-13A
03-Jun-2013
03-JUN-13
10-JUN-13
13-JUN-13
14-JUN-13
17-JUN-13
19-JUN-13
15-JUN-13
19-JUN-13
08-APR-13A
17-APR-13A
18-APR-13A
20-APR-13A
21-APR-13A
22-APR-13A
06-MAY-13A
12-MAY-13A
17-MAY-13A
06-Jul-2013
08-JUN-13
12-JUN-13
13-JUN-13
15-JUN-13
18-JUN-13
19-JUN-13
20-JUN-13
24-JUN-13
-81d
-87d
-87d
-88d
-86d
-83d
-90d
-94d
-97d
-138d
-138d
-138d
-138d
-138d
-138d
-138d
-138d
-138d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 2
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 3
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A59350
A59360
A59370
A59380
1
A57840
A57850
A57860
A57870
A57880
A57890
A57900
A57910
A57920
A57930
A57940
A57950
2
12-Jan-2013
18-Jan-2013
24-Jan-2013
26-Jan-2013
27-Dec-2012
27-Dec-2012
31-Dec-2012
03-Jan-2013
04-Jan-2013
07-Jan-2013
09-Jan-2013
05-Jan-2013
09-Jan-2013
12-Jan-2013
18-Jan-2013
24-Jan-2013
26-Jan-2013
24-Dec-2012
17-Jan-2013
23-Jan-2013
25-Jan-2013
26-Jan-2013
26-Jan-2013
29-Dec-2012
02-Jan-2013
03-Jan-2013
05-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
14-Jan-2013
17-Jan-2013
23-Jan-2013
25-Jan-2013
26-Jan-2013
23-Jan-2013
22-JUN-13
28-JUN-13
04-JUL-13
06-JUL-13
22-Jun-2013
22-JUN-13
15-JUL-13
06-AUG-13
26-AUG-13
17-SEP-13
08-OCT-13
16-SEP-13
19-SEP-13
23-SEP-13
17-OCT-13
11-NOV-13
02-DEC-13
31-May-2013
27-JUN-13
03-JUL-13
05-JUL-13
06-JUL-13
21-Dec-2013
15-JUL-13
06-AUG-13
26-AUG-13
16-SEP-13
08-OCT-13
28-OCT-13
10-OCT-13
14-OCT-13
17-OCT-13
11-NOV-13
02-DEC-13
21-DEC-13
16-Sep-2013
-138d
-138d
-138d
-138d
-282d
-168d
-185d
-201d
-217d
-233d
-249d
-233d
-233d
-233d
-249d
-266d
-282d
-202d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 10
10 Filling
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A57960
A57970
A57980
A57990
A58000
A58010
A58020
A58030
A58040
A58050
A58060
A58070
6
A58440
A58450
A58460
A58470
A58480
24-Dec-2012
27-Dec-2012
31-Dec-2012
01-Jan-2013
03-Jan-2013
05-Jan-2013
02-Jan-2013
05-Jan-2013
09-Jan-2013
15-Jan-2013
21-Jan-2013
23-Jan-2013
15-Sep-2012
15-Sep-2012
22-Sep-2012
26-Sep-2012
27-Sep-2012
29-Sep-2012
26-Dec-2012
29-Dec-2012
31-Dec-2012
02-Jan-2013
04-Jan-2013
05-Jan-2013
07-Jan-2013
10-Jan-2013
14-Jan-2013
19-Jan-2013
22-Jan-2013
23-Jan-2013
19-Oct-2012
21-Sep-2012
25-Sep-2012
26-Sep-2012
28-Sep-2012
01-Oct-2012
31-MAY-13
13-JUN-13
26-JUN-13
06-JUL-13
18-JUL-13
31-JUL-13
17-JUL-13
20-JUL-13
24-JUL-13
09-AUG-13
24-AUG-13
05-SEP-13
01-Nov-2012A
01-NOV-12A
04-NOV-12A
07-NOV-12A
10-NOV-12A
11-NOV-12A
13-JUN-13
26-JUN-13
06-JUL-13
18-JUL-13
30-JUL-13
10-AUG-13
01-AUG-13
05-AUG-13
08-AUG-13
24-AUG-13
05-SEP-13
16-SEP-13
31-May-2013
04-NOV-12A
06-NOV-12A
10-NOV-12A
12-NOV-12A
14-NOV-12A
-144d
-152d
-161d
-169d
-177d
-185d
-177d
-177d
-177d
-185d
-193d
-202d
-192d
-37d
-35d
-38d
-37d
-37d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 BT 7
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A58490
A58500
A58510
A58520
A58530
A58540
A58550
8
A58680
A58690
A58700
A58710
A58720
A58730
A58740
A58750
A58760
A58770
02-Oct-2012
28-Sep-2012
02-Oct-2012
05-Oct-2012
11-Oct-2012
17-Oct-2012
19-Oct-2012
24-Dec-2012
24-Dec-2012
31-Dec-2012
03-Jan-2013
04-Jan-2013
07-Jan-2013
09-Jan-2013
05-Jan-2013
09-Jan-2013
12-Jan-2013
18-Jan-2013
02-Oct-2012
03-Oct-2012
06-Oct-2012
10-Oct-2012
16-Oct-2012
18-Oct-2012
19-Oct-2012
26-Jan-2013
29-Dec-2012
02-Jan-2013
03-Jan-2013
05-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
14-Jan-2013
17-Jan-2013
23-Jan-2013
14-NOV-12A
13-NOV-12A
15-NOV-12A
20-NOV-12A
19-NOV-12A
21-NOV-12A
24-NOV-12A
19-Jul-2013
19-JUL-13
26-JUL-13
30-JUL-13
31-JUL-13
02-AUG-13
05-AUG-13
01-AUG-13
05-AUG-13
08-AUG-13
14-AUG-13
15-NOV-12A
18-NOV-12A
20-NOV-12A
21-NOV-12A
22-NOV-12A
23-NOV-12A
24-NOV-12A
22-Aug-2013
25-JUL-13
29-JUL-13
30-JUL-13
01-AUG-13
03-AUG-13
05-AUG-13
06-AUG-13
09-AUG-13
13-AUG-13
19-AUG-13
-37d
-39d
-37d
-35d
-31d
-30d
-30d
-178d
-178d
-178d
-178d
-178d
-178d
-178d
-178d
-178d
-178d
-178d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Slab Reinforcement
10 Slab Concrete
8 Main Tunnel
9 Main Tunnel -14
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -4
10 Excavation
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A58780
A58790
1
14
A55090
A55100
A55110
A55120
A55130
A55140
A55150
A55160
A55170
A55180
A55190
A55200
4
A27090
24-Jan-2013
26-Jan-2013
23-Aug-2012
19-Sep-2012
19-Sep-2012
01-Oct-2012
10-Oct-2012
12-Oct-2012
22-Oct-2012
31-Oct-2012
31-Oct-2012
05-Nov-2012
09-Nov-2012
16-Nov-2012
23-Nov-2012
01-Dec-2012
27-Sep-2012
27-Sep-2012
25-Jan-2013
26-Jan-2013
09-Jan-2013
03-Dec-2012
29-Sep-2012
09-Oct-2012
11-Oct-2012
20-Oct-2012
30-Oct-2012
01-Nov-2012
08-Nov-2012
13-Nov-2012
17-Nov-2012
24-Nov-2012
29-Nov-2012
03-Dec-2012
11-Dec-2012
08-Oct-2012
20-AUG-13
22-AUG-13
05-Oct-2012A
26-Dec-2012A
26-DEC-12A
26-JAN-13A
02-MAR-13A
10-MAR-13A
15-MAR-13A
29-MAR-13A
18-MAR-13A
15-MAY-13A
24-JUN-13
01-JUL-13
08-JUL-13
16-JUL-13
05-Oct-2012A
05-OCT-12A
21-AUG-13
22-AUG-13
19-Aug-2013
17-Jul-2013
07-JAN-13A
06-FEB-13A
06-MAR-13A
11-MAR-13A
20-MAR-13A
30-MAR-13A
04-JUN-13
27-JUN-13
02-JUL-13
09-JUL-13
13-JUL-13
17-JUL-13
31-May-2013
20-OCT-12A
-178d
-178d
-190d
-194d
-84d
-102d
-124d
-120d
-120d
-127d
-178d
-194d
-194d
-194d
-194d
-194d
-147d
-10d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -8
10 Filling
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A27100
A27110
A27120
A27130
A27140
A27150
A27160
A27170
A54470
A54480
A54490
8
A27570
A27580
A27590
A27600
A27610
A27620
09-Oct-2012
18-Oct-2012
20-Oct-2012
30-Oct-2012
08-Nov-2012
08-Nov-2012
13-Nov-2012
17-Nov-2012
24-Nov-2012
01-Dec-2012
10-Dec-2012
19-Sep-2012
19-Sep-2012
01-Oct-2012
10-Oct-2012
12-Oct-2012
22-Oct-2012
31-Oct-2012
17-Oct-2012
19-Oct-2012
29-Oct-2012
07-Nov-2012
09-Nov-2012
16-Nov-2012
21-Nov-2012
26-Nov-2012
03-Dec-2012
07-Dec-2012
11-Dec-2012
03-Dec-2012
29-Sep-2012
09-Oct-2012
11-Oct-2012
20-Oct-2012
30-Oct-2012
01-Nov-2012
15-OCT-12A
31-OCT-12A
03-NOV-12A
04-NOV-12A
19-NOV-12A
15-NOV-12A
05-JAN-13A
14-JAN-13A
09-MAR-13A
15-MAR-13A
22-MAR-13A
10-Mar-2013A
10-MAR-13A
24-MAR-13A
02-APR-13A
06-APR-13A
08-APR-13A
12-APR-13A
30-OCT-12A
02-NOV-12A
09-NOV-12A
18-NOV-12A
20-NOV-12A
28-FEB-13A
09-MAR-13A
11-MAR-13A
16-MAR-13A
22-MAR-13A
23-MAR-13A
26-Jun-2013
25-MAR-13A
01-APR-13A
03-APR-13A
07-APR-13A
12-APR-13A
13-APR-13A
-10d
-11d
-9d
-9d
-8d
-88d
-92d
-89d
-88d
-89d
-87d
-176d
-150d
-148d
-148d
-144d
-140d
-139d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -7
10 Filling
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A27630
A27640
A27650
A27660
A27670
A27680
7
A27450
A27460
A27470
A27480
A54680
A54690
A54700
A54710
A54720
A27540
A27550
31-Oct-2012
05-Nov-2012
09-Nov-2012
16-Nov-2012
23-Nov-2012
01-Dec-2012
07-Sep-2012
07-Sep-2012
19-Sep-2012
28-Sep-2012
01-Oct-2012
10-Oct-2012
19-Oct-2012
19-Oct-2012
24-Oct-2012
29-Oct-2012
05-Nov-2012
12-Nov-2012
08-Nov-2012
13-Nov-2012
17-Nov-2012
24-Nov-2012
29-Nov-2012
03-Dec-2012
21-Nov-2012
18-Sep-2012
27-Sep-2012
29-Sep-2012
09-Oct-2012
18-Oct-2012
20-Oct-2012
27-Oct-2012
01-Nov-2012
06-Nov-2012
13-Nov-2012
17-Nov-2012
11-APR-13A
16-APR-13A
27-APR-13A
28-MAY-13A
17-JUN-13
25-JUN-13
19-Oct-2012A
19-OCT-12A
29-MAR-13A
03-APR-13A
07-APR-13A
08-APR-13A
11-APR-13A
11-APR-13A
20-APR-13A
03-MAY-13A
31-MAY-13A
07-JUN-13
18-MAY-13A
25-MAY-13A
26-MAY-13A
18-JUN-13
22-JUN-13
26-JUN-13
17-Jun-2013
30-OCT-12A
01-APR-13A
04-APR-13A
09-APR-13A
11-APR-13A
12-APR-13A
23-MAY-13A
28-MAY-13A
29-MAY-13A
08-JUN-13
13-JUN-13
-163d
-165d
-162d
-176d
-176d
-176d
-178d
-35d
-158d
-159d
-155d
-149d
-148d
-177d
-177d
-174d
-178d
-178d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Slab Concrete
9 Main Tunnel -3
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -15
10 Excavation
10 Soling
10 PCC
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A27560
3
A26970
A26980
A26990
A27000
A27010
A27020
A27030
A27040
A27050
A27060
A27070
A27080
15
A55210
A55220
A55230
20-Nov-2012
15-Sep-2012
15-Sep-2012
27-Sep-2012
06-Oct-2012
09-Oct-2012
18-Oct-2012
27-Oct-2012
27-Oct-2012
01-Nov-2012
06-Nov-2012
13-Nov-2012
20-Nov-2012
28-Nov-2012
01-Oct-2012
01-Oct-2012
12-Oct-2012
22-Oct-2012
21-Nov-2012
29-Nov-2012
26-Sep-2012
05-Oct-2012
08-Oct-2012
17-Oct-2012
26-Oct-2012
29-Oct-2012
05-Nov-2012
09-Nov-2012
14-Nov-2012
21-Nov-2012
26-Nov-2012
29-Nov-2012
14-Dec-2012
11-Oct-2012
20-Oct-2012
23-Oct-2012
15-JUN-13
05-Oct-2012A
05-OCT-12A
15-OCT-12A
31-OCT-12A
03-NOV-12A
04-NOV-12A
19-NOV-12A
15-NOV-12A
05-JAN-13A
14-JAN-13A
04-MAR-13A
12-MAR-13A
18-MAR-13A
25-Dec-2012A
25-DEC-12A
25-JAN-13A
17-FEB-13A
17-JUN-13
31-May-2013
20-OCT-12A
30-OCT-12A
02-NOV-12A
09-NOV-12A
18-NOV-12A
20-NOV-12A
02-MAR-13A
04-MAR-13A
05-MAR-13A
13-MAR-13A
17-MAR-13A
19-MAR-13A
26-Jul-2013
05-JAN-13A
05-FEB-13A
19-FEB-13A
-178d
-157d
-20d
-20d
-21d
-19d
-19d
-18d
-100d
-97d
-94d
-95d
-95d
-93d
-192d
-73d
-91d
-101d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -1
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A55240
A55250
A55260
A55270
A55280
A55290
A55300
A55310
A55320
1
A26730
A26740
A26750
A26760
A26770
A26780
A26790
A26800
24-Oct-2012
02-Nov-2012
12-Nov-2012
12-Nov-2012
16-Nov-2012
21-Nov-2012
28-Nov-2012
05-Dec-2012
13-Dec-2012
23-Aug-2012
23-Aug-2012
04-Sep-2012
13-Sep-2012
15-Sep-2012
25-Sep-2012
04-Oct-2012
04-Oct-2012
09-Oct-2012
01-Nov-2012
10-Nov-2012
13-Nov-2012
20-Nov-2012
24-Nov-2012
29-Nov-2012
06-Dec-2012
11-Dec-2012
14-Dec-2012
06-Nov-2012
03-Sep-2012
12-Sep-2012
14-Sep-2012
24-Sep-2012
03-Oct-2012
05-Oct-2012
12-Oct-2012
17-Oct-2012
29-APR-13A
08-MAY-13A
17-MAY-13A
10-MAY-13A
01-JUN-13A
03-JUL-13
10-JUL-13
17-JUL-13
25-JUL-13
04-Mar-2013A
04-MAR-13A
05-MAR-13A
24-APR-13A
26-APR-13A
27-APR-13A
06-MAY-13A
05-MAY-13A
09-MAY-13A
09-MAY-13A
17-MAY-13A
29-MAY-13A
13-JUN-13
06-JUL-13
11-JUL-13
18-JUL-13
23-JUL-13
26-JUL-13
10-Jun-2013A
05-MAR-13A
06-MAR-13A
26-APR-13A
06-MAY-13A
08-MAY-13A
09-MAY-13A
20-MAY-13A
21-MAY-13A
-161d
-160d
-168d
-176d
-192d
-192d
-192d
-192d
-192d
-185d
-156d
-149d
-191d
-191d
-185d
-184d
-187d
-184d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -5
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -18
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A26810
A26820
A26830
A26840
5
A54500
A54510
A54520
A54530
A54540
A54550
A54560
A54570
A54580
A54590
A54600
A54610
18
13-Oct-2012
20-Oct-2012
27-Oct-2012
05-Nov-2012
09-Oct-2012
09-Oct-2012
20-Oct-2012
30-Oct-2012
01-Nov-2012
10-Nov-2012
20-Nov-2012
20-Nov-2012
24-Nov-2012
29-Nov-2012
06-Dec-2012
13-Dec-2012
21-Dec-2012
02-Nov-2012
22-Oct-2012
29-Oct-2012
02-Nov-2012
06-Nov-2012
22-Dec-2012
19-Oct-2012
29-Oct-2012
31-Oct-2012
09-Nov-2012
19-Nov-2012
21-Nov-2012
28-Nov-2012
03-Dec-2012
07-Dec-2012
14-Dec-2012
19-Dec-2012
22-Dec-2012
09-Jan-2013
11-MAY-13A
23-MAY-13A
26-MAY-13A
30-MAY-13A
15-Oct-2012A
15-OCT-12A
06-APR-13A
18-APR-13A
19-APR-13A
20-APR-13A
29-APR-13A
28-APR-13A
05-MAY-13A
25-MAY-13A
05-JUN-13
12-JUN-13
27-JUN-13
15-Apr-2013A
25-MAY-13A
01-JUN-13A
06-JUN-13A
10-JUN-13A
05-Jul-2013
25-OCT-12A
08-APR-13A
18-APR-13A
21-APR-13A
11-MAY-13A
14-MAY-13A
28-MAY-13A
08-JUN-13
13-JUN-13
20-JUN-13
25-JUN-13
05-JUL-13
19-Aug-2013
-184d
-184d
-184d
-184d
-167d
-4d
-137d
-144d
-139d
-149d
-149d
-154d
-161d
-161d
-161d
-161d
-167d
-190d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -16
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A55570
A55580
A55590
A55600
A55610
A55620
A55630
A55640
A55650
A55660
A55670
A55680
16
A55330
A55340
A55350
A55360
A55370
02-Nov-2012
12-Nov-2012
19-Nov-2012
23-Nov-2012
03-Dec-2012
10-Dec-2012
12-Dec-2012
17-Dec-2012
21-Dec-2012
28-Dec-2012
01-Jan-2013
09-Jan-2013
12-Oct-2012
12-Oct-2012
24-Oct-2012
02-Nov-2012
05-Nov-2012
14-Nov-2012
08-Nov-2012
17-Nov-2012
19-Nov-2012
29-Nov-2012
08-Dec-2012
10-Dec-2012
18-Dec-2012
22-Dec-2012
27-Dec-2012
03-Jan-2013
07-Jan-2013
09-Jan-2013
26-Dec-2012
23-Oct-2012
01-Nov-2012
03-Nov-2012
13-Nov-2012
22-Nov-2012
15-APR-13A
31-MAY-13
07-JUN-13
08-JUN-13
15-JUN-13
22-JUN-13
03-JUL-13
26-JUL-13
31-JUL-13
07-AUG-13
10-AUG-13
19-AUG-13
05-Apr-2013A
05-APR-13A
29-APR-13A
08-MAY-13A
10-MAY-13A
20-MAY-13A
19-APR-13A
06-JUN-13
07-JUN-13
14-JUN-13
21-JUN-13
22-JUN-13
09-JUL-13
01-AUG-13
06-AUG-13
13-AUG-13
16-AUG-13
19-AUG-13
05-Aug-2013
08-APR-13A
15-MAY-13A
17-MAY-13A
22-MAY-13A
28-MAY-13A
-138d
-172d
-172d
-169d
-167d
-167d
-174d
-190d
-190d
-190d
-190d
-190d
-190d
-142d
-166d
-166d
-162d
-160d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -9
10 Filling
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A55380
A55390
A55400
A55410
A55420
A55430
A55440
9
A27690
A27700
A27710
A27720
A27730
A27740
A27750
A27760
A27770
A27780
23-Nov-2012
23-Nov-2012
28-Nov-2012
03-Dec-2012
10-Dec-2012
17-Dec-2012
25-Dec-2012
01-Oct-2012
01-Oct-2012
12-Oct-2012
22-Oct-2012
24-Oct-2012
02-Nov-2012
12-Nov-2012
12-Nov-2012
16-Nov-2012
21-Nov-2012
28-Nov-2012
24-Nov-2012
01-Dec-2012
06-Dec-2012
11-Dec-2012
18-Dec-2012
22-Dec-2012
26-Dec-2012
14-Dec-2012
11-Oct-2012
20-Oct-2012
23-Oct-2012
01-Nov-2012
10-Nov-2012
13-Nov-2012
20-Nov-2012
24-Nov-2012
29-Nov-2012
06-Dec-2012
29-MAY-13A
27-MAY-13A
08-JUL-13
12-JUL-13
19-JUL-13
26-JUL-13
03-AUG-13
12-Mar-2013A
12-MAR-13A
25-MAR-13A
02-APR-13A
06-APR-13A
08-APR-13A
27-APR-13A
27-APR-13A
05-MAY-13A
09-MAY-13A
31-MAY-13A
30-MAY-13A
22-JUN-13
16-JUL-13
20-JUL-13
27-JUL-13
01-AUG-13
05-AUG-13
05-Jul-2013
23-MAR-13A
30-MAR-13A
03-APR-13A
07-APR-13A
30-APR-13A
02-MAY-13A
16-MAY-13A
28-MAY-13A
30-MAY-13A
27-JUN-13
-160d
-174d
-190d
-190d
-190d
-190d
-190d
-174d
-139d
-137d
-138d
-134d
-146d
-146d
-151d
-157d
-156d
-174d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -12
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -11
10 Excavation
10 Soling
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A27790
A27800
12
A54850
A54860
A54870
A54880
A54890
A54900
A54910
A54920
A54930
A54940
A54950
A54960
11
A54730
A54740
05-Dec-2012
13-Dec-2012
27-Aug-2012
27-Aug-2012
07-Sep-2012
17-Sep-2012
19-Sep-2012
28-Sep-2012
08-Oct-2012
08-Oct-2012
12-Oct-2012
17-Oct-2012
24-Oct-2012
31-Oct-2012
08-Nov-2012
24-Oct-2012
24-Oct-2012
05-Nov-2012
11-Dec-2012
14-Dec-2012
09-Nov-2012
06-Sep-2012
15-Sep-2012
18-Sep-2012
27-Sep-2012
06-Oct-2012
09-Oct-2012
16-Oct-2012
20-Oct-2012
25-Oct-2012
01-Nov-2012
06-Nov-2012
09-Nov-2012
07-Jan-2013
03-Nov-2012
13-Nov-2012
26-JUN-13
04-JUL-13
27-Dec-2012A
27-DEC-12A
27-JAN-13A
02-MAR-13A
10-MAR-13A
15-MAR-13A
29-MAR-13A
20-MAR-13A
02-MAY-13A
08-MAY-13A
12-JUN-13
19-JUN-13
27-JUN-13
05-Feb-2013A
05-FEB-13A
25-MAR-13A
02-JUL-13
05-JUL-13
28-Jun-2013
08-JAN-13A
08-FEB-13A
06-MAR-13A
12-MAR-13A
21-MAR-13A
30-MAR-13A
11-MAY-13A
08-JUN-13
13-JUN-13
20-JUN-13
25-JUN-13
28-JUN-13
24-Jul-2013
20-FEB-13A
28-MAR-13A
-174d
-174d
-198d
-105d
-124d
-144d
-141d
-141d
-147d
-178d
-198d
-198d
-198d
-198d
-198d
-170d
-92d
-115d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -10
10 Filling
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A54750
A54760
A54770
A54780
A54790
A54800
A54810
A54820
A54830
A54840
10
A27810
A27820
A27830
A27840
A27850
A27860
A27870
14-Nov-2012
16-Nov-2012
26-Nov-2012
05-Dec-2012
05-Dec-2012
10-Dec-2012
14-Dec-2012
21-Dec-2012
28-Dec-2012
05-Jan-2013
12-Oct-2012
12-Oct-2012
24-Oct-2012
02-Nov-2012
05-Nov-2012
14-Nov-2012
23-Nov-2012
23-Nov-2012
15-Nov-2012
24-Nov-2012
04-Dec-2012
06-Dec-2012
13-Dec-2012
18-Dec-2012
22-Dec-2012
29-Dec-2012
03-Jan-2013
07-Jan-2013
26-Dec-2012
23-Oct-2012
01-Nov-2012
03-Nov-2012
13-Nov-2012
22-Nov-2012
24-Nov-2012
01-Dec-2012
31-MAR-13A
04-APR-13A
05-APR-13A
09-APR-13A
08-APR-13A
15-APR-13A
27-APR-13A
31-MAY-13A
15-JUL-13
23-JUL-13
05-Feb-2013A
05-FEB-13A
25-MAR-13A
31-MAR-13A
04-APR-13A
06-APR-13A
09-APR-13A
08-APR-13A
01-APR-13A
05-APR-13A
09-APR-13A
10-APR-13A
14-MAY-13A
06-JUN-13A
13-JUN-13A
16-JUL-13
20-JUL-13
24-JUL-13
15-Jul-2013
20-FEB-13A
30-MAR-13A
01-APR-13A
05-APR-13A
09-APR-13A
10-APR-13A
15-APR-13A
-116d
-112d
-107d
-106d
-130d
-146d
-148d
-170d
-170d
-170d
-172d
-102d
-127d
-126d
-122d
-117d
-116d
-114d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -6
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -17
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A27880
A27890
A27900
A27910
A27920
6
A54630
A54640
A54650
A54660
A54670
A27390
A27400
A27410
A27420
A27430
A27440
17
28-Nov-2012
03-Dec-2012
10-Dec-2012
17-Dec-2012
25-Dec-2012
01-Nov-2012
01-Nov-2012
10-Nov-2012
13-Nov-2012
22-Nov-2012
01-Dec-2012
01-Dec-2012
06-Dec-2012
11-Dec-2012
18-Dec-2012
25-Dec-2012
02-Jan-2013
24-Oct-2012
06-Dec-2012
11-Dec-2012
18-Dec-2012
22-Dec-2012
26-Dec-2012
03-Jan-2013
09-Nov-2012
12-Nov-2012
21-Nov-2012
30-Nov-2012
03-Dec-2012
10-Dec-2012
14-Dec-2012
19-Dec-2012
26-Dec-2012
31-Dec-2012
03-Jan-2013
03-Jan-2013
12-APR-13A
20-APR-13A
27-APR-13A
05-JUL-13
13-JUL-13
29-Mar-2013A
29-MAR-13A
03-APR-13A
06-APR-13A
10-APR-13A
29-APR-13A
28-APR-13A
06-MAY-13A
18-MAY-13A
30-MAY-13A
26-JUN-13
12-JUL-13
07-Apr-2013A
28-MAY-13A
04-JUN-13A
06-JUL-13
11-JUL-13
15-JUL-13
24-Jul-2013
03-APR-13A
04-APR-13A
09-APR-13A
17-MAY-13A
20-MAY-13A
05-JUN-13A
14-JUN-13A
22-JUN-13A
06-JUL-13
11-JUL-13
24-JUL-13
13-Aug-2013
-148d
-150d
-172d
-172d
-172d
-173d
-123d
-122d
-118d
-144d
-144d
-152d
-156d
-158d
-165d
-165d
-172d
-190d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -13
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A55450
A55460
A55470
A55480
A55490
A55500
A55510
A55520
A55530
A55540
A55550
A55560
13
A54970
A54980
A54990
A55000
A55010
24-Oct-2012
02-Nov-2012
12-Nov-2012
14-Nov-2012
23-Nov-2012
03-Dec-2012
03-Dec-2012
07-Dec-2012
12-Dec-2012
19-Dec-2012
25-Dec-2012
02-Jan-2013
07-Sep-2012
07-Sep-2012
19-Sep-2012
28-Sep-2012
01-Oct-2012
10-Oct-2012
01-Nov-2012
10-Nov-2012
13-Nov-2012
22-Nov-2012
01-Dec-2012
04-Dec-2012
11-Dec-2012
15-Dec-2012
20-Dec-2012
27-Dec-2012
31-Dec-2012
03-Jan-2013
21-Nov-2012
18-Sep-2012
27-Sep-2012
29-Sep-2012
09-Oct-2012
18-Oct-2012
07-APR-13A
25-APR-13A
02-MAY-13A
15-MAY-13A
16-MAY-13A
29-MAY-13A
24-JUN-13
17-JUL-13
22-JUL-13
29-JUL-13
03-AUG-13
12-AUG-13
27-Dec-2012A
27-DEC-12A
26-JAN-13A
04-MAR-13A
10-MAR-13A
13-MAR-13A
10-APR-13A
16-MAY-13A
18-MAY-13A
28-MAY-13A
06-JUN-13A
08-JUN-13A
02-JUL-13
25-JUL-13
30-JUL-13
06-AUG-13
09-AUG-13
13-AUG-13
08-Jul-2013
07-JAN-13A
08-FEB-13A
06-MAR-13A
13-MAR-13A
20-MAR-13A
-136d
-160d
-160d
-160d
-160d
-160d
-174d
-190d
-190d
-190d
-190d
-190d
-196d
-94d
-114d
-134d
-132d
-130d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
10 Slab Reinforcement
10 Slab Concrete
9 Main Tunnel -2
10 Excavation
10 Soling
10 PCC
10 Raft Shuttering
10 Raft Reinforcement
10 Raft Concrete
10 Wall Reinforcement
10 Wall shuttering
10 Wall concrete
10 Slab Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A55020
A55030
A55040
A55050
A55060
A55070
A55080
2
A26850
A26860
A26870
A26880
A26890
A26900
A26910
A26920
A26930
A26940
19-Oct-2012
19-Oct-2012
24-Oct-2012
29-Oct-2012
05-Nov-2012
12-Nov-2012
20-Nov-2012
04-Sep-2012
04-Sep-2012
15-Sep-2012
25-Sep-2012
27-Sep-2012
06-Oct-2012
16-Oct-2012
16-Oct-2012
20-Oct-2012
25-Oct-2012
01-Nov-2012
20-Oct-2012
27-Oct-2012
01-Nov-2012
06-Nov-2012
13-Nov-2012
17-Nov-2012
21-Nov-2012
17-Nov-2012
14-Sep-2012
24-Sep-2012
26-Sep-2012
05-Oct-2012
15-Oct-2012
17-Oct-2012
24-Oct-2012
29-Oct-2012
02-Nov-2012
09-Nov-2012
21-MAR-13A
20-MAR-13A
06-MAY-13A
21-MAY-13A
21-JUN-13
28-JUN-13
06-JUL-13
03-Apr-2013A
03-APR-13A
04-APR-13A
06-APR-13A
09-APR-13A
11-APR-13A
22-APR-13A
22-APR-13A
26-APR-13A
08-MAY-13A
20-MAY-13A
22-MAR-13A
01-JUN-13
18-JUN-13
22-JUN-13
29-JUN-13
04-JUL-13
08-JUL-13
19-Jun-2013A
04-APR-13A
05-APR-13A
07-APR-13A
12-APR-13A
21-APR-13A
22-APR-13A
17-MAY-13A
27-MAY-13A
04-JUN-13A
11-JUN-13A
-130d
-186d
-196d
-196d
-196d
-196d
-196d
-183d
-172d
-165d
-165d
-161d
-161d
-159d
-176d
-180d
-182d
-182d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Slab Reinforcement
10 Slab Concrete
7 MEP Works
8 MEP works S1 Branch Tunnel
8 MEP works S2 branch Tunnel
8 MEP works S3 bracnh Tunel
8 MEP works S4 branch Tunnel
8 MEP works U1 branch Tunnel
8 MEP Works Main Tunnel (NSC)
7 Clearance for S2 Block
6 Kiosk 1
7 NSC Co-ordination Works
8 Facade works
8 HVAC Works
8 FPS Works
8 Electrical Works
8 Access Control & Networking
8 Interior Works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A26950
A26960
1
A15010
A15020
A15030
A15040
A15050
A53460
A14625
K1
NSC
K1-1026
K1-1011
K1-1012
K1-1013
K1-1014
K1-1016
08-Nov-2012
16-Nov-2012
18-Oct-2012
18-Oct-2012
28-Jan-2013
28-Jan-2013
28-Jan-2013
28-Jan-2013
20-Oct-2012
10-Sep-2012
13-Aug-2012
04-Jan-2013
20-May-2013
04-Jan-2013
22-Jan-2013
02-Feb-2013
02-Feb-2013
29-Jul-2013
14-Nov-2012
17-Nov-2012
12-Apr-2013
08-Dec-2012
12-Apr-2013
12-Apr-2013
12-Apr-2013
12-Apr-2013
12-Apr-2013
10-Sep-2012
05-Oct-2013
05-Oct-2013
27-Jul-2013
25-Feb-2013
25-Feb-2013
08-Mar-2013
08-Mar-2013
05-Oct-2013
25-MAY-13A
31-MAY-13A
18-Apr-2013A
08-MAY-13A
23-AUG-13
13-SEP-13
31-MAY-13
21-DEC-13
18-APR-13A
31-MAY-13
07-Jan-2013A
15-Aug-2013
15-AUG-13
07-SEP-13
25-SEP-13
07-OCT-13
07-OCT-13
21-NOV-13
15-JUN-13A
19-JUN-13A
26-Mar-2014
22-JUL-13
06-NOV-13
27-NOV-13
14-AUG-13
26-MAR-14
15-NOV-13
31-MAY-13
29-Jan-2014
29-Jan-2014
24-OCT-13
30-OCT-13
30-OCT-13
11-NOV-13
11-NOV-13
29-JAN-14
-182d
-182d
-298d
-193d
-178d
-196d
-106d
-298d
-186d
-226d
-99d
-99d
-76d
-212d
-212d
-212d
-212d
-99d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 Finishes
8 Block Work
8 Plastering
8 Floor Finishes
8 Wall Finishes
8 External Wall Finishes & Glass Railing
7 Sub Structure
8 Earth Works
8 Foundation
7 Plumbing Works
8 1st Fix
8 2nd Fix
8 3rd Fix
7 Super Structure
8 Ground Floor Slab (Grade Slab)
8 Terrace Slab
6 HT Panel & Switch yard
7 Civil Works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
Fin
K1-1004
K1-1005
K1-1006
K1-1007
K1-1015
Sub
K1-1000
K1-1001
PHE
K1-1008
K1-1009
K1-1010
Sup
K1-1002
K1-1003
4
A52620
15-Dec-2012
15-Dec-2012
02-Jan-2013
19-Jan-2013
06-Feb-2013
02-Jan-2013
13-Aug-2012
13-Aug-2012
31-Aug-2012
08-Feb-2013
08-Feb-2013
25-Feb-2013
14-Mar-2013
23-Oct-2012
23-Oct-2012
21-Nov-2012
04-Sep-2012
04-Sep-2012
12-Mar-2013
05-Feb-2013
05-Feb-2013
22-Feb-2013
12-Mar-2013
12-Mar-2013
22-Oct-2012
15-Sep-2012
22-Oct-2012
30-Mar-2013
04-Mar-2013
25-Mar-2013
30-Mar-2013
11-Dec-2012
19-Nov-2012
11-Dec-2012
19-Apr-2013
12-Nov-2012
19-Aug-2013
19-AUG-13
05-SEP-13
23-SEP-13
10-OCT-13
05-SEP-13
07-Jan-2013A
07-JAN-13A
09-APR-13A
12-Oct-2013
12-OCT-13
29-OCT-13
15-NOV-13
26-Jun-2013
26-JUN-13
25-JUL-13
29-Mar-2013A
29-MAR-13A
14-Nov-2013
10-OCT-13
10-OCT-13
28-OCT-13
14-NOV-13
14-NOV-13
26-Jun-2013
06-JUN-13
26-JUN-13
03-Dec-2013
06-NOV-13
27-NOV-13
03-DEC-13
15-Aug-2013
24-JUL-13
15-AUG-13
31-Dec-2013
27-JUL-13
-212d
-212d
-212d
-212d
-212d
-212d
-212d
-226d
-212d
-212d
-212d
-212d
-212d
-212d
-212d
-212d
-219d
-221d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A52630
3
A53470
A53480
U1
PHE
U1-1013
U1-1014
U1-1015
Sup
4
4
2
A26430
A26450
A26460
3
A26440
25-Dec-2012
13-Sep-2012
13-Sep-2012
22-Nov-2012
22-Aug-2012
26-Mar-2013
26-Mar-2013
06-Apr-2013
18-Apr-2013
17-Dec-2012
29-Dec-2012
29-Dec-2012
29-Dec-2012
07-Jan-2013
29-Dec-2012
04-Jan-2013
12-Jan-2013
17-Jan-2013
19-Apr-2013
06-Mar-2013
21-Nov-2012
06-Mar-2013
17-Dec-2013
08-Jun-2013
16-May-2013
28-May-2013
08-Jun-2013
18-Mar-2013
01-Feb-2013
28-Jan-2013
17-Jan-2013
17-Jan-2013
09-Jan-2013
15-Jan-2013
28-Jan-2013
28-Jan-2013
06-SEP-13
10-Apr-2013A
10-APR-13A
02-AUG-13
18-Aug-2012A
15-Jun-2013
15-JUN-13
27-JUN-13
09-JUL-13
17-Dec-2012A
14-Feb-2013A
23-Feb-2013A
23-Feb-2013A
25-FEB-13A
23-FEB-13A
24-FEB-13A
27-Feb-2013A
15-MAR-13A
31-DEC-13
16-Nov-2013
01-AUG-13
16-NOV-13
20-Mar-2014
30-Aug-2013
07-AUG-13
19-AUG-13
30-AUG-13
11-Jun-2013
31-May-2013
31-May-2013
31-May-2013
28-FEB-13A
26-FEB-13A
27-FEB-13A
31-May-2013
17-MAR-13A
-219d
-219d
-217d
-219d
-80d
-71d
-71d
-71d
-71d
-73d
-102d
-106d
-115d
-35d
-40d
-36d
-106d
-41d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Shuttering
11 Reinforcement
9 Zone 2 (1-6/A-C)
10 Column
11 Concrete
11 Reinforcement
11 Shuttering
10 Slab
11 Concrete
11 Shuttering
11 Reinforcement
9 Zone 3 (6-11/C-E)
10 Column
11 Shuttering
11 Reinforcement
11 Concrete
10 Slab
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A26470
A26480
2
2
A26310
A26330
A26340
3
A26320
A26350
A26360
3
2
A26400
A26390
A26370
3
A26410
12-Jan-2013
15-Jan-2013
07-Jan-2013
07-Jan-2013
15-Jan-2013
07-Jan-2013
12-Jan-2013
18-Jan-2013
22-Jan-2013
18-Jan-2013
21-Jan-2013
29-Dec-2012
29-Dec-2012
04-Jan-2013
29-Dec-2012
07-Jan-2013
12-Jan-2013
12-Jan-2013
23-Jan-2013
25-Jan-2013
01-Feb-2013
23-Jan-2013
23-Jan-2013
15-Jan-2013
21-Jan-2013
01-Feb-2013
01-Feb-2013
29-Jan-2013
31-Jan-2013
28-Jan-2013
17-Jan-2013
15-Jan-2013
09-Jan-2013
17-Jan-2013
28-Jan-2013
23-Jan-2013
27-FEB-13A
05-MAR-13A
23-Feb-2013A
23-Feb-2013A
25-FEB-13A
23-FEB-13A
24-FEB-13A
27-Feb-2013A
15-MAR-13A
27-FEB-13A
05-MAR-13A
14-Feb-2013A
14-Feb-2013A
15-FEB-13A
14-FEB-13A
18-FEB-13A
18-Feb-2013A
18-FEB-13A
10-MAR-13A
14-MAR-13A
31-May-2013
31-May-2013
28-FEB-13A
26-FEB-13A
27-FEB-13A
31-May-2013
17-MAR-13A
10-MAR-13A
14-MAR-13A
31-May-2013
31-May-2013
18-FEB-13A
16-FEB-13A
19-FEB-13A
31-May-2013
27-FEB-13A
-39d
-40d
-102d
-110d
-30d
-35d
-31d
-102d
-37d
-34d
-35d
-106d
-115d
-28d
-32d
-27d
-106d
-29d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
11 Concrete
9 Zone 1 (6-11/A-C
10 Slab
11 Concrete
11 Shuttering
11 Reinforcement
10 Column
11 Concrete
11 Reinforcement
11 Shuttering
8 Mazenine Floor (+5.9m Lvl)
9 Zone 3 (6-11/C-E)
10 Column
11 Concrete
11 Reinforcement
11 Shuttering
9 Zone 4 (1-6/C-E)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A26420
A26380
1
3
A26260
A26290
A26300
2
A26250
A26270
A26280
5
3
2
A26130
A26150
A26160
4
15-Jan-2013
17-Jan-2013
07-Jan-2013
18-Jan-2013
22-Jan-2013
18-Jan-2013
21-Jan-2013
07-Jan-2013
15-Jan-2013
07-Jan-2013
12-Jan-2013
17-Dec-2012
17-Dec-2012
17-Dec-2012
20-Dec-2012
17-Dec-2012
19-Dec-2012
17-Dec-2012
25-Jan-2013
28-Jan-2013
01-Feb-2013
01-Feb-2013
01-Feb-2013
29-Jan-2013
31-Jan-2013
23-Jan-2013
23-Jan-2013
15-Jan-2013
21-Jan-2013
05-Jan-2013
28-Dec-2012
28-Dec-2012
28-Dec-2012
25-Dec-2012
27-Dec-2012
28-Dec-2012
25-FEB-13A
06-MAR-13A
14-Feb-2013A
18-Feb-2013A
06-MAR-13A
18-FEB-13A
25-FEB-13A
14-Feb-2013A
18-FEB-13A
14-FEB-13A
15-FEB-13A
17-Dec-2012A
17-Dec-2012A
17-Dec-2012A
20-DEC-12A
17-DEC-12A
19-DEC-12A
17-Dec-2012A
06-MAR-13A
07-MAR-13A
31-May-2013
31-May-2013
07-MAR-13A
27-FEB-13A
06-MAR-13A
31-May-2013
19-FEB-13A
16-FEB-13A
18-FEB-13A
31-May-2013
31-May-2013
31-May-2013
17-JAN-13A
14-JAN-13A
16-JAN-13A
31-May-2013
-33d
-32d
-102d
-102d
-28d
-24d
-28d
-110d
-22d
-27d
-23d
-125d
-132d
-132d
-16d
-16d
-16d
-132d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Column
11 Concrete
11 Reinforcement
11 Shuttering
9 Zone 2 (1-6/A-C)
10 Slab
11 Concrete
11 Shuttering
11 Reinforcement
10 Column
11 Concrete
11 Reinforcement
11 Shuttering
9 Zone 1 (6-11/A-C
10 Column
11 Concrete
11 Reinforcement
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
2
A26190
A26210
A26220
2
3
A26080
A26110
A26120
2
A26070
A26090
A26100
1
2
A53490
A26030
A26040
17-Dec-2012
20-Dec-2012
17-Dec-2012
19-Dec-2012
17-Dec-2012
24-Dec-2012
26-Dec-2012
24-Dec-2012
25-Dec-2012
17-Dec-2012
20-Dec-2012
17-Dec-2012
19-Dec-2012
17-Dec-2012
17-Dec-2012
20-Dec-2012
17-Dec-2012
19-Dec-2012
28-Dec-2012
28-Dec-2012
25-Dec-2012
27-Dec-2012
05-Jan-2013
05-Jan-2013
05-Jan-2013
03-Jan-2013
04-Jan-2013
28-Dec-2012
28-Dec-2012
25-Dec-2012
27-Dec-2012
05-Jan-2013
28-Dec-2012
28-Dec-2012
25-Dec-2012
27-Dec-2012
17-Dec-2012A
20-DEC-12A
17-DEC-12A
19-DEC-12A
17-Dec-2012A
24-Dec-2012A
26-DEC-12A
24-DEC-12A
25-DEC-12A
17-Dec-2012A
20-DEC-12A
17-DEC-12A
19-DEC-12A
17-Dec-2012A
17-Dec-2012A
20-DEC-12A
17-DEC-12A
19-DEC-12A
31-May-2013
22-JAN-13A
16-JAN-13A
21-JAN-13A
31-May-2013
31-May-2013
23-FEB-13A
17-FEB-13A
20-FEB-13A
31-May-2013
06-FEB-13A
04-FEB-13A
05-FEB-13A
31-May-2013
31-May-2013
24-JAN-13A
22-JAN-13A
23-JAN-13A
-132d
-20d
-18d
-20d
-125d
-125d
-41d
-38d
-39d
-132d
-33d
-34d
-33d
-125d
-132d
-22d
-23d
-22d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Slab
11 Concrete
11 Shuttering
11 Reinforcement
8 Terrace Floor (+17m Lvl)-2
9 Zone 2 (1-7/A-C)
10 Slab
11 Concrete
11 Shuttering
11 Reinforcement
10 Column
11 Concrete
11 Reinforcement
11 Shuttering
9 Zone 4 (1-7/C-E)
10 Slab
11 Concrete
11 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
3
A53500
A26050
A26060
6
2
3
A26560
A26590
A26600
2
A26550
A26570
A26580
4
3
A26680
A26710
24-Dec-2012
26-Dec-2012
24-Dec-2012
25-Dec-2012
29-Jan-2013
02-Feb-2013
11-Feb-2013
15-Feb-2013
11-Feb-2013
13-Feb-2013
02-Feb-2013
07-Feb-2013
02-Feb-2013
05-Feb-2013
29-Jan-2013
07-Feb-2013
12-Feb-2013
07-Feb-2013
05-Jan-2013
05-Jan-2013
03-Jan-2013
04-Jan-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
28-Feb-2013
23-Feb-2013
26-Feb-2013
18-Feb-2013
18-Feb-2013
13-Feb-2013
15-Feb-2013
25-Feb-2013
25-Feb-2013
25-Feb-2013
20-Feb-2013
24-Dec-2012A
26-DEC-12A
24-DEC-12A
25-DEC-12A
08-Mar-2013A
18-Mar-2013A
24-Mar-2013A
08-APR-13A
24-MAR-13A
30-MAR-13A
18-Mar-2013A
19-MAR-13A
18-MAR-13A
18-MAR-13A
18-Mar-2013A
25-Mar-2013A
08-APR-13A
25-MAR-13A
31-May-2013
13-FEB-13A
07-FEB-13A
12-FEB-13A
31-May-2013
31-May-2013
31-May-2013
18-APR-13A
16-APR-13A
17-APR-13A
31-May-2013
03-APR-13A
01-APR-13A
02-APR-13A
31-May-2013
31-May-2013
18-APR-13A
14-APR-13A
-125d
-32d
-29d
-32d
-79d
-79d
-79d
-41d
-43d
-42d
-88d
-37d
-39d
-38d
-82d
-82d
-44d
-45d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Reinforcement
10 Column
11 Concrete
11 Reinforcement
11 Shuttering
9 Zone 3 (7-11/C-E)
10 Column
11 Concrete
11 Reinforcement
11 Shuttering
9 Zone 1 (7-11/A-C)
10 Column
11 Concrete
11 Reinforcement
11 Shuttering
8 Above Terrace Works
9 Staircase Head rooms
9 Parapet Wall
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A26720
2
A26670
A26690
A26700
3
2
A26610
A26630
A26640
1
2
A26490
A26510
A26520
1
A53510
A53520
09-Feb-2013
29-Jan-2013
04-Feb-2013
29-Jan-2013
01-Feb-2013
29-Jan-2013
29-Jan-2013
01-Feb-2013
29-Jan-2013
31-Jan-2013
02-Feb-2013
02-Feb-2013
06-Feb-2013
02-Feb-2013
05-Feb-2013
01-Mar-2013
07-Mar-2013
01-Mar-2013
22-Feb-2013
14-Feb-2013
14-Feb-2013
08-Feb-2013
12-Feb-2013
09-Feb-2013
09-Feb-2013
09-Feb-2013
06-Feb-2013
08-Feb-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
11-Feb-2013
13-Feb-2013
18-Mar-2013
18-Mar-2013
12-Mar-2013
01-APR-13A
18-Mar-2013A
20-MAR-13A
18-MAR-13A
19-MAR-13A
08-Mar-2013A
08-Mar-2013A
14-MAR-13A
08-MAR-13A
12-MAR-13A
08-Mar-2013A
08-Mar-2013A
13-MAR-13A
08-MAR-13A
10-MAR-13A
10-May-2013A
10-MAY-13A
31-MAY-13
17-APR-13A
31-May-2013
28-MAR-13A
26-MAR-13A
28-MAR-13A
31-May-2013
31-May-2013
30-APR-13A
15-APR-13A
29-APR-13A
31-May-2013
31-May-2013
17-MAY-13A
15-MAR-13A
16-MAY-13A
11-Jun-2013
11-JUN-13
11-JUN-13
-45d
-91d
-35d
-38d
-37d
-95d
-95d
-67d
-57d
-67d
-91d
-91d
-79d
-27d
-79d
-73d
-73d
-78d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
Nsc
U1-1017
U1-1018
U1-1019
U1-1020
U1-1021
U1-1031
U1-1041
U1-1042
U1-1016
Fin
U1-1032
U1-1009
U1-1010
U1-1022
U1-1012
Sub
3
01-Mar-2013
26-Mar-2013
14-Mar-2013
14-Mar-2013
14-Mar-2013
14-Mar-2013
01-Mar-2013
07-Mar-2013
26-Jun-2013
14-Mar-2013
07-Feb-2013
01-Mar-2013
07-Feb-2013
26-Mar-2013
02-Apr-2013
02-Apr-2013
22-Aug-2012
22-Sep-2012
17-Dec-2013
12-Aug-2013
31-Jul-2013
31-Jul-2013
31-Jul-2013
23-Aug-2013
22-Aug-2013
28-Aug-2013
17-Dec-2013
12-Aug-2013
27-Jun-2013
23-Mar-2013
04-May-2013
20-Jun-2013
27-Jun-2013
27-Jun-2013
15-Dec-2012
06-Dec-2012
15-May-2013A
09-AUG-13
15-MAY-13A
31-MAY-13
31-MAY-13
20-JUN-13
23-AUG-13
13-SEP-13
21-OCT-13
13-SEP-13
02-Apr-2013A
31-MAY-13
02-APR-13A
09-APR-13A
25-APR-13A
15-JUN-13
18-Aug-2012A
25-Sep-2012A
20-Mar-2014
26-DEC-13
17-OCT-13
17-OCT-13
17-OCT-13
14-DEC-13
12-FEB-14
31-JAN-14
20-MAR-14
10-FEB-14
11-Sep-2013
22-JUN-13
26-JUL-13
03-SEP-13
11-SEP-13
11-SEP-13
31-May-2013
31-May-2013
-80d
-117d
-67d
-67d
-67d
-97d
-149d
-134d
-80d
-156d
-65d
-78d
-71d
-63d
-65d
-65d
-143d
-151d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 Grade Slab
10 Filling in plinth
10 PCC
10 Shuttering
9 Column
10 Reinforcement
10 Shuttering
10 Concrete
9 Raft
10 Drilling for rock anchoring
10 PCC
10 Shuttering
10 Reinforcement
10 Concreteing
10 Rock anchor stressing
9 Plinth Works
10 Plinth beam Shuttering
10 Plinth Beam reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
8
A25940
A25980
A25740
4
A25620
A25630
A25640
3
A25530
A25540
A25550
A25560
A25570
A25580
5
A25680
A25690
19-Nov-2012
19-Nov-2012
20-Nov-2012
26-Nov-2012
18-Oct-2012
18-Oct-2012
24-Oct-2012
26-Oct-2012
22-Sep-2012
22-Sep-2012
22-Sep-2012
25-Sep-2012
28-Sep-2012
01-Oct-2012
03-Oct-2012
12-Oct-2012
31-Oct-2012
03-Nov-2012
06-Dec-2012
24-Nov-2012
30-Nov-2012
06-Dec-2012
06-Nov-2012
29-Oct-2012
03-Nov-2012
06-Nov-2012
13-Oct-2012
01-Oct-2012
03-Oct-2012
05-Oct-2012
09-Oct-2012
11-Oct-2012
13-Oct-2012
17-Nov-2012
10-Nov-2012
14-Nov-2012
19-Nov-2012A
19-NOV-12A
20-NOV-12A
26-NOV-12A
15-Oct-2012A
15-OCT-12A
18-OCT-12A
20-OCT-12A
25-Sep-2012A
27-SEP-12A
25-SEP-12A
30-SEP-12A
06-OCT-12A
07-OCT-12A
09-OCT-12A
27-Oct-2012A
31-OCT-12A
03-NOV-12A
31-May-2013
08-DEC-12A
11-DEC-12A
12-DEC-12A
31-May-2013
02-DEC-12A
04-DEC-12A
06-DEC-12A
31-May-2013
12-OCT-12A
10-OCT-12A
13-OCT-12A
17-OCT-12A
19-OCT-12A
20-OCT-12A
31-May-2013
12-DEC-12A
13-DEC-12A
-151d
-11d
-8d
-4d
-177d
-29d
-26d
-25d
-197d
-9d
-5d
-6d
-6d
-6d
-5d
-167d
-26d
-24d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A25700
A25650
A25660
A25670
4
3
A25790
A25800
A25810
A25820
A25830
A25840
4
A25880
A25890
A25900
8
A26140
07-Nov-2012
12-Oct-2012
30-Oct-2012
27-Oct-2012
22-Sep-2012
22-Sep-2012
22-Sep-2012
22-Sep-2012
25-Sep-2012
28-Sep-2012
01-Oct-2012
03-Oct-2012
18-Oct-2012
18-Oct-2012
24-Oct-2012
26-Oct-2012
19-Nov-2012
19-Nov-2012
17-Nov-2012
29-Oct-2012
03-Nov-2012
07-Nov-2012
15-Dec-2012
13-Oct-2012
01-Oct-2012
03-Oct-2012
05-Oct-2012
09-Oct-2012
11-Oct-2012
13-Oct-2012
06-Nov-2012
29-Oct-2012
03-Nov-2012
06-Nov-2012
15-Dec-2012
24-Nov-2012
07-NOV-12A
29-OCT-12A
30-OCT-12A
27-OCT-12A
20-Sep-2012A
20-Sep-2012A
22-SEP-12A
20-SEP-12A
27-SEP-12A
28-SEP-12A
29-SEP-12A
03-OCT-12A
25-Oct-2012A
25-OCT-12A
31-OCT-12A
02-NOV-12A
19-Nov-2012A
19-NOV-12A
15-DEC-12A
07-DEC-12A
10-DEC-12A
11-DEC-12A
31-May-2013
31-May-2013
07-OCT-12A
05-OCT-12A
16-OCT-12A
18-OCT-12A
19-OCT-12A
16-OCT-12A
31-May-2013
30-NOV-12A
03-DEC-12A
05-DEC-12A
31-May-2013
07-DEC-12A
-23d
-33d
-30d
-28d
-143d
-197d
-5d
-1d
-8d
-7d
-6d
-1d
-177d
-27d
-24d
-24d
-143d
-10d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 PCC
10 Shuttering
10 Reinforcement
10 Grade Slab Concrete
9 Plinth Works
10 Plinth Beam Shuttering
10 Plinth Beam reinforcement
10 Plinth Beam Concrete
10 Back Filling
10 Antitermite treatment
10 PCC
8 Zone 2 (1-6/A-C)
9 Footing
10 Reinforcement
10 Concrete
10 Shuttering
9 Wall up to GL
10 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A26170
A26000
A26010
A26020
5
A25950
A25960
A25970
A25910
A25920
A25930
2
1
A25340
A25350
A25330
7
A25450
20-Nov-2012
26-Nov-2012
01-Dec-2012
11-Dec-2012
12-Oct-2012
31-Oct-2012
03-Nov-2012
07-Nov-2012
12-Oct-2012
30-Oct-2012
27-Oct-2012
22-Sep-2012
05-Oct-2012
10-Oct-2012
12-Oct-2012
05-Oct-2012
10-Nov-2012
10-Nov-2012
30-Nov-2012
06-Dec-2012
12-Dec-2012
15-Dec-2012
17-Nov-2012
10-Nov-2012
14-Nov-2012
17-Nov-2012
29-Oct-2012
03-Nov-2012
07-Nov-2012
15-Dec-2012
23-Oct-2012
20-Oct-2012
23-Oct-2012
16-Oct-2012
30-Nov-2012
21-Nov-2012
20-NOV-12A
26-NOV-12A
01-DEC-12A
15-DEC-12A
12-Oct-2012A
31-OCT-12A
03-NOV-12A
07-NOV-12A
12-OCT-12A
30-OCT-12A
27-OCT-12A
22-Sep-2012A
12-Oct-2012A
20-OCT-12A
12-OCT-12A
15-OCT-12A
10-Nov-2012A
10-NOV-12A
12-DEC-12A
06-JAN-13A
08-JAN-13A
09-JAN-13A
31-May-2013
06-JAN-13A
08-JAN-13A
09-JAN-13A
06-DEC-12A
11-DEC-12A
12-DEC-12A
31-May-2013
31-May-2013
29-OCT-12A
30-OCT-12A
21-OCT-12A
31-May-2013
23-JAN-13A
-9d
-26d
-22d
-20d
-167d
-48d
-46d
-44d
-32d
-31d
-29d
-143d
-189d
-6d
-5d
-4d
-156d
-53d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Shuttering
10 Concrete
9 Raft
10 Drilling for rock anchoring
10 PCC
10 Shuttering
10 Reinforcement
10 Concreteing
10 Rock anchor stressing
9 Water tank slab
10 Shuttering
10 Reinforcement
10 Concrete
9 Wall up to water tank slab
10 Reinforcement
10 Shuttering
10 Concrete
9 Ground Floor slab
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A25460
A25470
3
A25270
A25280
A25290
A25300
A25310
A25320
6
A25420
A25430
A25440
5
A25390
A25400
A25410
8
16-Nov-2012
20-Nov-2012
22-Sep-2012
22-Sep-2012
22-Sep-2012
25-Sep-2012
28-Sep-2012
01-Oct-2012
03-Oct-2012
24-Oct-2012
24-Oct-2012
30-Oct-2012
05-Nov-2012
01-Oct-2012
01-Oct-2012
12-Oct-2012
18-Oct-2012
26-Nov-2012
27-Nov-2012
30-Nov-2012
13-Oct-2012
01-Oct-2012
03-Oct-2012
05-Oct-2012
09-Oct-2012
11-Oct-2012
13-Oct-2012
15-Nov-2012
03-Nov-2012
09-Nov-2012
15-Nov-2012
29-Oct-2012
17-Oct-2012
23-Oct-2012
29-Oct-2012
15-Dec-2012
16-NOV-12A
20-NOV-12A
22-Sep-2012A
22-SEP-12A
22-SEP-12A
25-SEP-12A
28-SEP-12A
01-OCT-12A
03-OCT-12A
24-Oct-2012A
24-OCT-12A
30-OCT-12A
05-NOV-12A
01-Oct-2012A
01-OCT-12A
12-OCT-12A
18-OCT-12A
26-Nov-2012A
27-JAN-13A
30-JAN-13A
31-May-2013
19-OCT-12A
18-OCT-12A
21-OCT-12A
29-OCT-12A
30-OCT-12A
29-NOV-12A
31-May-2013
05-JAN-13A
09-JAN-13A
10-JAN-13A
31-May-2013
05-JAN-13A
09-JAN-13A
10-JAN-13A
31-May-2013
-52d
-51d
-197d
-15d
-12d
-13d
-16d
-15d
-39d
-169d
-53d
-51d
-47d
-184d
-68d
-66d
-62d
-143d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Shuttering
10 Reinforcement
10 Concrete
9 Column
10 Reinforcement
10 Shuttering
10 Concrete
8 Zone 1 (6-11/A-C)
9 Raft
10 Drilling for rock anchoring
10 PCC
10 Shuttering
10 Reinforcement
10 Concreteing
10 Rock anchor stressing
9 Water tank slab
10 Shuttering
10 Reinforcement
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A25480
A25490
A25500
4
A25360
A25370
A25380
1
3
A25010
A25020
A25030
A25040
A25050
A25060
6
A25160
A25170
26-Nov-2012
01-Dec-2012
05-Dec-2012
18-Oct-2012
18-Oct-2012
24-Oct-2012
26-Oct-2012
22-Aug-2012
22-Sep-2012
22-Sep-2012
22-Sep-2012
25-Sep-2012
28-Sep-2012
01-Oct-2012
03-Oct-2012
24-Oct-2012
24-Oct-2012
30-Oct-2012
06-Dec-2012
12-Dec-2012
15-Dec-2012
06-Nov-2012
29-Oct-2012
03-Nov-2012
06-Nov-2012
15-Dec-2012
13-Oct-2012
01-Oct-2012
03-Oct-2012
05-Oct-2012
09-Oct-2012
11-Oct-2012
13-Oct-2012
15-Nov-2012
03-Nov-2012
09-Nov-2012
26-NOV-12A
01-DEC-12A
05-DEC-12A
18-Oct-2012A
18-OCT-12A
24-OCT-12A
26-OCT-12A
18-Aug-2012A
25-Sep-2012A
28-SEP-12A
25-SEP-12A
25-SEP-12A
28-SEP-12A
01-OCT-12A
03-OCT-12A
26-Nov-2012A
26-NOV-12A
15-MAR-13A
24-JAN-13A
28-JAN-13A
30-JAN-13A
31-May-2013
05-JAN-13A
09-JAN-13A
10-JAN-13A
31-May-2013
31-May-2013
11-OCT-12A
07-OCT-12A
15-OCT-12A
17-OCT-12A
18-OCT-12A
09-NOV-12A
31-May-2013
30-APR-13A
05-MAY-13A
-41d
-39d
-38d
-177d
-58d
-56d
-55d
-143d
-197d
-8d
-3d
-7d
-6d
-5d
-22d
-169d
-151d
-151d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Concrete
9 Ground Floor slab
10 Shuttering
10 Reinforcement
10 Concrete
9 Column
10 Reinforcement
10 Shuttering
10 Concrete
9 Wall up to GL
10 Reinforcement
10 Shuttering
10 Concrete
9 Excavation
10 Mass Excavation
9 Wall up to water tank slab
10 Reinforcement
10 Shuttering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A25180
8
A25220
A25230
A25240
4
A25100
A25110
A25120
7
A25190
A25200
A25210
2
A24990
5
A25130
A25140
05-Nov-2012
26-Nov-2012
26-Nov-2012
01-Dec-2012
05-Dec-2012
18-Oct-2012
18-Oct-2012
24-Oct-2012
26-Oct-2012
10-Nov-2012
10-Nov-2012
16-Nov-2012
20-Nov-2012
22-Aug-2012
22-Aug-2012
01-Oct-2012
01-Oct-2012
12-Oct-2012
15-Nov-2012
15-Dec-2012
06-Dec-2012
12-Dec-2012
15-Dec-2012
06-Nov-2012
29-Oct-2012
03-Nov-2012
06-Nov-2012
30-Nov-2012
21-Nov-2012
27-Nov-2012
30-Nov-2012
13-Sep-2012
13-Sep-2012
29-Oct-2012
17-Oct-2012
23-Oct-2012
18-APR-13A
26-Nov-2012A
26-NOV-12A
01-DEC-12A
05-DEC-12A
18-Oct-2012A
18-OCT-12A
24-OCT-12A
30-OCT-12A
10-Nov-2012A
10-NOV-12A
16-NOV-12A
20-NOV-12A
18-Aug-2012A
18-AUG-12A
01-Oct-2012A
01-OCT-12A
12-OCT-12A
10-MAY-13A
31-May-2013
12-JAN-13A
14-JAN-13A
15-JAN-13A
31-May-2013
04-JAN-13A
07-JAN-13A
10-JAN-13A
31-May-2013
10-JAN-13A
11-JAN-13A
12-JAN-13A
31-May-2013
15-SEP-12A
31-May-2013
04-JAN-13A
07-JAN-13A
-151d
-143d
-31d
-27d
-25d
-177d
-57d
-54d
-55d
-156d
-42d
-38d
-36d
-223d
-1d
-184d
-67d
-64d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Concrete
6 Plumbing works in S2 & P1
7 Clearance of S2 block GF for plumbing
7 S2 block GF plumbing works
7 Clearance of S2 Block FF for plumbing
7 S2 block FF plumbing works
7 Clearance of S2 Block SF for plumbing
7 S2 block SF plumbing works
7 Clearance of S2 Block TF for plumbing
7 S2 block TF plumbing works
7 Clearance of S2 Block 4th Floor for plumbing
7 S2 block 4th floor plumbing works
7 Clearance of S2 Block 5th Floor for plumbing
7 S2 block 5th Floor plumbing works
7 Clearance of S2 Block Terrace for plumbing
7 S2 block Terrace plumbing works
7 Clearance of P1 Block B2 Floor for plumbing
7 P1 block B2 floor plumbing works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A25150
5
A15990
A16000
A16010
A16020
A16030
A16040
A16050
A16060
A16070
A16080
A16090
A16100
A16150
A16160
A16170
A16180
18-Oct-2012
01-Jan-2013
01-Jan-2013
01-Jan-2013
28-Jan-2013
16-Apr-2013
25-Feb-2013
25-Feb-2013
23-Mar-2013
23-Mar-2013
19-Apr-2013
19-Apr-2013
16-May-2013
16-May-2013
12-Jun-2013
12-Jun-2013
22-Jan-2013
22-Jan-2013
29-Oct-2012
01-Jan-2014
01-Jan-2013
15-Apr-2013
28-Jan-2013
29-Jul-2013
25-Feb-2013
08-Jun-2013
23-Mar-2013
05-Jul-2013
19-Apr-2013
01-Aug-2013
16-May-2013
28-Aug-2013
12-Jun-2013
24-Sep-2013
22-Jan-2013
06-May-2013
18-OCT-12A
25-Apr-2013A
31-MAY-13
25-APR-13A
05-JUN-13
06-JUN-13
31-MAY-13
31-MAY-13
31-MAY-13
31-MAY-13
11-JUN-13
12-JUN-13
11-JUN-13
12-JUN-13
13-JUN-13
14-JUN-13
31-MAY-13
01-JUN-13
10-JAN-13A
29-Jan-2014
31-MAY-13
10-AUG-13A
05-JUN-13
23-NOV-13
31-MAY-13
12-SEP-13
31-MAY-13
12-SEP-13
11-JUN-13
24-SEP-13
11-JUN-13
24-SEP-13
13-JUN-13
26-SEP-13
31-MAY-13
13-SEP-13
-62d
-24d
-129d
-101d
-111d
-101d
-82d
-82d
-59d
-59d
-46d
-46d
-23d
-23d
-2d
-2d
-112d
-112d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A16200
A16210
A16220
A16230
A16240
A16250
A16260
A16270
Ext
Ext-1001
Ext-1002
Ext-1035
2
A53530
A53540
2
6
2
22-Jan-2013
22-Jan-2013
12-Apr-2013
12-Apr-2013
01-Jul-2013
01-Jul-2013
19-Sep-2013
19-Sep-2013
22-Nov-2012
22-Mar-2013
22-Nov-2012
20-Apr-2013
13-Sep-2012
13-Sep-2012
30-Oct-2012
23-Aug-2012
29-Nov-2012
07-Dec-2012
22-Jan-2013
06-May-2013
12-Apr-2013
25-Jul-2013
01-Jul-2013
12-Oct-2013
19-Sep-2013
01-Jan-2014
21-Nov-2013
21-Nov-2013
19-Jun-2013
23-Oct-2013
27-May-2013
30-Jan-2013
27-May-2013
21-Feb-2014
21-Feb-2014
23-Oct-2013
31-MAY-13
01-JUN-13
01-JUL-13
02-JUL-13
28-AUG-13
29-AUG-13
17-OCT-13
18-OCT-13
26-Feb-2013A
19-SEP-13
26-FEB-13A
07-JAN-14
10-Dec-2012A
10-DEC-12A
18-JUN-13
23-Aug-2012A
31-May-2013
31-May-2013
31-MAY-13
13-SEP-13
01-JUL-13
14-OCT-13
28-AUG-13
11-DEC-13
17-OCT-13
29-JAN-14
26-May-2014
15-APR-14
03-FEB-14
26-MAY-14
13-Jan-2014
08-AUG-13
13-JAN-14
06-Jun-2014
06-Jun-2014
09-Nov-2013
-112d
-112d
-69d
-69d
-51d
-51d
-25d
-24d
-159d
-124d
-196d
-184d
-198d
-163d
-198d
-90d
-90d
-15d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
MS-13
MS-14
MS-15
MS-16
MS-18
MS-19
MS-20
MS-21
MS-22
1
MS-05
MS-06
MS-07
MS-08
MS-09
MS-10
MS-11
MS-12
07-Dec-2012
16-Jan-2013
06-Apr-2013
25-Jun-2013
31-Jan-2013
25-Feb-2013
16-May-2013
05-Aug-2013
23-Oct-2013
29-Nov-2012
29-Nov-2012
26-Oct-2013
07-Nov-2013
29-Nov-2013
16-Dec-2013
11-Jan-2014
31-Jan-2014
21-Feb-2014
07-Dec-2012
16-Jan-2013
06-Apr-2013
25-Jun-2013
31-Jan-2013
25-Feb-2013
16-May-2013
05-Aug-2013
23-Oct-2013
21-Feb-2014
29-Nov-2012
26-Oct-2013
07-Nov-2013
29-Nov-2013
16-Dec-2013
11-Jan-2014
31-Jan-2014
21-Feb-2014
31-MAY-13
31-MAY-13
31-MAY-13
26-JUN-13
31-MAY-13
31-MAY-13
16-JUL-13
12-SEP-13
09-NOV-13
31-May-2013
31-MAY-13
05-MAR-14
05-MAR-14
05-MAR-14
28-MAR-14
21-APR-14
14-MAY-14
06-JUN-14
31-MAY-13
31-MAY-13
31-MAY-13
26-JUN-13
31-MAY-13
31-MAY-13
16-JUL-13
12-SEP-13
09-NOV-13
06-Jun-2014
31-MAY-13
05-MAR-14
05-MAR-14
05-MAR-14
28-MAR-14
21-APR-14
14-MAY-14
06-JUN-14
-150d
-116d
-47d
-2d
-103d
-82d
-52d
-33d
-15d
-90d
-157d
-112d
-102d
-83d
-89d
-86d
-89d
-91d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Project Milestones
6 S2 Block
7 S2 Block - GF Start
7 S2 Block - 1F Start
7 S2 Block - 2F Start
7 S2 Block - 3F Start
7 S2 Block - 4F Start
7 S2 Block - 5F Start
7 S2 Block - 6F Start
6 P1 Block
7 P1 Block - Part-1 (Gr 31~16) BS1 Start
7 P1 Block - Part-2 (Gr 16~1) BS1 Start
7 P1 Block - Part-1 (Gr 31~16) GF Start
7 P1 Block - Part-2 (Gr 16~1) GF Start
7 P1 Block - Part-1 (Gr 31~16) FF Start
7 P1 Block - Part-2 (Gr 16~1) FF Start
7 P1 Block - Part-1 (Gr 31~16) TF Start
7 P1 Block - Part-2 (Gr 16~1) TF Start
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
001
1
MS-37
MS-58
MS-39
MS-30
MS-41
MS-40
MS-43
2
MS-28
MS-48
MS-29
MS-35
MS-31
MS-26
MS-32
MS-27
21-Sep-2012
03-Nov-2012
03-Nov-2012
19-Nov-2012
04-Dec-2012
03-Jan-2013
01-Feb-2013
02-Mar-2013
02-Apr-2013
22-Sep-2012
22-Sep-2012
17-Nov-2012
26-Nov-2012
09-Jan-2013
14-Feb-2013
30-Mar-2013
06-May-2013
19-Jun-2013
21-Feb-2014
02-Apr-2013
03-Nov-2012
19-Nov-2012
04-Dec-2012
03-Jan-2013
01-Feb-2013
02-Mar-2013
02-Apr-2013
19-Jun-2013
22-Sep-2012
17-Nov-2012
26-Nov-2012
09-Jan-2013
14-Feb-2013
30-Mar-2013
06-May-2013
19-Jun-2013
08-Nov-2012A
04-Dec-2012A
04-DEC-12A
12-JAN-13A
07-FEB-13A
26-FEB-13A
31-MAY-13
31-MAY-13
31-MAY-13
08-Nov-2012A
08-NOV-12A
31-JAN-13A
23-JAN-13A
31-MAY-13
31-MAY-13
22-JUN-13
31-MAY-13
20-AUG-13
06-Jun-2014
31-May-2013
04-DEC-12A
12-JAN-13A
07-FEB-13A
26-FEB-13A
31-MAY-13
31-MAY-13
31-MAY-13
20-Aug-2013
08-NOV-12A
31-JAN-13A
23-JAN-13A
31-MAY-13
31-MAY-13
22-JUN-13
31-MAY-13
20-AUG-13
-90d
-51d
-26d
-47d
-56d
-46d
-102d
-77d
-51d
-53d
-40d
-64d
-50d
-122d
-91d
-72d
-22d
-53d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
6 Project Finish
6 Mobilization
6 SPCL Infrastructure Works
5 Procurement
6 APPOINTMENT OF NSC BY CLIENT
7 Elevator
7 DG Sets
7 Electrical Packages
7 HVAC
7 Fire Fighting
7 LV System
7 Networking
7 Facade Works
7 Interior Works (Partitions & Furniture)
7 Solar Power System
7 Land Scaping
5 Construction Works
6 P1 Block
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
MS-23
MS-03
MS-04
003
001
PROC001
PROC002
PROC003
PROC004
PROC005
PROC006
PROC007
PROC008
PROC009
PROC010
PROC011
3
005
21-Feb-2014
21-Sep-2012
01-Dec-2012
01-Nov-2012
01-Nov-2012
06-Dec-2012
01-Nov-2012
01-Nov-2012
01-Nov-2012
01-Nov-2012
20-Nov-2012
02-Feb-2013
25-Apr-2013
25-Apr-2013
16-Feb-2013
25-Apr-2013
27-Aug-2012
27-Aug-2012
21-Feb-2014
21-Sep-2012
01-Dec-2012
25-Apr-2013
25-Apr-2013
06-Dec-2012
01-Nov-2012
01-Nov-2012
01-Nov-2012
01-Nov-2012
20-Nov-2012
02-Feb-2013
25-Apr-2013
25-Apr-2013
16-Feb-2013
25-Apr-2013
20-Feb-2014
20-Feb-2014
06-JUN-14
31-DEC-12A
30-JAN-13A
04-Jan-2013A
04-Jan-2013A
04-JAN-13A
04-JAN-13A
20-MAR-13A
07-MAR-13A
07-JAN-13A
06-JUN-13
06-JUN-13
08-AUG-13
08-AUG-13
24-JUL-13
08-AUG-13
23-Aug-2012A
23-Aug-2012A
06-JUN-14
31-DEC-12A
30-JAN-13A
08-Aug-2013
08-Aug-2013
04-JAN-13A
04-JAN-13A
20-MAR-13A
07-MAR-13A
07-JAN-13A
06-JUN-13
06-JUN-13
08-AUG-13
08-AUG-13
24-JUL-13
08-AUG-13
05-Jun-2014
07-Mar-2014
-91d
-86d
-51d
-90d
-90d
-25d
-55d
-119d
-108d
-57d
-171d
-107d
-91d
-91d
-136d
-91d
-90d
-13d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 Structure Works
8 BS2
9 PART-02 (GRID 01~16)
10 POUR-11 (GRID E~H / 12~16)
11 Preparatory works for PCC
11 PCC
11 Drilling for Rock Anchoring
11 Brush Bond
11 Plastering Above Brush Bond
11 Rebar works for Footings
11 Rebar works for the Columns & Shear Walls
11 Rebar works for the Raft
11 Form works for the Raft
11 Concreting of the Raft
10 POUR-12 (GRID E~H / 09~12)
11 Preparatory works for PCC
11 PCC
11 Drilling for Rock Anchoring
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
001
001
002
011
S2CONP10112
S2CONP10113
S2CONP10114
S2CONP10115
S2CONP10116
S2CONP10117
S2CONP10118
S2CONP10119
S2CONP10120
S2CONP10121
012
S2CONP10123
S2CONP10124
S2CONP10125
27-Aug-2012
27-Aug-2012
29-Oct-2012
15-Nov-2012
15-Nov-2012
17-Nov-2012
20-Nov-2012
26-Nov-2012
28-Nov-2012
01-Dec-2012
01-Dec-2012
01-Dec-2012
07-Dec-2012
12-Dec-2012
26-Nov-2012
26-Nov-2012
28-Nov-2012
30-Nov-2012
22-Oct-2013
21-Jan-2013
21-Jan-2013
12-Dec-2012
16-Nov-2012
19-Nov-2012
24-Nov-2012
30-Nov-2012
04-Dec-2012
06-Dec-2012
06-Dec-2012
07-Dec-2012
11-Dec-2012
12-Dec-2012
22-Dec-2012
27-Nov-2012
29-Nov-2012
05-Dec-2012
23-Aug-2012A
23-Aug-2012A
22-Oct-2012A
20-Nov-2012A
20-NOV-12A
25-NOV-12A
01-DEC-12A
02-DEC-12A
04-DEC-12A
11-DEC-12A
15-DEC-12A
17-JAN-13A
28-FEB-13A
07-MAR-13A
06-Dec-2012A
06-DEC-12A
08-DEC-12A
10-DEC-12A
21-Nov-2013
31-May-2013
31-May-2013
31-May-2013
07-JAN-13A
07-JAN-13A
11-JAN-13A
08-JAN-13A
10-JAN-13A
11-JAN-13A
14-JAN-13A
15-FEB-13A
06-MAR-13A
08-MAR-13A
31-May-2013
25-DEC-12A
26-DEC-12A
29-DEC-12A
-26d
-112d
-112d
-146d
-43d
-41d
-40d
-32d
-31d
-30d
-32d
-59d
-72d
-73d
-137d
-23d
-22d
-20d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Brush Bond
11 Plastering Above Brush Bond
11 Rebar works for Footings
11 Rebar works for the Columns & Shear Walls
11 Rebar works for the Raft
11 Form works for the Raft
11 Concreting of the Raft
10 POUR-13 (GRID A~D / 05~09)
11 Preparatory works for PCC
11 PCC
11 Drilling for Rock Anchoring
11 Brush Bond
11 Plastering Above Brush Bond
11 Rebar works for Footings
11 Rebar works for the Columns & Shear Walls
11 Rebar works for the Raft
11 Form works for the Raft
11 Concreting of the Raft
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10126
S2CONP10127
S2CONP10128
S2CONP10129
S2CONP10130
S2CONP10131
S2CONP10132
013
S2CONP10134
S2CONP10135
S2CONP10136
S2CONP10137
S2CONP10138
S2CONP10139
S2CONP10140
S2CONP10141
S2CONP10142
S2CONP10143
06-Dec-2012
08-Dec-2012
12-Dec-2012
12-Dec-2012
12-Dec-2012
18-Dec-2012
22-Dec-2012
05-Dec-2012
05-Dec-2012
07-Dec-2012
10-Dec-2012
15-Dec-2012
18-Dec-2012
21-Dec-2012
21-Dec-2012
21-Dec-2012
27-Dec-2012
01-Jan-2013
11-Dec-2012
14-Dec-2012
17-Dec-2012
17-Dec-2012
18-Dec-2012
21-Dec-2012
22-Dec-2012
01-Jan-2013
06-Dec-2012
08-Dec-2012
14-Dec-2012
20-Dec-2012
24-Dec-2012
26-Dec-2012
26-Dec-2012
27-Dec-2012
31-Dec-2012
01-Jan-2013
11-DEC-12A
12-DEC-12A
13-DEC-12A
15-DEC-12A
15-DEC-12A
16-DEC-12A
18-DEC-12A
06-Jan-2013A
06-JAN-13A
14-JAN-13A
15-JAN-13A
17-JAN-13A
18-JAN-13A
25-JAN-13A
02-FEB-13A
05-FEB-13A
15-FEB-13A
22-FEB-13A
31-DEC-12A
02-JAN-13A
04-JAN-13A
04-JAN-13A
05-JAN-13A
07-JAN-13A
08-JAN-13A
31-May-2013
11-JAN-13A
18-JAN-13A
24-JAN-13A
30-JAN-13A
01-FEB-13A
05-FEB-13A
09-FEB-13A
15-FEB-13A
19-FEB-13A
22-FEB-13A
-16d
-15d
-15d
-15d
-15d
-13d
-13d
-129d
-30d
-34d
-34d
-34d
-33d
-34d
-38d
-42d
-42d
-44d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
014
S2CONP10145
S2CONP10146
S2CONP10147
S2CONP10148
S2CONP10149
S2CONP10150
S2CONP10151
S2CONP10152
S2CONP10153
S2CONP10154
015
S2CONP10156
S2CONP10157
S2CONP10158
S2CONP10159
S2CONP10160
S2CONP10161
14-Dec-2012
14-Dec-2012
17-Dec-2012
19-Dec-2012
25-Dec-2012
27-Dec-2012
31-Dec-2012
31-Dec-2012
31-Dec-2012
05-Jan-2013
10-Jan-2013
25-Dec-2012
25-Dec-2012
27-Dec-2012
29-Dec-2012
04-Jan-2013
07-Jan-2013
10-Jan-2013
10-Jan-2013
15-Dec-2012
18-Dec-2012
24-Dec-2012
29-Dec-2012
02-Jan-2013
04-Jan-2013
04-Jan-2013
05-Jan-2013
09-Jan-2013
10-Jan-2013
21-Jan-2013
26-Dec-2012
28-Dec-2012
03-Jan-2013
09-Jan-2013
12-Jan-2013
15-Jan-2013
01-Nov-2012A
23-NOV-12A
26-NOV-12A
28-NOV-12A
01-NOV-12A
05-DEC-12A
07-DEC-12A
07-DEC-12A
10-DEC-12A
13-DEC-12A
17-DEC-12A
22-Oct-2012A
22-OCT-12A
07-NOV-12A
16-NOV-12A
18-NOV-12A
20-NOV-12A
22-NOV-12A
31-May-2013
14-FEB-13A
15-FEB-13A
16-FEB-13A
17-FEB-13A
19-FEB-13A
21-FEB-13A
21-FEB-13A
22-FEB-13A
24-FEB-13A
26-FEB-13A
31-May-2013
10-JAN-13A
17-JAN-13A
22-JAN-13A
25-JAN-13A
01-FEB-13A
07-FEB-13A
-121d
-51d
-50d
-46d
-42d
-41d
-40d
-40d
-40d
-39d
-39d
-112d
-12d
-16d
-15d
-13d
-16d
-19d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10162
S2CONP10163
S2CONP10164
S2CONP10165
010
S2CONP10101
S2CONP10102
S2CONP10103
S2CONP10104
S2CONP10105
S2CONP10106
S2CONP10107
S2CONP10108
S2CONP10109
S2CONP10110
009
S2CONP10091
S2CONP10092
10-Jan-2013
10-Jan-2013
16-Jan-2013
21-Jan-2013
05-Nov-2012
05-Nov-2012
07-Nov-2012
09-Nov-2012
15-Nov-2012
17-Nov-2012
21-Nov-2012
21-Nov-2012
21-Nov-2012
27-Nov-2012
01-Dec-2012
29-Oct-2012
29-Oct-2012
31-Oct-2012
15-Jan-2013
16-Jan-2013
19-Jan-2013
21-Jan-2013
01-Dec-2012
06-Nov-2012
08-Nov-2012
14-Nov-2012
20-Nov-2012
23-Nov-2012
26-Nov-2012
26-Nov-2012
27-Nov-2012
30-Nov-2012
01-Dec-2012
22-Nov-2012
30-Oct-2012
05-Nov-2012
22-NOV-12A
23-NOV-12A
25-NOV-12A
28-DEC-12A
06-Dec-2012A
06-DEC-12A
07-DEC-12A
10-DEC-12A
11-DEC-12A
13-DEC-12A
15-DEC-12A
15-DEC-12A
17-DEC-12A
19-DEC-12A
24-JAN-13A
09-Nov-2012A
09-NOV-12A
20-NOV-12A
09-FEB-13A
15-FEB-13A
24-FEB-13A
28-FEB-13A
31-May-2013
06-JAN-13A
07-JAN-13A
11-JAN-13A
08-JAN-13A
10-JAN-13A
11-JAN-13A
12-JAN-13A
22-JAN-13A
23-JAN-13A
24-JAN-13A
31-May-2013
16-NOV-12A
25-NOV-12A
-21d
-25d
-30d
-32d
-155d
-52d
-50d
-49d
-41d
-40d
-39d
-40d
-47d
-45d
-45d
-163d
-14d
-17d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Brush Bond
11 Plastering Above Brush Bond
11 Rebar works for Footings
11 Rebar works for the Columns & Shear Walls
11 Rebar works for the Raft
11 Form works for the Raft
11 Concreting of the Raft
9 PART-01 (GRID 16~31)
10 POUR-03 (GRID E~H / 28~31)
11 Preparatory works for PCC
11 PCC
11 Drilling for Rock Anchoring
11 Brush Bond
11 Plastering Above Brush Bond
11 Rebar works for Footings
11 Rebar works for the Columns & Shear Walls
11 Rebar works for the Raft
11 Form works for the Raft
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10093
S2CONP10094
S2CONP10095
S2CONP10096
S2CONP10097
S2CONP10098
S2CONP10099
001
003
S2CONP10024
S2CONP10025
S2CONP10026
S2CONP10027
S2CONP10028
S2CONP10029
S2CONP10030
S2CONP10031
S2CONP10032
06-Nov-2012
08-Nov-2012
12-Nov-2012
12-Nov-2012
12-Nov-2012
17-Nov-2012
22-Nov-2012
27-Aug-2012
20-Sep-2012
20-Sep-2012
22-Sep-2012
25-Sep-2012
01-Oct-2012
03-Oct-2012
06-Oct-2012
06-Oct-2012
06-Oct-2012
12-Oct-2012
10-Nov-2012
14-Nov-2012
16-Nov-2012
16-Nov-2012
17-Nov-2012
21-Nov-2012
22-Nov-2012
01-Dec-2012
17-Oct-2012
21-Sep-2012
24-Sep-2012
29-Sep-2012
05-Oct-2012
09-Oct-2012
11-Oct-2012
11-Oct-2012
12-Oct-2012
16-Oct-2012
21-NOV-12A
23-NOV-12A
24-NOV-12A
24-NOV-12A
25-NOV-12A
26-NOV-12A
01-DEC-12A
23-Aug-2012A
21-Sep-2012A
21-SEP-12A
10-NOV-12A
13-NOV-12A
26-NOV-12A
28-NOV-12A
29-NOV-12A
03-DEC-12A
04-DEC-12A
05-DEC-12A
26-NOV-12A
28-NOV-12A
29-NOV-12A
29-NOV-12A
30-NOV-12A
30-NOV-12A
01-DEC-12A
31-May-2013
31-May-2013
22-SEP-12A
25-NOV-12A
27-NOV-12A
29-NOV-12A
01-DEC-12A
04-DEC-12A
05-DEC-12A
05-DEC-12A
06-DEC-12A
-12d
-11d
-10d
-10d
-10d
-7d
-7d
-155d
-194d
-1d
-53d
-49d
-46d
-45d
-45d
-46d
-45d
-43d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10033
002
S2CONP10012
S2CONP10013
S2CONP10014
S2CONP10015
S2CONP10016
S2CONP10017
S2CONP10018
S2CONP10019
S2CONP10020
S2CONP10021
S2CONP10022
005
S2CONP10047
S2CONP10048
S2CONP10049
S2CONP10050
17-Oct-2012
06-Sep-2012
06-Sep-2012
11-Sep-2012
13-Sep-2012
15-Sep-2012
21-Sep-2012
24-Sep-2012
27-Sep-2012
27-Sep-2012
27-Sep-2012
03-Oct-2012
08-Oct-2012
13-Oct-2012
13-Oct-2012
16-Oct-2012
22-Oct-2012
24-Oct-2012
17-Oct-2012
08-Oct-2012
10-Sep-2012
12-Sep-2012
14-Sep-2012
20-Sep-2012
26-Sep-2012
29-Sep-2012
02-Oct-2012
02-Oct-2012
03-Oct-2012
06-Oct-2012
08-Oct-2012
07-Nov-2012
15-Oct-2012
20-Oct-2012
26-Oct-2012
30-Oct-2012
06-DEC-12A
23-Aug-2012A
23-AUG-12A
21-SEP-12A
08-OCT-12A
11-OCT-12A
15-OCT-12A
18-OCT-12A
20-OCT-12A
25-OCT-12A
24-OCT-12A
26-OCT-12A
28-OCT-12A
20-Oct-2012A
20-OCT-12A
22-OCT-12A
30-OCT-12A
03-NOV-12A
06-DEC-12A
31-May-2013
20-SEP-12A
22-SEP-12A
12-OCT-12A
20-OCT-12A
29-OCT-12A
02-NOV-12A
07-NOV-12A
09-NOV-12A
09-NOV-12A
10-NOV-12A
10-NOV-12A
31-May-2013
28-OCT-12A
30-OCT-12A
03-NOV-12A
07-NOV-12A
-42d
-202d
-8d
-9d
-23d
-25d
-27d
-28d
-30d
-32d
-31d
-29d
-28d
-176d
-11d
-7d
-6d
-6d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10051
S2CONP10052
S2CONP10053
S2CONP10054
S2CONP10055
006
S2CONP10058
S2CONP10059
S2CONP10061
S2CONP10062
S2CONP10063
S2CONP10064
S2CONP10065
S2CONP10066
007
S2CONP10068
S2CONP10069
S2CONP10070
27-Oct-2012
27-Oct-2012
27-Oct-2012
02-Nov-2012
07-Nov-2012
24-Oct-2012
24-Oct-2012
26-Oct-2012
03-Nov-2012
07-Nov-2012
07-Nov-2012
07-Nov-2012
13-Nov-2012
17-Nov-2012
31-Oct-2012
31-Oct-2012
02-Nov-2012
05-Nov-2012
01-Nov-2012
01-Nov-2012
02-Nov-2012
06-Nov-2012
07-Nov-2012
17-Nov-2012
25-Oct-2012
31-Oct-2012
09-Nov-2012
12-Nov-2012
12-Nov-2012
13-Nov-2012
16-Nov-2012
17-Nov-2012
27-Nov-2012
01-Nov-2012
03-Nov-2012
09-Nov-2012
08-NOV-12A
08-NOV-12A
12-NOV-12A
15-NOV-12A
20-NOV-12A
12-Oct-2012A
12-OCT-12A
15-OCT-12A
06-NOV-12A
12-NOV-12A
14-NOV-12A
19-NOV-12A
19-NOV-12A
24-NOV-12A
20-Nov-2012A
20-NOV-12A
01-DEC-12A
04-DEC-12A
16-NOV-12A
16-NOV-12A
19-NOV-12A
19-NOV-12A
20-NOV-12A
31-May-2013
30-OCT-12A
05-NOV-12A
15-NOV-12A
17-NOV-12A
19-NOV-12A
23-NOV-12A
23-NOV-12A
24-NOV-12A
31-May-2013
22-NOV-12A
01-DEC-12A
05-JAN-13A
-12d
-12d
-13d
-10d
-10d
-167d
-3d
-3d
-4d
-4d
-5d
-8d
-5d
-5d
-159d
-17d
-23d
-48d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Brush Bond
11 Plastering Above Brush Bond
11 Rebar works for Footings
11 Rebar works for the Columns & Shear Walls
11 Rebar works for the Raft
11 Form works for the Raft
11 Concreting of the Raft
10 POUR-01 (GRID A~D / 28~31)
11 Mass Excavation
11 Preparatory works for PCC
11 PCC
11 Drilling for Rock Anchoring
11 Brush Bond
11 Plastering Above Brush Bond
11 Rebar works for Footings
11 Rebar works for the Columns & Shear Walls
11 Rebar works for the Raft
11 Form works for the Raft
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10071
S2CONP10072
S2CONP10073
S2CONP10074
S2CONP10075
S2CONP10076
S2CONP10077
001
S2CONP10001
S2CONP10002
S2CONP10003
S2CONP10004
S2CONP10005
S2CONP10006
S2CONP10007
S2CONP10008
S2CONP10009
S2CONP10010
10-Nov-2012
13-Nov-2012
16-Nov-2012
16-Nov-2012
16-Nov-2012
22-Nov-2012
27-Nov-2012
27-Aug-2012
27-Aug-2012
31-Aug-2012
03-Sep-2012
05-Sep-2012
11-Sep-2012
13-Sep-2012
17-Sep-2012
17-Sep-2012
17-Sep-2012
22-Sep-2012
15-Nov-2012
19-Nov-2012
21-Nov-2012
21-Nov-2012
22-Nov-2012
26-Nov-2012
27-Nov-2012
27-Sep-2012
30-Aug-2012
01-Sep-2012
04-Sep-2012
10-Sep-2012
15-Sep-2012
19-Sep-2012
21-Sep-2012
21-Sep-2012
22-Sep-2012
26-Sep-2012
05-DEC-12A
07-DEC-12A
09-DEC-12A
09-DEC-12A
10-DEC-12A
12-DEC-12A
13-DEC-12A
23-Aug-2012A
23-AUG-12A
21-SEP-12A
18-OCT-12A
20-OCT-12A
22-OCT-12A
24-OCT-12A
02-NOV-12A
06-NOV-12A
15-SEP-12A
10-NOV-12A
04-JAN-13A
06-JAN-13A
08-JAN-13A
08-JAN-13A
08-JAN-13A
09-JAN-13A
09-JAN-13A
31-May-2013
20-SEP-12A
24-SEP-12A
06-NOV-12A
25-OCT-12A
27-OCT-12A
29-OCT-12A
08-NOV-12A
10-NOV-12A
12-NOV-12A
13-NOV-12A
-42d
-41d
-40d
-40d
-39d
-37d
-36d
-211d
-17d
-18d
-53d
-38d
-35d
-34d
-40d
-42d
-42d
-40d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10011
008
S2CONP10079
S2CONP10080
S2CONP10081
S2CONP10082
S2CONP10083
S2CONP10084
S2CONP10085
S2CONP10086
004
S2CONP10036
S2CONP10037
S2CONP10038
S2CONP10039
S2CONP10040
S2CONP10041
S2CONP10042
27-Sep-2012
09-Nov-2012
09-Nov-2012
12-Nov-2012
14-Nov-2012
20-Nov-2012
22-Nov-2012
26-Nov-2012
26-Nov-2012
26-Nov-2012
03-Oct-2012
03-Oct-2012
05-Oct-2012
11-Oct-2012
13-Oct-2012
17-Oct-2012
17-Oct-2012
17-Oct-2012
27-Sep-2012
01-Dec-2012
10-Nov-2012
13-Nov-2012
19-Nov-2012
24-Nov-2012
28-Nov-2012
30-Nov-2012
30-Nov-2012
01-Dec-2012
27-Oct-2012
04-Oct-2012
10-Oct-2012
16-Oct-2012
19-Oct-2012
22-Oct-2012
22-Oct-2012
23-Oct-2012
14-NOV-12A
21-Nov-2012A
21-NOV-12A
24-NOV-12A
26-NOV-12A
28-NOV-12A
29-NOV-12A
30-NOV-12A
30-NOV-12A
01-DEC-12A
09-Nov-2012A
09-NOV-12A
12-NOV-12A
14-NOV-12A
16-NOV-12A
23-NOV-12A
24-NOV-12A
24-NOV-12A
14-NOV-12A
31-May-2013
23-NOV-12A
24-NOV-12A
29-NOV-12A
01-DEC-12A
03-DEC-12A
02-DEC-12A
02-DEC-12A
05-DEC-12A
31-May-2013
12-NOV-12A
15-NOV-12A
17-NOV-12A
22-NOV-12A
26-NOV-12A
27-NOV-12A
06-DEC-12A
-40d
-155d
-10d
-9d
-8d
-5d
-3d
-1d
-1d
-2d
-185d
-32d
-31d
-28d
-28d
-29d
-30d
-37d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10043
S2CONP10044
005
002
015
S2CONP11181
S2CONP11182
S2CONP11183
S2CONP11184
S2CONP11185
S2CONP11186
S2CONP11187
S2CONP11188
S2CONP11189
S2CONP11190
009
S2CONP11121
S2CONP11122
23-Oct-2012
27-Oct-2012
06-May-2013
19-Jun-2013
06-Aug-2013
06-Aug-2013
09-Aug-2013
19-Aug-2013
30-Aug-2013
06-Sep-2013
13-Sep-2013
24-Sep-2013
04-Oct-2013
10-Oct-2013
19-Oct-2013
19-Jun-2013
19-Jun-2013
22-Jun-2013
26-Oct-2012
27-Oct-2012
22-Oct-2013
22-Oct-2013
19-Oct-2013
08-Aug-2013
17-Aug-2013
29-Aug-2013
10-Sep-2013
17-Sep-2013
26-Sep-2013
04-Oct-2013
09-Oct-2013
18-Oct-2013
19-Oct-2013
02-Sep-2013
21-Jun-2013
01-Jul-2013
27-NOV-12A
05-DEC-12A
31-May-2013
20-Aug-2013
04-Sep-2013
04-SEP-13
07-SEP-13
17-SEP-13
24-SEP-13
27-SEP-13
30-SEP-13
08-OCT-13
16-OCT-13
22-OCT-13
31-OCT-13
20-Aug-2013
20-AUG-13
23-AUG-13
05-DEC-12A
06-DEC-12A
21-Nov-2013
21-Nov-2013
01-Nov-2013
07-SEP-13
17-SEP-13
24-SEP-13
02-OCT-13
04-OCT-13
11-OCT-13
17-OCT-13
22-OCT-13
31-OCT-13
01-NOV-13
16-Oct-2013
22-AUG-13
31-AUG-13
-33d
-33d
-26d
-26d
-11d
-25d
-25d
-21d
-18d
-14d
-12d
-10d
-10d
-10d
-10d
-38d
-53d
-53d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11123
S2CONP11124
S2CONP11125
S2CONP11126
S2CONP11127
S2CONP11128
S2CONP11129
S2CONP11130
012
S2CONP11151
S2CONP11152
S2CONP11153
S2CONP11154
S2CONP11155
S2CONP11156
S2CONP11157
S2CONP11158
S2CONP11159
02-Jul-2013
13-Jul-2013
20-Jul-2013
27-Jul-2013
07-Aug-2013
17-Aug-2013
23-Aug-2013
02-Sep-2013
16-Jul-2013
16-Jul-2013
19-Jul-2013
29-Jul-2013
09-Aug-2013
16-Aug-2013
23-Aug-2013
03-Sep-2013
13-Sep-2013
19-Sep-2013
12-Jul-2013
24-Jul-2013
31-Jul-2013
09-Aug-2013
17-Aug-2013
22-Aug-2013
31-Aug-2013
02-Sep-2013
28-Sep-2013
18-Jul-2013
27-Jul-2013
08-Aug-2013
20-Aug-2013
27-Aug-2013
05-Sep-2013
13-Sep-2013
18-Sep-2013
27-Sep-2013
02-SEP-13
09-SEP-13
12-SEP-13
14-SEP-13
23-SEP-13
01-OCT-13
07-OCT-13
16-OCT-13
21-Aug-2013
21-AUG-13
24-AUG-13
03-SEP-13
10-SEP-13
13-SEP-13
16-SEP-13
24-SEP-13
02-OCT-13
08-OCT-13
07-SEP-13
16-SEP-13
18-SEP-13
25-SEP-13
01-OCT-13
05-OCT-13
15-OCT-13
16-OCT-13
17-Oct-2013
23-AUG-13
02-SEP-13
09-SEP-13
17-SEP-13
19-SEP-13
26-SEP-13
02-OCT-13
07-OCT-13
16-OCT-13
-49d
-46d
-42d
-40d
-38d
-38d
-38d
-38d
-16d
-31d
-31d
-27d
-24d
-20d
-18d
-16d
-16d
-16d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting of TF
10 POUR-14 (GRID A~D / 01~05)
11 Starters for the Columns / Shear Walls
11 Staging for the Columns / Shear Walls
11 Rebar works for the Columns / Shear Walls
11 Form works for the Columns / Shear Walls
11 Concreting of the Columns / Shear Walls
11 Table & Conventional Form Works for the TF
11 Bottom Rebar works for the TF
11 PT Tandons Laying works for the TF
11 Top Rebar works for the TF
11 Concreting of TF
10 POUR-10 (GRID A~D / 09~12)
11 Starters for the Columns / Shear Walls
11 Staging for the Columns / Shear Walls
11 Rebar works for the Columns / Shear Walls
11 Form works for the Columns / Shear Walls
11 Concreting of the Columns / Shear Walls
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11160
014
S2CONP11171
S2CONP11172
S2CONP11173
S2CONP11174
S2CONP11175
S2CONP11176
S2CONP11177
S2CONP11178
S2CONP11179
S2CONP11180
010
S2CONP11131
S2CONP11132
S2CONP11133
S2CONP11134
S2CONP11135
28-Sep-2013
29-Jul-2013
29-Jul-2013
01-Aug-2013
10-Aug-2013
22-Aug-2013
29-Aug-2013
05-Sep-2013
16-Sep-2013
26-Sep-2013
02-Oct-2013
11-Oct-2013
28-Jun-2013
28-Jun-2013
02-Jul-2013
11-Jul-2013
23-Jul-2013
30-Jul-2013
28-Sep-2013
11-Oct-2013
31-Jul-2013
09-Aug-2013
21-Aug-2013
02-Sep-2013
09-Sep-2013
18-Sep-2013
26-Sep-2013
01-Oct-2013
10-Oct-2013
11-Oct-2013
11-Sep-2013
01-Jul-2013
10-Jul-2013
22-Jul-2013
02-Aug-2013
09-Aug-2013
17-OCT-13
04-Sep-2013
04-SEP-13
07-SEP-13
17-SEP-13
24-SEP-13
27-SEP-13
30-SEP-13
08-OCT-13
16-OCT-13
22-OCT-13
31-OCT-13
25-Sep-2013
25-SEP-13
28-SEP-13
08-OCT-13
15-OCT-13
18-OCT-13
17-OCT-13
31-Oct-2013
06-SEP-13
16-SEP-13
23-SEP-13
01-OCT-13
03-OCT-13
10-OCT-13
16-OCT-13
21-OCT-13
30-OCT-13
31-OCT-13
21-Nov-2013
27-SEP-13
07-OCT-13
14-OCT-13
22-OCT-13
24-OCT-13
-16d
-17d
-32d
-32d
-28d
-25d
-21d
-19d
-17d
-17d
-17d
-17d
-61d
-76d
-76d
-72d
-69d
-65d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11136
S2CONP11137
S2CONP11138
S2CONP11139
S2CONP11140
016
S2CONP11191
S2CONP11192
S2CONP11193
S2CONP11194
S2CONP11195
S2CONP11196
S2CONP11197
S2CONP11198
S2CONP11199
S2CONP11200
011
S2CONP11141
06-Aug-2013
16-Aug-2013
27-Aug-2013
02-Sep-2013
11-Sep-2013
08-Aug-2013
08-Aug-2013
12-Aug-2013
21-Aug-2013
02-Sep-2013
09-Sep-2013
16-Sep-2013
26-Sep-2013
07-Oct-2013
12-Oct-2013
22-Oct-2013
05-Jul-2013
05-Jul-2013
19-Aug-2013
27-Aug-2013
31-Aug-2013
10-Sep-2013
11-Sep-2013
22-Oct-2013
10-Aug-2013
20-Aug-2013
31-Aug-2013
12-Sep-2013
19-Sep-2013
28-Sep-2013
07-Oct-2013
11-Oct-2013
21-Oct-2013
22-Oct-2013
18-Sep-2013
08-Jul-2013
21-OCT-13
29-OCT-13
06-NOV-13
12-NOV-13
21-NOV-13
12-Sep-2013
12-SEP-13
16-SEP-13
25-SEP-13
02-OCT-13
05-OCT-13
08-OCT-13
16-OCT-13
24-OCT-13
30-OCT-13
08-NOV-13
20-Aug-2013
20-AUG-13
31-OCT-13
06-NOV-13
11-NOV-13
20-NOV-13
21-NOV-13
09-Nov-2013
16-SEP-13
25-SEP-13
02-OCT-13
10-OCT-13
12-OCT-13
19-OCT-13
25-OCT-13
30-OCT-13
08-NOV-13
09-NOV-13
16-Oct-2013
22-AUG-13
-63d
-61d
-61d
-61d
-61d
-16d
-30d
-30d
-26d
-23d
-19d
-17d
-15d
-15d
-15d
-15d
-24d
-39d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11142
S2CONP11143
S2CONP11144
S2CONP11145
S2CONP11146
S2CONP11147
S2CONP11148
S2CONP11149
S2CONP11150
013
S2CONP11161
S2CONP11162
S2CONP11163
S2CONP11164
S2CONP11165
S2CONP11166
S2CONP11167
S2CONP11168
09-Jul-2013
18-Jul-2013
30-Jul-2013
06-Aug-2013
13-Aug-2013
23-Aug-2013
03-Sep-2013
09-Sep-2013
18-Sep-2013
22-Jul-2013
22-Jul-2013
25-Jul-2013
03-Aug-2013
15-Aug-2013
22-Aug-2013
29-Aug-2013
09-Sep-2013
19-Sep-2013
17-Jul-2013
29-Jul-2013
09-Aug-2013
16-Aug-2013
26-Aug-2013
03-Sep-2013
07-Sep-2013
17-Sep-2013
18-Sep-2013
04-Oct-2013
24-Jul-2013
02-Aug-2013
14-Aug-2013
26-Aug-2013
02-Sep-2013
11-Sep-2013
19-Sep-2013
24-Sep-2013
23-AUG-13
02-SEP-13
09-SEP-13
12-SEP-13
14-SEP-13
23-SEP-13
01-OCT-13
07-OCT-13
16-OCT-13
11-Sep-2013
11-SEP-13
14-SEP-13
24-SEP-13
01-OCT-13
04-OCT-13
07-OCT-13
15-OCT-13
23-OCT-13
31-AUG-13
07-SEP-13
16-SEP-13
18-SEP-13
25-SEP-13
01-OCT-13
05-OCT-13
15-OCT-13
16-OCT-13
07-Nov-2013
13-SEP-13
23-SEP-13
30-SEP-13
08-OCT-13
10-OCT-13
17-OCT-13
23-OCT-13
28-OCT-13
-39d
-35d
-32d
-28d
-26d
-24d
-24d
-24d
-24d
-29d
-44d
-44d
-40d
-37d
-33d
-31d
-29d
-29d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11169
S2CONP11170
001
001
S2CONP11041
S2CONP11042
S2CONP11043
S2CONP11044
S2CONP11045
S2CONP11046
S2CONP11047
S2CONP11048
S2CONP11049
S2CONP11050
002
S2CONP11051
S2CONP11052
S2CONP11053
25-Sep-2013
04-Oct-2013
06-May-2013
06-May-2013
06-May-2013
09-May-2013
18-May-2013
30-May-2013
06-Jun-2013
13-Jun-2013
24-Jun-2013
04-Jul-2013
10-Jul-2013
19-Jul-2013
14-May-2013
14-May-2013
17-May-2013
27-May-2013
03-Oct-2013
04-Oct-2013
13-Aug-2013
19-Jul-2013
08-May-2013
17-May-2013
29-May-2013
10-Jun-2013
17-Jun-2013
26-Jun-2013
04-Jul-2013
09-Jul-2013
18-Jul-2013
19-Jul-2013
27-Jul-2013
16-May-2013
25-May-2013
06-Jun-2013
29-OCT-13
07-NOV-13
31-May-2013
31-May-2013
31-MAY-13
04-JUN-13
13-JUN-13
25-JUN-13
02-JUL-13
09-JUL-13
19-JUL-13
30-JUL-13
05-AUG-13
14-AUG-13
31-May-2013
31-MAY-13
04-JUN-13
13-JUN-13
06-NOV-13
07-NOV-13
14-Aug-2013
14-Aug-2013
03-JUN-13
12-JUN-13
24-JUN-13
05-JUL-13
12-JUL-13
22-JUL-13
30-JUL-13
03-AUG-13
13-AUG-13
14-AUG-13
14-Aug-2013
03-JUN-13
12-JUN-13
24-JUN-13
-29d
-29d
-1d
-22d
-22d
-22d
-22d
-22d
-22d
-22d
-22d
-22d
-22d
-22d
-15d
-15d
-15d
-15d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11054
S2CONP11055
S2CONP11056
S2CONP11057
S2CONP11058
S2CONP11059
S2CONP11060
003
S2CONP11061
S2CONP11062
S2CONP11063
S2CONP11064
S2CONP11065
S2CONP11066
S2CONP11067
S2CONP11068
S2CONP11069
S2CONP11070
07-Jun-2013
14-Jun-2013
21-Jun-2013
02-Jul-2013
12-Jul-2013
18-Jul-2013
27-Jul-2013
21-May-2013
21-May-2013
24-May-2013
03-Jun-2013
14-Jun-2013
21-Jun-2013
28-Jun-2013
09-Jul-2013
19-Jul-2013
25-Jul-2013
03-Aug-2013
18-Jun-2013
25-Jun-2013
04-Jul-2013
12-Jul-2013
17-Jul-2013
26-Jul-2013
27-Jul-2013
03-Aug-2013
23-May-2013
01-Jun-2013
13-Jun-2013
25-Jun-2013
02-Jul-2013
11-Jul-2013
19-Jul-2013
24-Jul-2013
02-Aug-2013
03-Aug-2013
25-JUN-13
02-JUL-13
09-JUL-13
19-JUL-13
30-JUL-13
05-AUG-13
14-AUG-13
31-May-2013
31-MAY-13
04-JUN-13
13-JUN-13
25-JUN-13
02-JUL-13
09-JUL-13
19-JUL-13
30-JUL-13
05-AUG-13
14-AUG-13
05-JUL-13
12-JUL-13
22-JUL-13
30-JUL-13
03-AUG-13
13-AUG-13
14-AUG-13
14-Aug-2013
03-JUN-13
12-JUN-13
24-JUN-13
05-JUL-13
12-JUL-13
22-JUL-13
30-JUL-13
03-AUG-13
13-AUG-13
14-AUG-13
-15d
-15d
-15d
-15d
-15d
-15d
-15d
-9d
-9d
-9d
-9d
-9d
-9d
-9d
-9d
-9d
-9d
-9d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
004
S2CONP11071
S2CONP11072
S2CONP11073
S2CONP11074
S2CONP11075
S2CONP11076
S2CONP11077
S2CONP11078
S2CONP11079
S2CONP11080
002
001
004
S2CONP10264
S2CONP10265
S2CONP10266
S2CONP10267
30-May-2013
30-May-2013
03-Jun-2013
12-Jun-2013
24-Jun-2013
01-Jul-2013
08-Jul-2013
18-Jul-2013
29-Jul-2013
03-Aug-2013
13-Aug-2013
22-Sep-2012
22-Sep-2012
23-Oct-2012
23-Oct-2012
25-Oct-2012
29-Oct-2012
31-Oct-2012
13-Aug-2013
01-Jun-2013
11-Jun-2013
22-Jun-2013
04-Jul-2013
11-Jul-2013
20-Jul-2013
29-Jul-2013
02-Aug-2013
12-Aug-2013
13-Aug-2013
23-Feb-2013
15-Jan-2013
14-Dec-2012
25-Oct-2012
29-Oct-2012
31-Oct-2012
02-Nov-2012
31-May-2013
31-MAY-13
04-JUN-13
13-JUN-13
25-JUN-13
02-JUL-13
09-JUL-13
19-JUL-13
30-JUL-13
05-AUG-13
14-AUG-13
29-Oct-2012A
29-Oct-2012A
03-Dec-2012A
06-DEC-12A
07-DEC-12A
14-DEC-12A
14-DEC-12A
14-Aug-2013
03-JUN-13
12-JUN-13
24-JUN-13
05-JUL-13
12-JUL-13
22-JUL-13
30-JUL-13
03-AUG-13
13-AUG-13
14-AUG-13
31-May-2013
31-May-2013
31-May-2013
08-DEC-12A
11-DEC-12A
15-DEC-12A
15-DEC-12A
-1d
-1d
-1d
-1d
-1d
-1d
-1d
-1d
-1d
-1d
-1d
-83d
-117d
-144d
-38d
-37d
-38d
-36d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10268
S2CONP10269
S2CONP10270
S2CONP10271
S2CONP10272
S2CONP10274
S2CONP10275
S2CONP10276
S2CONP10277
S2CONP10278
S2CONP10279
S2CONP10280
S2CONP10281
S2CONP10282
S2CONP10283
S2CONP10284
S2CONP10285
S2CONP10286
31-Oct-2012
02-Nov-2012
06-Nov-2012
08-Nov-2012
14-Nov-2012
01-Nov-2012
02-Nov-2012
03-Nov-2012
05-Nov-2012
06-Nov-2012
07-Nov-2012
08-Nov-2012
09-Nov-2012
10-Nov-2012
20-Nov-2012
22-Nov-2012
23-Nov-2012
22-Nov-2012
01-Nov-2012
06-Nov-2012
10-Nov-2012
13-Nov-2012
14-Nov-2012
05-Nov-2012
06-Nov-2012
07-Nov-2012
08-Nov-2012
09-Nov-2012
10-Nov-2012
12-Nov-2012
13-Nov-2012
14-Nov-2012
22-Nov-2012
24-Nov-2012
26-Nov-2012
28-Nov-2012
03-DEC-12A
04-DEC-12A
05-DEC-12A
06-DEC-12A
07-DEC-12A
18-DEC-12A
19-DEC-12A
20-DEC-12A
23-DEC-12A
04-DEC-12A
04-DEC-12A
05-DEC-12A
06-DEC-12A
11-DEC-12A
15-DEC-12A
17-DEC-12A
18-DEC-12A
21-DEC-12A
05-DEC-12A
06-DEC-12A
08-DEC-12A
09-DEC-12A
11-DEC-12A
21-DEC-12A
22-DEC-12A
22-DEC-12A
23-DEC-12A
06-DEC-12A
06-DEC-12A
08-DEC-12A
10-DEC-12A
11-DEC-12A
18-DEC-12A
20-DEC-12A
20-DEC-12A
23-DEC-12A
-28d
-25d
-23d
-22d
-22d
-39d
-39d
-38d
-38d
-22d
-21d
-22d
-22d
-22d
-21d
-21d
-20d
-21d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10287
S2CONP10288
S2CONP10289
S2CONP10290
S2CONP10291
S2CONP10292
005
S2CONP10293
S2CONP10294
S2CONP10295
S2CONP10296
S2CONP10297
S2CONP10298
S2CONP10299
S2CONP10300
S2CONP10301
S2CONP10302
S2CONP10303
29-Nov-2012
30-Nov-2012
07-Dec-2012
10-Dec-2012
11-Dec-2012
14-Dec-2012
02-Nov-2012
02-Nov-2012
05-Nov-2012
08-Nov-2012
10-Nov-2012
10-Nov-2012
13-Nov-2012
14-Nov-2012
16-Nov-2012
22-Nov-2012
10-Nov-2012
12-Nov-2012
30-Nov-2012
08-Dec-2012
10-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
22-Dec-2012
05-Nov-2012
08-Nov-2012
10-Nov-2012
13-Nov-2012
12-Nov-2012
16-Nov-2012
19-Nov-2012
21-Nov-2012
22-Nov-2012
14-Nov-2012
15-Nov-2012
29-DEC-12A
28-JAN-13A
31-JAN-13A
31-JAN-13A
31-JAN-13A
04-FEB-13A
14-Dec-2012A
24-DEC-12A
26-DEC-12A
02-JAN-13A
03-JAN-13A
14-DEC-12A
15-DEC-12A
16-DEC-12A
16-DEC-12A
17-DEC-12A
19-DEC-12A
19-DEC-12A
01-JAN-13A
03-FEB-13A
04-FEB-13A
04-FEB-13A
04-FEB-13A
05-FEB-13A
31-May-2013
12-JAN-13A
14-JAN-13A
15-JAN-13A
16-JAN-13A
11-JAN-13A
12-JAN-13A
14-JAN-13A
15-JAN-13A
16-JAN-13A
23-JAN-13A
23-JAN-13A
-26d
-48d
-47d
-45d
-44d
-44d
-137d
-58d
-56d
-55d
-54d
-51d
-48d
-47d
-46d
-46d
-59d
-58d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10304
S2CONP10305
S2CONP10306
S2CONP10307
S2CONP10308
S2CONP10309
S2CONP10310
S2CONP10311
S2CONP10312
S2CONP10313
S2CONP10314
S2CONP10315
S2CONP10316
S2CONP10317
S2CONP10318
S2CONP10319
S2CONP10320
S2CONP10321
13-Nov-2012
14-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
19-Nov-2012
20-Nov-2012
21-Nov-2012
28-Nov-2012
30-Nov-2012
01-Dec-2012
30-Nov-2012
07-Dec-2012
08-Dec-2012
15-Dec-2012
18-Dec-2012
19-Dec-2012
22-Dec-2012
16-Nov-2012
17-Nov-2012
19-Nov-2012
20-Nov-2012
21-Nov-2012
22-Nov-2012
23-Nov-2012
24-Nov-2012
30-Nov-2012
03-Dec-2012
04-Dec-2012
06-Dec-2012
08-Dec-2012
17-Dec-2012
18-Dec-2012
20-Dec-2012
21-Dec-2012
22-Dec-2012
23-DEC-12A
22-DEC-12A
24-DEC-12A
09-JAN-13A
10-JAN-13A
12-JAN-13A
14-JAN-13A
15-JAN-13A
18-JAN-13A
20-JAN-13A
21-JAN-13A
18-JAN-13A
22-JAN-13A
28-JAN-13A
30-JAN-13A
30-JAN-13A
30-JAN-13A
09-FEB-13A
27-JAN-13A
26-JAN-13A
28-JAN-13A
18-JAN-13A
20-JAN-13A
21-JAN-13A
22-JAN-13A
23-JAN-13A
29-JAN-13A
29-JAN-13A
30-JAN-13A
28-JAN-13A
30-JAN-13A
02-FEB-13A
09-FEB-13A
09-FEB-13A
09-FEB-13A
10-FEB-13A
-61d
-59d
-59d
-50d
-51d
-50d
-50d
-51d
-50d
-49d
-48d
-44d
-44d
-40d
-45d
-43d
-42d
-42d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
002
S2CONP10206
S2CONP10207
S2CONP10208
S2CONP10209
S2CONP10210
S2CONP10211
S2CONP10212
S2CONP10213
S2CONP10214
S2CONP10215
S2CONP10216
S2CONP10217
S2CONP10218
S2CONP10219
S2CONP10220
S2CONP10221
S2CONP10222
03-Oct-2012
03-Oct-2012
05-Oct-2012
09-Oct-2012
11-Oct-2012
11-Oct-2012
13-Oct-2012
16-Oct-2012
18-Oct-2012
24-Oct-2012
11-Oct-2012
12-Oct-2012
13-Oct-2012
15-Oct-2012
16-Oct-2012
17-Oct-2012
18-Oct-2012
19-Oct-2012
28-Nov-2012
05-Oct-2012
09-Oct-2012
11-Oct-2012
13-Oct-2012
12-Oct-2012
17-Oct-2012
20-Oct-2012
23-Oct-2012
24-Oct-2012
15-Oct-2012
16-Oct-2012
17-Oct-2012
18-Oct-2012
19-Oct-2012
20-Oct-2012
22-Oct-2012
23-Oct-2012
29-Oct-2012A
16-NOV-12A
17-NOV-12A
24-NOV-12A
06-DEC-12A
05-DEC-12A
06-NOV-12A
07-NOV-12A
08-NOV-12A
12-NOV-12A
29-OCT-12A
30-OCT-12A
01-NOV-12A
01-NOV-12A
03-NOV-12A
13-DEC-12A
13-DEC-12A
15-DEC-12A
31-May-2013
19-NOV-12A
21-NOV-12A
10-DEC-12A
11-DEC-12A
07-DEC-12A
08-NOV-12A
09-NOV-12A
10-NOV-12A
16-NOV-12A
15-NOV-12A
16-NOV-12A
17-NOV-12A
19-NOV-12A
20-NOV-12A
15-DEC-12A
15-DEC-12A
17-DEC-12A
-158d
-37d
-36d
-50d
-49d
-47d
-18d
-16d
-15d
-19d
-26d
-26d
-26d
-26d
-26d
-47d
-46d
-46d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10223
S2CONP10224
S2CONP10225
S2CONP10226
S2CONP10227
S2CONP10228
S2CONP10229
S2CONP10230
S2CONP10231
S2CONP10232
S2CONP10233
S2CONP10234
006
S2CONP10322
S2CONP10323
S2CONP10324
S2CONP10325
S2CONP10326
20-Oct-2012
22-Oct-2012
30-Oct-2012
01-Nov-2012
02-Nov-2012
06-Nov-2012
13-Nov-2012
14-Nov-2012
21-Nov-2012
23-Nov-2012
24-Nov-2012
28-Nov-2012
13-Nov-2012
13-Nov-2012
15-Nov-2012
19-Nov-2012
21-Nov-2012
21-Nov-2012
24-Oct-2012
25-Oct-2012
01-Nov-2012
03-Nov-2012
05-Nov-2012
12-Nov-2012
14-Nov-2012
22-Nov-2012
23-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
31-Dec-2012
15-Nov-2012
19-Nov-2012
21-Nov-2012
23-Nov-2012
22-Nov-2012
17-DEC-12A
19-DEC-12A
06-DEC-12A
10-DEC-12A
14-DEC-12A
04-DEC-12A
17-DEC-12A
04-JAN-13A
07-JAN-13A
07-JAN-13A
07-JAN-13A
13-JAN-13A
08-Dec-2012A
08-JAN-13A
10-JAN-13A
11-JAN-13A
12-JAN-13A
08-DEC-12A
19-DEC-12A
20-DEC-12A
10-DEC-12A
13-DEC-12A
14-DEC-12A
19-DEC-12A
22-DEC-12A
10-JAN-13A
12-JAN-13A
12-JAN-13A
12-JAN-13A
13-JAN-13A
31-May-2013
11-JAN-13A
14-JAN-13A
15-JAN-13A
16-JAN-13A
10-DEC-12A
-47d
-47d
-32d
-33d
-33d
-31d
-32d
-41d
-42d
-40d
-39d
-39d
-130d
-48d
-47d
-46d
-45d
-14d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10327
S2CONP10328
S2CONP10329
S2CONP10330
S2CONP10331
S2CONP10332
S2CONP10333
S2CONP10334
S2CONP10335
S2CONP10336
S2CONP10337
S2CONP10338
S2CONP10339
S2CONP10340
S2CONP10341
S2CONP10342
S2CONP10343
S2CONP10344
23-Nov-2012
24-Nov-2012
26-Nov-2012
01-Dec-2012
21-Nov-2012
22-Nov-2012
23-Nov-2012
24-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
08-Dec-2012
27-Nov-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
24-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
14-Dec-2012
10-DEC-12A
11-DEC-12A
11-DEC-12A
12-DEC-12A
13-DEC-12A
13-DEC-12A
14-DEC-12A
15-DEC-12A
14-DEC-12A
08-DEC-12A
09-DEC-12A
10-DEC-12A
11-DEC-12A
14-DEC-12A
18-JAN-13A
20-JAN-13A
21-JAN-13A
18-JAN-13A
11-DEC-12A
13-DEC-12A
13-DEC-12A
12-DEC-12A
17-JAN-13A
17-JAN-13A
18-JAN-13A
19-JAN-13A
20-JAN-13A
10-DEC-12A
11-DEC-12A
12-JAN-13A
13-DEC-12A
14-DEC-12A
24-JAN-13A
25-JAN-13A
25-JAN-13A
26-JAN-13A
-11d
-11d
-10d
-8d
-45d
-44d
-44d
-44d
-44d
-7d
-7d
-34d
-7d
-7d
-39d
-38d
-38d
-36d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10345
S2CONP10346
S2CONP10347
S2CONP10348
S2CONP10349
S2CONP10350
001
S2CONP10177
S2CONP10178
S2CONP10179
S2CONP10180
S2CONP10181
S2CONP10182
S2CONP10183
S2CONP10184
S2CONP10185
S2CONP10186
S2CONP10187
15-Dec-2012
17-Dec-2012
24-Dec-2012
26-Dec-2012
27-Dec-2012
31-Dec-2012
22-Sep-2012
22-Sep-2012
25-Sep-2012
28-Sep-2012
01-Oct-2012
01-Oct-2012
03-Oct-2012
05-Oct-2012
08-Oct-2012
13-Oct-2012
01-Oct-2012
02-Oct-2012
17-Dec-2012
25-Dec-2012
26-Dec-2012
28-Dec-2012
29-Dec-2012
31-Dec-2012
20-Nov-2012
25-Sep-2012
28-Sep-2012
01-Oct-2012
03-Oct-2012
02-Oct-2012
06-Oct-2012
10-Oct-2012
12-Oct-2012
13-Oct-2012
04-Oct-2012
05-Oct-2012
29-JAN-13A
15-FEB-13A
19-FEB-13A
19-FEB-13A
19-FEB-13A
25-FEB-13A
08-Nov-2012A
08-NOV-12A
10-NOV-12A
06-DEC-12A
07-DEC-12A
04-DEC-12A
06-DEC-12A
08-DEC-12A
10-DEC-12A
15-DEC-12A
16-NOV-12A
17-NOV-12A
18-FEB-13A
22-FEB-13A
24-FEB-13A
24-FEB-13A
24-FEB-13A
25-FEB-13A
31-May-2013
15-NOV-12A
16-NOV-12A
10-DEC-12A
11-DEC-12A
10-DEC-12A
13-DEC-12A
14-DEC-12A
14-DEC-12A
15-DEC-12A
07-DEC-12A
07-DEC-12A
-53d
-50d
-51d
-49d
-48d
-47d
-165d
-43d
-41d
-59d
-58d
-58d
-57d
-55d
-53d
-53d
-54d
-53d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10188
S2CONP10189
S2CONP10190
S2CONP10191
S2CONP10192
S2CONP10193
S2CONP10194
S2CONP10195
S2CONP10196
S2CONP10197
S2CONP10198
S2CONP10199
S2CONP10200
S2CONP10201
S2CONP10202
S2CONP10203
S2CONP10204
S2CONP10205
03-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
08-Oct-2012
09-Oct-2012
10-Oct-2012
11-Oct-2012
19-Oct-2012
22-Oct-2012
23-Oct-2012
26-Oct-2012
02-Nov-2012
05-Nov-2012
12-Nov-2012
14-Nov-2012
16-Nov-2012
20-Nov-2012
06-Oct-2012
08-Oct-2012
09-Oct-2012
10-Oct-2012
11-Oct-2012
12-Oct-2012
13-Oct-2012
15-Oct-2012
22-Oct-2012
24-Oct-2012
25-Oct-2012
01-Nov-2012
03-Nov-2012
13-Nov-2012
14-Nov-2012
16-Nov-2012
19-Nov-2012
20-Nov-2012
19-NOV-12A
19-NOV-12A
20-NOV-12A
09-DEC-12A
11-DEC-12A
14-DEC-12A
17-DEC-12A
19-DEC-12A
20-DEC-12A
22-DEC-12A
25-DEC-12A
18-DEC-12A
29-DEC-12A
11-JAN-13A
15-JAN-13A
15-JAN-13A
15-JAN-13A
21-JAN-13A
08-DEC-12A
10-DEC-12A
11-DEC-12A
11-DEC-12A
13-DEC-12A
18-DEC-12A
19-DEC-12A
19-DEC-12A
23-DEC-12A
24-DEC-12A
25-DEC-12A
26-DEC-12A
31-DEC-12A
15-JAN-13A
20-JAN-13A
20-JAN-13A
20-JAN-13A
21-JAN-13A
-53d
-53d
-53d
-52d
-53d
-56d
-56d
-55d
-53d
-51d
-51d
-46d
-48d
-53d
-57d
-55d
-53d
-52d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
003
S2CONP10235
S2CONP10236
S2CONP10237
S2CONP10238
S2CONP10239
S2CONP10240
S2CONP10241
S2CONP10242
S2CONP10243
S2CONP10244
S2CONP10245
S2CONP10246
S2CONP10247
S2CONP10248
S2CONP10249
S2CONP10250
S2CONP10251
12-Oct-2012
12-Oct-2012
15-Oct-2012
18-Oct-2012
20-Oct-2012
20-Oct-2012
23-Oct-2012
25-Oct-2012
27-Oct-2012
02-Nov-2012
20-Oct-2012
22-Oct-2012
23-Oct-2012
24-Oct-2012
25-Oct-2012
26-Oct-2012
27-Oct-2012
29-Oct-2012
05-Dec-2012
15-Oct-2012
18-Oct-2012
20-Oct-2012
23-Oct-2012
22-Oct-2012
26-Oct-2012
30-Oct-2012
01-Nov-2012
02-Nov-2012
24-Oct-2012
25-Oct-2012
26-Oct-2012
27-Oct-2012
29-Oct-2012
30-Oct-2012
31-Oct-2012
01-Nov-2012
01-Dec-2012A
06-DEC-12A
07-DEC-12A
14-DEC-12A
14-DEC-12A
01-DEC-12A
02-DEC-12A
03-DEC-12A
05-DEC-12A
12-DEC-12A
06-DEC-12A
07-DEC-12A
11-DEC-12A
12-DEC-12A
14-DEC-12A
11-DEC-12A
11-DEC-12A
17-DEC-12A
31-May-2013
08-DEC-12A
10-DEC-12A
15-DEC-12A
15-DEC-12A
02-DEC-12A
04-DEC-12A
06-DEC-12A
10-DEC-12A
12-DEC-12A
08-DEC-12A
10-DEC-12A
12-DEC-12A
13-DEC-12A
15-DEC-12A
13-DEC-12A
13-DEC-12A
24-DEC-12A
-152d
-46d
-44d
-47d
-45d
-35d
-32d
-31d
-32d
-33d
-38d
-38d
-39d
-39d
-40d
-37d
-36d
-44d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10252
S2CONP10253
S2CONP10254
S2CONP10255
S2CONP10256
S2CONP10257
S2CONP10258
S2CONP10259
S2CONP10260
S2CONP10261
S2CONP10262
S2CONP10263
007
S2CONP10351
S2CONP10352
S2CONP10353
S2CONP10354
S2CONP10355
30-Oct-2012
31-Oct-2012
08-Nov-2012
10-Nov-2012
12-Nov-2012
13-Nov-2012
20-Nov-2012
21-Nov-2012
28-Nov-2012
30-Nov-2012
01-Dec-2012
05-Dec-2012
22-Nov-2012
22-Nov-2012
24-Nov-2012
28-Nov-2012
30-Nov-2012
30-Nov-2012
02-Nov-2012
03-Nov-2012
10-Nov-2012
13-Nov-2012
14-Nov-2012
19-Nov-2012
21-Nov-2012
29-Nov-2012
30-Nov-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
08-Jan-2013
24-Nov-2012
28-Nov-2012
30-Nov-2012
03-Dec-2012
01-Dec-2012
17-DEC-12A
25-DEC-12A
10-DEC-12A
11-DEC-12A
12-DEC-12A
18-DEC-12A
29-DEC-12A
12-JAN-13A
10-JAN-13A
10-JAN-13A
10-JAN-13A
28-JAN-13A
07-Dec-2012A
03-JAN-13A
04-JAN-13A
06-JAN-13A
08-JAN-13A
07-DEC-12A
24-DEC-12A
25-DEC-12A
14-DEC-12A
15-DEC-12A
16-DEC-12A
26-DEC-12A
31-DEC-12A
27-JAN-13A
25-JAN-13A
25-JAN-13A
25-JAN-13A
28-JAN-13A
31-May-2013
07-JAN-13A
09-JAN-13A
10-JAN-13A
11-JAN-13A
01-JAN-13A
-43d
-43d
-28d
-27d
-27d
-31d
-33d
-50d
-47d
-45d
-44d
-45d
-123d
-36d
-35d
-34d
-33d
-25d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10356
S2CONP10357
S2CONP10358
S2CONP10359
S2CONP10360
S2CONP10361
S2CONP10362
S2CONP10363
S2CONP10364
S2CONP10365
S2CONP10366
S2CONP10367
S2CONP10368
S2CONP10369
S2CONP10370
S2CONP10371
S2CONP10372
S2CONP10373
03-Dec-2012
03-Dec-2012
04-Dec-2012
10-Dec-2012
30-Nov-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
15-Dec-2012
17-Dec-2012
18-Dec-2012
17-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
04-Dec-2012
05-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
18-Dec-2012
19-Dec-2012
20-Dec-2012
22-Dec-2012
07-DEC-12A
08-DEC-12A
10-DEC-12A
11-DEC-12A
14-DEC-12A
14-DEC-12A
16-DEC-12A
18-DEC-12A
21-DEC-12A
15-DEC-12A
16-DEC-12A
18-DEC-12A
21-DEC-12A
26-DEC-12A
29-DEC-12A
31-DEC-12A
03-JAN-13A
14-JAN-13A
03-JAN-13A
05-JAN-13A
07-JAN-13A
08-JAN-13A
04-JAN-13A
04-JAN-13A
06-JAN-13A
08-JAN-13A
10-JAN-13A
19-DEC-12A
21-DEC-12A
23-DEC-12A
25-DEC-12A
26-DEC-12A
03-JAN-13A
05-JAN-13A
07-JAN-13A
08-FEB-13A
-23d
-24d
-24d
-24d
-26d
-25d
-26d
-26d
-27d
-7d
-8d
-9d
-9d
-9d
-13d
-14d
-14d
-40d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10374
S2CONP10375
S2CONP10376
S2CONP10377
S2CONP10378
S2CONP10379
008
S2CONP10380
S2CONP10381
S2CONP10382
S2CONP10383
S2CONP10389
S2CONP10390
S2CONP10391
S2CONP10392
S2CONP10393
S2CONP10399
S2CONP10400
24-Dec-2012
25-Dec-2012
01-Jan-2013
03-Jan-2013
04-Jan-2013
08-Jan-2013
01-Dec-2012
01-Dec-2012
04-Dec-2012
07-Dec-2012
10-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
25-Dec-2012
26-Dec-2012
25-Dec-2012
02-Jan-2013
03-Jan-2013
05-Jan-2013
07-Jan-2013
08-Jan-2013
15-Jan-2013
04-Dec-2012
07-Dec-2012
10-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
18-Dec-2012
27-Dec-2012
28-Dec-2012
03-FEB-13A
06-FEB-13A
12-FEB-13A
12-FEB-13A
12-FEB-13A
18-FEB-13A
07-Dec-2012A
07-DEC-12A
08-DEC-12A
15-DEC-12A
16-DEC-12A
19-DEC-12A
19-DEC-12A
20-DEC-12A
22-DEC-12A
24-DEC-12A
01-JAN-13A
03-JAN-13A
06-FEB-13A
16-FEB-13A
17-FEB-13A
17-FEB-13A
17-FEB-13A
18-FEB-13A
31-May-2013
10-DEC-12A
13-DEC-12A
09-JAN-13A
11-JAN-13A
12-JAN-13A
12-JAN-13A
13-JAN-13A
14-JAN-13A
15-JAN-13A
04-JAN-13A
08-JAN-13A
-36d
-39d
-38d
-36d
-35d
-35d
-117d
-4d
-4d
-25d
-25d
-25d
-24d
-24d
-23d
-23d
-6d
-8d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10401
S2CONP10402
S2CONP10403
S2CONP10404
S2CONP10405
S2CONP10406
S2CONP10407
S2CONP10408
002
009
S2CONP10412
S2CONP10413
S2CONP10414
S2CONP10415
S2CONP10416
S2CONP10417
S2CONP10418
S2CONP10419
27-Dec-2012
26-Dec-2012
02-Jan-2013
03-Jan-2013
08-Jan-2013
10-Jan-2013
11-Jan-2013
15-Jan-2013
17-Nov-2012
17-Nov-2012
26-Nov-2012
26-Nov-2012
28-Nov-2012
28-Nov-2012
29-Nov-2012
05-Dec-2012
26-Nov-2012
27-Nov-2012
29-Dec-2012
01-Jan-2013
03-Jan-2013
09-Jan-2013
10-Jan-2013
12-Jan-2013
14-Jan-2013
15-Jan-2013
23-Feb-2013
03-Jan-2013
28-Nov-2012
27-Nov-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
29-Nov-2012
30-Nov-2012
05-JAN-13A
14-JAN-13A
02-FEB-13A
20-FEB-13A
23-FEB-13A
23-FEB-13A
23-FEB-13A
28-FEB-13A
18-Dec-2012A
24-Jan-2013A
07-FEB-13A
09-FEB-13A
13-FEB-13A
15-FEB-13A
16-FEB-13A
17-FEB-13A
24-JAN-13A
25-JAN-13A
09-JAN-13A
06-FEB-13A
18-FEB-13A
25-FEB-13A
27-FEB-13A
27-FEB-13A
27-FEB-13A
28-FEB-13A
31-May-2013
31-May-2013
12-FEB-13A
13-FEB-13A
09-MAR-13A
10-MAR-13A
11-MAR-13A
12-MAR-13A
28-JAN-13A
29-JAN-13A
-8d
-31d
-38d
-39d
-40d
-38d
-37d
-38d
-83d
-127d
-64d
-67d
-83d
-83d
-82d
-82d
-50d
-50d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10420
S2CONP10421
S2CONP10422
S2CONP10423
S2CONP10424
S2CONP10425
S2CONP10426
S2CONP10427
S2CONP10428
S2CONP10429
S2CONP10430
S2CONP10431
S2CONP10432
S2CONP10433
S2CONP10434
S2CONP10435
S2CONP10436
S2CONP10437
28-Nov-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
06-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
12-Dec-2012
19-Dec-2012
20-Dec-2012
27-Dec-2012
29-Dec-2012
31-Dec-2012
03-Jan-2013
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
18-Dec-2012
20-Dec-2012
28-Dec-2012
29-Dec-2012
01-Jan-2013
02-Jan-2013
03-Jan-2013
28-JAN-13A
29-JAN-13A
30-JAN-13A
02-FEB-13A
02-FEB-13A
03-FEB-13A
11-FEB-13A
12-FEB-13A
08-MAR-13A
10-MAR-13A
12-MAR-13A
10-MAR-13A
11-MAR-13A
14-MAR-13A
15-MAR-13A
16-MAR-13A
18-MAR-13A
21-MAR-13A
30-JAN-13A
31-JAN-13A
02-FEB-13A
10-FEB-13A
10-FEB-13A
13-FEB-13A
15-FEB-13A
16-FEB-13A
12-MAR-13A
13-MAR-13A
14-MAR-13A
15-MAR-13A
16-MAR-13A
17-MAR-13A
18-MAR-13A
19-MAR-13A
20-MAR-13A
21-MAR-13A
-50d
-50d
-51d
-57d
-56d
-58d
-59d
-59d
-75d
-75d
-75d
-74d
-73d
-67d
-66d
-65d
-65d
-65d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10409
S2CONP10410
S2CONP10411
011
S2CONP10467
S2CONP10468
S2CONP10469
S2CONP10470
S2CONP10471
S2CONP10472
S2CONP10473
S2CONP10474
S2CONP10475
S2CONP10476
S2CONP10477
S2CONP10478
S2CONP10479
S2CONP10480
17-Nov-2012
20-Nov-2012
23-Nov-2012
07-Dec-2012
07-Dec-2012
10-Dec-2012
13-Dec-2012
15-Dec-2012
15-Dec-2012
18-Dec-2012
18-Dec-2012
19-Dec-2012
25-Dec-2012
15-Dec-2012
17-Dec-2012
18-Dec-2012
19-Dec-2012
20-Dec-2012
20-Nov-2012
23-Nov-2012
26-Nov-2012
19-Jan-2013
10-Dec-2012
13-Dec-2012
15-Dec-2012
18-Dec-2012
17-Dec-2012
21-Dec-2012
22-Dec-2012
24-Dec-2012
25-Dec-2012
19-Dec-2012
20-Dec-2012
21-Dec-2012
22-Dec-2012
24-Dec-2012
31-JAN-13A
05-FEB-13A
06-FEB-13A
19-Dec-2012A
29-JAN-13A
31-JAN-13A
31-JAN-13A
01-FEB-13A
24-JAN-13A
27-JAN-13A
28-JAN-13A
01-FEB-13A
02-FEB-13A
19-DEC-12A
20-DEC-12A
21-DEC-12A
22-DEC-12A
24-DEC-12A
09-FEB-13A
10-FEB-13A
12-FEB-13A
31-May-2013
01-FEB-13A
02-FEB-13A
03-FEB-13A
04-FEB-13A
26-JAN-13A
05-FEB-13A
07-FEB-13A
10-FEB-13A
12-FEB-13A
09-JAN-13A
10-JAN-13A
12-JAN-13A
13-JAN-13A
14-JAN-13A
-69d
-67d
-66d
-113d
-45d
-43d
-42d
-40d
-34d
-38d
-39d
-41d
-41d
-17d
-17d
-18d
-18d
-17d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10481
S2CONP10482
S2CONP10483
S2CONP10484
S2CONP10485
S2CONP10486
S2CONP10487
S2CONP10488
S2CONP10489
S2CONP10490
S2CONP10491
S2CONP10492
S2CONP10493
S2CONP10494
S2CONP10495
010
S2CONP10438
S2CONP10439
21-Dec-2012
22-Dec-2012
24-Dec-2012
25-Dec-2012
26-Dec-2012
31-Dec-2012
01-Jan-2013
02-Jan-2013
01-Jan-2013
07-Jan-2013
08-Jan-2013
14-Jan-2013
16-Jan-2013
16-Jan-2013
19-Jan-2013
27-Nov-2012
27-Nov-2012
29-Nov-2012
25-Dec-2012
26-Dec-2012
27-Dec-2012
28-Dec-2012
29-Dec-2012
02-Jan-2013
03-Jan-2013
04-Jan-2013
05-Jan-2013
08-Jan-2013
15-Jan-2013
16-Jan-2013
17-Jan-2013
18-Jan-2013
19-Jan-2013
12-Jan-2013
29-Nov-2012
03-Dec-2012
14-JAN-13A
14-JAN-13A
15-JAN-13A
16-JAN-13A
18-JAN-13A
28-FEB-13A
01-MAR-13A
02-MAR-13A
01-MAR-13A
07-MAR-13A
08-MAR-13A
14-MAR-13A
16-MAR-13A
20-MAR-13A
25-MAR-13A
26-Dec-2012A
03-FEB-13A
05-FEB-13A
29-JAN-13A
29-JAN-13A
30-JAN-13A
01-FEB-13A
04-FEB-13A
02-MAR-13A
04-MAR-13A
05-MAR-13A
06-MAR-13A
08-MAR-13A
15-MAR-13A
16-MAR-13A
18-MAR-13A
24-MAR-13A
30-MAR-13A
31-May-2013
15-MAR-13A
16-MAR-13A
-29d
-28d
-28d
-29d
-30d
-51d
-51d
-51d
-51d
-51d
-51d
-51d
-51d
-55d
-59d
-119d
-90d
-88d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10440
S2CONP10441
S2CONP10442
S2CONP10443
S2CONP10444
S2CONP10445
S2CONP10446
S2CONP10447
S2CONP10448
S2CONP10449
S2CONP10450
S2CONP10451
S2CONP10452
S2CONP10453
S2CONP10454
S2CONP10455
S2CONP10456
S2CONP10457
03-Dec-2012
05-Dec-2012
05-Dec-2012
07-Dec-2012
07-Dec-2012
08-Dec-2012
14-Dec-2012
05-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
20-Dec-2012
05-Dec-2012
07-Dec-2012
06-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
18-Dec-2012
19-Dec-2012
22-Dec-2012
06-FEB-13A
06-FEB-13A
06-MAR-13A
09-MAR-13A
09-MAR-13A
10-MAR-13A
15-MAR-13A
26-DEC-12A
27-DEC-12A
28-DEC-12A
29-DEC-12A
30-DEC-12A
31-DEC-12A
31-DEC-12A
01-JAN-13A
02-JAN-13A
03-JAN-13A
07-MAR-13A
17-MAR-13A
18-MAR-13A
08-MAR-13A
12-MAR-13A
13-MAR-13A
14-MAR-13A
15-MAR-13A
25-FEB-13A
27-FEB-13A
02-MAR-13A
03-MAR-13A
04-MAR-13A
04-MAR-13A
05-MAR-13A
07-MAR-13A
08-MAR-13A
10-MAR-13A
09-MAR-13A
-87d
-85d
-78d
-77d
-77d
-77d
-77d
-66d
-67d
-69d
-69d
-68d
-67d
-67d
-68d
-68d
-69d
-65d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10458
S2CONP10459
S2CONP10460
S2CONP10461
S2CONP10462
S2CONP10463
S2CONP10464
S2CONP10465
S2CONP10466
012
S2CONP10496
S2CONP10497
S2CONP10498
S2CONP10499
S2CONP10500
S2CONP10501
S2CONP10502
S2CONP10503
21-Dec-2012
22-Dec-2012
21-Dec-2012
28-Dec-2012
29-Dec-2012
05-Jan-2013
08-Jan-2013
09-Jan-2013
12-Jan-2013
18-Dec-2012
18-Dec-2012
20-Dec-2012
24-Dec-2012
26-Dec-2012
26-Dec-2012
28-Dec-2012
28-Dec-2012
29-Dec-2012
24-Dec-2012
25-Dec-2012
27-Dec-2012
29-Dec-2012
07-Jan-2013
08-Jan-2013
10-Jan-2013
11-Jan-2013
12-Jan-2013
30-Jan-2013
20-Dec-2012
24-Dec-2012
26-Dec-2012
28-Dec-2012
27-Dec-2012
01-Jan-2013
02-Jan-2013
03-Jan-2013
08-MAR-13A
11-MAR-13A
11-MAR-13A
13-MAR-13A
23-APR-13A
20-MAY-13A
23-MAY-13A
23-MAY-13A
31-MAY-13A
24-Dec-2012A
16-FEB-13A
20-FEB-13A
24-FEB-13A
25-FEB-13A
27-FEB-13A
02-MAR-13A
06-MAR-13A
11-MAR-13A
10-MAR-13A
12-MAR-13A
18-MAR-13A
20-MAR-13A
20-MAY-13A
25-MAY-13A
30-MAY-13A
28-MAY-13A
31-MAY-13A
31-May-2013
20-FEB-13A
24-FEB-13A
26-FEB-13A
27-FEB-13A
03-MAR-13A
06-MAR-13A
11-MAR-13A
15-MAR-13A
-65d
-65d
-68d
-68d
-113d
-117d
-120d
-116d
-118d
-104d
-52d
-53d
-52d
-51d
-56d
-54d
-57d
-60d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10504
S2CONP10505
S2CONP10506
S2CONP10507
S2CONP10508
S2CONP10509
S2CONP10510
S2CONP10511
S2CONP10512
S2CONP10513
S2CONP10514
S2CONP10515
S2CONP10516
S2CONP10517
S2CONP10518
S2CONP10519
S2CONP10520
S2CONP10521
04-Jan-2013
26-Dec-2012
27-Dec-2012
28-Dec-2012
29-Dec-2012
31-Dec-2012
01-Jan-2013
02-Jan-2013
03-Jan-2013
04-Jan-2013
05-Jan-2013
10-Jan-2013
11-Jan-2013
12-Jan-2013
11-Jan-2013
17-Jan-2013
18-Jan-2013
24-Jan-2013
04-Jan-2013
29-Dec-2012
31-Dec-2012
01-Jan-2013
02-Jan-2013
03-Jan-2013
04-Jan-2013
05-Jan-2013
07-Jan-2013
08-Jan-2013
09-Jan-2013
12-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
18-Jan-2013
25-Jan-2013
26-Jan-2013
16-MAR-13A
24-DEC-12A
25-DEC-12A
26-DEC-12A
27-DEC-12A
28-DEC-12A
29-DEC-12A
29-DEC-12A
30-DEC-12A
31-DEC-12A
01-JAN-13A
01-MAR-13A
05-MAR-13A
09-MAR-13A
01-APR-13A
01-APR-13A
16-APR-13A
20-APR-13A
16-MAR-13A
25-FEB-13A
28-FEB-13A
01-MAR-13A
02-MAR-13A
04-MAR-13A
22-FEB-13A
26-FEB-13A
28-FEB-13A
01-MAR-13A
04-MAR-13A
05-MAR-13A
09-MAR-13A
10-MAR-13A
03-APR-13A
06-APR-13A
19-APR-13A
21-APR-13A
-60d
-48d
-50d
-50d
-50d
-50d
-41d
-43d
-44d
-44d
-45d
-43d
-46d
-46d
-65d
-66d
-71d
-72d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10522
S2CONP10523
S2CONP10524
015
S2CONP10583
S2CONP10584
S2CONP10585
S2CONP10586
S2CONP10587
S2CONP10588
S2CONP10589
S2CONP10590
S2CONP10591
S2CONP10592
S2CONP10593
S2CONP10594
S2CONP10595
S2CONP10596
26-Jan-2013
26-Jan-2013
30-Jan-2013
11-Jan-2013
11-Jan-2013
14-Jan-2013
17-Jan-2013
19-Jan-2013
22-Jan-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
31-Jan-2013
22-Jan-2013
23-Jan-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
28-Jan-2013
29-Jan-2013
30-Jan-2013
20-Feb-2013
14-Jan-2013
17-Jan-2013
19-Jan-2013
22-Jan-2013
23-Jan-2013
28-Jan-2013
29-Jan-2013
30-Jan-2013
31-Jan-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
28-Jan-2013
29-Jan-2013
20-APR-13A
22-APR-13A
24-APR-13A
09-Feb-2013A
15-FEB-13A
20-FEB-13A
26-FEB-13A
28-FEB-13A
04-MAR-13A
09-MAR-13A
14-MAR-13A
17-MAR-13A
18-MAR-13A
09-FEB-13A
12-FEB-13A
15-FEB-13A
19-FEB-13A
26-FEB-13A
21-APR-13A
23-APR-13A
24-APR-13A
31-May-2013
19-FEB-13A
24-FEB-13A
28-FEB-13A
01-MAR-13A
08-MAR-13A
13-MAR-13A
16-MAR-13A
19-MAR-13A
19-MAR-13A
11-FEB-13A
14-FEB-13A
18-FEB-13A
25-FEB-13A
01-MAR-13A
-71d
-71d
-71d
-86d
-30d
-32d
-33d
-32d
-37d
-37d
-39d
-40d
-39d
-14d
-16d
-18d
-23d
-26d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10597
S2CONP10598
S2CONP10599
S2CONP10600
S2CONP10601
S2CONP10602
S2CONP10603
S2CONP10604
S2CONP10605
S2CONP10606
S2CONP10607
S2CONP10608
S2CONP10610
S2CONP10611
S2CONP10609
013
S2CONP10525
S2CONP10526
28-Jan-2013
29-Jan-2013
29-Jan-2013
30-Jan-2013
31-Jan-2013
01-Feb-2013
02-Feb-2013
04-Feb-2013
02-Feb-2013
08-Feb-2013
09-Feb-2013
14-Feb-2013
16-Feb-2013
20-Feb-2013
16-Feb-2013
27-Dec-2012
27-Dec-2012
29-Dec-2012
30-Jan-2013
31-Jan-2013
01-Feb-2013
02-Feb-2013
04-Feb-2013
04-Feb-2013
05-Feb-2013
06-Feb-2013
07-Feb-2013
09-Feb-2013
15-Feb-2013
16-Feb-2013
19-Feb-2013
20-Feb-2013
18-Feb-2013
05-Feb-2013
29-Dec-2012
02-Jan-2013
02-MAR-13A
07-MAR-13A
11-MAR-13A
15-MAR-13A
20-MAR-13A
15-MAR-13A
18-MAR-13A
20-MAR-13A
30-MAR-13A
01-APR-13A
15-APR-13A
19-APR-13A
22-APR-13A
02-MAY-13A
22-APR-13A
18-Dec-2012A
20-FEB-13A
21-FEB-13A
06-MAR-13A
10-MAR-13A
14-MAR-13A
19-MAR-13A
23-MAR-13A
18-MAR-13A
20-MAR-13A
22-MAR-13A
03-APR-13A
05-APR-13A
19-APR-13A
22-APR-13A
24-APR-13A
03-MAY-13A
23-APR-13A
31-May-2013
23-FEB-13A
24-FEB-13A
-29d
-32d
-34d
-37d
-40d
-35d
-36d
-37d
-46d
-46d
-54d
-55d
-55d
-61d
-55d
-99d
-47d
-45d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10527
S2CONP10528
S2CONP10529
S2CONP10530
S2CONP10531
S2CONP10532
S2CONP10533
S2CONP10534
S2CONP10535
S2CONP10536
S2CONP10537
S2CONP10538
S2CONP10539
S2CONP10540
S2CONP10541
S2CONP10542
S2CONP10543
S2CONP10544
02-Jan-2013
04-Jan-2013
04-Jan-2013
07-Jan-2013
08-Jan-2013
09-Jan-2013
14-Jan-2013
04-Jan-2013
05-Jan-2013
07-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
11-Jan-2013
11-Jan-2013
12-Jan-2013
14-Jan-2013
17-Jan-2013
04-Jan-2013
07-Jan-2013
05-Jan-2013
10-Jan-2013
11-Jan-2013
12-Jan-2013
14-Jan-2013
07-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
11-Jan-2013
12-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
17-Jan-2013
19-Jan-2013
22-FEB-13A
25-FEB-13A
12-MAR-13A
13-MAR-13A
14-MAR-13A
15-MAR-13A
19-MAR-13A
18-DEC-12A
19-DEC-12A
16-FEB-13A
17-FEB-13A
18-FEB-13A
19-FEB-13A
27-FEB-13A
04-MAR-13A
12-MAR-13A
15-MAR-13A
28-FEB-13A
25-FEB-13A
27-FEB-13A
15-MAR-13A
16-MAR-13A
17-MAR-13A
18-MAR-13A
19-MAR-13A
14-FEB-13A
15-FEB-13A
17-FEB-13A
18-FEB-13A
18-FEB-13A
26-FEB-13A
05-MAR-13A
11-MAR-13A
14-MAR-13A
19-MAR-13A
03-MAR-13A
-43d
-43d
-58d
-55d
-55d
-54d
-54d
-32d
-32d
-33d
-32d
-31d
-37d
-42d
-46d
-48d
-51d
-36d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10545
S2CONP10546
S2CONP10547
S2CONP10548
S2CONP10549
S2CONP10550
S2CONP10551
S2CONP10552
S2CONP10553
014
S2CONP10554
S2CONP10555
S2CONP10556
S2CONP10557
S2CONP10558
S2CONP10559
S2CONP10560
S2CONP10561
18-Jan-2013
19-Jan-2013
18-Jan-2013
24-Jan-2013
25-Jan-2013
30-Jan-2013
01-Feb-2013
01-Feb-2013
05-Feb-2013
03-Jan-2013
03-Jan-2013
05-Jan-2013
09-Jan-2013
11-Jan-2013
14-Jan-2013
16-Jan-2013
17-Jan-2013
18-Jan-2013
21-Jan-2013
22-Jan-2013
23-Jan-2013
25-Jan-2013
31-Jan-2013
01-Feb-2013
02-Feb-2013
04-Feb-2013
05-Feb-2013
12-Feb-2013
05-Jan-2013
09-Jan-2013
11-Jan-2013
14-Jan-2013
15-Jan-2013
19-Jan-2013
21-Jan-2013
22-Jan-2013
03-MAR-13A
07-MAR-13A
29-MAR-13A
24-APR-13A
29-APR-13A
03-MAY-13A
06-MAY-13A
06-MAY-13A
22-MAY-13A
11-Feb-2013A
11-FEB-13A
12-FEB-13A
19-FEB-13A
23-FEB-13A
27-FEB-13A
01-MAR-13A
08-MAR-13A
15-MAR-13A
06-MAR-13A
08-MAR-13A
01-APR-13A
25-APR-13A
14-MAY-13A
17-MAY-13A
19-MAY-13A
18-MAY-13A
22-MAY-13A
31-May-2013
15-FEB-13A
18-FEB-13A
22-FEB-13A
26-FEB-13A
28-FEB-13A
07-MAR-13A
12-MAR-13A
19-MAR-13A
-37d
-38d
-57d
-77d
-87d
-89d
-90d
-88d
-90d
-93d
-34d
-33d
-35d
-36d
-37d
-39d
-42d
-47d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10562
S2CONP10563
S2CONP10564
S2CONP10565
S2CONP10566
S2CONP10567
S2CONP10568
S2CONP10569
S2CONP10570
S2CONP10571
S2CONP10572
S2CONP10573
S2CONP10574
S2CONP10575
S2CONP10576
S2CONP10577
S2CONP10578
S2CONP10579
23-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
17-Jan-2013
18-Jan-2013
19-Jan-2013
21-Jan-2013
21-Jan-2013
22-Jan-2013
23-Jan-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
25-Jan-2013
31-Jan-2013
01-Feb-2013
06-Feb-2013
23-Jan-2013
16-Jan-2013
17-Jan-2013
18-Jan-2013
19-Jan-2013
21-Jan-2013
22-Jan-2013
23-Jan-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
26-Jan-2013
28-Jan-2013
29-Jan-2013
30-Jan-2013
01-Feb-2013
07-Feb-2013
08-Feb-2013
19-MAR-13A
12-FEB-13A
16-FEB-13A
21-FEB-13A
25-FEB-13A
01-MAR-13A
05-MAR-13A
08-MAR-13A
12-MAR-13A
16-MAR-13A
21-MAR-13A
21-MAR-13A
23-MAR-13A
25-MAR-13A
28-MAR-13A
01-APR-13A
05-APR-13A
09-APR-13A
20-MAR-13A
15-FEB-13A
20-FEB-13A
23-FEB-13A
28-FEB-13A
04-MAR-13A
07-MAR-13A
11-MAR-13A
15-MAR-13A
21-MAR-13A
22-MAR-13A
22-MAR-13A
24-MAR-13A
26-MAR-13A
01-APR-13A
05-APR-13A
10-APR-13A
12-APR-13A
-47d
-25d
-28d
-30d
-33d
-35d
-37d
-39d
-42d
-46d
-46d
-46d
-47d
-47d
-51d
-53d
-52d
-53d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10580
S2CONP10581
S2CONP10582
016
S2CONP10612
S2CONP10613
S2CONP10614
S2CONP10615
S2CONP10616
S2CONP10617
S2CONP10618
S2CONP10619
S2CONP10620
S2CONP10631
S2CONP10632
S2CONP10633
S2CONP10634
S2CONP10635
08-Feb-2013
08-Feb-2013
12-Feb-2013
15-Jan-2013
15-Jan-2013
17-Jan-2013
21-Jan-2013
23-Jan-2013
31-Jan-2013
02-Feb-2013
04-Feb-2013
05-Feb-2013
09-Feb-2013
06-Feb-2013
07-Feb-2013
08-Feb-2013
07-Feb-2013
13-Feb-2013
09-Feb-2013
11-Feb-2013
12-Feb-2013
23-Feb-2013
17-Jan-2013
21-Jan-2013
23-Jan-2013
25-Jan-2013
01-Feb-2013
06-Feb-2013
07-Feb-2013
08-Feb-2013
09-Feb-2013
08-Feb-2013
09-Feb-2013
11-Feb-2013
12-Feb-2013
14-Feb-2013
09-APR-13A
12-APR-13A
15-APR-13A
31-Jan-2013A
31-JAN-13A
02-FEB-13A
10-FEB-13A
15-FEB-13A
05-MAR-13A
09-MAR-13A
12-MAR-13A
17-MAR-13A
21-MAR-13A
14-MAR-13A
16-MAR-13A
22-MAR-13A
26-MAR-13A
29-MAR-13A
12-APR-13A
14-APR-13A
16-APR-13A
31-May-2013
02-FEB-13A
08-FEB-13A
14-FEB-13A
20-FEB-13A
08-MAR-13A
11-MAR-13A
16-MAR-13A
20-MAR-13A
21-MAR-13A
17-MAR-13A
20-MAR-13A
23-MAR-13A
01-APR-13A
05-APR-13A
-52d
-53d
-53d
-83d
-13d
-15d
-18d
-21d
-29d
-27d
-31d
-33d
-33d
-31d
-32d
-34d
-40d
-42d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10636
S2CONP10637
S2CONP10638
S2CONP10639
S2CONP10640
004
002
009
S2CONP10961
S2CONP10962
S2CONP10963
S2CONP10964
S2CONP10965
S2CONP10966
S2CONP10967
S2CONP10968
S2CONP10969
S2CONP10970
14-Feb-2013
18-Feb-2013
20-Feb-2013
20-Feb-2013
23-Feb-2013
14-Feb-2013
30-Mar-2013
30-Mar-2013
30-Mar-2013
03-Apr-2013
12-Apr-2013
24-Apr-2013
01-May-2013
08-May-2013
18-May-2013
29-May-2013
04-Jun-2013
13-Jun-2013
19-Feb-2013
20-Feb-2013
21-Feb-2013
22-Feb-2013
23-Feb-2013
03-Aug-2013
03-Aug-2013
13-Jun-2013
02-Apr-2013
11-Apr-2013
23-Apr-2013
04-May-2013
11-May-2013
21-May-2013
29-May-2013
03-Jun-2013
12-Jun-2013
13-Jun-2013
10-APR-13A
22-APR-13A
24-APR-13A
04-MAY-13A
09-MAY-13A
06-Mar-2013A
22-Jun-2013
22-Jun-2013
22-JUN-13
26-JUN-13
05-JUL-13
12-JUL-13
16-JUL-13
18-JUL-13
26-JUL-13
03-AUG-13
09-AUG-13
19-AUG-13
23-APR-13A
01-MAY-13A
06-MAY-13A
08-MAY-13A
09-MAY-13A
24-Sep-2013
24-Sep-2013
19-Aug-2013
25-JUN-13
04-JUL-13
11-JUL-13
19-JUL-13
22-JUL-13
29-JUL-13
03-AUG-13
08-AUG-13
17-AUG-13
19-AUG-13
-54d
-60d
-62d
-63d
-63d
-44d
-44d
-57d
-72d
-72d
-68d
-65d
-61d
-59d
-57d
-57d
-57d
-57d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
010
S2CONP10971
S2CONP10972
S2CONP10973
S2CONP10974
S2CONP10975
S2CONP10976
S2CONP10977
S2CONP10978
S2CONP10979
S2CONP10980
011
S2CONP10981
S2CONP10982
S2CONP10983
S2CONP10984
S2CONP10985
S2CONP10986
09-Apr-2013
09-Apr-2013
12-Apr-2013
22-Apr-2013
03-May-2013
10-May-2013
17-May-2013
28-May-2013
07-Jun-2013
13-Jun-2013
22-Jun-2013
16-Apr-2013
16-Apr-2013
19-Apr-2013
29-Apr-2013
10-May-2013
17-May-2013
24-May-2013
22-Jun-2013
11-Apr-2013
20-Apr-2013
02-May-2013
14-May-2013
21-May-2013
30-May-2013
07-Jun-2013
12-Jun-2013
21-Jun-2013
22-Jun-2013
29-Jun-2013
18-Apr-2013
27-Apr-2013
09-May-2013
21-May-2013
28-May-2013
06-Jun-2013
29-Jul-2013
29-JUL-13
01-AUG-13
10-AUG-13
17-AUG-13
21-AUG-13
23-AUG-13
31-AUG-13
09-SEP-13
14-SEP-13
24-SEP-13
22-Jun-2013
22-JUN-13
26-JUN-13
05-JUL-13
12-JUL-13
16-JUL-13
18-JUL-13
24-Sep-2013
31-JUL-13
09-AUG-13
16-AUG-13
24-AUG-13
27-AUG-13
03-SEP-13
09-SEP-13
13-SEP-13
23-SEP-13
24-SEP-13
19-Aug-2013
25-JUN-13
04-JUL-13
11-JUL-13
19-JUL-13
22-JUL-13
29-JUL-13
-80d
-95d
-95d
-91d
-88d
-84d
-82d
-80d
-80d
-80d
-80d
-43d
-58d
-58d
-54d
-51d
-47d
-45d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10987
S2CONP10988
S2CONP10989
S2CONP10990
013
S2CONP11001
S2CONP11002
S2CONP11003
S2CONP11004
S2CONP11005
S2CONP11006
S2CONP11007
S2CONP11008
S2CONP11009
S2CONP11010
015
S2CONP11021
S2CONP11022
04-Jun-2013
14-Jun-2013
20-Jun-2013
29-Jun-2013
02-May-2013
02-May-2013
06-May-2013
15-May-2013
27-May-2013
03-Jun-2013
10-Jun-2013
20-Jun-2013
01-Jul-2013
06-Jul-2013
16-Jul-2013
17-May-2013
17-May-2013
21-May-2013
14-Jun-2013
19-Jun-2013
28-Jun-2013
29-Jun-2013
16-Jul-2013
04-May-2013
14-May-2013
25-May-2013
06-Jun-2013
13-Jun-2013
22-Jun-2013
01-Jul-2013
05-Jul-2013
15-Jul-2013
16-Jul-2013
31-Jul-2013
20-May-2013
29-May-2013
26-JUL-13
03-AUG-13
09-AUG-13
19-AUG-13
15-Jul-2013
15-JUL-13
18-JUL-13
27-JUL-13
03-AUG-13
07-AUG-13
09-AUG-13
17-AUG-13
26-AUG-13
31-AUG-13
10-SEP-13
08-Jul-2013
08-JUL-13
11-JUL-13
03-AUG-13
08-AUG-13
17-AUG-13
19-AUG-13
10-Sep-2013
17-JUL-13
26-JUL-13
02-AUG-13
10-AUG-13
13-AUG-13
20-AUG-13
26-AUG-13
30-AUG-13
09-SEP-13
10-SEP-13
04-Sep-2013
11-JUL-13
20-JUL-13
-43d
-43d
-43d
-43d
-48d
-63d
-63d
-59d
-56d
-52d
-50d
-48d
-48d
-48d
-48d
-30d
-44d
-44d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11023
S2CONP11024
S2CONP11025
S2CONP11026
S2CONP11027
S2CONP11028
S2CONP11029
S2CONP11030
016
S2CONP11031
S2CONP11032
S2CONP11033
S2CONP11034
S2CONP11035
S2CONP11036
S2CONP11037
S2CONP11038
S2CONP11039
30-May-2013
11-Jun-2013
18-Jun-2013
25-Jun-2013
05-Jul-2013
16-Jul-2013
22-Jul-2013
31-Jul-2013
21-May-2013
21-May-2013
24-May-2013
03-Jun-2013
14-Jun-2013
21-Jun-2013
28-Jun-2013
09-Jul-2013
19-Jul-2013
25-Jul-2013
10-Jun-2013
21-Jun-2013
28-Jun-2013
08-Jul-2013
16-Jul-2013
20-Jul-2013
30-Jul-2013
31-Jul-2013
03-Aug-2013
23-May-2013
01-Jun-2013
13-Jun-2013
25-Jun-2013
02-Jul-2013
11-Jul-2013
19-Jul-2013
24-Jul-2013
02-Aug-2013
20-JUL-13
27-JUL-13
31-JUL-13
02-AUG-13
10-AUG-13
19-AUG-13
24-AUG-13
03-SEP-13
16-Jul-2013
16-JUL-13
19-JUL-13
29-JUL-13
05-AUG-13
08-AUG-13
10-AUG-13
19-AUG-13
27-AUG-13
02-SEP-13
27-JUL-13
05-AUG-13
07-AUG-13
14-AUG-13
20-AUG-13
24-AUG-13
03-SEP-13
04-SEP-13
12-Sep-2013
19-JUL-13
29-JUL-13
05-AUG-13
13-AUG-13
15-AUG-13
22-AUG-13
28-AUG-13
02-SEP-13
11-SEP-13
-40d
-37d
-33d
-31d
-29d
-29d
-29d
-29d
-34d
-48d
-48d
-44d
-41d
-37d
-35d
-33d
-33d
-33d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting of FF
10 POUR-12 (GRID E~H / 09~12)
11 Starters for the Columns / Shear Walls
11 Staging for the Columns / Shear Walls
11 Rebar works for the Columns / Shear Walls
11 Form works for the Columns / Shear Walls
11 Concreting of the Columns / Shear Walls
11 Table & Conventional Form Works for the FF
11 Bottom Rebar works for the FF
11 PT Tandons Laying works for the FF
11 Top Rebar works for the FF
11 Concreting of FF
10 POUR-14 (GRID A~D / 01~05)
11 Starters for the Columns / Shear Walls
11 Staging for the Columns / Shear Walls
11 Rebar works for the Columns / Shear Walls
11 Form works for the Columns / Shear Walls
11 Concreting of the Columns / Shear Walls
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11040
012
S2CONP10991
S2CONP10992
S2CONP10993
S2CONP10994
S2CONP10995
S2CONP10996
S2CONP10997
S2CONP10998
S2CONP10999
S2CONP11000
014
S2CONP11011
S2CONP11012
S2CONP11013
S2CONP11014
S2CONP11015
03-Aug-2013
26-Apr-2013
26-Apr-2013
30-Apr-2013
09-May-2013
21-May-2013
28-May-2013
04-Jun-2013
14-Jun-2013
25-Jun-2013
01-Jul-2013
10-Jul-2013
09-May-2013
09-May-2013
13-May-2013
22-May-2013
03-Jun-2013
10-Jun-2013
03-Aug-2013
10-Jul-2013
29-Apr-2013
08-May-2013
20-May-2013
31-May-2013
07-Jun-2013
17-Jun-2013
25-Jun-2013
29-Jun-2013
09-Jul-2013
10-Jul-2013
23-Jul-2013
11-May-2013
21-May-2013
01-Jun-2013
13-Jun-2013
20-Jun-2013
11-SEP-13
24-Jun-2013
24-JUN-13
27-JUN-13
06-JUL-13
13-JUL-13
17-JUL-13
19-JUL-13
27-JUL-13
05-AUG-13
10-AUG-13
20-AUG-13
08-Jul-2013
08-JUL-13
11-JUL-13
20-JUL-13
27-JUL-13
31-JUL-13
12-SEP-13
20-Aug-2013
26-JUN-13
05-JUL-13
12-JUL-13
20-JUL-13
23-JUL-13
30-JUL-13
05-AUG-13
09-AUG-13
19-AUG-13
20-AUG-13
03-Sep-2013
10-JUL-13
19-JUL-13
26-JUL-13
03-AUG-13
06-AUG-13
-33d
-35d
-50d
-50d
-46d
-43d
-39d
-37d
-35d
-35d
-35d
-35d
-36d
-51d
-51d
-47d
-44d
-40d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11016
S2CONP11017
S2CONP11018
S2CONP11019
S2CONP11020
001
001
S2CONP10881
S2CONP10882
S2CONP10883
S2CONP10884
S2CONP10885
S2CONP10886
003
S2CONP10901
S2CONP10902
S2CONP10908
S2CONP10909
17-Jun-2013
27-Jun-2013
08-Jul-2013
13-Jul-2013
23-Jul-2013
14-Feb-2013
14-Feb-2013
14-Feb-2013
18-Feb-2013
27-Feb-2013
11-Mar-2013
18-Mar-2013
25-Mar-2013
01-Mar-2013
01-Mar-2013
05-Mar-2013
30-Apr-2013
06-May-2013
29-Jun-2013
08-Jul-2013
12-Jul-2013
22-Jul-2013
23-Jul-2013
24-Jun-2013
06-Apr-2013
16-Feb-2013
26-Feb-2013
09-Mar-2013
21-Mar-2013
28-Mar-2013
06-Apr-2013
15-May-2013
04-Mar-2013
13-Mar-2013
04-May-2013
14-May-2013
02-AUG-13
10-AUG-13
19-AUG-13
24-AUG-13
03-SEP-13
06-Mar-2013A
01-Apr-2013A
01-APR-13A
01-APR-13A
03-APR-13A
05-APR-13A
06-APR-13A
03-APR-13A
06-Mar-2013A
06-MAR-13A
14-MAR-13A
29-APR-13A
01-MAY-13A
13-AUG-13
19-AUG-13
23-AUG-13
02-SEP-13
03-SEP-13
26-Jun-2013
31-May-2013
03-APR-13A
09-APR-13A
08-APR-13A
10-APR-13A
11-APR-13A
11-APR-13A
31-May-2013
13-MAR-13A
18-MAR-13A
18-MAY-13A
18-MAY-13A
-38d
-36d
-36d
-36d
-36d
-2d
-47d
-39d
-36d
-25d
-17d
-12d
-4d
-14d
-7d
-3d
-11d
-3d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Concreting of FF
10 POUR-04 (GRID E~H / 24~28)
11 Starters for the Columns / Shear Walls
11 Staging for the Columns / Shear Walls
10 POUR-05 (GRID A~D / 20~24)
11 Starters for the Columns / Shear Walls
11 Staging for the Columns / Shear Walls
11 Rebar works for the Columns / Shear Walls
10 POUR-02 (GRID A~D / 24~28)
11 Starters for the Columns / Shear Walls
11 Staging for the Columns / Shear Walls
10 POUR-07 (GRID E~H / 20~24)
11 Starters for the Columns / Shear Walls
10 POUR-08 (GRID E~H / 16~20)
11 Starters for the Columns / Shear Walls
11 Staging for the Columns / Shear Walls
11 Table & Conventional Form Works for the FF
11 Bottom Rebar works for the FF
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10910
004
S2CONP10911
S2CONP10912
005
S2CONP10921
S2CONP10922
S2CONP10923
002
S2CONP10891
S2CONP10892
007
S2CONP10941
008
S2CONP10951
S2CONP10952
S2CONP10956
S2CONP10957
15-May-2013
11-Mar-2013
11-Mar-2013
14-Mar-2013
19-Mar-2013
19-Mar-2013
22-Mar-2013
01-Apr-2013
22-Feb-2013
22-Feb-2013
26-Feb-2013
04-Apr-2013
04-Apr-2013
10-Apr-2013
10-Apr-2013
13-Apr-2013
18-May-2013
29-May-2013
15-May-2013
22-Mar-2013
13-Mar-2013
22-Mar-2013
11-Apr-2013
21-Mar-2013
30-Mar-2013
11-Apr-2013
06-Mar-2013
25-Feb-2013
06-Mar-2013
06-Apr-2013
06-Apr-2013
24-Jun-2013
12-Apr-2013
22-Apr-2013
31-May-2013
08-Jun-2013
20-MAY-13A
18-Mar-2013A
18-MAR-13A
21-MAR-13A
29-Mar-2013A
29-MAR-13A
02-APR-13A
09-APR-13A
08-Mar-2013A
08-MAR-13A
11-MAR-13A
05-Apr-2013A
05-APR-13A
22-Apr-2013A
22-APR-13A
22-APR-13A
10-MAY-13A
31-MAY-13
20-MAY-13A
31-May-2013
20-MAR-13A
25-MAR-13A
31-May-2013
01-APR-13A
09-APR-13A
15-APR-13A
31-May-2013
11-MAR-13A
15-MAR-13A
31-May-2013
08-APR-13A
26-Jun-2013
24-APR-13A
30-APR-13A
01-JUN-13
11-JUN-13
-3d
-60d
-5d
-1d
-43d
-8d
-7d
-2d
-74d
-11d
-7d
-47d
-1d
-2d
-10d
-7d
0d
-2d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10958
S2CONP10959
S2CONP10960
006
S2CONP10931
S2CONP10932
S2CONP10937
003
001
005
S2CONP10714
S2CONP10715
S2CONP10713
S2CONP10701
S2CONP10702
S2CONP10703
S2CONP10704
S2CONP10705
08-Jun-2013
14-Jun-2013
24-Jun-2013
27-Mar-2013
27-Mar-2013
30-Mar-2013
15-May-2013
26-Nov-2012
26-Nov-2012
28-Dec-2012
06-Mar-2013
13-Mar-2013
28-Feb-2013
28-Dec-2012
01-Jan-2013
08-Jan-2013
19-Jan-2013
26-Jan-2013
13-Jun-2013
22-Jun-2013
24-Jun-2013
25-May-2013
29-Mar-2013
08-Apr-2013
25-May-2013
15-May-2013
05-Apr-2013
13-Mar-2013
12-Mar-2013
13-Mar-2013
05-Mar-2013
31-Dec-2012
07-Jan-2013
18-Jan-2013
30-Jan-2013
06-Feb-2013
11-JUN-13
17-JUN-13
26-JUN-13
05-Apr-2013A
05-APR-13A
09-APR-13A
26-APR-13A
28-Dec-2012A
28-Dec-2012A
28-Dec-2012A
22-MAR-13A
28-MAR-13A
23-MAR-13A
11-FEB-13A
13-FEB-13A
08-MAR-13A
10-MAR-13A
17-MAR-13A
15-JUN-13
25-JUN-13
26-JUN-13
31-May-2013
08-APR-13A
17-APR-13A
31-MAY-13
27-Jul-2013
31-May-2013
31-May-2013
27-MAR-13A
29-MAR-13A
26-MAR-13A
26-FEB-13A
05-MAR-13A
09-MAR-13A
12-MAR-13A
19-MAR-13A
-2d
-2d
-2d
-5d
-8d
-8d
-4d
-63d
-48d
-68d
-12d
-13d
-17d
-49d
-49d
-42d
-34d
-34d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10706
S2CONP10707
S2CONP10708
S2CONP10709
S2CONP10710
S2CONP10711
S2CONP10712
006
S2CONP10716
S2CONP10717
S2CONP10718
S2CONP10719
S2CONP10720
S2CONP10721
S2CONP10722
S2CONP10723
S2CONP10724
S2CONP10725
28-Dec-2012
31-Dec-2012
05-Jan-2013
17-Jan-2013
31-Jan-2013
07-Feb-2013
18-Feb-2013
05-Jan-2013
05-Jan-2013
09-Jan-2013
16-Jan-2013
28-Jan-2013
04-Feb-2013
05-Jan-2013
08-Jan-2013
14-Jan-2013
25-Jan-2013
08-Feb-2013
29-Dec-2012
04-Jan-2013
16-Jan-2013
30-Jan-2013
31-Jan-2013
20-Feb-2013
28-Feb-2013
21-Mar-2013
08-Jan-2013
15-Jan-2013
26-Jan-2013
07-Feb-2013
14-Feb-2013
07-Jan-2013
12-Jan-2013
24-Jan-2013
07-Feb-2013
08-Feb-2013
28-DEC-12A
26-FEB-13A
04-MAR-13A
15-MAR-13A
16-MAR-13A
14-MAR-13A
20-MAR-13A
21-Feb-2013A
21-FEB-13A
25-FEB-13A
11-MAR-13A
22-MAR-13A
04-MAR-13A
26-FEB-13A
28-FEB-13A
08-MAR-13A
25-MAR-13A
27-MAR-13A
25-FEB-13A
02-MAR-13A
07-MAR-13A
16-MAR-13A
16-MAR-13A
21-MAR-13A
23-MAR-13A
31-May-2013
23-FEB-13A
02-MAR-13A
21-MAR-13A
25-MAR-13A
14-MAR-13A
27-FEB-13A
05-MAR-13A
19-MAR-13A
26-MAR-13A
28-MAR-13A
-49d
-49d
-42d
-38d
-37d
-24d
-19d
-61d
-40d
-40d
-46d
-38d
-24d
-44d
-44d
-46d
-39d
-40d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10726
S2CONP10727
S2CONP10728
S2CONP10729
S2CONP10730
007
S2CONP10731
S2CONP10732
S2CONP10733
S2CONP10734
S2CONP10735
S2CONP10736
S2CONP10737
S2CONP10738
S2CONP10739
S2CONP10740
S2CONP10741
S2CONP10742
15-Feb-2013
26-Feb-2013
08-Mar-2013
14-Mar-2013
21-Mar-2013
14-Jan-2013
14-Jan-2013
17-Jan-2013
24-Jan-2013
05-Feb-2013
12-Feb-2013
14-Jan-2013
16-Jan-2013
22-Jan-2013
02-Feb-2013
16-Feb-2013
23-Feb-2013
06-Mar-2013
28-Feb-2013
08-Mar-2013
13-Mar-2013
20-Mar-2013
21-Mar-2013
29-Mar-2013
16-Jan-2013
23-Jan-2013
04-Feb-2013
15-Feb-2013
22-Feb-2013
15-Jan-2013
21-Jan-2013
01-Feb-2013
15-Feb-2013
16-Feb-2013
08-Mar-2013
16-Mar-2013
26-MAR-13A
03-APR-13A
07-APR-13A
07-APR-13A
09-APR-13A
20-Feb-2013A
20-FEB-13A
21-FEB-13A
22-FEB-13A
25-FEB-13A
26-FEB-13A
20-FEB-13A
20-FEB-13A
22-FEB-13A
25-FEB-13A
16-MAR-13A
19-MAR-13A
23-MAR-13A
03-APR-13A
07-APR-13A
09-APR-13A
09-APR-13A
10-APR-13A
31-May-2013
23-FEB-13A
02-MAR-13A
06-MAR-13A
11-MAR-13A
14-MAR-13A
25-FEB-13A
02-MAR-13A
04-MAR-13A
15-MAR-13A
16-MAR-13A
23-MAR-13A
26-MAR-13A
-28d
-25d
-22d
-16d
-16d
-54d
-33d
-33d
-25d
-19d
-17d
-35d
-35d
-25d
-23d
-23d
-12d
-7d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10743
S2CONP10744
S2CONP10745
008
S2CONP10746
S2CONP10747
S2CONP10748
S2CONP10749
S2CONP10750
S2CONP10751
S2CONP10752
S2CONP10754
S2CONP10755
S2CONP10756
S2CONP10757
S2CONP10758
S2CONP10759
S2CONP10760
16-Mar-2013
22-Mar-2013
29-Mar-2013
21-Jan-2013
21-Jan-2013
24-Jan-2013
31-Jan-2013
12-Feb-2013
19-Feb-2013
21-Jan-2013
23-Jan-2013
09-Feb-2013
23-Feb-2013
02-Mar-2013
13-Mar-2013
23-Mar-2013
29-Mar-2013
05-Apr-2013
21-Mar-2013
28-Mar-2013
29-Mar-2013
05-Apr-2013
23-Jan-2013
30-Jan-2013
11-Feb-2013
22-Feb-2013
01-Mar-2013
22-Jan-2013
28-Jan-2013
22-Feb-2013
23-Feb-2013
15-Mar-2013
23-Mar-2013
28-Mar-2013
04-Apr-2013
05-Apr-2013
26-MAR-13A
29-MAR-13A
02-APR-13A
21-Feb-2013A
21-FEB-13A
25-FEB-13A
11-MAR-13A
04-MAR-13A
11-MAR-13A
26-FEB-13A
02-MAR-13A
20-MAR-13A
24-MAR-13A
26-MAR-13A
03-APR-13A
07-APR-13A
10-APR-13A
12-APR-13A
29-MAR-13A
31-MAR-13A
03-APR-13A
31-May-2013
23-FEB-13A
02-MAR-13A
21-MAR-13A
14-MAR-13A
21-MAR-13A
27-FEB-13A
07-MAR-13A
23-MAR-13A
24-MAR-13A
02-APR-13A
07-APR-13A
10-APR-13A
12-APR-13A
13-APR-13A
-6d
-2d
-3d
-48d
-27d
-27d
-33d
-17d
-17d
-31d
-33d
-24d
-24d
-14d
-12d
-10d
-6d
-6d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10753
004
S2CONP10686
S2CONP10687
S2CONP10688
S2CONP10689
S2CONP10690
S2CONP10691
S2CONP10692
S2CONP10693
S2CONP10694
S2CONP10695
S2CONP10696
S2CONP10697
S2CONP10698
S2CONP10699
S2CONP10700
001
29-Jan-2013
20-Dec-2012
20-Dec-2012
24-Dec-2012
31-Dec-2012
11-Jan-2013
18-Jan-2013
20-Dec-2012
22-Dec-2012
28-Dec-2012
09-Jan-2013
23-Jan-2013
30-Jan-2013
09-Feb-2013
20-Feb-2013
26-Feb-2013
05-Mar-2013
26-Nov-2012
08-Feb-2013
05-Mar-2013
22-Dec-2012
29-Dec-2012
10-Jan-2013
22-Jan-2013
29-Jan-2013
21-Dec-2012
27-Dec-2012
08-Jan-2013
22-Jan-2013
23-Jan-2013
12-Feb-2013
20-Feb-2013
25-Feb-2013
04-Mar-2013
05-Mar-2013
08-Feb-2013
08-MAR-13A
07-Feb-2013A
07-FEB-13A
08-FEB-13A
10-FEB-13A
11-FEB-13A
12-FEB-13A
10-FEB-13A
10-FEB-13A
14-FEB-13A
02-MAR-13A
07-MAR-13A
07-MAR-13A
10-MAR-13A
14-MAR-13A
16-MAR-13A
18-MAR-13A
23-Jan-2013A
19-MAR-13A
31-May-2013
08-FEB-13A
11-FEB-13A
12-FEB-13A
13-FEB-13A
14-FEB-13A
22-FEB-13A
28-FEB-13A
01-MAR-13A
06-MAR-13A
07-MAR-13A
09-MAR-13A
14-MAR-13A
15-MAR-13A
17-MAR-13A
18-MAR-13A
31-May-2013
-33d
-75d
-40d
-36d
-27d
-18d
-13d
-54d
-54d
-44d
-36d
-36d
-21d
-18d
-15d
-11d
-10d
-96d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10641
S2CONP10642
S2CONP10643
S2CONP10644
S2CONP10645
S2CONP10646
S2CONP10647
S2CONP10648
S2CONP10649
S2CONP10650
S2CONP10651
S2CONP10652
S2CONP10653
S2CONP10654
S2CONP10655
003
S2CONP10671
S2CONP10672
26-Nov-2012
29-Nov-2012
06-Dec-2012
18-Dec-2012
25-Dec-2012
26-Nov-2012
28-Nov-2012
04-Dec-2012
15-Dec-2012
29-Dec-2012
05-Jan-2013
16-Jan-2013
26-Jan-2013
01-Feb-2013
08-Feb-2013
11-Dec-2012
11-Dec-2012
14-Dec-2012
28-Nov-2012
05-Dec-2012
17-Dec-2012
28-Dec-2012
04-Jan-2013
27-Nov-2012
03-Dec-2012
14-Dec-2012
28-Dec-2012
29-Dec-2012
18-Jan-2013
26-Jan-2013
31-Jan-2013
07-Feb-2013
08-Feb-2013
23-Feb-2013
13-Dec-2012
20-Dec-2012
23-JAN-13A
25-JAN-13A
27-JAN-13A
28-JAN-13A
30-JAN-13A
26-JAN-13A
26-JAN-13A
10-FEB-13A
12-FEB-13A
16-FEB-13A
22-FEB-13A
01-MAR-13A
05-MAR-13A
06-MAR-13A
11-MAR-13A
30-Jan-2013A
30-JAN-13A
02-FEB-13A
24-JAN-13A
27-FEB-13A
13-MAR-13A
25-MAR-13A
11-MAR-13A
11-FEB-13A
11-FEB-13A
13-FEB-13A
15-FEB-13A
16-FEB-13A
01-MAR-13A
04-MAR-13A
06-MAR-13A
09-MAR-13A
11-MAR-13A
31-May-2013
23-FEB-13A
02-MAR-13A
-48d
-72d
-74d
-74d
-56d
-64d
-59d
-51d
-41d
-41d
-35d
-30d
-28d
-25d
-25d
-83d
-62d
-62d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10673
S2CONP10674
S2CONP10675
S2CONP10676
S2CONP10677
S2CONP10678
S2CONP10679
S2CONP10680
S2CONP10681
S2CONP10682
S2CONP10683
S2CONP10684
S2CONP10685
002
S2CONP10656
S2CONP10657
S2CONP10658
S2CONP10659
21-Dec-2012
02-Jan-2013
09-Jan-2013
11-Dec-2012
13-Dec-2012
19-Dec-2012
31-Dec-2012
14-Jan-2013
21-Jan-2013
31-Jan-2013
11-Feb-2013
16-Feb-2013
23-Feb-2013
04-Dec-2012
04-Dec-2012
07-Dec-2012
14-Dec-2012
26-Dec-2012
01-Jan-2013
12-Jan-2013
19-Jan-2013
12-Dec-2012
18-Dec-2012
29-Dec-2012
12-Jan-2013
14-Jan-2013
02-Feb-2013
11-Feb-2013
15-Feb-2013
22-Feb-2013
23-Feb-2013
16-Feb-2013
06-Dec-2012
13-Dec-2012
25-Dec-2012
05-Jan-2013
04-FEB-13A
04-MAR-13A
05-FEB-13A
04-FEB-13A
04-FEB-13A
06-FEB-13A
07-FEB-13A
08-FEB-13A
02-MAR-13A
12-MAR-13A
15-MAR-13A
18-MAR-13A
21-MAR-13A
15-Jan-2013A
15-JAN-13A
16-JAN-13A
18-JAN-13A
20-JAN-13A
08-MAR-13A
14-MAR-13A
14-MAR-13A
09-FEB-13A
09-FEB-13A
10-FEB-13A
11-FEB-13A
12-FEB-13A
12-MAR-13A
15-MAR-13A
18-MAR-13A
20-MAR-13A
21-MAR-13A
31-May-2013
17-JAN-13A
20-JAN-13A
23-JAN-13A
24-JAN-13A
-56d
-51d
-46d
-50d
-45d
-36d
-24d
-24d
-31d
-27d
-25d
-21d
-21d
-89d
-35d
-32d
-24d
-15d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10660
S2CONP10661
S2CONP10662
S2CONP10663
S2CONP10664
S2CONP10665
S2CONP10666
S2CONP10667
S2CONP10668
S2CONP10669
S2CONP10670
002
009
S2CONP10761
S2CONP10762
S2CONP10763
S2CONP10764
S2CONP10765
02-Jan-2013
04-Dec-2012
06-Dec-2012
12-Dec-2012
24-Dec-2012
07-Jan-2013
14-Jan-2013
24-Jan-2013
04-Feb-2013
09-Feb-2013
16-Feb-2013
09-Jan-2013
09-Jan-2013
09-Jan-2013
12-Jan-2013
19-Jan-2013
31-Jan-2013
07-Feb-2013
12-Jan-2013
05-Dec-2012
11-Dec-2012
22-Dec-2012
05-Jan-2013
07-Jan-2013
26-Jan-2013
04-Feb-2013
08-Feb-2013
15-Feb-2013
16-Feb-2013
15-May-2013
25-Mar-2013
11-Jan-2013
18-Jan-2013
30-Jan-2013
11-Feb-2013
18-Feb-2013
22-JAN-13A
22-JAN-13A
22-JAN-13A
29-JAN-13A
31-JAN-13A
12-FEB-13A
19-FEB-13A
25-FEB-13A
27-FEB-13A
01-MAR-13A
03-MAR-13A
25-Feb-2013A
01-Mar-2013A
25-MAR-13A
26-MAR-13A
01-APR-13A
01-APR-13A
04-APR-13A
28-JAN-13A
25-JAN-13A
25-JAN-13A
10-FEB-13A
11-FEB-13A
12-FEB-13A
25-FEB-13A
26-FEB-13A
28-FEB-13A
02-MAR-13A
03-MAR-13A
27-Jul-2013
21-Jun-2013
27-MAR-13A
01-APR-13A
02-APR-13A
03-APR-13A
04-APR-13A
-12d
-43d
-38d
-42d
-30d
-30d
-24d
-18d
-16d
-12d
-12d
-63d
-76d
-63d
-61d
-52d
-43d
-38d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10766
S2CONP10767
S2CONP10768
S2CONP10769
S2CONP10770
S2CONP10771
S2CONP10772
S2CONP10773
S2CONP10774
S2CONP10775
010
S2CONP10776
S2CONP10777
S2CONP10778
S2CONP10779
S2CONP10780
S2CONP10781
S2CONP10782
09-Jan-2013
11-Jan-2013
17-Jan-2013
29-Jan-2013
12-Feb-2013
19-Feb-2013
01-Mar-2013
12-Mar-2013
18-Mar-2013
25-Mar-2013
18-Jan-2013
18-Jan-2013
22-Jan-2013
29-Jan-2013
09-Feb-2013
16-Feb-2013
18-Jan-2013
21-Jan-2013
10-Jan-2013
16-Jan-2013
28-Jan-2013
11-Feb-2013
12-Feb-2013
04-Mar-2013
12-Mar-2013
16-Mar-2013
23-Mar-2013
25-Mar-2013
03-Apr-2013
21-Jan-2013
28-Jan-2013
08-Feb-2013
20-Feb-2013
27-Feb-2013
19-Jan-2013
25-Jan-2013
01-MAR-13A
04-MAR-13A
09-MAR-13A
21-MAR-13A
23-MAR-13A
15-APR-13A
31-MAY-13
08-JUN-13
14-JUN-13
21-JUN-13
06-Mar-2013A
31-MAY-13
04-JUN-13
11-JUN-13
18-JUN-13
21-JUN-13
06-MAR-13A
08-MAR-13A
02-MAR-13A
08-MAR-13A
20-MAR-13A
22-MAR-13A
23-MAR-13A
01-JUN-13
08-JUN-13
13-JUN-13
20-JUN-13
21-JUN-13
27-Jul-2013
03-JUN-13
10-JUN-13
17-JUN-13
25-JUN-13
27-JUN-13
07-MAR-13A
13-MAR-13A
-44d
-44d
-44d
-33d
-34d
-77d
-76d
-76d
-76d
-76d
-99d
-114d
-114d
-110d
-107d
-103d
-40d
-40d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10783
S2CONP10784
S2CONP10785
S2CONP10786
S2CONP10787
S2CONP10788
S2CONP10789
S2CONP10790
012
S2CONP10806
S2CONP10807
S2CONP10808
S2CONP10809
S2CONP10810
S2CONP10811
S2CONP10812
S2CONP10813
S2CONP10814
26-Jan-2013
07-Feb-2013
21-Feb-2013
28-Feb-2013
11-Mar-2013
21-Mar-2013
27-Mar-2013
03-Apr-2013
05-Feb-2013
05-Feb-2013
08-Feb-2013
15-Feb-2013
27-Feb-2013
06-Mar-2013
05-Feb-2013
07-Feb-2013
13-Feb-2013
25-Feb-2013
06-Feb-2013
20-Feb-2013
21-Feb-2013
13-Mar-2013
21-Mar-2013
26-Mar-2013
02-Apr-2013
03-Apr-2013
20-Apr-2013
07-Feb-2013
14-Feb-2013
26-Feb-2013
09-Mar-2013
16-Mar-2013
06-Feb-2013
12-Feb-2013
23-Feb-2013
09-Mar-2013
14-MAR-13A
20-MAR-13A
26-MAR-13A
28-JUN-13
06-JUL-13
15-JUL-13
20-JUL-13
27-JUL-13
28-Feb-2013A
29-APR-13A
02-MAY-13A
05-MAY-13A
06-MAY-13A
09-MAY-13A
28-FEB-13A
02-MAR-13A
08-MAR-13A
16-MAR-13A
20-MAR-13A
25-MAR-13A
26-MAR-13A
09-JUL-13
15-JUL-13
19-JUL-13
26-JUL-13
27-JUL-13
22-Jun-2013
01-MAY-13A
06-MAY-13A
07-MAY-13A
08-MAY-13A
10-MAY-13A
01-MAR-13A
07-MAR-13A
15-MAR-13A
20-MAR-13A
-35d
-27d
-28d
-101d
-99d
-99d
-99d
-99d
-54d
-71d
-68d
-59d
-50d
-46d
-20d
-20d
-16d
-8d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10815
S2CONP10816
S2CONP10817
S2CONP10818
S2CONP10819
S2CONP10820
013
S2CONP10821
S2CONP10822
S2CONP10823
S2CONP10824
S2CONP10825
S2CONP10826
S2CONP10827
S2CONP10828
S2CONP10829
S2CONP10830
S2CONP10831
11-Mar-2013
18-Mar-2013
28-Mar-2013
08-Apr-2013
13-Apr-2013
20-Apr-2013
11-Feb-2013
11-Feb-2013
14-Feb-2013
21-Feb-2013
05-Mar-2013
12-Mar-2013
11-Feb-2013
13-Feb-2013
19-Feb-2013
02-Mar-2013
16-Mar-2013
23-Mar-2013
11-Mar-2013
30-Mar-2013
08-Apr-2013
12-Apr-2013
19-Apr-2013
20-Apr-2013
26-Apr-2013
13-Feb-2013
20-Feb-2013
04-Mar-2013
15-Mar-2013
22-Mar-2013
12-Feb-2013
18-Feb-2013
01-Mar-2013
15-Mar-2013
16-Mar-2013
05-Apr-2013
21-MAR-13A
18-MAY-13A
01-JUN-13
10-JUN-13
15-JUN-13
22-JUN-13
06-Mar-2013A
24-MAY-13A
25-MAY-13A
28-MAY-13A
04-JUN-13
07-JUN-13
06-MAR-13A
08-MAR-13A
14-MAR-13A
21-MAR-13A
24-MAR-13A
14-JUN-13
21-MAR-13A
04-JUN-13
10-JUN-13
14-JUN-13
21-JUN-13
22-JUN-13
13-Jul-2013
27-MAY-13A
28-MAY-13A
03-JUN-13
11-JUN-13
13-JUN-13
07-MAR-13A
13-MAR-13A
20-MAR-13A
24-MAR-13A
24-MAR-13A
25-JUN-13
-8d
-56d
-54d
-54d
-54d
-54d
-67d
-88d
-82d
-78d
-75d
-71d
-20d
-20d
-15d
-7d
-6d
-69d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10832
S2CONP10833
S2CONP10834
S2CONP10835
014
S2CONP10836
S2CONP10837
S2CONP10838
S2CONP10839
S2CONP10840
S2CONP10841
S2CONP10842
S2CONP10843
S2CONP10846
S2CONP10847
S2CONP10848
S2CONP10849
S2CONP10850
03-Apr-2013
13-Apr-2013
19-Apr-2013
26-Apr-2013
18-Feb-2013
18-Feb-2013
21-Feb-2013
28-Feb-2013
12-Mar-2013
19-Mar-2013
18-Feb-2013
20-Feb-2013
26-Feb-2013
30-Mar-2013
10-Apr-2013
20-Apr-2013
26-Apr-2013
03-May-2013
13-Apr-2013
18-Apr-2013
25-Apr-2013
26-Apr-2013
03-May-2013
20-Feb-2013
27-Feb-2013
11-Mar-2013
22-Mar-2013
29-Mar-2013
19-Feb-2013
25-Feb-2013
08-Mar-2013
12-Apr-2013
20-Apr-2013
25-Apr-2013
02-May-2013
03-May-2013
22-JUN-13
01-JUL-13
06-JUL-13
13-JUL-13
25-Feb-2013A
29-APR-13A
02-MAY-13A
09-MAY-13A
29-MAY-13A
31-MAY-13
25-FEB-13A
27-FEB-13A
05-MAR-13A
07-JUN-13
15-JUN-13
24-JUN-13
29-JUN-13
06-JUL-13
01-JUL-13
05-JUL-13
12-JUL-13
13-JUL-13
06-Jul-2013
01-MAY-13A
08-MAY-13A
29-MAY-13A
04-JUN-13
06-JUN-13
26-FEB-13A
04-MAR-13A
15-MAR-13A
18-JUN-13
24-JUN-13
28-JUN-13
05-JUL-13
06-JUL-13
-67d
-67d
-67d
-67d
-55d
-60d
-60d
-67d
-63d
-59d
-6d
-6d
-6d
-57d
-55d
-55d
-55d
-55d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
016
S2CONP10866
S2CONP10867
S2CONP10868
S2CONP10869
S2CONP10870
S2CONP10876
S2CONP10877
S2CONP10878
S2CONP10879
S2CONP10880
015
S2CONP10851
S2CONP10852
S2CONP10853
S2CONP10854
S2CONP10855
S2CONP10856
01-Mar-2013
01-Mar-2013
05-Mar-2013
12-Mar-2013
23-Mar-2013
30-Mar-2013
11-Apr-2013
22-Apr-2013
02-May-2013
08-May-2013
15-May-2013
26-Feb-2013
26-Feb-2013
01-Mar-2013
08-Mar-2013
20-Mar-2013
27-Mar-2013
26-Feb-2013
15-May-2013
04-Mar-2013
11-Mar-2013
22-Mar-2013
03-Apr-2013
10-Apr-2013
24-Apr-2013
02-May-2013
07-May-2013
14-May-2013
15-May-2013
11-May-2013
28-Feb-2013
07-Mar-2013
19-Mar-2013
30-Mar-2013
06-Apr-2013
27-Feb-2013
24-May-2013A
24-MAY-13A
26-MAY-13A
29-MAY-13A
05-JUN-13
08-JUN-13
15-JUN-13
24-JUN-13
02-JUL-13
08-JUL-13
15-JUL-13
12-Mar-2013A
30-APR-13A
03-MAY-13A
24-MAY-13A
31-MAY-13A
31-MAY-13
12-MAR-13A
16-Jul-2013
26-MAY-13A
29-MAY-13A
05-JUN-13
13-JUN-13
15-JUN-13
27-JUN-13
03-JUL-13
08-JUL-13
15-JUL-13
16-JUL-13
08-Jul-2013
02-MAY-13A
09-MAY-13A
30-MAY-13A
05-JUN-13
07-JUN-13
13-MAR-13A
-53d
-71d
-67d
-63d
-60d
-56d
-54d
-52d
-52d
-52d
-52d
-49d
-54d
-54d
-62d
-56d
-52d
-12d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP10857
S2CONP10858
S2CONP10861
S2CONP10862
S2CONP10863
S2CONP10864
S2CONP10865
011
S2CONP10791
S2CONP10792
S2CONP10793
S2CONP10794
S2CONP10795
S2CONP10801
S2CONP10802
S2CONP10803
S2CONP10804
S2CONP10805
28-Feb-2013
06-Mar-2013
08-Apr-2013
18-Apr-2013
29-Apr-2013
04-May-2013
11-May-2013
25-Jan-2013
25-Jan-2013
29-Jan-2013
05-Feb-2013
16-Feb-2013
23-Feb-2013
07-Mar-2013
18-Mar-2013
28-Mar-2013
03-Apr-2013
10-Apr-2013
05-Mar-2013
16-Mar-2013
20-Apr-2013
29-Apr-2013
03-May-2013
10-May-2013
11-May-2013
10-Apr-2013
28-Jan-2013
04-Feb-2013
15-Feb-2013
27-Feb-2013
06-Mar-2013
20-Mar-2013
28-Mar-2013
02-Apr-2013
09-Apr-2013
10-Apr-2013
14-MAR-13A
20-MAR-13A
07-JUN-13
15-JUN-13
24-JUN-13
29-JUN-13
06-JUL-13
29-Apr-2013A
29-APR-13A
02-MAY-13A
04-MAY-13A
06-MAY-13A
08-MAY-13A
18-MAY-13A
31-MAY-13
08-JUN-13
14-JUN-13
21-JUN-13
19-MAR-13A
22-MAR-13A
19-JUN-13
25-JUN-13
29-JUN-13
06-JUL-13
08-JUL-13
21-Jun-2013
01-MAY-13A
04-MAY-13A
05-MAY-13A
08-MAY-13A
10-MAY-13A
01-JUN-13
08-JUN-13
13-JUN-13
20-JUN-13
21-JUN-13
-12d
-4d
-50d
-48d
-48d
-48d
-48d
-62d
-80d
-76d
-67d
-59d
-55d
-63d
-62d
-62d
-62d
-62d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
7 FINISHING WORKS
8 BS2
9 PART-02 (GRID 01~16)
10 POUR-11 (GRID E~H / 12~16)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-12 (GRID E~H / 09~12)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
003
001
002
011
S2CONP11313
S2CONP11314
S2CONP11315
S2CONP11316
S2CONP11317
S2CONP11318
S2CONP11319
S2CONP11320
S2CONP11321
S2CONP11322
012
S2CONP11324
S2CONP11325
S2CONP11326
31-Dec-2012
31-Dec-2012
11-Jan-2013
28-Jan-2013
29-Jan-2013
29-Jan-2013
25-Feb-2013
11-Mar-2013
28-Jan-2013
19-Feb-2013
11-Apr-2013
22-Apr-2013
11-Apr-2013
24-Apr-2013
07-Feb-2013
08-Feb-2013
08-Feb-2013
07-Mar-2013
20-Feb-2014
27-Jun-2013
27-Jun-2013
23-May-2013
29-Jan-2013
27-Feb-2013
13-Mar-2013
03-Apr-2013
13-Feb-2013
11-Apr-2013
22-Apr-2013
26-Apr-2013
18-Apr-2013
23-May-2013
03-Jun-2013
08-Feb-2013
09-Mar-2013
23-Mar-2013
31-May-2013
31-May-2013
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
07-Mar-2014
01-Oct-2013
01-Oct-2013
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
-13d
-82d
-82d
-105d
-105d
-105d
-105d
-105d
-106d
-105d
-105d
-105d
-105d
-105d
-96d
-96d
-96d
-96d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-16 (GRID E~H / 01~05)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11327
S2CONP11328
S2CONP11329
S2CONP11330
S2CONP11331
S2CONP11332
S2CONP11333
016
S2CONP11368
S2CONP11369
S2CONP11370
S2CONP11371
S2CONP11372
S2CONP11373
S2CONP11374
S2CONP11375
S2CONP11376
S2CONP11377
21-Mar-2013
07-Feb-2013
01-Mar-2013
22-Apr-2013
02-May-2013
22-Apr-2013
04-May-2013
04-Mar-2013
05-Mar-2013
05-Mar-2013
01-Apr-2013
15-Apr-2013
04-Mar-2013
26-Mar-2013
16-May-2013
27-May-2013
16-May-2013
29-May-2013
13-Apr-2013
23-Feb-2013
22-Apr-2013
02-May-2013
07-May-2013
29-Apr-2013
03-Jun-2013
27-Jun-2013
05-Mar-2013
03-Apr-2013
17-Apr-2013
08-May-2013
20-Mar-2013
16-May-2013
27-May-2013
31-May-2013
23-May-2013
27-Jun-2013
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
-96d
-97d
-96d
-96d
-96d
-96d
-96d
-75d
-75d
-75d
-75d
-75d
-76d
-75d
-75d
-75d
-75d
-75d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
010
S2CONP11302
S2CONP11303
S2CONP11304
S2CONP11305
S2CONP11306
S2CONP11307
S2CONP11308
S2CONP11309
S2CONP11310
S2CONP11311
013
S2CONP11335
S2CONP11336
S2CONP11337
S2CONP11338
S2CONP11339
S2CONP11340
21-Jan-2013
22-Jan-2013
22-Jan-2013
18-Feb-2013
04-Mar-2013
21-Jan-2013
12-Feb-2013
04-Apr-2013
15-Apr-2013
04-Apr-2013
17-Apr-2013
13-Feb-2013
14-Feb-2013
14-Feb-2013
13-Mar-2013
27-Mar-2013
13-Feb-2013
07-Mar-2013
16-May-2013
22-Jan-2013
20-Feb-2013
06-Mar-2013
27-Mar-2013
06-Feb-2013
04-Apr-2013
15-Apr-2013
19-Apr-2013
11-Apr-2013
16-May-2013
08-Jun-2013
14-Feb-2013
15-Mar-2013
29-Mar-2013
19-Apr-2013
01-Mar-2013
27-Apr-2013
07-Jun-2013
08-JUN-13
08-JUN-13
05-JUL-13
19-JUL-13
07-JUN-13
29-JUN-13
20-AUG-13
30-AUG-13
20-AUG-13
02-SEP-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
01-Oct-2013
08-JUN-13
08-JUL-13
22-JUL-13
12-AUG-13
24-JUN-13
20-AUG-13
30-AUG-13
04-SEP-13
27-AUG-13
01-OCT-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
-118d
-118d
-118d
-118d
-118d
-118d
-118d
-118d
-118d
-118d
-118d
-91d
-91d
-91d
-91d
-91d
-92d
-91d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-15 (GRID E~H / 05~09)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-09 (GRID A~D / 12~16)
11 Block Work
11 Plastering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11341
S2CONP11342
S2CONP11343
S2CONP11344
015
S2CONP11357
S2CONP11358
S2CONP11359
S2CONP11360
S2CONP11361
S2CONP11362
S2CONP11363
S2CONP11364
S2CONP11365
S2CONP11366
009
S2CONP11292
S2CONP11293
27-Apr-2013
08-May-2013
27-Apr-2013
10-May-2013
28-Feb-2013
01-Mar-2013
01-Mar-2013
28-Mar-2013
11-Apr-2013
28-Feb-2013
22-Mar-2013
13-May-2013
23-May-2013
13-May-2013
25-May-2013
11-Jan-2013
12-Jan-2013
08-Feb-2013
08-May-2013
13-May-2013
04-May-2013
08-Jun-2013
24-Jun-2013
01-Mar-2013
30-Mar-2013
13-Apr-2013
04-May-2013
16-Mar-2013
13-May-2013
23-May-2013
28-May-2013
20-May-2013
24-Jun-2013
07-May-2013
11-Feb-2013
25-Feb-2013
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-May-2013
31-MAY-13
27-JUN-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
23-Sep-2013
29-JUN-13
13-JUL-13
-91d
-91d
-91d
-91d
-78d
-78d
-78d
-78d
-78d
-79d
-78d
-78d
-78d
-78d
-78d
-119d
-119d
-119d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
11 Clearance of the Floor after Structure
10 POUR-14 (GRID A~D / 01~05)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11294
S2CONP11295
S2CONP11296
S2CONP11297
S2CONP11298
S2CONP11299
S2CONP11300
S2CONP11291
014
S2CONP11346
S2CONP11347
S2CONP11348
S2CONP11349
S2CONP11350
S2CONP11351
S2CONP11352
S2CONP11353
S2CONP11354
22-Feb-2013
11-Jan-2013
02-Feb-2013
26-Mar-2013
05-Apr-2013
26-Mar-2013
08-Apr-2013
12-Jan-2013
20-Feb-2013
21-Feb-2013
21-Feb-2013
20-Mar-2013
03-Apr-2013
20-Feb-2013
14-Mar-2013
04-May-2013
15-May-2013
04-May-2013
18-Mar-2013
28-Jan-2013
26-Mar-2013
05-Apr-2013
10-Apr-2013
02-Apr-2013
07-May-2013
12-Jan-2013
15-Jun-2013
21-Feb-2013
22-Mar-2013
05-Apr-2013
26-Apr-2013
08-Mar-2013
04-May-2013
15-May-2013
20-May-2013
11-May-2013
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-MAY-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
31-MAY-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
-119d
-120d
-119d
-119d
-119d
-119d
-119d
-119d
-85d
-85d
-85d
-85d
-85d
-86d
-85d
-85d
-85d
-85d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Signages
9 PART-01 (GRID 16~31)
10 POUR-01 (GRID A~D / 28~31)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-03 (GRID E~H / 28~31)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11355
001
001
S2CONP11203
S2CONP11204
S2CONP11205
S2CONP11206
S2CONP11207
S2CONP11208
S2CONP11209
S2CONP11210
S2CONP11211
S2CONP11212
003
S2CONP11225
S2CONP11226
S2CONP11227
S2CONP11228
17-May-2013
31-Dec-2012
31-Dec-2012
01-Jan-2013
02-Jan-2013
30-Jan-2013
13-Feb-2013
31-Dec-2012
25-Jan-2013
16-Mar-2013
28-Mar-2013
16-Mar-2013
29-Mar-2013
07-Jan-2013
08-Jan-2013
09-Jan-2013
06-Feb-2013
20-Feb-2013
15-Jun-2013
18-May-2013
27-Apr-2013
01-Jan-2013
31-Jan-2013
15-Feb-2013
08-Mar-2013
16-Jan-2013
18-Mar-2013
27-Mar-2013
02-Apr-2013
23-Mar-2013
27-Apr-2013
04-May-2013
08-Jan-2013
07-Feb-2013
22-Feb-2013
15-Mar-2013
24-AUG-13
31-May-2013
31-May-2013
31-MAY-13
01-JUN-13
29-JUN-13
13-JUL-13
31-MAY-13
25-JUN-13
14-AUG-13
26-AUG-13
14-AUG-13
27-AUG-13
31-May-2013
31-MAY-13
01-JUN-13
29-JUN-13
13-JUL-13
23-SEP-13
25-Sep-2013
25-Sep-2013
31-MAY-13
01-JUL-13
16-JUL-13
06-AUG-13
17-JUN-13
15-AUG-13
24-AUG-13
30-AUG-13
21-AUG-13
25-SEP-13
25-Sep-2013
31-MAY-13
01-JUL-13
16-JUL-13
06-AUG-13
-85d
-111d
-129d
-129d
-129d
-129d
-129d
-130d
-129d
-129d
-129d
-129d
-129d
-123d
-123d
-123d
-123d
-123d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11229
S2CONP11230
S2CONP11231
S2CONP11232
S2CONP11233
S2CONP11234
005
S2CONP11247
S2CONP11248
S2CONP11249
S2CONP11250
S2CONP11251
S2CONP11252
S2CONP11253
S2CONP11254
S2CONP11255
S2CONP11256
006
07-Jan-2013
01-Feb-2013
23-Mar-2013
04-Apr-2013
23-Mar-2013
05-Apr-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
23-Feb-2013
09-Mar-2013
24-Jan-2013
15-Feb-2013
06-Apr-2013
18-Apr-2013
06-Apr-2013
10-Apr-2013
01-Feb-2013
23-Jan-2013
25-Mar-2013
03-Apr-2013
09-Apr-2013
30-Mar-2013
04-May-2013
09-May-2013
25-Jan-2013
25-Feb-2013
12-Mar-2013
02-Apr-2013
09-Feb-2013
08-Apr-2013
17-Apr-2013
23-Apr-2013
13-Apr-2013
09-May-2013
13-May-2013
31-MAY-13
25-JUN-13
14-AUG-13
26-AUG-13
14-AUG-13
27-AUG-13
31-May-2013
31-MAY-13
01-JUN-13
29-JUN-13
13-JUL-13
31-MAY-13
21-JUN-13
10-AUG-13
22-AUG-13
10-AUG-13
14-AUG-13
31-May-2013
17-JUN-13
15-AUG-13
24-AUG-13
30-AUG-13
21-AUG-13
25-SEP-13
12-Sep-2013
31-MAY-13
01-JUL-13
16-JUL-13
06-AUG-13
17-JUN-13
12-AUG-13
21-AUG-13
27-AUG-13
17-AUG-13
12-SEP-13
07-Sep-2013
-124d
-123d
-123d
-123d
-123d
-123d
-108d
-108d
-108d
-108d
-108d
-109d
-108d
-108d
-108d
-108d
-108d
-101d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11258
S2CONP11259
S2CONP11260
S2CONP11261
S2CONP11262
S2CONP11263
S2CONP11264
S2CONP11265
S2CONP11266
S2CONP11267
008
S2CONP11280
S2CONP11281
S2CONP11282
S2CONP11283
S2CONP11284
S2CONP11285
S2CONP11286
02-Feb-2013
04-Feb-2013
28-Feb-2013
11-Mar-2013
01-Feb-2013
19-Feb-2013
10-Apr-2013
22-Apr-2013
10-Apr-2013
13-Apr-2013
21-Jan-2013
22-Jan-2013
23-Jan-2013
20-Feb-2013
06-Mar-2013
21-Jan-2013
14-Feb-2013
06-Apr-2013
02-Feb-2013
05-Mar-2013
16-Mar-2013
03-Apr-2013
18-Feb-2013
11-Apr-2013
20-Apr-2013
26-Apr-2013
17-Apr-2013
13-May-2013
18-May-2013
22-Jan-2013
21-Feb-2013
08-Mar-2013
29-Mar-2013
06-Feb-2013
06-Apr-2013
17-Apr-2013
31-MAY-13
01-JUN-13
26-JUN-13
06-JUL-13
31-MAY-13
17-JUN-13
06-AUG-13
17-AUG-13
06-AUG-13
09-AUG-13
31-May-2013
31-MAY-13
01-JUN-13
29-JUN-13
13-JUL-13
31-MAY-13
24-JUN-13
14-AUG-13
31-MAY-13
01-JUL-13
12-JUL-13
30-JUL-13
17-JUN-13
07-AUG-13
16-AUG-13
22-AUG-13
13-AUG-13
07-SEP-13
25-Sep-2013
31-MAY-13
01-JUL-13
16-JUL-13
06-AUG-13
17-JUN-13
14-AUG-13
24-AUG-13
-101d
-101d
-101d
-101d
-102d
-101d
-101d
-101d
-101d
-101d
-111d
-111d
-111d
-111d
-111d
-112d
-111d
-111d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-02 (GRID A~D / 24~28)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-04 (GRID E~H / 24~28)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11287
S2CONP11288
S2CONP11289
002
S2CONP11214
S2CONP11215
S2CONP11216
S2CONP11217
S2CONP11218
S2CONP11219
S2CONP11220
S2CONP11221
S2CONP11222
S2CONP11223
004
S2CONP11236
S2CONP11237
S2CONP11238
17-Apr-2013
06-Apr-2013
19-Apr-2013
02-Jan-2013
03-Jan-2013
04-Jan-2013
01-Feb-2013
15-Feb-2013
02-Jan-2013
28-Jan-2013
19-Mar-2013
30-Mar-2013
19-Mar-2013
01-Apr-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
13-Feb-2013
22-Apr-2013
13-Apr-2013
18-May-2013
30-Apr-2013
03-Jan-2013
02-Feb-2013
18-Feb-2013
11-Mar-2013
18-Jan-2013
20-Mar-2013
29-Mar-2013
04-Apr-2013
26-Mar-2013
30-Apr-2013
06-May-2013
15-Jan-2013
14-Feb-2013
01-Mar-2013
24-AUG-13
14-AUG-13
27-AUG-13
31-May-2013
31-MAY-13
01-JUN-13
29-JUN-13
13-JUL-13
31-MAY-13
25-JUN-13
14-AUG-13
26-AUG-13
14-AUG-13
27-AUG-13
31-May-2013
31-MAY-13
01-JUN-13
29-JUN-13
29-AUG-13
21-AUG-13
25-SEP-13
25-Sep-2013
31-MAY-13
01-JUL-13
16-JUL-13
06-AUG-13
17-JUN-13
15-AUG-13
24-AUG-13
30-AUG-13
21-AUG-13
25-SEP-13
19-Sep-2013
31-MAY-13
01-JUL-13
16-JUL-13
-111d
-111d
-111d
-127d
-127d
-127d
-127d
-127d
-128d
-127d
-127d
-127d
-127d
-127d
-117d
-117d
-117d
-117d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-07 (GRID E~H / 20~24)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11239
S2CONP11240
S2CONP11241
S2CONP11242
S2CONP11243
S2CONP11244
S2CONP11245
007
S2CONP11269
S2CONP11270
S2CONP11271
S2CONP11272
S2CONP11273
S2CONP11274
S2CONP11275
S2CONP11276
S2CONP11277
S2CONP11278
27-Feb-2013
14-Jan-2013
08-Feb-2013
30-Mar-2013
11-Apr-2013
30-Mar-2013
06-Apr-2013
09-Feb-2013
11-Feb-2013
12-Feb-2013
02-Mar-2013
08-Mar-2013
09-Feb-2013
21-Feb-2013
12-Apr-2013
24-Apr-2013
12-Apr-2013
16-Apr-2013
22-Mar-2013
30-Jan-2013
01-Apr-2013
10-Apr-2013
16-Apr-2013
06-Apr-2013
06-May-2013
15-May-2013
11-Feb-2013
13-Mar-2013
19-Mar-2013
01-Apr-2013
26-Feb-2013
13-Apr-2013
23-Apr-2013
29-Apr-2013
19-Apr-2013
15-May-2013
13-JUL-13
31-MAY-13
25-JUN-13
14-AUG-13
26-AUG-13
14-AUG-13
21-AUG-13
31-May-2013
31-MAY-13
01-JUN-13
20-JUN-13
26-JUN-13
31-MAY-13
11-JUN-13
31-JUL-13
12-AUG-13
31-JUL-13
03-AUG-13
06-AUG-13
17-JUN-13
15-AUG-13
24-AUG-13
30-AUG-13
21-AUG-13
19-SEP-13
02-Sep-2013
31-MAY-13
01-JUL-13
06-JUL-13
19-JUL-13
17-JUN-13
01-AUG-13
10-AUG-13
16-AUG-13
07-AUG-13
02-SEP-13
-117d
-118d
-117d
-117d
-117d
-117d
-117d
-94d
-94d
-94d
-94d
-94d
-95d
-94d
-94d
-94d
-94d
-94d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
8 BS1
9 PART-02 (GRID 01~16)
10 POUR-14 (GRID A~D / 01~05)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-15 (GRID E~H / 05~09)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
002
002
014
S2CONP11522
S2CONP11523
S2CONP11524
S2CONP11525
S2CONP11526
S2CONP11527
S2CONP11528
S2CONP11529
S2CONP11530
S2CONP11531
015
S2CONP11533
S2CONP11534
S2CONP11535
S2CONP11536
16-Feb-2013
02-Apr-2013
11-May-2013
13-May-2013
13-May-2013
08-Jun-2013
22-Jun-2013
11-May-2013
03-Jun-2013
24-Jul-2013
03-Aug-2013
24-Jul-2013
06-Aug-2013
20-May-2013
21-May-2013
21-May-2013
17-Jun-2013
01-Jul-2013
14-Sep-2013
14-Sep-2013
04-Sep-2013
13-May-2013
11-Jun-2013
25-Jun-2013
16-Jul-2013
28-May-2013
24-Jul-2013
03-Aug-2013
08-Aug-2013
31-Jul-2013
04-Sep-2013
12-Sep-2013
21-May-2013
19-Jun-2013
03-Jul-2013
24-Jul-2013
31-May-2013
29-Jun-2013
15-Jul-2013
16-JUL-13
16-JUL-13
12-AUG-13
26-AUG-13
15-JUL-13
06-AUG-13
26-SEP-13
07-OCT-13
26-SEP-13
09-OCT-13
15-Jul-2013
16-JUL-13
16-JUL-13
12-AUG-13
26-AUG-13
28-Nov-2013
28-Nov-2013
07-Nov-2013
16-JUL-13
14-AUG-13
28-AUG-13
18-SEP-13
31-JUL-13
26-SEP-13
07-OCT-13
11-OCT-13
03-OCT-13
07-NOV-13
08-Nov-2013
17-JUL-13
15-AUG-13
29-AUG-13
19-SEP-13
-64d
-64d
-55d
-55d
-55d
-55d
-55d
-55d
-55d
-55d
-55d
-55d
-55d
-49d
-48d
-48d
-48d
-48d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11537
S2CONP11538
S2CONP11539
S2CONP11540
S2CONP11541
S2CONP11542
009
S2CONP11467
S2CONP11468
S2CONP11469
S2CONP11470
S2CONP11471
S2CONP11472
S2CONP11473
S2CONP11474
S2CONP11475
S2CONP11476
010
20-May-2013
11-Jun-2013
01-Aug-2013
12-Aug-2013
01-Aug-2013
14-Aug-2013
02-Apr-2013
03-Apr-2013
03-Apr-2013
30-Apr-2013
14-May-2013
02-Apr-2013
24-Apr-2013
14-Jun-2013
25-Jun-2013
14-Jun-2013
27-Jun-2013
11-Apr-2013
05-Jun-2013
01-Aug-2013
12-Aug-2013
16-Aug-2013
08-Aug-2013
12-Sep-2013
26-Jul-2013
03-Apr-2013
02-May-2013
16-May-2013
06-Jun-2013
18-Apr-2013
14-Jun-2013
25-Jun-2013
29-Jun-2013
21-Jun-2013
26-Jul-2013
05-Aug-2013
15-JUL-13
06-AUG-13
26-SEP-13
07-OCT-13
26-SEP-13
09-OCT-13
29-Jun-2013
01-JUL-13
01-JUL-13
27-JUL-13
10-AUG-13
29-JUN-13
22-JUL-13
11-SEP-13
21-SEP-13
11-SEP-13
24-SEP-13
05-Aug-2013
01-AUG-13
27-SEP-13
08-OCT-13
12-OCT-13
04-OCT-13
08-NOV-13
23-Oct-2013
01-JUL-13
30-JUL-13
13-AUG-13
03-SEP-13
16-JUL-13
11-SEP-13
21-SEP-13
26-SEP-13
18-SEP-13
23-OCT-13
28-Nov-2013
-48d
-48d
-48d
-48d
-48d
-48d
-76d
-76d
-76d
-76d
-76d
-76d
-76d
-76d
-76d
-76d
-76d
-99d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11478
S2CONP11479
S2CONP11480
S2CONP11481
S2CONP11482
S2CONP11483
S2CONP11484
S2CONP11485
S2CONP11486
S2CONP11487
012
S2CONP11500
S2CONP11501
S2CONP11502
S2CONP11503
S2CONP11504
S2CONP11505
S2CONP11506
12-Apr-2013
12-Apr-2013
09-May-2013
23-May-2013
11-Apr-2013
03-May-2013
24-Jun-2013
04-Jul-2013
24-Jun-2013
06-Jul-2013
29-Apr-2013
30-Apr-2013
30-Apr-2013
27-May-2013
10-Jun-2013
29-Apr-2013
21-May-2013
11-Jul-2013
12-Apr-2013
11-May-2013
25-May-2013
15-Jun-2013
27-Apr-2013
24-Jun-2013
04-Jul-2013
09-Jul-2013
01-Jul-2013
05-Aug-2013
22-Aug-2013
30-Apr-2013
29-May-2013
12-Jun-2013
03-Jul-2013
15-May-2013
11-Jul-2013
22-Jul-2013
06-AUG-13
06-AUG-13
02-SEP-13
16-SEP-13
05-AUG-13
27-AUG-13
17-OCT-13
28-OCT-13
17-OCT-13
30-OCT-13
01-Jul-2013
02-JUL-13
02-JUL-13
29-JUL-13
12-AUG-13
01-JUL-13
23-JUL-13
12-SEP-13
06-AUG-13
04-SEP-13
18-SEP-13
09-OCT-13
21-AUG-13
17-OCT-13
28-OCT-13
01-NOV-13
24-OCT-13
28-NOV-13
24-Oct-2013
02-JUL-13
31-JUL-13
14-AUG-13
04-SEP-13
17-JUL-13
12-SEP-13
23-SEP-13
-99d
-99d
-99d
-99d
-99d
-99d
-99d
-99d
-99d
-99d
-54d
-54d
-54d
-54d
-54d
-54d
-54d
-54d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-13 (GRID A~D / 05~09)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-16 (GRID E~H / 01~05)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11507
S2CONP11508
S2CONP11509
013
S2CONP11511
S2CONP11512
S2CONP11513
S2CONP11514
S2CONP11515
S2CONP11516
S2CONP11517
S2CONP11518
S2CONP11519
S2CONP11520
016
S2CONP11544
S2CONP11545
S2CONP11546
22-Jul-2013
11-Jul-2013
24-Jul-2013
04-May-2013
06-May-2013
06-May-2013
01-Jun-2013
15-Jun-2013
04-May-2013
27-May-2013
17-Jul-2013
27-Jul-2013
17-Jul-2013
30-Jul-2013
22-May-2013
23-May-2013
23-May-2013
19-Jun-2013
26-Jul-2013
18-Jul-2013
22-Aug-2013
28-Aug-2013
06-May-2013
04-Jun-2013
18-Jun-2013
09-Jul-2013
21-May-2013
17-Jul-2013
27-Jul-2013
01-Aug-2013
24-Jul-2013
28-Aug-2013
14-Sep-2013
23-May-2013
21-Jun-2013
05-Jul-2013
23-SEP-13
12-SEP-13
25-SEP-13
22-Jul-2013
23-JUL-13
23-JUL-13
19-AUG-13
02-SEP-13
22-JUL-13
13-AUG-13
03-OCT-13
14-OCT-13
03-OCT-13
16-OCT-13
22-Jul-2013
23-JUL-13
23-JUL-13
19-AUG-13
27-SEP-13
19-SEP-13
24-OCT-13
14-Nov-2013
23-JUL-13
21-AUG-13
04-SEP-13
25-SEP-13
07-AUG-13
03-OCT-13
14-OCT-13
18-OCT-13
10-OCT-13
14-NOV-13
15-Nov-2013
24-JUL-13
22-AUG-13
05-SEP-13
-54d
-54d
-54d
-67d
-67d
-67d
-67d
-67d
-67d
-67d
-67d
-67d
-67d
-67d
-53d
-52d
-52d
-52d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-11 (GRID E~H / 12~16)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11547
S2CONP11548
S2CONP11549
S2CONP11550
S2CONP11551
S2CONP11552
S2CONP11553
011
S2CONP11489
S2CONP11490
S2CONP11491
S2CONP11492
S2CONP11493
S2CONP11494
S2CONP11495
S2CONP11496
S2CONP11497
S2CONP11498
03-Jul-2013
22-May-2013
13-Jun-2013
03-Aug-2013
14-Aug-2013
03-Aug-2013
16-Aug-2013
18-Apr-2013
19-Apr-2013
19-Apr-2013
16-May-2013
30-May-2013
18-Apr-2013
10-May-2013
01-Jul-2013
11-Jul-2013
01-Jul-2013
13-Jul-2013
26-Jul-2013
07-Jun-2013
03-Aug-2013
14-Aug-2013
19-Aug-2013
10-Aug-2013
14-Sep-2013
12-Aug-2013
19-Apr-2013
18-May-2013
01-Jun-2013
22-Jun-2013
04-May-2013
01-Jul-2013
11-Jul-2013
16-Jul-2013
08-Jul-2013
12-Aug-2013
02-SEP-13
22-JUL-13
13-AUG-13
03-OCT-13
14-OCT-13
03-OCT-13
16-OCT-13
29-Jun-2013
01-JUL-13
01-JUL-13
27-JUL-13
10-AUG-13
29-JUN-13
22-JUL-13
11-SEP-13
21-SEP-13
11-SEP-13
24-SEP-13
26-SEP-13
08-AUG-13
04-OCT-13
15-OCT-13
19-OCT-13
11-OCT-13
15-NOV-13
23-Oct-2013
01-JUL-13
30-JUL-13
13-AUG-13
03-SEP-13
16-JUL-13
11-SEP-13
21-SEP-13
26-SEP-13
18-SEP-13
23-OCT-13
-52d
-52d
-52d
-52d
-52d
-52d
-52d
-62d
-62d
-62d
-62d
-62d
-62d
-62d
-62d
-62d
-62d
-62d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
001
003
S2CONP11401
S2CONP11402
S2CONP11403
S2CONP11404
S2CONP11405
S2CONP11406
S2CONP11407
S2CONP11408
S2CONP11409
S2CONP11410
004
S2CONP11412
S2CONP11413
S2CONP11414
S2CONP11415
S2CONP11416
16-Feb-2013
04-Mar-2013
05-Mar-2013
05-Mar-2013
01-Apr-2013
15-Apr-2013
04-Mar-2013
26-Mar-2013
16-May-2013
27-May-2013
16-May-2013
29-May-2013
13-Mar-2013
14-Mar-2013
14-Mar-2013
10-Apr-2013
24-Apr-2013
13-Mar-2013
06-Aug-2013
27-Jun-2013
05-Mar-2013
03-Apr-2013
17-Apr-2013
08-May-2013
20-Mar-2013
16-May-2013
27-May-2013
31-May-2013
23-May-2013
27-Jun-2013
06-Jul-2013
14-Mar-2013
12-Apr-2013
26-Apr-2013
17-May-2013
29-Mar-2013
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
23-Sep-2013
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
-41d
-75d
-75d
-75d
-75d
-75d
-76d
-75d
-75d
-75d
-75d
-75d
-67d
-67d
-67d
-67d
-67d
-68d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-01 (GRID A~D / 28~31)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-08 (GRID E~H / 16~20)
11 Clearance of the Floor after Structure
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11417
S2CONP11418
S2CONP11419
S2CONP11420
S2CONP11421
001
S2CONP11379
S2CONP11380
S2CONP11381
S2CONP11382
S2CONP11383
S2CONP11384
S2CONP11385
S2CONP11386
S2CONP11387
S2CONP11388
008
S2CONP11456
04-Apr-2013
25-May-2013
05-Jun-2013
25-May-2013
07-Jun-2013
16-Feb-2013
18-Feb-2013
18-Feb-2013
16-Mar-2013
30-Mar-2013
16-Feb-2013
11-Mar-2013
01-May-2013
11-May-2013
01-May-2013
14-May-2013
12-Apr-2013
13-Apr-2013
25-May-2013
05-Jun-2013
10-Jun-2013
01-Jun-2013
06-Jul-2013
12-Jun-2013
18-Feb-2013
19-Mar-2013
02-Apr-2013
23-Apr-2013
05-Mar-2013
01-May-2013
11-May-2013
16-May-2013
08-May-2013
12-Jun-2013
06-Aug-2013
13-Apr-2013
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-May-2013
31-MAY-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
23-Sep-2013
31-MAY-13
-67d
-67d
-67d
-67d
-67d
-88d
-88d
-88d
-88d
-88d
-89d
-88d
-88d
-88d
-88d
-88d
-41d
-41d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
10 POUR-06 (GRID A~D / 16~20)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11457
S2CONP11458
S2CONP11459
S2CONP11460
S2CONP11461
S2CONP11462
S2CONP11463
S2CONP11464
S2CONP11465
006
S2CONP11434
S2CONP11435
S2CONP11436
S2CONP11437
S2CONP11438
S2CONP11439
S2CONP11440
S2CONP11441
13-Apr-2013
10-May-2013
24-May-2013
12-Apr-2013
04-May-2013
25-Jun-2013
05-Jul-2013
25-Jun-2013
08-Jul-2013
29-Mar-2013
30-Mar-2013
30-Mar-2013
26-Apr-2013
10-May-2013
29-Mar-2013
20-Apr-2013
11-Jun-2013
21-Jun-2013
13-May-2013
27-May-2013
17-Jun-2013
29-Apr-2013
25-Jun-2013
05-Jul-2013
10-Jul-2013
02-Jul-2013
06-Aug-2013
23-Jul-2013
30-Mar-2013
29-Apr-2013
13-May-2013
03-Jun-2013
15-Apr-2013
11-Jun-2013
21-Jun-2013
26-Jun-2013
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
-41d
-41d
-41d
-42d
-41d
-41d
-41d
-41d
-41d
-53d
-53d
-53d
-53d
-53d
-54d
-53d
-53d
-53d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11442
S2CONP11443
005
S2CONP11423
S2CONP11424
S2CONP11425
S2CONP11426
S2CONP11427
S2CONP11428
S2CONP11429
S2CONP11430
S2CONP11431
S2CONP11432
007
S2CONP11445
S2CONP11446
S2CONP11447
S2CONP11448
11-Jun-2013
24-Jun-2013
21-Mar-2013
22-Mar-2013
22-Mar-2013
18-Apr-2013
02-May-2013
21-Mar-2013
12-Apr-2013
03-Jun-2013
13-Jun-2013
03-Jun-2013
15-Jun-2013
06-Apr-2013
08-Apr-2013
08-Apr-2013
04-May-2013
18-May-2013
18-Jun-2013
23-Jul-2013
15-Jul-2013
22-Mar-2013
20-Apr-2013
04-May-2013
25-May-2013
06-Apr-2013
03-Jun-2013
13-Jun-2013
18-Jun-2013
10-Jun-2013
15-Jul-2013
31-Jul-2013
08-Apr-2013
07-May-2013
21-May-2013
11-Jun-2013
12-AUG-13
24-AUG-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
19-AUG-13
23-SEP-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
-53d
-53d
-60d
-60d
-60d
-60d
-60d
-61d
-60d
-60d
-60d
-60d
-60d
-46d
-46d
-46d
-46d
-46d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11449
S2CONP11450
S2CONP11451
S2CONP11452
S2CONP11453
S2CONP11454
002
S2CONP11390
S2CONP11391
S2CONP11392
S2CONP11393
S2CONP11394
S2CONP11395
S2CONP11396
S2CONP11397
S2CONP11398
S2CONP11399
003
06-Apr-2013
29-Apr-2013
19-Jun-2013
29-Jun-2013
19-Jun-2013
02-Jul-2013
25-Feb-2013
26-Feb-2013
26-Feb-2013
25-Mar-2013
08-Apr-2013
25-Feb-2013
19-Mar-2013
09-May-2013
20-May-2013
09-May-2013
22-May-2013
08-May-2013
23-Apr-2013
19-Jun-2013
29-Jun-2013
04-Jul-2013
26-Jun-2013
31-Jul-2013
20-Jun-2013
26-Feb-2013
27-Mar-2013
10-Apr-2013
01-May-2013
13-Mar-2013
09-May-2013
20-May-2013
24-May-2013
16-May-2013
20-Jun-2013
04-Dec-2013
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
31-May-2013
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
25-Jan-2014
-47d
-46d
-46d
-46d
-46d
-46d
-81d
-81d
-81d
-81d
-81d
-82d
-81d
-81d
-81d
-81d
-81d
-45d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
001
001
S2CONP11555
S2CONP11556
S2CONP11557
S2CONP11558
S2CONP11559
S2CONP11560
S2CONP11562
S2CONP11563
S2CONP11564
S2CONP11565
S2CONP11561
002
S2CONP11567
S2CONP11568
S2CONP11569
S2CONP11570
08-May-2013
08-May-2013
09-May-2013
09-May-2013
05-Jun-2013
19-Jun-2013
08-May-2013
30-May-2013
20-Jul-2013
31-Jul-2013
20-Jul-2013
02-Aug-2013
01-Aug-2013
16-May-2013
17-May-2013
17-May-2013
13-Jun-2013
27-Jun-2013
25-Oct-2013
31-Aug-2013
09-May-2013
07-Jun-2013
21-Jun-2013
12-Jul-2013
24-May-2013
20-Jul-2013
31-Jul-2013
05-Aug-2013
27-Jul-2013
31-Aug-2013
24-Aug-2013
09-Sep-2013
17-May-2013
15-Jun-2013
29-Jun-2013
20-Jul-2013
31-May-2013
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
27-AUG-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
28-Oct-2013
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
19-SEP-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
-2d
-19d
-19d
-19d
-19d
-19d
-20d
-19d
-19d
-19d
-19d
-19d
-22d
-12d
-12d
-12d
-12d
-12d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11571
S2CONP11572
S2CONP11574
S2CONP11575
S2CONP11576
S2CONP11577
S2CONP11573
004
S2CONP11597
008
S2CONP11639
S2CONP11640
S2CONP11641
S2CONP11642
S2CONP11643
S2CONP11644
S2CONP11646
S2CONP11647
16-May-2013
07-Jun-2013
29-Jul-2013
08-Aug-2013
29-Jul-2013
10-Aug-2013
09-Aug-2013
26-Aug-2013
26-Aug-2013
02-Jul-2013
03-Jul-2013
03-Jul-2013
30-Jul-2013
13-Aug-2013
02-Jul-2013
24-Jul-2013
13-Sep-2013
24-Sep-2013
01-Jun-2013
29-Jul-2013
08-Aug-2013
13-Aug-2013
05-Aug-2013
09-Sep-2013
02-Sep-2013
18-Sep-2013
18-Sep-2013
25-Oct-2013
03-Jul-2013
01-Aug-2013
15-Aug-2013
05-Sep-2013
18-Jul-2013
13-Sep-2013
24-Sep-2013
28-Sep-2013
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
27-AUG-13
27-Aug-2013
27-AUG-13
04-Jul-2013
05-JUL-13
05-JUL-13
01-AUG-13
15-AUG-13
04-JUL-13
26-JUL-13
16-SEP-13
26-SEP-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
19-SEP-13
19-Sep-2013
19-SEP-13
28-Oct-2013
05-JUL-13
03-AUG-13
17-AUG-13
07-SEP-13
20-JUL-13
16-SEP-13
26-SEP-13
01-OCT-13
-13d
-12d
-12d
-12d
-12d
-12d
-15d
-1d
-1d
-2d
-2d
-2d
-2d
-2d
-2d
-2d
-2d
-2d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11648
S2CONP11649
003
S2CONP11579
S2CONP11580
S2CONP11581
S2CONP11582
S2CONP11583
S2CONP11584
S2CONP11586
S2CONP11587
S2CONP11588
S2CONP11589
S2CONP11585
002
010
S2CONP11663
S2CONP11664
13-Sep-2013
26-Sep-2013
23-May-2013
24-May-2013
24-May-2013
20-Jun-2013
04-Jul-2013
23-May-2013
14-Jun-2013
05-Aug-2013
15-Aug-2013
05-Aug-2013
17-Aug-2013
16-Aug-2013
21-Jun-2013
01-Jul-2013
02-Jul-2013
02-Jul-2013
20-Sep-2013
25-Oct-2013
16-Sep-2013
24-May-2013
22-Jun-2013
06-Jul-2013
27-Jul-2013
08-Jun-2013
05-Aug-2013
15-Aug-2013
20-Aug-2013
12-Aug-2013
16-Sep-2013
09-Sep-2013
04-Dec-2013
24-Oct-2013
02-Jul-2013
31-Jul-2013
16-SEP-13
28-SEP-13
31-May-2013
31-MAY-13
31-MAY-13
27-JUN-13
11-JUL-13
31-MAY-13
21-JUN-13
12-AUG-13
22-AUG-13
12-AUG-13
24-AUG-13
27-AUG-13
27-Aug-2013
02-Oct-2013
03-OCT-13
03-OCT-13
23-SEP-13
28-OCT-13
23-Sep-2013
31-MAY-13
29-JUN-13
13-JUL-13
03-AUG-13
17-JUN-13
12-AUG-13
22-AUG-13
27-AUG-13
19-AUG-13
23-SEP-13
19-SEP-13
25-Jan-2014
25-Jan-2014
03-OCT-13
01-NOV-13
-2d
-2d
-6d
-6d
-6d
-6d
-6d
-7d
-6d
-6d
-6d
-6d
-6d
-9d
-45d
-80d
-80d
-80d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
11 Faced Erection Works
10 POUR-13 (GRID A~D / 05~09)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11665
S2CONP11666
S2CONP11667
S2CONP11668
S2CONP11670
S2CONP11671
S2CONP11672
S2CONP11673
S2CONP11669
013
S2CONP11699
S2CONP11700
S2CONP11701
S2CONP11702
S2CONP11703
S2CONP11704
S2CONP11706
S2CONP11707
29-Jul-2013
12-Aug-2013
01-Jul-2013
23-Jul-2013
12-Sep-2013
23-Sep-2013
12-Sep-2013
25-Sep-2013
24-Sep-2013
24-Jul-2013
25-Jul-2013
25-Jul-2013
21-Aug-2013
04-Sep-2013
24-Jul-2013
15-Aug-2013
05-Oct-2013
16-Oct-2013
14-Aug-2013
04-Sep-2013
17-Jul-2013
12-Sep-2013
23-Sep-2013
27-Sep-2013
19-Sep-2013
24-Oct-2013
17-Oct-2013
16-Nov-2013
25-Jul-2013
23-Aug-2013
06-Sep-2013
27-Sep-2013
09-Aug-2013
05-Oct-2013
16-Oct-2013
21-Oct-2013
30-OCT-13
13-NOV-13
02-OCT-13
24-OCT-13
14-DEC-13
25-DEC-13
14-DEC-13
27-DEC-13
04-DEC-13
18-Sep-2013
19-SEP-13
19-SEP-13
16-OCT-13
30-OCT-13
18-SEP-13
10-OCT-13
30-NOV-13
11-DEC-13
15-NOV-13
06-DEC-13
18-OCT-13
14-DEC-13
25-DEC-13
30-DEC-13
21-DEC-13
25-JAN-14
27-DEC-13
11-Jan-2014
19-SEP-13
18-OCT-13
01-NOV-13
22-NOV-13
04-OCT-13
30-NOV-13
11-DEC-13
16-DEC-13
-80d
-80d
-80d
-80d
-80d
-80d
-80d
-80d
-61d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
-48d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11708
S2CONP11709
S2CONP11705
015
S2CONP11723
S2CONP11724
S2CONP11725
S2CONP11726
S2CONP11727
S2CONP11728
S2CONP11730
S2CONP11731
S2CONP11732
S2CONP11733
S2CONP11729
016
S2CONP11735
S2CONP11736
05-Oct-2013
18-Oct-2013
17-Oct-2013
08-Aug-2013
09-Aug-2013
09-Aug-2013
05-Sep-2013
19-Sep-2013
08-Aug-2013
30-Aug-2013
21-Oct-2013
31-Oct-2013
21-Oct-2013
02-Nov-2013
01-Nov-2013
10-Aug-2013
12-Aug-2013
12-Aug-2013
12-Oct-2013
16-Nov-2013
09-Nov-2013
02-Dec-2013
09-Aug-2013
07-Sep-2013
21-Sep-2013
12-Oct-2013
24-Aug-2013
21-Oct-2013
31-Oct-2013
05-Nov-2013
28-Oct-2013
02-Dec-2013
25-Nov-2013
04-Dec-2013
12-Aug-2013
10-Sep-2013
30-NOV-13
13-DEC-13
20-NOV-13
11-Sep-2013
12-SEP-13
12-SEP-13
09-OCT-13
23-OCT-13
11-SEP-13
03-OCT-13
23-NOV-13
04-DEC-13
23-NOV-13
06-DEC-13
13-NOV-13
18-Sep-2013
19-SEP-13
19-SEP-13
07-DEC-13
11-JAN-14
13-DEC-13
06-Jan-2014
13-SEP-13
12-OCT-13
26-OCT-13
16-NOV-13
28-SEP-13
25-NOV-13
05-DEC-13
10-DEC-13
02-DEC-13
06-JAN-14
07-DEC-13
13-Jan-2014
20-SEP-13
19-OCT-13
-48d
-48d
-29d
-30d
-29d
-29d
-29d
-29d
-29d
-29d
-29d
-29d
-29d
-29d
-10d
-34d
-33d
-33d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
11 Faced Erection Works
10 POUR-11 (GRID E~H / 12~16)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11737
S2CONP11738
S2CONP11739
S2CONP11740
S2CONP11742
S2CONP11743
S2CONP11744
S2CONP11745
S2CONP11741
011
S2CONP11675
S2CONP11676
S2CONP11677
S2CONP11678
S2CONP11679
S2CONP11680
S2CONP11682
S2CONP11683
07-Sep-2013
21-Sep-2013
10-Aug-2013
02-Sep-2013
23-Oct-2013
02-Nov-2013
23-Oct-2013
05-Nov-2013
04-Nov-2013
08-Jul-2013
09-Jul-2013
09-Jul-2013
05-Aug-2013
19-Aug-2013
08-Jul-2013
30-Jul-2013
19-Sep-2013
30-Sep-2013
24-Sep-2013
15-Oct-2013
27-Aug-2013
23-Oct-2013
02-Nov-2013
07-Nov-2013
30-Oct-2013
04-Dec-2013
27-Nov-2013
31-Oct-2013
09-Jul-2013
07-Aug-2013
21-Aug-2013
11-Sep-2013
24-Jul-2013
19-Sep-2013
30-Sep-2013
04-Oct-2013
16-OCT-13
30-OCT-13
18-SEP-13
10-OCT-13
30-NOV-13
11-DEC-13
30-NOV-13
13-DEC-13
21-NOV-13
27-Aug-2013
28-AUG-13
28-AUG-13
24-SEP-13
08-OCT-13
27-AUG-13
18-SEP-13
08-NOV-13
19-NOV-13
02-NOV-13
23-NOV-13
05-OCT-13
02-DEC-13
12-DEC-13
17-DEC-13
09-DEC-13
13-JAN-14
16-DEC-13
20-Dec-2013
28-AUG-13
26-SEP-13
10-OCT-13
31-OCT-13
12-SEP-13
08-NOV-13
19-NOV-13
23-NOV-13
-33d
-33d
-33d
-33d
-33d
-33d
-33d
-33d
-15d
-43d
-43d
-43d
-43d
-43d
-43d
-43d
-43d
-43d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11684
S2CONP11685
S2CONP11681
014
S2CONP11711
S2CONP11712
S2CONP11713
S2CONP11714
S2CONP11715
S2CONP11716
S2CONP11718
S2CONP11719
S2CONP11720
S2CONP11721
S2CONP11717
009
S2CONP11651
S2CONP11652
19-Sep-2013
02-Oct-2013
01-Oct-2013
31-Jul-2013
01-Aug-2013
01-Aug-2013
28-Aug-2013
11-Sep-2013
31-Jul-2013
22-Aug-2013
12-Oct-2013
23-Oct-2013
12-Oct-2013
25-Oct-2013
24-Oct-2013
21-Jun-2013
22-Jun-2013
22-Jun-2013
26-Sep-2013
31-Oct-2013
24-Oct-2013
23-Nov-2013
01-Aug-2013
30-Aug-2013
13-Sep-2013
04-Oct-2013
16-Aug-2013
12-Oct-2013
23-Oct-2013
28-Oct-2013
19-Oct-2013
23-Nov-2013
16-Nov-2013
15-Oct-2013
22-Jun-2013
22-Jul-2013
08-NOV-13
21-NOV-13
29-OCT-13
11-Sep-2013
12-SEP-13
12-SEP-13
09-OCT-13
23-OCT-13
11-SEP-13
03-OCT-13
23-NOV-13
04-DEC-13
23-NOV-13
06-DEC-13
13-NOV-13
27-Aug-2013
28-AUG-13
28-AUG-13
15-NOV-13
20-DEC-13
21-NOV-13
04-Jan-2014
12-SEP-13
11-OCT-13
25-OCT-13
15-NOV-13
27-SEP-13
23-NOV-13
04-DEC-13
09-DEC-13
30-NOV-13
04-JAN-14
06-DEC-13
20-Dec-2013
28-AUG-13
26-SEP-13
-43d
-43d
-24d
-36d
-36d
-36d
-36d
-36d
-36d
-36d
-36d
-36d
-36d
-36d
-17d
-57d
-57d
-57d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
11 Faced Erection Works
10 POUR-12 (GRID E~H / 09~12)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11653
S2CONP11654
S2CONP11655
S2CONP11656
S2CONP11658
S2CONP11659
S2CONP11660
S2CONP11661
S2CONP11657
012
S2CONP11687
S2CONP11688
S2CONP11689
S2CONP11690
S2CONP11691
S2CONP11692
S2CONP11694
S2CONP11695
19-Jul-2013
02-Aug-2013
21-Jun-2013
13-Jul-2013
03-Sep-2013
13-Sep-2013
03-Sep-2013
16-Sep-2013
14-Sep-2013
18-Jul-2013
19-Jul-2013
19-Jul-2013
15-Aug-2013
29-Aug-2013
18-Jul-2013
09-Aug-2013
30-Sep-2013
10-Oct-2013
05-Aug-2013
26-Aug-2013
08-Jul-2013
03-Sep-2013
13-Sep-2013
18-Sep-2013
10-Sep-2013
15-Oct-2013
08-Oct-2013
11-Nov-2013
19-Jul-2013
17-Aug-2013
31-Aug-2013
21-Sep-2013
03-Aug-2013
30-Sep-2013
10-Oct-2013
15-Oct-2013
24-SEP-13
08-OCT-13
27-AUG-13
18-SEP-13
08-NOV-13
19-NOV-13
08-NOV-13
21-NOV-13
29-OCT-13
28-Aug-2013
29-AUG-13
29-AUG-13
25-SEP-13
09-OCT-13
28-AUG-13
19-SEP-13
09-NOV-13
20-NOV-13
10-OCT-13
31-OCT-13
12-SEP-13
08-NOV-13
19-NOV-13
23-NOV-13
15-NOV-13
20-DEC-13
21-NOV-13
21-Dec-2013
29-AUG-13
27-SEP-13
11-OCT-13
01-NOV-13
13-SEP-13
09-NOV-13
20-NOV-13
25-NOV-13
-57d
-57d
-57d
-57d
-57d
-57d
-57d
-57d
-38d
-35d
-35d
-35d
-35d
-35d
-35d
-35d
-35d
-35d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11696
S2CONP11697
S2CONP11693
004
002
010
S2CONP11877
S2CONP11878
S2CONP11879
S2CONP11880
S2CONP11882
S2CONP11883
S2CONP11884
S2CONP11885
S2CONP11881
S2CONP11886
S2CONP11875
S2CONP11876
30-Sep-2013
12-Oct-2013
11-Oct-2013
27-Jul-2013
10-Sep-2013
19-Sep-2013
17-Oct-2013
31-Oct-2013
19-Sep-2013
11-Oct-2013
02-Dec-2013
12-Dec-2013
02-Dec-2013
14-Dec-2013
15-Oct-2013
07-Oct-2013
20-Sep-2013
20-Sep-2013
07-Oct-2013
11-Nov-2013
04-Nov-2013
20-Feb-2014
20-Feb-2014
13-Jan-2014
02-Nov-2013
23-Nov-2013
05-Oct-2013
02-Dec-2013
12-Dec-2013
17-Dec-2013
09-Dec-2013
13-Jan-2014
07-Nov-2013
09-Nov-2013
20-Sep-2013
19-Oct-2013
09-NOV-13
22-NOV-13
30-OCT-13
22-Aug-2013
16-Oct-2013
29-Nov-2013
27-DEC-13
06-JAN-14
29-NOV-13
21-DEC-13
05-FEB-14
04-FEB-14
10-FEB-14
06-FEB-14
14-DEC-13
17-DEC-13
30-NOV-13
30-NOV-13
16-NOV-13
21-DEC-13
22-NOV-13
07-Mar-2014
07-Mar-2014
07-Mar-2014
13-JAN-14
29-JAN-14
16-DEC-13
11-FEB-14
15-FEB-14
08-FEB-14
17-FEB-14
07-MAR-14
06-JAN-14
20-JAN-14
30-NOV-13
30-DEC-13
-35d
-35d
-16d
-13d
-13d
-46d
-61d
-57d
-61d
-61d
-56d
-46d
-60d
-46d
-51d
-61d
-61d
-61d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
014
S2CONP11927
S2CONP11928
S2CONP11929
S2CONP11930
S2CONP11931
S2CONP11932
S2CONP11934
S2CONP11935
S2CONP11936
S2CONP11937
S2CONP11933
S2CONP11938
011
S2CONP11888
S2CONP11889
S2CONP11890
S2CONP11891
19-Oct-2013
21-Oct-2013
21-Oct-2013
16-Nov-2013
30-Nov-2013
19-Oct-2013
11-Nov-2013
01-Jan-2014
11-Jan-2014
01-Jan-2014
14-Jan-2014
14-Nov-2013
06-Nov-2013
26-Sep-2013
27-Sep-2013
27-Sep-2013
24-Oct-2013
07-Nov-2013
12-Feb-2014
21-Oct-2013
19-Nov-2013
03-Dec-2013
24-Dec-2013
05-Nov-2013
01-Jan-2014
11-Jan-2014
16-Jan-2014
08-Jan-2014
12-Feb-2014
07-Dec-2013
10-Dec-2013
20-Jan-2014
27-Sep-2013
26-Oct-2013
09-Nov-2013
30-Nov-2013
31-Oct-2013
01-NOV-13
01-NOV-13
28-NOV-13
12-DEC-13
31-OCT-13
22-NOV-13
13-JAN-14
23-JAN-14
13-JAN-14
25-JAN-14
19-NOV-13
26-NOV-13
24-Oct-2013
25-OCT-13
25-OCT-13
21-NOV-13
05-DEC-13
24-Feb-2014
01-NOV-13
30-NOV-13
14-DEC-13
04-JAN-14
16-NOV-13
13-JAN-14
23-JAN-14
28-JAN-14
20-JAN-14
24-FEB-14
12-DEC-13
30-DEC-13
17-Feb-2014
25-OCT-13
23-NOV-13
07-DEC-13
28-DEC-13
-10d
-10d
-10d
-10d
-10d
-10d
-10d
-10d
-10d
-10d
-10d
-4d
-17d
-24d
-24d
-24d
-24d
-24d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11892
S2CONP11893
S2CONP11895
S2CONP11896
S2CONP11897
S2CONP11898
S2CONP11894
S2CONP11899
009
S2CONP11862
S2CONP11863
S2CONP11864
S2CONP11865
S2CONP11866
S2CONP11867
S2CONP11869
S2CONP11870
S2CONP11871
26-Sep-2013
18-Oct-2013
09-Dec-2013
19-Dec-2013
09-Dec-2013
21-Dec-2013
22-Oct-2013
14-Oct-2013
10-Sep-2013
11-Sep-2013
11-Sep-2013
08-Oct-2013
22-Oct-2013
10-Sep-2013
02-Oct-2013
22-Nov-2013
03-Dec-2013
22-Nov-2013
12-Oct-2013
09-Dec-2013
19-Dec-2013
24-Dec-2013
16-Dec-2013
20-Jan-2014
14-Nov-2013
16-Nov-2013
03-Jan-2014
11-Sep-2013
10-Oct-2013
24-Oct-2013
14-Nov-2013
26-Sep-2013
22-Nov-2013
03-Dec-2013
07-Dec-2013
29-Nov-2013
24-OCT-13
15-NOV-13
06-JAN-14
16-JAN-14
06-JAN-14
18-JAN-14
19-NOV-13
11-NOV-13
16-Oct-2013
17-OCT-13
17-OCT-13
13-NOV-13
27-NOV-13
16-OCT-13
07-NOV-13
28-DEC-13
08-JAN-14
28-DEC-13
09-NOV-13
06-JAN-14
16-JAN-14
21-JAN-14
13-JAN-14
17-FEB-14
12-DEC-13
14-DEC-13
08-Feb-2014
17-OCT-13
15-NOV-13
29-NOV-13
19-DEC-13
01-NOV-13
28-DEC-13
08-JAN-14
13-JAN-14
04-JAN-14
-24d
-24d
-24d
-24d
-24d
-24d
-24d
-24d
-31d
-31d
-31d
-31d
-30d
-31d
-31d
-31d
-31d
-31d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Signages
11 Faced Erection Works
11 Above Terrace Landfilling Works
10 POUR-12 (GRID E~H / 09~12)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
11 Above Terrace Landfilling Works
10 POUR-13 (GRID A~D / 05~09)
11 Clearance of the Floor after Structure
11 Block Work
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11872
S2CONP11868
S2CONP11873
012
S2CONP11901
S2CONP11902
S2CONP11903
S2CONP11904
S2CONP11905
S2CONP11906
S2CONP11908
S2CONP11909
S2CONP11910
S2CONP11911
S2CONP11912
013
S2CONP11914
S2CONP11915
05-Dec-2013
05-Oct-2013
27-Sep-2013
07-Oct-2013
08-Oct-2013
08-Oct-2013
04-Nov-2013
18-Nov-2013
07-Oct-2013
29-Oct-2013
19-Dec-2013
30-Dec-2013
19-Dec-2013
01-Jan-2014
24-Oct-2013
12-Oct-2013
14-Oct-2013
14-Oct-2013
03-Jan-2014
29-Oct-2013
31-Oct-2013
30-Jan-2014
08-Oct-2013
06-Nov-2013
20-Nov-2013
11-Dec-2013
23-Oct-2013
19-Dec-2013
30-Dec-2013
03-Jan-2014
26-Dec-2013
30-Jan-2014
27-Nov-2013
05-Feb-2014
14-Oct-2013
12-Nov-2013
10-JAN-14
25-OCT-13
25-OCT-13
17-Oct-2013
18-OCT-13
18-OCT-13
23-NOV-13
03-DEC-13
17-OCT-13
08-NOV-13
30-DEC-13
06-JAN-14
30-DEC-13
08-JAN-14
26-OCT-13
07-Nov-2013
08-NOV-13
08-NOV-13
08-FEB-14
18-NOV-13
28-NOV-13
06-Feb-2014
18-OCT-13
16-NOV-13
10-DEC-13
19-DEC-13
02-NOV-13
30-DEC-13
09-JAN-14
10-JAN-14
06-JAN-14
06-FEB-14
29-NOV-13
28-Feb-2014
08-NOV-13
07-DEC-13
-31d
-17d
-24d
-6d
-9d
-9d
-17d
-7d
-9d
-9d
-9d
-6d
-9d
-6d
-2d
-20d
-22d
-22d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
11 Faced Erection Works
11 Above Terrace Landfilling Works
10 POUR-15 (GRID E~H / 05~09)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11916
S2CONP11917
S2CONP11918
S2CONP11919
S2CONP11921
S2CONP11922
S2CONP11923
S2CONP11924
S2CONP11920
S2CONP11925
015
S2CONP11940
S2CONP11941
S2CONP11942
S2CONP11943
S2CONP11944
S2CONP11945
S2CONP11947
09-Nov-2013
23-Nov-2013
12-Oct-2013
04-Nov-2013
25-Dec-2013
04-Jan-2014
25-Dec-2013
07-Jan-2014
07-Nov-2013
30-Oct-2013
26-Oct-2013
28-Oct-2013
28-Oct-2013
23-Nov-2013
07-Dec-2013
26-Oct-2013
18-Nov-2013
08-Jan-2014
26-Nov-2013
17-Dec-2013
29-Oct-2013
25-Dec-2013
04-Jan-2014
09-Jan-2014
01-Jan-2014
05-Feb-2014
30-Nov-2013
03-Dec-2013
19-Feb-2014
28-Oct-2013
26-Nov-2013
10-Dec-2013
31-Dec-2013
12-Nov-2013
08-Jan-2014
18-Jan-2014
05-DEC-13
19-DEC-13
07-NOV-13
29-NOV-13
20-JAN-14
30-JAN-14
20-JAN-14
30-JAN-14
29-NOV-13
03-DEC-13
31-Oct-2013
01-NOV-13
01-NOV-13
28-NOV-13
12-DEC-13
31-OCT-13
22-NOV-13
13-JAN-14
21-DEC-13
11-JAN-14
23-NOV-13
20-JAN-14
30-JAN-14
04-FEB-14
27-JAN-14
28-FEB-14
23-DEC-13
06-JAN-14
25-Feb-2014
02-NOV-13
02-DEC-13
16-DEC-13
04-JAN-14
18-NOV-13
14-JAN-14
24-JAN-14
-22d
-22d
-22d
-22d
-22d
-22d
-22d
-20d
-19d
-29d
-5d
-4d
-4d
-4d
-3d
-4d
-4d
-4d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Interior Works
11 Cabling & Fixing Works
11 Signages
11 Above Terrace Landfilling Works
10 POUR-16 (GRID E~H / 01~05)
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Screed Concreting & Tiling
11 MEP Works
11 False Ceiling
11 Interior Works
11 Cabling & Fixing Works
11 Signages
11 Faced Erection Works
11 Above Terrace Landfilling Works
9 PART-01 (GRID 16~31)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11948
S2CONP11949
S2CONP11950
S2CONP11951
016
S2CONP11953
S2CONP11954
S2CONP11955
S2CONP11956
S2CONP11957
S2CONP11958
S2CONP11960
S2CONP11961
S2CONP11962
S2CONP11963
S2CONP11959
S2CONP11964
001
18-Jan-2014
08-Jan-2014
21-Jan-2014
14-Nov-2013
29-Oct-2013
30-Oct-2013
30-Oct-2013
26-Nov-2013
10-Dec-2013
29-Oct-2013
20-Nov-2013
10-Jan-2014
21-Jan-2014
10-Jan-2014
22-Jan-2014
25-Nov-2013
16-Nov-2013
27-Jul-2013
23-Jan-2014
15-Jan-2014
19-Feb-2014
18-Dec-2013
20-Feb-2014
30-Oct-2013
28-Nov-2013
12-Dec-2013
02-Jan-2014
14-Nov-2013
10-Jan-2014
21-Jan-2014
25-Jan-2014
17-Jan-2014
20-Feb-2014
18-Dec-2013
20-Dec-2013
28-Nov-2013
23-JAN-14
13-JAN-14
25-JAN-14
19-NOV-13
08-Nov-2013
09-NOV-13
09-NOV-13
06-DEC-13
20-DEC-13
08-NOV-13
30-NOV-13
21-JAN-14
29-JAN-14
21-JAN-14
24-JAN-14
12-DEC-13
04-DEC-13
22-Aug-2013
29-JAN-14
21-JAN-14
25-FEB-14
24-DEC-13
24-Feb-2014
11-NOV-13
10-DEC-13
24-DEC-13
14-JAN-14
26-NOV-13
22-JAN-14
01-FEB-14
04-FEB-14
29-JAN-14
24-FEB-14
06-JAN-14
08-JAN-14
16-Dec-2013
-4d
-4d
-4d
-4d
-3d
-9d
-9d
-9d
-9d
-9d
-9d
-9d
-7d
-9d
-2d
-15d
-15d
-15d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
002
S2CONP11771
S2CONP11772
S2CONP11773
S2CONP11774
S2CONP11775
S2CONP11776
S2CONP11778
S2CONP11779
S2CONP11780
S2CONP11781
S2CONP11777
S2CONP11782
001
S2CONP11758
S2CONP11759
S2CONP11760
S2CONP11761
05-Aug-2013
06-Aug-2013
06-Aug-2013
02-Sep-2013
16-Sep-2013
05-Aug-2013
27-Aug-2013
17-Oct-2013
28-Oct-2013
17-Oct-2013
30-Oct-2013
30-Aug-2013
22-Aug-2013
27-Jul-2013
29-Jul-2013
29-Jul-2013
24-Aug-2013
07-Sep-2013
28-Nov-2013
06-Aug-2013
04-Sep-2013
18-Sep-2013
09-Oct-2013
21-Aug-2013
17-Oct-2013
28-Oct-2013
01-Nov-2013
24-Oct-2013
28-Nov-2013
23-Sep-2013
25-Sep-2013
01-Oct-2013
29-Jul-2013
27-Aug-2013
10-Sep-2013
01-Oct-2013
22-Aug-2013
23-AUG-13
23-AUG-13
19-SEP-13
03-OCT-13
22-AUG-13
13-SEP-13
04-NOV-13
14-NOV-13
04-NOV-13
16-NOV-13
17-SEP-13
09-SEP-13
22-Aug-2013
23-AUG-13
23-AUG-13
19-SEP-13
03-OCT-13
16-Dec-2013
23-AUG-13
21-SEP-13
05-OCT-13
26-OCT-13
07-SEP-13
04-NOV-13
14-NOV-13
19-NOV-13
11-NOV-13
16-DEC-13
10-OCT-13
12-OCT-13
26-Oct-2013
23-AUG-13
21-SEP-13
05-OCT-13
26-OCT-13
-15d
-15d
-15d
-15d
-15d
-15d
-15d
-15d
-15d
-15d
-15d
-15d
-15d
-22d
-22d
-22d
-22d
-22d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11762
S2CONP11764
003
S2CONP11784
S2CONP11785
S2CONP11786
S2CONP11787
S2CONP11788
S2CONP11790
004
S2CONP11797
S2CONP11798
S2CONP11799
S2CONP11800
S2CONP11801
S2CONP11802
S2CONP11804
S2CONP11805
27-Jul-2013
22-Aug-2013
12-Aug-2013
13-Aug-2013
13-Aug-2013
09-Sep-2013
23-Sep-2013
12-Aug-2013
06-Sep-2013
21-Aug-2013
22-Aug-2013
22-Aug-2013
18-Sep-2013
02-Oct-2013
21-Aug-2013
12-Sep-2013
02-Nov-2013
13-Nov-2013
13-Aug-2013
14-Sep-2013
16-Oct-2013
13-Aug-2013
11-Sep-2013
25-Sep-2013
16-Oct-2013
28-Aug-2013
30-Sep-2013
18-Nov-2013
22-Aug-2013
20-Sep-2013
04-Oct-2013
25-Oct-2013
06-Sep-2013
02-Nov-2013
13-Nov-2013
18-Nov-2013
22-AUG-13
17-SEP-13
22-Aug-2013
23-AUG-13
23-AUG-13
19-SEP-13
03-OCT-13
22-AUG-13
17-SEP-13
22-Aug-2013
23-AUG-13
23-AUG-13
19-SEP-13
03-OCT-13
22-AUG-13
13-SEP-13
04-NOV-13
14-NOV-13
07-SEP-13
10-OCT-13
26-Oct-2013
23-AUG-13
21-SEP-13
05-OCT-13
26-OCT-13
07-SEP-13
10-OCT-13
19-Nov-2013
23-AUG-13
21-SEP-13
05-OCT-13
26-OCT-13
07-SEP-13
04-NOV-13
14-NOV-13
19-NOV-13
-22d
-22d
-9d
-9d
-9d
-9d
-9d
-9d
-9d
-1d
-1d
-1d
-1d
-1d
-1d
-1d
-1d
-1d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11806
S2CONP11803
004
004
002
S2CON01330
S2CON01331
S2CON01332
S2CON01333
001
007
003
S2CON2823
S2CON2824
S2CON2825
S2CON2826
S2CON2827
S2CON2828
02-Nov-2013
16-Sep-2013
15-Sep-2012
12-Dec-2012
08-Aug-2013
08-Aug-2013
08-Aug-2013
26-Aug-2013
13-Dec-2013
12-Dec-2012
18-Mar-2013
23-May-2013
23-May-2013
04-Jun-2013
27-Jun-2013
15-Jul-2013
15-Jul-2013
15-Jul-2013
09-Nov-2013
09-Oct-2013
17-Feb-2014
17-Feb-2014
13-Dec-2013
20-Nov-2013
20-Nov-2013
07-Dec-2013
13-Dec-2013
17-Feb-2014
17-Feb-2014
10-Feb-2014
03-Jun-2013
26-Jun-2013
31-Jul-2013
17-Aug-2013
17-Aug-2013
12-Aug-2013
04-NOV-13
17-SEP-13
05-Sep-2012A
01-Apr-2013A
27-Aug-2013
27-AUG-13
07-OCT-13
24-OCT-13
27-MAR-14
01-Apr-2013A
03-Jun-2013
13-Jun-2013
13-JUN-13
25-JUN-13
18-JUL-13
05-AUG-13
05-AUG-13
22-AUG-13
11-NOV-13
10-OCT-13
05-Jun-2014
05-Jun-2014
16-Apr-2014
09-DEC-13
18-JAN-14
05-FEB-14
16-APR-14
05-Jun-2014
05-Jun-2014
18-Apr-2014
24-JUN-13
17-JUL-13
21-AUG-13
07-SEP-13
07-SEP-13
19-SEP-13
-1d
-1d
-93d
-93d
-106d
-16d
-51d
-51d
-106d
-93d
-93d
-58d
-18d
-18d
-18d
-18d
-18d
-33d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2829
S2CON2830
S2CON2831
S2CON2832
S2CON2833
S2CON2834
S2CON2835
004
S2CON2851
S2CON2852
S2CON2853
S2CON2854
S2CON2855
S2CON2856
S2CON2857
S2CON2858
S2CON2859
S2CON2860
04-Sep-2013
18-Nov-2013
09-Oct-2013
28-Oct-2013
13-Nov-2013
31-Dec-2013
30-Jan-2014
27-May-2013
27-May-2013
07-Jun-2013
01-Jul-2013
18-Jul-2013
18-Jul-2013
18-Jul-2013
07-Sep-2013
21-Nov-2013
12-Oct-2013
31-Oct-2013
08-Oct-2013
02-Jan-2014
12-Nov-2013
30-Nov-2013
28-Dec-2013
28-Jan-2014
10-Feb-2014
13-Feb-2014
06-Jun-2013
29-Jun-2013
03-Aug-2013
21-Aug-2013
21-Aug-2013
15-Aug-2013
11-Oct-2013
06-Jan-2014
15-Nov-2013
04-Dec-2013
25-SEP-13
20-JAN-14
25-JAN-14
31-JAN-14
12-FEB-14
08-MAR-14
08-APR-14
14-Jun-2013
14-JUN-13
26-JUN-13
19-JUL-13
06-AUG-13
06-AUG-13
23-AUG-13
26-SEP-13
20-JAN-14
25-JAN-14
31-JAN-14
29-OCT-13
17-FEB-14
28-FEB-14
06-MAR-14
06-MAR-14
05-APR-14
18-APR-14
18-Apr-2014
25-JUN-13
18-JUL-13
22-AUG-13
09-SEP-13
09-SEP-13
20-SEP-13
30-OCT-13
17-FEB-14
28-FEB-14
06-MAR-14
-18d
-39d
-93d
-82d
-58d
-58d
-58d
-55d
-16d
-16d
-16d
-16d
-16d
-31d
-16d
-36d
-90d
-79d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2861
S2CON2862
S2CON2863
005
S2CON2795
S2CON2796
S2CON2797
S2CON2798
S2CON2799
S2CON2800
S2CON2801
S2CON2802
S2CON2803
S2CON2804
S2CON2805
S2CON2806
S2CON2807
006
16-Nov-2013
03-Jan-2014
03-Feb-2014
30-May-2013
30-May-2013
11-Jun-2013
04-Jul-2013
22-Jul-2013
22-Jul-2013
22-Jul-2013
11-Sep-2013
25-Nov-2013
16-Oct-2013
04-Nov-2013
20-Nov-2013
07-Jan-2014
06-Feb-2014
18-Mar-2013
01-Jan-2014
31-Jan-2014
13-Feb-2014
17-Feb-2014
10-Jun-2013
03-Jul-2013
07-Aug-2013
24-Aug-2013
24-Aug-2013
19-Aug-2013
15-Oct-2013
09-Jan-2014
19-Nov-2013
07-Dec-2013
04-Jan-2014
04-Feb-2014
17-Feb-2014
30-Nov-2013
12-FEB-14
08-MAR-14
08-APR-14
17-Jun-2013
17-JUN-13
29-JUN-13
24-JUL-13
12-AUG-13
12-AUG-13
29-AUG-13
03-OCT-13
29-JAN-14
04-FEB-14
10-FEB-14
21-FEB-14
18-MAR-14
17-APR-14
28-Jun-2013
06-MAR-14
05-APR-14
18-APR-14
28-Apr-2014
28-JUN-13
23-JUL-13
28-AUG-13
16-SEP-13
16-SEP-13
27-SEP-13
07-NOV-13
26-FEB-14
10-MAR-14
15-MAR-14
15-MAR-14
15-APR-14
28-APR-14
08-Mar-2014
-55d
-55d
-55d
-60d
-16d
-17d
-18d
-19d
-19d
-34d
-20d
-41d
-95d
-84d
-60d
-60d
-60d
-84d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2781
S2CON2782
S2CON2783
S2CON2784
S2CON2785
S2CON2786
S2CON2787
S2CON2788
S2CON2789
S2CON2790
S2CON2791
S2CON2792
S2CON2793
008
S2CON2882
S2CON2883
S2CON2884
S2CON2885
18-Mar-2013
05-Apr-2013
29-Apr-2013
16-May-2013
08-Apr-2013
14-May-2013
06-Jul-2013
12-Aug-2013
10-Aug-2013
29-Aug-2013
14-Sep-2013
26-Oct-2013
20-Nov-2013
03-Jun-2013
01-Aug-2013
24-Jun-2013
30-Jul-2013
21-Sep-2013
28-Mar-2013
27-Apr-2013
01-Jun-2013
19-Jun-2013
11-May-2013
11-Jun-2013
09-Aug-2013
26-Sep-2013
13-Sep-2013
02-Oct-2013
30-Oct-2013
23-Nov-2013
30-Nov-2013
14-Feb-2014
04-Sep-2013
27-Jul-2013
27-Aug-2013
25-Oct-2013
28-JUN-13
17-JUL-13
09-AUG-13
27-AUG-13
19-JUL-13
24-AUG-13
17-OCT-13
21-DEC-13
27-DEC-13
02-JAN-14
14-JAN-14
01-FEB-14
26-FEB-14
08-Jul-2013
19-SEP-13
12-AUG-13
17-SEP-13
14-NOV-13
09-JUL-13
08-AUG-13
12-SEP-13
30-SEP-13
22-AUG-13
21-SEP-13
20-NOV-13
18-JAN-14
30-JAN-14
05-FEB-14
05-FEB-14
01-MAR-14
08-MAR-14
05-Apr-2014
28-OCT-13
19-SEP-13
19-OCT-13
23-DEC-13
-88d
-88d
-88d
-88d
-88d
-88d
-88d
-98d
-119d
-108d
-84d
-84d
-84d
-43d
-46d
-46d
-46d
-50d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2886
S2CON2887
S2CON2888
S2CON2889
S2CON2890
S2CON2891
S2CON2879
S2CON2880
S2CON2881
007
S2CON2865
S2CON2866
S2CON2867
S2CON2868
S2CON2869
S2CON2870
S2CON2871
S2CON2872
28-Oct-2013
26-Oct-2013
14-Nov-2013
30-Nov-2013
11-Jan-2014
04-Feb-2014
03-Jun-2013
21-Jun-2013
15-Jul-2013
16-May-2013
16-May-2013
04-Jun-2013
27-Jun-2013
15-Jul-2013
06-Jun-2013
12-Jul-2013
04-Sep-2013
10-Oct-2013
12-Dec-2013
29-Nov-2013
18-Dec-2013
15-Jan-2014
08-Feb-2014
14-Feb-2014
13-Jun-2013
13-Jul-2013
17-Aug-2013
29-Jan-2014
27-May-2013
26-Jun-2013
31-Jul-2013
17-Aug-2013
10-Jul-2013
09-Aug-2013
08-Oct-2013
25-Nov-2013
20-JAN-14
25-JAN-14
31-JAN-14
12-FEB-14
03-MAR-14
26-MAR-14
08-JUL-13
31-JUL-13
28-AUG-13
08-Jun-2013
08-JUN-13
27-JUN-13
20-JUL-13
07-AUG-13
01-JUL-13
05-AUG-13
27-SEP-13
20-JAN-14
17-FEB-14
28-FEB-14
06-MAR-14
06-MAR-14
31-MAR-14
05-APR-14
23-JUL-13
27-AUG-13
05-OCT-13
07-Apr-2014
19-JUN-13
19-JUL-13
23-AUG-13
10-SEP-13
03-AUG-13
02-SEP-13
31-OCT-13
17-FEB-14
-57d
-78d
-67d
-43d
-43d
-43d
-34d
-38d
-42d
-58d
-20d
-20d
-20d
-20d
-21d
-20d
-20d
-72d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z1-GRID E~J / 21~15
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2873
S2CON2874
S2CON2875
S2CON2876
S2CON2877
001
S2CON2837
S2CON2838
S2CON2839
S2CON2840
S2CON2841
S2CON2842
S2CON2843
S2CON2844
S2CON2845
S2CON2846
S2CON2847
S2CON2848
09-Oct-2013
28-Oct-2013
13-Nov-2013
25-Dec-2013
18-Jan-2014
09-May-2013
09-May-2013
21-May-2013
13-Jun-2013
01-Jul-2013
01-Jul-2013
01-Jul-2013
21-Aug-2013
04-Nov-2013
25-Sep-2013
14-Oct-2013
30-Oct-2013
17-Dec-2013
12-Nov-2013
30-Nov-2013
28-Dec-2013
22-Jan-2014
29-Jan-2014
27-Jan-2014
20-May-2013
12-Jun-2013
17-Jul-2013
03-Aug-2013
03-Aug-2013
29-Jul-2013
24-Sep-2013
19-Dec-2013
29-Oct-2013
16-Nov-2013
14-Dec-2013
14-Jan-2014
25-JAN-14
31-JAN-14
12-FEB-14
03-MAR-14
27-MAR-14
03-Jun-2013
03-JUN-13
14-JUN-13
08-JUL-13
25-JUL-13
25-JUL-13
12-AUG-13
14-SEP-13
08-MAR-14
14-MAR-14
20-MAR-14
01-APR-14
25-APR-14
28-FEB-14
06-MAR-14
06-MAR-14
31-MAR-14
07-APR-14
05-Jun-2014
13-JUN-13
06-JUL-13
10-AUG-13
28-AUG-13
28-AUG-13
09-SEP-13
18-OCT-13
05-APR-14
17-APR-14
23-APR-14
23-APR-14
23-MAY-14
-93d
-82d
-58d
-58d
-58d
-111d
-21d
-21d
-21d
-21d
-21d
-36d
-21d
-92d
-146d
-135d
-111d
-111d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2849
002
S2CON2809
S2CON2810
S2CON2811
S2CON2812
S2CON2813
S2CON2814
S2CON2815
S2CON2816
S2CON2817
S2CON2818
S2CON2819
S2CON2820
S2CON2821
002
001
S2CON2277
16-Jan-2014
13-May-2013
13-May-2013
24-May-2013
17-Jun-2013
04-Jul-2013
04-Jul-2013
04-Jul-2013
24-Aug-2013
07-Nov-2013
28-Sep-2013
17-Oct-2013
02-Nov-2013
20-Dec-2013
20-Jan-2014
12-Dec-2012
12-Dec-2012
12-Dec-2012
27-Jan-2014
30-Jan-2014
23-May-2013
15-Jun-2013
20-Jul-2013
07-Aug-2013
07-Aug-2013
01-Aug-2013
27-Sep-2013
23-Dec-2013
01-Nov-2013
20-Nov-2013
18-Dec-2013
17-Jan-2014
30-Jan-2014
01-Nov-2013
21-Sep-2013
22-Dec-2012
26-MAY-14
08-Jun-2013
08-JUN-13
20-JUN-13
13-JUL-13
31-JUL-13
31-JUL-13
17-AUG-13
20-SEP-13
20-JAN-14
25-JAN-14
31-JAN-14
12-FEB-14
08-MAR-14
08-APR-14
01-Apr-2013A
01-Apr-2013A
01-APR-13A
05-JUN-14
18-Apr-2014
19-JUN-13
12-JUL-13
16-AUG-13
03-SEP-13
03-SEP-13
14-SEP-13
24-OCT-13
17-FEB-14
28-FEB-14
06-MAR-14
06-MAR-14
05-APR-14
18-APR-14
04-Mar-2014
08-Feb-2014
05-APR-13A
-111d
-67d
-23d
-23d
-23d
-23d
-23d
-38d
-23d
-48d
-102d
-91d
-67d
-67d
-67d
-105d
-120d
-88d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z2-GRID A~E / 21~15
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2278
S2CON2279
S2CON2280
S2CON2281
S2CON2282
S2CON2283
S2CON2284
S2CON2285
S2CON2286
S2CON2287
S2CON2288
S2CON2289
002
S2CON2249
S2CON2250
S2CON2251
S2CON2252
S2CON2253
24-Dec-2012
16-Jan-2013
20-Feb-2013
20-Feb-2013
27-Mar-2013
12-Apr-2013
07-Aug-2013
17-May-2013
05-Jun-2013
21-Jun-2013
08-Aug-2013
07-Sep-2013
15-Dec-2012
15-Dec-2012
27-Dec-2012
19-Jan-2013
23-Feb-2013
23-Feb-2013
15-Jan-2013
19-Feb-2013
26-Mar-2013
26-Mar-2013
24-Apr-2013
16-May-2013
21-Sep-2013
20-Jun-2013
09-Jul-2013
06-Aug-2013
05-Sep-2013
18-Sep-2013
25-Sep-2013
26-Dec-2012
18-Jan-2013
22-Feb-2013
29-Mar-2013
29-Mar-2013
10-APR-13A
17-MAY-13A
26-JUL-13
26-JUL-13
13-AUG-13
25-APR-13A
12-NOV-13
18-NOV-13
23-NOV-13
05-DEC-13
30-DEC-13
29-JAN-14
10-Apr-2013A
10-APR-13A
12-APR-13A
24-JUN-13
29-JUL-13
29-JUL-13
20-JUN-13
25-JUL-13
29-AUG-13
29-AUG-13
10-SEP-13
19-OCT-13
10-DEC-13
21-DEC-13
27-DEC-13
27-DEC-13
27-JAN-14
08-FEB-14
31-Jan-2014
14-APR-13A
22-JUN-13
27-JUL-13
31-AUG-13
31-AUG-13
-134d
-134d
-134d
-134d
-119d
-134d
-68d
-158d
-147d
-123d
-123d
-123d
-110d
-93d
-133d
-133d
-133d
-133d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2254
S2CON2255
S2CON2256
S2CON2257
S2CON2258
S2CON2259
S2CON2260
S2CON2261
003
S2CON2263
S2CON2264
S2CON2265
S2CON2266
S2CON2267
S2CON2268
S2CON2269
S2CON2270
S2CON2271
30-Mar-2013
16-Apr-2013
10-Aug-2013
21-May-2013
08-Jun-2013
25-Jun-2013
12-Aug-2013
11-Sep-2013
26-Dec-2012
26-Dec-2012
07-Jan-2013
30-Jan-2013
06-Mar-2013
06-Mar-2013
10-Apr-2013
26-Apr-2013
21-Aug-2013
31-May-2013
27-Apr-2013
20-May-2013
25-Sep-2013
24-Jun-2013
12-Jul-2013
09-Aug-2013
09-Sep-2013
21-Sep-2013
05-Oct-2013
05-Jan-2013
29-Jan-2013
05-Mar-2013
09-Apr-2013
09-Apr-2013
08-May-2013
30-May-2013
05-Oct-2013
04-Jul-2013
15-AUG-13
18-SEP-13
25-SEP-13
26-APR-13A
07-OCT-13
27-NOV-13
21-DEC-13
21-JAN-14
21-Apr-2013A
29-APR-13A
01-MAY-13A
24-JUN-13
30-JUL-13
30-JUL-13
16-AUG-13
21-APR-13A
25-SEP-13
26-OCT-13
12-SEP-13
22-OCT-13
23-OCT-13
26-NOV-13
09-NOV-13
19-DEC-13
18-JAN-14
31-JAN-14
19-Feb-2014
09-MAY-13A
22-JUN-13
29-JUL-13
03-SEP-13
02-SEP-13
13-SEP-13
25-OCT-13
23-OCT-13
30-NOV-13
-118d
-133d
-24d
-133d
-103d
-113d
-113d
-113d
-117d
-106d
-124d
-125d
-126d
-125d
-110d
-127d
-15d
-128d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z4-GRID A~E / 15-10
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2272
S2CON2273
S2CON2274
S2CON2275
004
S2CON2301
S2CON2302
S2CON2303
S2CON2291
S2CON2292
S2CON2293
S2CON2294
S2CON2295
S2CON2296
S2CON2297
S2CON2298
S2CON2299
S2CON2300
19-Jun-2013
05-Jul-2013
22-Aug-2013
21-Sep-2013
29-Dec-2012
09-Jul-2013
26-Aug-2013
25-Sep-2013
29-Dec-2012
10-Jan-2013
02-Feb-2013
09-Mar-2013
09-Mar-2013
13-Apr-2013
30-Apr-2013
24-Aug-2013
04-Jun-2013
22-Jun-2013
23-Jul-2013
20-Aug-2013
19-Sep-2013
02-Oct-2013
09-Oct-2013
23-Aug-2013
23-Sep-2013
05-Oct-2013
09-Jan-2013
01-Feb-2013
08-Mar-2013
12-Apr-2013
12-Apr-2013
11-May-2013
03-Jun-2013
09-Oct-2013
08-Jul-2013
26-Jul-2013
09-OCT-13
21-OCT-13
03-DEC-13
21-JAN-14
29-Apr-2013A
30-OCT-13
12-DEC-13
30-JAN-14
29-APR-13A
01-MAY-13A
24-JUN-13
30-JUL-13
30-JUL-13
16-AUG-13
01-MAY-13A
25-SEP-13
26-OCT-13
09-OCT-13
12-NOV-13
30-NOV-13
18-JAN-14
19-FEB-14
28-Feb-2014
10-DEC-13
28-JAN-14
28-FEB-14
09-MAY-13A
22-JUN-13
29-JUL-13
03-SEP-13
02-SEP-13
13-SEP-13
25-OCT-13
23-OCT-13
30-NOV-13
12-NOV-13
-96d
-88d
-104d
-120d
-122d
-93d
-109d
-125d
-103d
-121d
-122d
-123d
-122d
-107d
-124d
-12d
-125d
-93d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
005
S2CON2235
S2CON2236
S2CON2237
S2CON2238
S2CON2239
S2CON2240
S2CON2241
S2CON2242
S2CON2243
S2CON2244
S2CON2245
S2CON2246
S2CON2247
006
S2CON2221
S2CON2222
S2CON2223
03-Jan-2013
03-Jan-2013
15-Jan-2013
07-Feb-2013
14-Mar-2013
14-Mar-2013
18-Apr-2013
04-May-2013
29-Aug-2013
08-Jun-2013
27-Jun-2013
13-Jul-2013
30-Aug-2013
30-Sep-2013
28-Dec-2012
28-Dec-2012
16-Jan-2013
08-Feb-2013
14-Oct-2013
14-Jan-2013
06-Feb-2013
13-Mar-2013
17-Apr-2013
17-Apr-2013
16-May-2013
07-Jun-2013
14-Oct-2013
12-Jul-2013
31-Jul-2013
28-Aug-2013
27-Sep-2013
10-Oct-2013
12-Oct-2013
08-Jan-2013
07-Feb-2013
14-Mar-2013
29-Apr-2013A
29-APR-13A
01-MAY-13A
05-JUL-13
10-AUG-13
10-AUG-13
28-AUG-13
02-MAY-13A
04-OCT-13
07-NOV-13
21-OCT-13
12-NOV-13
21-DEC-13
05-FEB-14
31-May-2013
31-MAY-13
19-JUN-13
12-JUL-13
04-Mar-2014
11-JUN-13
04-JUL-13
09-AUG-13
14-SEP-13
13-SEP-13
25-SEP-13
06-NOV-13
01-NOV-13
11-DEC-13
23-NOV-13
20-DEC-13
04-FEB-14
04-MAR-14
07-Feb-2014
11-JUN-13
11-JUL-13
15-AUG-13
-121d
-127d
-127d
-128d
-129d
-128d
-113d
-130d
-16d
-130d
-99d
-97d
-111d
-124d
-101d
-132d
-132d
-132d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z7-GRID E~J / 5~1
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2224
S2CON2225
S2CON2226
S2CON2227
S2CON2228
S2CON2229
S2CON2230
S2CON2231
S2CON2232
S2CON2233
007
S2CON2305
S2CON2306
S2CON2307
S2CON2308
S2CON2309
S2CON2310
S2CON2311
15-Mar-2013
05-Feb-2013
13-Mar-2013
06-May-2013
11-Jun-2013
10-Jun-2013
28-Jun-2013
27-Jul-2013
07-Sep-2013
02-Oct-2013
20-Dec-2012
20-Dec-2012
08-Jan-2013
31-Jan-2013
07-Mar-2013
28-Jan-2013
05-Mar-2013
27-Apr-2013
18-Apr-2013
11-Mar-2013
10-Apr-2013
08-Jun-2013
26-Jul-2013
13-Jul-2013
01-Aug-2013
11-Sep-2013
05-Oct-2013
12-Oct-2013
04-Oct-2013
31-Dec-2012
30-Jan-2013
06-Mar-2013
10-Apr-2013
02-Mar-2013
02-Apr-2013
31-May-2013
16-AUG-13
18-JUL-13
14-AUG-13
07-OCT-13
27-AUG-13
11-NOV-13
25-OCT-13
16-DEC-13
03-JAN-14
28-JAN-14
10-Apr-2013A
10-APR-13A
18-APR-13A
21-JUN-13
26-JUL-13
18-JUL-13
05-AUG-13
04-MAY-13A
19-SEP-13
21-AUG-13
11-SEP-13
09-NOV-13
24-SEP-13
14-DEC-13
28-NOV-13
07-JAN-14
31-JAN-14
07-FEB-14
21-Dec-2013
12-APR-13A
20-JUN-13
25-JUL-13
29-AUG-13
21-AUG-13
02-SEP-13
19-OCT-13
-132d
-140d
-132d
-132d
-51d
-132d
-102d
-101d
-101d
-101d
-67d
-87d
-121d
-121d
-121d
-147d
-131d
-121d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2312
S2CON2313
S2CON2314
S2CON2315
S2CON2316
S2CON2317
008
S2CON2319
S2CON2320
S2CON2321
S2CON2322
S2CON2323
S2CON2324
S2CON2325
S2CON2326
S2CON2327
S2CON2328
S2CON2329
03-Jun-2013
01-Jun-2013
20-Jun-2013
19-Jul-2013
30-Aug-2013
24-Sep-2013
17-Jan-2013
17-Jan-2013
05-Feb-2013
28-Feb-2013
04-Apr-2013
25-Feb-2013
02-Apr-2013
25-May-2013
01-Jul-2013
29-Jun-2013
18-Jul-2013
16-Aug-2013
18-Jul-2013
05-Jul-2013
24-Jul-2013
03-Sep-2013
27-Sep-2013
04-Oct-2013
01-Nov-2013
28-Jan-2013
27-Feb-2013
03-Apr-2013
08-May-2013
30-Mar-2013
30-Apr-2013
28-Jun-2013
15-Aug-2013
02-Aug-2013
21-Aug-2013
01-Oct-2013
25-SEP-13
21-OCT-13
07-OCT-13
29-OCT-13
16-NOV-13
11-DEC-13
10-Apr-2013A
10-APR-13A
18-APR-13A
21-JUN-13
26-JUL-13
18-JUL-13
05-AUG-13
05-MAY-13A
25-SEP-13
21-OCT-13
07-OCT-13
30-OCT-13
23-OCT-13
23-NOV-13
09-NOV-13
20-NOV-13
14-DEC-13
21-DEC-13
06-Jan-2014
12-APR-13A
20-JUN-13
25-JUL-13
29-AUG-13
21-AUG-13
02-SEP-13
19-OCT-13
23-OCT-13
23-NOV-13
09-NOV-13
26-NOV-13
-83d
-121d
-93d
-67d
-67d
-67d
-56d
-63d
-97d
-97d
-97d
-123d
-107d
-97d
-59d
-97d
-69d
-48d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Workstations
11 Chairs, Blinds and Carpets
9 GF/ MEZ
10 Z1-GRID E~J / 21~15
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z3-GRID E~J / 15~10
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2330
S2CON2331
001
001
S2CON00742
S2CON00743
S2CON00744
S2CON00745
S2CON00746
S2CON00747
S2CON00748
S2CON00749
S2CON00750
S2CON00751
S2CON00752
S2CON00753
S2CON00754
003
27-Sep-2013
22-Oct-2013
14-Dec-2012
14-Dec-2012
14-Dec-2012
20-Dec-2012
12-Jan-2013
16-Feb-2013
16-Feb-2013
16-Feb-2013
09-Apr-2013
22-Jun-2013
14-May-2013
01-Jun-2013
18-Jun-2013
05-Aug-2013
04-Sep-2013
28-Dec-2012
25-Oct-2013
01-Nov-2013
07-Oct-2013
14-Sep-2013
19-Dec-2012
11-Jan-2013
15-Feb-2013
22-Mar-2013
22-Mar-2013
16-Mar-2013
13-May-2013
07-Aug-2013
17-Jun-2013
05-Jul-2013
02-Aug-2013
02-Sep-2013
14-Sep-2013
28-Sep-2013
22-NOV-13
21-DEC-13
31-May-2013
31-May-2013
31-MAY-13
06-JUN-13
29-JUN-13
03-AUG-13
03-AUG-13
21-AUG-13
24-SEP-13
18-OCT-13
29-OCT-13
30-OCT-13
03-DEC-13
27-DEC-13
27-JAN-14
31-May-2013
25-DEC-13
06-JAN-14
15-Feb-2014
06-Feb-2014
05-JUN-13
28-JUN-13
02-AUG-13
06-SEP-13
06-SEP-13
18-SEP-13
28-OCT-13
15-NOV-13
02-DEC-13
03-DEC-13
25-DEC-13
24-JAN-14
06-FEB-14
06-Feb-2014
-52d
-56d
-113d
-124d
-144d
-144d
-144d
-144d
-144d
-159d
-144d
-86d
-144d
-129d
-124d
-124d
-124d
-112d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00770
S2CON00771
S2CON00772
S2CON00773
S2CON00774
S2CON00775
S2CON00776
S2CON00777
S2CON00778
S2CON00779
S2CON00780
S2CON00781
S2CON00782
004
S2CON00784
S2CON00785
S2CON00786
S2CON00787
28-Dec-2012
03-Jan-2013
26-Jan-2013
02-Mar-2013
02-Mar-2013
02-Mar-2013
23-Apr-2013
06-Jul-2013
28-May-2013
15-Jun-2013
02-Jul-2013
19-Aug-2013
18-Sep-2013
01-Jan-2013
01-Jan-2013
07-Jan-2013
30-Jan-2013
06-Mar-2013
02-Jan-2013
25-Jan-2013
01-Mar-2013
05-Apr-2013
05-Apr-2013
30-Mar-2013
27-May-2013
21-Aug-2013
01-Jul-2013
19-Jul-2013
16-Aug-2013
16-Sep-2013
28-Sep-2013
02-Oct-2013
05-Jan-2013
29-Jan-2013
05-Mar-2013
09-Apr-2013
31-MAY-13
06-JUN-13
29-JUN-13
03-AUG-13
03-AUG-13
21-AUG-13
24-SEP-13
02-SEP-13
29-OCT-13
12-OCT-13
03-DEC-13
27-DEC-13
27-JAN-14
31-May-2013
31-MAY-13
06-JUN-13
29-JUN-13
03-AUG-13
05-JUN-13
28-JUN-13
02-AUG-13
06-SEP-13
06-SEP-13
18-SEP-13
28-OCT-13
30-SEP-13
02-DEC-13
15-NOV-13
25-DEC-13
24-JAN-14
06-FEB-14
06-Feb-2014
05-JUN-13
28-JUN-13
02-AUG-13
06-SEP-13
-132d
-132d
-132d
-132d
-132d
-147d
-132d
-34d
-132d
-102d
-112d
-112d
-112d
-109d
-129d
-129d
-129d
-129d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z5-GRID E~J / 10~5
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00788
S2CON00789
S2CON00790
S2CON00791
S2CON00792
S2CON00793
S2CON00794
S2CON00795
S2CON00796
005
S2CON00798
S2CON00799
S2CON00800
S2CON00801
S2CON00802
S2CON00803
S2CON00804
S2CON00805
06-Mar-2013
06-Mar-2013
26-Apr-2013
10-Jul-2013
31-May-2013
19-Jun-2013
05-Jul-2013
22-Aug-2013
21-Sep-2013
05-Jan-2013
05-Jan-2013
11-Jan-2013
04-Feb-2013
11-Mar-2013
11-Mar-2013
11-Mar-2013
01-May-2013
15-Jul-2013
09-Apr-2013
03-Apr-2013
30-May-2013
24-Aug-2013
04-Jul-2013
23-Jul-2013
20-Aug-2013
19-Sep-2013
02-Oct-2013
07-Oct-2013
10-Jan-2013
02-Feb-2013
09-Mar-2013
13-Apr-2013
13-Apr-2013
08-Apr-2013
04-Jun-2013
29-Aug-2013
03-AUG-13
21-AUG-13
24-SEP-13
02-SEP-13
29-OCT-13
12-OCT-13
03-DEC-13
27-DEC-13
27-JAN-14
10-Jun-2013
10-JUN-13
15-JUN-13
09-JUL-13
13-AUG-13
13-AUG-13
30-AUG-13
03-OCT-13
11-SEP-13
06-SEP-13
18-SEP-13
28-OCT-13
30-SEP-13
02-DEC-13
15-NOV-13
25-DEC-13
24-JAN-14
06-FEB-14
15-Feb-2014
14-JUN-13
08-JUL-13
12-AUG-13
16-SEP-13
16-SEP-13
27-SEP-13
06-NOV-13
09-OCT-13
-129d
-144d
-129d
-31d
-129d
-99d
-109d
-109d
-109d
-113d
-133d
-133d
-133d
-133d
-133d
-148d
-133d
-35d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z6-GRID A~E / 10~5
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00806
S2CON00807
S2CON00808
S2CON00809
S2CON00810
006
S2CON00812
S2CON00813
S2CON00814
S2CON00815
S2CON00816
S2CON00817
S2CON00818
S2CON00819
S2CON00820
S2CON00821
S2CON00822
S2CON00823
05-Jun-2013
24-Jun-2013
10-Jul-2013
27-Aug-2013
26-Sep-2013
01-Jan-2013
01-Jan-2013
14-Jan-2013
06-Feb-2013
13-Mar-2013
02-Feb-2013
11-Mar-2013
03-May-2013
08-Jun-2013
07-Jun-2013
26-Jun-2013
12-Jul-2013
23-Aug-2013
09-Jul-2013
27-Jul-2013
24-Aug-2013
24-Sep-2013
07-Oct-2013
27-Sep-2013
05-Jan-2013
05-Feb-2013
12-Mar-2013
16-Apr-2013
08-Mar-2013
08-Apr-2013
06-Jun-2013
24-Jul-2013
11-Jul-2013
30-Jul-2013
27-Aug-2013
20-Sep-2013
07-NOV-13
22-OCT-13
12-DEC-13
06-JAN-14
05-FEB-14
31-May-2013
31-MAY-13
13-JUN-13
06-JUL-13
10-AUG-13
03-JUL-13
08-AUG-13
01-OCT-13
03-AUG-13
05-NOV-13
19-OCT-13
10-DEC-13
28-DEC-13
11-DEC-13
25-NOV-13
03-JAN-14
03-FEB-14
15-FEB-14
01-Feb-2014
05-JUN-13
05-JUL-13
09-AUG-13
13-SEP-13
06-AUG-13
05-SEP-13
04-NOV-13
31-AUG-13
09-DEC-13
22-NOV-13
01-JAN-14
25-JAN-14
-133d
-103d
-113d
-113d
-113d
-109d
-129d
-129d
-129d
-129d
-129d
-129d
-129d
-33d
-129d
-99d
-109d
-109d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00824
007
S2CON2193
S2CON2194
S2CON2195
S2CON2196
S2CON2197
S2CON2198
S2CON2199
S2CON2200
S2CON2201
S2CON2202
S2CON2203
S2CON2204
S2CON2205
008
S2CON2207
S2CON2208
17-Sep-2013
22-Dec-2012
22-Dec-2012
04-Jan-2013
28-Jan-2013
04-Mar-2013
24-Jan-2013
01-Mar-2013
24-Apr-2013
30-May-2013
29-May-2013
17-Jun-2013
03-Jul-2013
14-Aug-2013
07-Sep-2013
09-Jan-2013
09-Jan-2013
22-Jan-2013
27-Sep-2013
18-Sep-2013
27-Dec-2012
26-Jan-2013
02-Mar-2013
06-Apr-2013
27-Feb-2013
29-Mar-2013
28-May-2013
15-Jul-2013
02-Jul-2013
20-Jul-2013
17-Aug-2013
11-Sep-2013
18-Sep-2013
05-Oct-2013
14-Jan-2013
13-Feb-2013
22-JAN-14
31-May-2013
31-MAY-13
13-JUN-13
06-JUL-13
10-AUG-13
03-JUL-13
08-AUG-13
01-OCT-13
02-SEP-13
05-NOV-13
19-OCT-13
10-DEC-13
28-DEC-13
22-JAN-14
12-Jun-2013
12-JUN-13
25-JUN-13
01-FEB-14
01-Feb-2014
05-JUN-13
05-JUL-13
09-AUG-13
13-SEP-13
06-AUG-13
05-SEP-13
04-NOV-13
30-SEP-13
09-DEC-13
22-NOV-13
01-JAN-14
25-JAN-14
01-FEB-14
13-Feb-2014
17-JUN-13
17-JUL-13
-109d
-117d
-137d
-137d
-137d
-137d
-137d
-137d
-137d
-66d
-137d
-107d
-117d
-117d
-117d
-112d
-132d
-132d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z2-GRID A~E / 21~15
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2209
S2CON2210
S2CON2211
S2CON2212
S2CON2213
S2CON2214
S2CON2215
S2CON2216
S2CON2217
S2CON2218
S2CON2219
002
S2CON00756
S2CON00757
S2CON00758
S2CON00759
S2CON00760
S2CON00761
14-Feb-2013
21-Mar-2013
11-Feb-2013
19-Mar-2013
11-May-2013
17-Jun-2013
15-Jun-2013
04-Jul-2013
20-Jul-2013
31-Aug-2013
25-Sep-2013
18-Dec-2012
18-Dec-2012
24-Dec-2012
16-Jan-2013
20-Feb-2013
20-Feb-2013
20-Feb-2013
20-Mar-2013
24-Apr-2013
16-Mar-2013
16-Apr-2013
14-Jun-2013
01-Aug-2013
19-Jul-2013
07-Aug-2013
04-Sep-2013
28-Sep-2013
05-Oct-2013
18-Sep-2013
22-Dec-2012
15-Jan-2013
19-Feb-2013
26-Mar-2013
26-Mar-2013
20-Mar-2013
18-JUL-13
22-AUG-13
15-JUL-13
20-AUG-13
12-OCT-13
02-SEP-13
16-NOV-13
31-OCT-13
21-DEC-13
09-JAN-14
03-FEB-14
31-May-2013
31-MAY-13
06-JUN-13
29-JUN-13
03-AUG-13
03-AUG-13
21-AUG-13
21-AUG-13
25-SEP-13
17-AUG-13
17-SEP-13
15-NOV-13
30-SEP-13
20-DEC-13
04-DEC-13
13-JAN-14
06-FEB-14
13-FEB-14
06-Feb-2014
05-JUN-13
28-JUN-13
02-AUG-13
06-SEP-13
06-SEP-13
18-SEP-13
-132d
-132d
-132d
-132d
-132d
-51d
-132d
-102d
-112d
-112d
-112d
-121d
-141d
-141d
-141d
-141d
-141d
-156d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00762
S2CON00763
S2CON00764
S2CON00765
S2CON00766
S2CON00767
S2CON00768
004
004
S2CON2515
S2CON2516
S2CON2517
S2CON2518
S2CON2519
S2CON2520
S2CON2521
S2CON2522
S2CON2523
12-Apr-2013
26-Jun-2013
17-May-2013
05-Jun-2013
21-Jun-2013
08-Aug-2013
07-Sep-2013
30-Jan-2013
27-Feb-2013
27-Feb-2013
11-Mar-2013
03-Apr-2013
08-May-2013
08-May-2013
12-Jun-2013
28-Jun-2013
11-Sep-2013
02-Aug-2013
16-May-2013
10-Aug-2013
20-Jun-2013
09-Jul-2013
06-Aug-2013
05-Sep-2013
18-Sep-2013
13-Dec-2013
04-Dec-2013
09-Mar-2013
02-Apr-2013
07-May-2013
11-Jun-2013
11-Jun-2013
10-Jul-2013
01-Aug-2013
26-Oct-2013
05-Sep-2013
24-SEP-13
02-SEP-13
29-OCT-13
16-NOV-13
03-DEC-13
27-DEC-13
27-JAN-14
31-May-2013
31-May-2013
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
11-NOV-13
16-NOV-13
28-OCT-13
30-SEP-13
02-DEC-13
20-DEC-13
25-DEC-13
24-JAN-14
06-FEB-14
27-Mar-2014
12-Feb-2014
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
09-DEC-13
20-DEC-13
-141d
-43d
-141d
-141d
-121d
-121d
-121d
-89d
-60d
-80d
-80d
-80d
-80d
-80d
-65d
-80d
-37d
-91d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Interior Works
11 Workstations
11 Chairs, Blinds and Carpets
11 Floor Cabling and Ceiling Fixes
10 Z5-GRID E~J / 10~5
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2524
S2CON2526
S2CON2527
S2CON2525
005
S2CON2459
S2CON2460
S2CON2461
S2CON2462
S2CON2463
S2CON2464
S2CON2465
S2CON2466
S2CON2467
S2CON2468
S2CON2469
S2CON2470
S2CON2471
21-Aug-2013
24-Oct-2013
23-Nov-2013
06-Sep-2013
04-Mar-2013
04-Mar-2013
15-Mar-2013
08-Apr-2013
13-May-2013
13-May-2013
17-Jun-2013
03-Jul-2013
16-Sep-2013
07-Aug-2013
26-Aug-2013
11-Sep-2013
29-Oct-2013
28-Nov-2013
24-Sep-2013
21-Nov-2013
04-Dec-2013
22-Oct-2013
09-Dec-2013
14-Mar-2013
06-Apr-2013
11-May-2013
15-Jun-2013
15-Jun-2013
15-Jul-2013
06-Aug-2013
31-Oct-2013
10-Sep-2013
28-Sep-2013
26-Oct-2013
26-Nov-2013
09-Dec-2013
22-NOV-13
02-JAN-14
01-FEB-14
09-DEC-13
31-May-2013
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
20-NOV-13
26-NOV-13
02-DEC-13
13-DEC-13
07-JAN-14
06-FEB-14
26-DEC-13
30-JAN-14
12-FEB-14
31-DEC-13
17-Feb-2014
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
18-DEC-13
30-DEC-13
04-JAN-14
04-JAN-14
04-FEB-14
17-FEB-14
-80d
-60d
-60d
-60d
-60d
-76d
-76d
-76d
-76d
-76d
-61d
-76d
-41d
-95d
-84d
-60d
-60d
-60d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
006
S2CON2445
S2CON2446
S2CON2447
S2CON2448
S2CON2449
S2CON2450
S2CON2451
S2CON2452
S2CON2453
S2CON2454
S2CON2455
S2CON2456
S2CON2457
007
S2CON2529
S2CON2530
S2CON2531
30-Jan-2013
30-Jan-2013
18-Feb-2013
13-Mar-2013
17-Apr-2013
09-Mar-2013
15-Apr-2013
07-Jun-2013
13-Jul-2013
12-Jul-2013
31-Jul-2013
16-Aug-2013
27-Sep-2013
22-Oct-2013
18-Feb-2013
18-Feb-2013
08-Mar-2013
01-Apr-2013
01-Nov-2013
09-Feb-2013
12-Mar-2013
16-Apr-2013
21-May-2013
12-Apr-2013
13-May-2013
11-Jul-2013
28-Aug-2013
15-Aug-2013
03-Sep-2013
01-Oct-2013
25-Oct-2013
01-Nov-2013
20-Nov-2013
28-Feb-2013
30-Mar-2013
04-May-2013
31-May-2013
31-MAY-13
19-JUN-13
12-JUL-13
16-AUG-13
18-JUL-13
14-AUG-13
07-OCT-13
12-OCT-13
11-NOV-13
25-OCT-13
16-DEC-13
03-JAN-14
28-JAN-14
31-May-2013
31-MAY-13
19-JUN-13
12-JUL-13
07-Feb-2014
11-JUN-13
11-JUL-13
15-AUG-13
19-SEP-13
21-AUG-13
11-SEP-13
09-NOV-13
09-NOV-13
14-DEC-13
28-NOV-13
07-JAN-14
31-JAN-14
07-FEB-14
07-Feb-2014
11-JUN-13
11-JUL-13
15-AUG-13
-84d
-104d
-104d
-104d
-104d
-112d
-104d
-104d
-63d
-104d
-74d
-84d
-84d
-84d
-68d
-88d
-88d
-88d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z8-GRID A~E / 5~1
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2532
S2CON2533
S2CON2534
S2CON2535
S2CON2536
S2CON2537
S2CON2538
S2CON2539
S2CON2540
S2CON2541
008
S2CON2543
S2CON2544
S2CON2545
S2CON2546
S2CON2547
S2CON2548
S2CON2549
06-May-2013
28-Mar-2013
03-May-2013
26-Jun-2013
01-Aug-2013
31-Jul-2013
19-Aug-2013
04-Sep-2013
16-Oct-2013
09-Nov-2013
13-Mar-2013
13-Mar-2013
01-Apr-2013
24-Apr-2013
29-May-2013
20-Apr-2013
27-May-2013
19-Jul-2013
08-Jun-2013
01-May-2013
31-May-2013
30-Jul-2013
16-Sep-2013
03-Sep-2013
21-Sep-2013
19-Oct-2013
13-Nov-2013
20-Nov-2013
13-Dec-2013
23-Mar-2013
23-Apr-2013
28-May-2013
02-Jul-2013
24-May-2013
24-Jun-2013
22-Aug-2013
16-AUG-13
18-JUL-13
14-AUG-13
07-OCT-13
11-NOV-13
16-NOV-13
22-NOV-13
16-DEC-13
03-JAN-14
28-JAN-14
31-May-2013
31-MAY-13
19-JUN-13
12-JUL-13
16-AUG-13
18-JUL-13
14-AUG-13
07-OCT-13
19-SEP-13
21-AUG-13
11-SEP-13
09-NOV-13
09-DEC-13
20-DEC-13
26-DEC-13
07-JAN-14
31-JAN-14
07-FEB-14
07-Feb-2014
11-JUN-13
11-JUL-13
15-AUG-13
19-SEP-13
21-AUG-13
11-SEP-13
09-NOV-13
-88d
-96d
-88d
-88d
-72d
-93d
-82d
-68d
-68d
-68d
-48d
-68d
-68d
-68d
-68d
-76d
-68d
-68d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2550
S2CON2551
S2CON2552
S2CON2553
S2CON2554
S2CON2555
001
S2CON2501
S2CON2502
S2CON2503
S2CON2504
S2CON2505
S2CON2506
S2CON2507
S2CON2508
S2CON2509
S2CON2510
S2CON2511
24-Aug-2013
23-Aug-2013
11-Sep-2013
27-Sep-2013
08-Nov-2013
03-Dec-2013
09-Feb-2013
09-Feb-2013
21-Feb-2013
16-Mar-2013
20-Apr-2013
20-Apr-2013
25-May-2013
11-Jun-2013
24-Aug-2013
16-Jul-2013
03-Aug-2013
20-Aug-2013
09-Oct-2013
26-Sep-2013
15-Oct-2013
12-Nov-2013
06-Dec-2013
13-Dec-2013
16-Nov-2013
20-Feb-2013
15-Mar-2013
19-Apr-2013
24-May-2013
24-May-2013
22-Jun-2013
15-Jul-2013
09-Oct-2013
19-Aug-2013
06-Sep-2013
04-Oct-2013
11-NOV-13
16-NOV-13
22-NOV-13
16-DEC-13
03-JAN-14
28-JAN-14
31-May-2013
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
28-DEC-13
03-JAN-14
09-JAN-14
21-JAN-14
09-DEC-13
20-DEC-13
26-DEC-13
07-JAN-14
31-JAN-14
07-FEB-14
27-Mar-2014
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
25-JAN-14
06-FEB-14
12-FEB-14
12-FEB-14
-52d
-73d
-62d
-48d
-48d
-48d
-112d
-95d
-95d
-95d
-95d
-95d
-80d
-95d
-93d
-147d
-136d
-112d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Workstations
11 Chairs, Blinds and Carpets
10 Z2-GRID A~E / 21~15
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z3-GRID E~J / 15~10
11 Clearance of the Floor after Structure
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2512
S2CON2513
002
S2CON2473
S2CON2474
S2CON2475
S2CON2476
S2CON2477
S2CON2478
S2CON2479
S2CON2480
S2CON2481
S2CON2482
S2CON2483
S2CON2484
S2CON2485
003
S2CON2487
07-Oct-2013
06-Nov-2013
13-Feb-2013
13-Feb-2013
25-Feb-2013
20-Mar-2013
24-Apr-2013
24-Apr-2013
29-May-2013
14-Jun-2013
28-Aug-2013
19-Jul-2013
07-Aug-2013
23-Aug-2013
10-Oct-2013
09-Nov-2013
23-Feb-2013
23-Feb-2013
04-Nov-2013
16-Nov-2013
20-Nov-2013
23-Feb-2013
19-Mar-2013
23-Apr-2013
28-May-2013
28-May-2013
26-Jun-2013
18-Jul-2013
12-Oct-2013
22-Aug-2013
10-Sep-2013
08-Oct-2013
07-Nov-2013
20-Nov-2013
30-Nov-2013
06-Mar-2013
14-FEB-14
17-MAR-14
31-May-2013
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
11-NOV-13
16-NOV-13
22-NOV-13
09-DEC-13
02-JAN-14
01-FEB-14
31-May-2013
31-MAY-13
14-MAR-14
27-MAR-14
12-Feb-2014
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
09-DEC-13
20-DEC-13
26-DEC-13
31-DEC-13
30-JAN-14
12-FEB-14
12-Feb-2014
11-JUN-13
-112d
-112d
-72d
-92d
-92d
-92d
-92d
-92d
-77d
-92d
-49d
-103d
-92d
-72d
-72d
-72d
-63d
-83d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
9 2F
10 Z1-GRID E~J / 21~15
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2488
S2CON2489
S2CON2490
S2CON2491
S2CON2492
S2CON2493
S2CON2494
S2CON2495
S2CON2496
S2CON2497
S2CON2498
S2CON2499
003
001
S2CON2389
S2CON2390
S2CON2391
S2CON2392
07-Mar-2013
30-Mar-2013
04-May-2013
04-May-2013
08-Jun-2013
25-Jun-2013
07-Sep-2013
30-Jul-2013
17-Aug-2013
03-Sep-2013
21-Oct-2013
20-Nov-2013
07-Jan-2013
11-Jan-2013
11-Jan-2013
23-Jan-2013
15-Feb-2013
22-Mar-2013
29-Mar-2013
03-May-2013
07-Jun-2013
07-Jun-2013
06-Jul-2013
29-Jul-2013
23-Oct-2013
02-Sep-2013
20-Sep-2013
18-Oct-2013
18-Nov-2013
30-Nov-2013
21-Nov-2013
22-Oct-2013
22-Jan-2013
14-Feb-2013
21-Mar-2013
25-Apr-2013
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
11-NOV-13
16-NOV-13
22-NOV-13
09-DEC-13
02-JAN-14
01-FEB-14
29-Apr-2013A
29-Apr-2013A
29-APR-13A
05-MAY-13A
24-JUN-13
29-JUL-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
09-DEC-13
20-DEC-13
26-DEC-13
31-DEC-13
30-JAN-14
12-FEB-14
04-Mar-2014
04-Mar-2014
09-MAY-13A
22-JUN-13
27-JUL-13
31-AUG-13
-83d
-83d
-83d
-83d
-68d
-83d
-40d
-94d
-83d
-63d
-63d
-63d
-88d
-114d
-92d
-110d
-110d
-110d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z2-GRID A~E / 21~15
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2393
S2CON2394
S2CON2395
S2CON2396
S2CON2397
S2CON2398
S2CON2399
S2CON2400
S2CON2401
002
S2CON2361
S2CON2362
S2CON2363
S2CON2364
S2CON2365
S2CON2366
S2CON2367
S2CON2368
22-Mar-2013
22-Mar-2013
13-May-2013
06-Sep-2013
17-Jun-2013
05-Jul-2013
22-Jul-2013
07-Sep-2013
08-Oct-2013
07-Jan-2013
07-Jan-2013
18-Jan-2013
11-Feb-2013
18-Mar-2013
18-Mar-2013
18-Mar-2013
08-May-2013
02-Sep-2013
25-Apr-2013
19-Apr-2013
15-Jun-2013
22-Oct-2013
20-Jul-2013
08-Aug-2013
05-Sep-2013
05-Oct-2013
18-Oct-2013
17-Oct-2013
17-Jan-2013
09-Feb-2013
16-Mar-2013
20-Apr-2013
20-Apr-2013
15-Apr-2013
11-Jun-2013
17-Oct-2013
29-JUL-13
15-AUG-13
18-SEP-13
05-DEC-13
11-DEC-13
17-DEC-13
28-DEC-13
22-JAN-14
21-FEB-14
29-Apr-2013A
29-APR-13A
10-MAY-13A
24-JUN-13
29-JUL-13
29-JUL-13
15-AUG-13
18-SEP-13
18-OCT-13
31-AUG-13
12-SEP-13
22-OCT-13
02-JAN-14
14-JAN-14
20-JAN-14
20-JAN-14
19-FEB-14
04-MAR-14
31-Jan-2014
09-MAY-13A
22-JUN-13
27-JUL-13
31-AUG-13
31-AUG-13
12-SEP-13
22-OCT-13
15-NOV-13
-110d
-125d
-110d
-62d
-152d
-141d
-117d
-117d
-117d
-91d
-96d
-114d
-114d
-114d
-114d
-129d
-114d
-25d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z3-GRID E~J / 15~10
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2369
S2CON2370
S2CON2371
S2CON2372
S2CON2373
003
S2CON2375
S2CON2376
S2CON2377
S2CON2378
S2CON2379
S2CON2380
S2CON2381
S2CON2382
S2CON2383
S2CON2384
S2CON2385
S2CON2386
12-Jun-2013
01-Jul-2013
17-Jul-2013
03-Sep-2013
03-Oct-2013
17-Jan-2013
17-Jan-2013
29-Jan-2013
21-Feb-2013
28-Mar-2013
28-Mar-2013
28-Mar-2013
18-May-2013
12-Sep-2013
22-Jun-2013
11-Jul-2013
27-Jul-2013
13-Sep-2013
16-Jul-2013
03-Aug-2013
31-Aug-2013
01-Oct-2013
14-Oct-2013
28-Oct-2013
28-Jan-2013
20-Feb-2013
27-Mar-2013
01-May-2013
01-May-2013
25-Apr-2013
21-Jun-2013
28-Oct-2013
26-Jul-2013
14-Aug-2013
11-Sep-2013
11-Oct-2013
24-OCT-13
30-OCT-13
27-NOV-13
21-DEC-13
21-JAN-14
29-Apr-2013A
29-APR-13A
10-MAY-13A
24-JUN-13
29-JUL-13
29-JUL-13
15-AUG-13
18-SEP-13
18-OCT-13
24-OCT-13
30-OCT-13
27-NOV-13
21-DEC-13
27-NOV-13
03-DEC-13
19-DEC-13
18-JAN-14
31-JAN-14
31-Jan-2014
09-MAY-13A
22-JUN-13
27-JUL-13
31-AUG-13
31-AUG-13
12-SEP-13
22-OCT-13
15-NOV-13
27-NOV-13
03-DEC-13
19-DEC-13
18-JAN-14
-115d
-104d
-94d
-94d
-94d
-82d
-87d
-105d
-105d
-105d
-105d
-120d
-105d
-16d
-106d
-95d
-85d
-85d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2387
004
S2CON2403
S2CON2404
S2CON2405
S2CON2406
S2CON2407
S2CON2408
S2CON2409
S2CON2410
S2CON2411
S2CON2412
S2CON2413
S2CON2414
S2CON2415
005
S2CON2347
S2CON2348
14-Oct-2013
21-Jan-2013
21-Jan-2013
01-Feb-2013
25-Feb-2013
01-Apr-2013
01-Apr-2013
01-Apr-2013
22-May-2013
16-Sep-2013
26-Jun-2013
15-Jul-2013
31-Jul-2013
17-Sep-2013
17-Oct-2013
25-Jan-2013
25-Jan-2013
06-Feb-2013
24-Oct-2013
31-Oct-2013
31-Jan-2013
23-Feb-2013
30-Mar-2013
04-May-2013
04-May-2013
29-Apr-2013
25-Jun-2013
31-Oct-2013
30-Jul-2013
17-Aug-2013
14-Sep-2013
15-Oct-2013
28-Oct-2013
05-Nov-2013
05-Feb-2013
28-Feb-2013
21-JAN-14
29-Apr-2013A
29-APR-13A
10-MAY-13A
24-JUN-13
29-JUL-13
29-JUL-13
15-AUG-13
18-SEP-13
18-OCT-13
24-OCT-13
30-OCT-13
27-NOV-13
21-DEC-13
21-JAN-14
10-May-2013A
10-MAY-13A
10-MAY-13A
31-JAN-14
31-Jan-2014
09-MAY-13A
22-JUN-13
27-JUL-13
31-AUG-13
31-AUG-13
12-SEP-13
22-OCT-13
15-NOV-13
27-NOV-13
03-DEC-13
19-DEC-13
18-JAN-14
31-JAN-14
12-Feb-2014
11-JUN-13
04-JUL-13
-85d
-79d
-84d
-102d
-102d
-102d
-102d
-117d
-102d
-13d
-103d
-92d
-82d
-82d
-82d
-85d
-108d
-108d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z6-GRID A~E / 10~5
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2349
S2CON2350
S2CON2351
S2CON2352
S2CON2353
S2CON2354
S2CON2355
S2CON2356
S2CON2357
S2CON2358
S2CON2359
006
S2CON2333
S2CON2334
S2CON2335
S2CON2336
S2CON2337
S2CON2338
01-Mar-2013
05-Apr-2013
05-Apr-2013
05-Apr-2013
27-May-2013
20-Sep-2013
01-Jul-2013
19-Jul-2013
05-Aug-2013
21-Sep-2013
22-Oct-2013
07-Jan-2013
07-Jan-2013
25-Jan-2013
18-Feb-2013
25-Mar-2013
14-Feb-2013
22-Mar-2013
04-Apr-2013
09-May-2013
09-May-2013
03-May-2013
29-Jun-2013
05-Nov-2013
03-Aug-2013
22-Aug-2013
19-Sep-2013
19-Oct-2013
01-Nov-2013
22-Oct-2013
17-Jan-2013
16-Feb-2013
23-Mar-2013
27-Apr-2013
20-Mar-2013
19-Apr-2013
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
28-OCT-13
04-NOV-13
08-NOV-13
09-DEC-13
02-JAN-14
01-FEB-14
10-May-2013A
10-MAY-13A
11-MAY-13A
12-JUL-13
16-AUG-13
18-JUL-13
14-AUG-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
25-NOV-13
07-DEC-13
12-DEC-13
31-DEC-13
30-JAN-14
12-FEB-14
07-Feb-2014
11-JUN-13
11-JUL-13
15-AUG-13
19-SEP-13
21-AUG-13
11-SEP-13
-108d
-108d
-108d
-123d
-108d
-17d
-108d
-96d
-88d
-88d
-88d
-93d
-124d
-124d
-124d
-124d
-132d
-124d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2339
S2CON2340
S2CON2341
S2CON2342
S2CON2343
S2CON2344
S2CON2345
007
S2CON2417
S2CON2418
S2CON2419
S2CON2420
S2CON2421
S2CON2422
S2CON2423
S2CON2424
S2CON2425
S2CON2426
15-May-2013
20-Jun-2013
19-Jun-2013
08-Jul-2013
06-Aug-2013
17-Sep-2013
11-Oct-2013
11-Jan-2013
11-Jan-2013
30-Jan-2013
22-Feb-2013
29-Mar-2013
19-Feb-2013
27-Mar-2013
20-May-2013
25-Jun-2013
24-Jun-2013
12-Jul-2013
18-Jun-2013
05-Aug-2013
23-Jul-2013
10-Aug-2013
20-Sep-2013
15-Oct-2013
22-Oct-2013
26-Oct-2013
22-Jan-2013
21-Feb-2013
28-Mar-2013
02-May-2013
25-Mar-2013
24-Apr-2013
22-Jun-2013
09-Aug-2013
27-Jul-2013
15-Aug-2013
07-OCT-13
19-SEP-13
11-NOV-13
25-OCT-13
16-DEC-13
03-JAN-14
28-JAN-14
10-May-2013A
10-MAY-13A
11-MAY-13A
12-JUL-13
16-AUG-13
18-JUL-13
14-AUG-13
07-OCT-13
18-OCT-13
11-NOV-13
30-OCT-13
09-NOV-13
17-OCT-13
14-DEC-13
28-NOV-13
07-JAN-14
31-JAN-14
07-FEB-14
07-Feb-2014
11-JUN-13
11-JUL-13
15-AUG-13
19-SEP-13
21-AUG-13
11-SEP-13
09-NOV-13
15-NOV-13
14-DEC-13
03-DEC-13
-124d
-63d
-124d
-94d
-93d
-93d
-93d
-89d
-120d
-120d
-120d
-120d
-128d
-120d
-120d
-84d
-120d
-94d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2427
S2CON2428
S2CON2429
008
S2CON2431
S2CON2432
S2CON2433
S2CON2434
S2CON2435
S2CON2436
S2CON2437
S2CON2438
S2CON2439
S2CON2440
S2CON2442
S2CON2443
S2CON2441
006
10-Aug-2013
21-Sep-2013
16-Oct-2013
06-Feb-2013
06-Feb-2013
25-Feb-2013
20-Mar-2013
24-Apr-2013
16-Mar-2013
22-Apr-2013
14-Jun-2013
20-Jul-2013
19-Jul-2013
07-Aug-2013
17-Oct-2013
11-Nov-2013
05-Sep-2013
22-Feb-2013
25-Sep-2013
19-Oct-2013
26-Oct-2013
21-Nov-2013
16-Feb-2013
19-Mar-2013
23-Apr-2013
28-May-2013
19-Apr-2013
20-May-2013
18-Jul-2013
04-Sep-2013
22-Aug-2013
10-Sep-2013
14-Nov-2013
21-Nov-2013
21-Oct-2013
29-Jan-2014
16-DEC-13
03-JAN-14
28-JAN-14
10-May-2013A
10-MAY-13A
12-MAY-13A
12-JUL-13
16-AUG-13
18-JUL-13
14-AUG-13
07-OCT-13
18-OCT-13
11-NOV-13
30-OCT-13
03-JAN-14
28-JAN-14
16-DEC-13
31-May-2013
07-JAN-14
31-JAN-14
07-FEB-14
07-Feb-2014
11-JUN-13
11-JUL-13
15-AUG-13
19-SEP-13
21-AUG-13
11-SEP-13
09-NOV-13
15-NOV-13
14-DEC-13
03-DEC-13
31-JAN-14
07-FEB-14
07-JAN-14
13-May-2014
-89d
-89d
-89d
-67d
-98d
-98d
-98d
-98d
-106d
-98d
-98d
-62d
-98d
-72d
-67d
-67d
-67d
-89d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
007
S2CON2753
S2CON2754
S2CON2755
S2CON2756
S2CON2757
S2CON2758
S2CON2759
S2CON2760
S2CON2761
S2CON2762
S2CON2763
S2CON2764
S2CON2765
008
S2CON2767
S2CON2768
S2CON2769
09-Apr-2013
09-Apr-2013
27-Apr-2013
21-May-2013
25-Jun-2013
17-May-2013
22-Jun-2013
15-Aug-2013
20-Sep-2013
19-Sep-2013
08-Oct-2013
24-Oct-2013
05-Dec-2013
30-Dec-2013
29-Apr-2013
29-Apr-2013
17-May-2013
10-Jun-2013
09-Jan-2014
19-Apr-2013
20-May-2013
24-Jun-2013
29-Jul-2013
20-Jun-2013
20-Jul-2013
18-Sep-2013
05-Nov-2013
23-Oct-2013
11-Nov-2013
09-Dec-2013
02-Jan-2014
09-Jan-2014
29-Jan-2014
09-May-2013
08-Jun-2013
13-Jul-2013
31-May-2013
31-MAY-13
19-JUN-13
12-JUL-13
16-AUG-13
18-JUL-13
14-AUG-13
07-OCT-13
27-DEC-13
02-JAN-14
08-JAN-14
20-JAN-14
07-FEB-14
04-MAR-14
31-May-2013
31-MAY-13
19-JUN-13
12-JUL-13
14-Mar-2014
11-JUN-13
11-JUL-13
15-AUG-13
19-SEP-13
21-AUG-13
11-SEP-13
09-NOV-13
24-JAN-14
05-FEB-14
11-FEB-14
11-FEB-14
07-MAR-14
14-MAR-14
14-Mar-2014
11-JUN-13
11-JUL-13
15-AUG-13
-55d
-45d
-45d
-45d
-45d
-53d
-45d
-45d
-69d
-90d
-79d
-55d
-55d
-55d
-38d
-28d
-28d
-28d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z4-GRID A~E / 15-10
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2770
S2CON2771
S2CON2772
S2CON2773
S2CON2774
S2CON2775
S2CON2776
S2CON2777
S2CON2778
S2CON2779
004
S2CON2739
S2CON2740
S2CON2741
S2CON2742
S2CON2743
S2CON2744
S2CON2745
15-Jul-2013
06-Jun-2013
12-Jul-2013
04-Sep-2013
10-Oct-2013
09-Oct-2013
28-Oct-2013
13-Nov-2013
25-Dec-2013
18-Jan-2014
19-Apr-2013
19-Apr-2013
01-May-2013
24-May-2013
28-Jun-2013
28-Jun-2013
28-Jun-2013
19-Aug-2013
17-Aug-2013
10-Jul-2013
09-Aug-2013
08-Oct-2013
25-Nov-2013
12-Nov-2013
30-Nov-2013
28-Dec-2013
22-Jan-2014
29-Jan-2014
24-Jan-2014
30-Apr-2013
23-May-2013
27-Jun-2013
01-Aug-2013
01-Aug-2013
26-Jul-2013
21-Sep-2013
16-AUG-13
18-JUL-13
14-AUG-13
07-OCT-13
27-DEC-13
02-JAN-14
08-JAN-14
20-JAN-14
07-FEB-14
04-MAR-14
31-May-2013
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
19-SEP-13
21-AUG-13
11-SEP-13
09-NOV-13
24-JAN-14
05-FEB-14
11-FEB-14
11-FEB-14
07-MAR-14
14-MAR-14
26-Mar-2014
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
-28d
-36d
-28d
-28d
-52d
-73d
-62d
-38d
-38d
-38d
-52d
-36d
-36d
-36d
-36d
-36d
-51d
-36d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2746
S2CON2747
S2CON2748
S2CON2749
S2CON2750
S2CON2751
001
S2CON2725
S2CON2726
S2CON2727
S2CON2728
S2CON2729
S2CON2730
S2CON2731
S2CON2732
S2CON2733
S2CON2734
S2CON2735
01-Nov-2013
23-Sep-2013
11-Oct-2013
28-Oct-2013
14-Dec-2013
14-Jan-2014
10-Apr-2013
10-Apr-2013
22-Apr-2013
15-May-2013
19-Jun-2013
19-Jun-2013
19-Jun-2013
09-Aug-2013
23-Oct-2013
13-Sep-2013
02-Oct-2013
18-Oct-2013
17-Dec-2013
26-Oct-2013
14-Nov-2013
12-Dec-2013
11-Jan-2014
24-Jan-2014
15-Jan-2014
20-Apr-2013
14-May-2013
18-Jun-2013
23-Jul-2013
23-Jul-2013
17-Jul-2013
12-Sep-2013
07-Dec-2013
17-Oct-2013
05-Nov-2013
03-Dec-2013
27-DEC-13
02-JAN-14
08-JAN-14
20-JAN-14
13-FEB-14
15-MAR-14
31-May-2013
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
13-FEB-14
19-FEB-14
25-FEB-14
08-MAR-14
24-JAN-14
05-FEB-14
11-FEB-14
11-FEB-14
13-MAR-14
26-MAR-14
13-May-2014
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
13-MAR-14
25-MAR-14
31-MAR-14
31-MAR-14
-33d
-87d
-76d
-52d
-52d
-52d
-101d
-44d
-44d
-44d
-44d
-44d
-59d
-44d
-82d
-136d
-125d
-101d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Workstations
11 Chairs, Blinds and Carpets
10 Z2-GRID A~E / 21~15
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z3-GRID E~J / 15~10
11 Clearance of the Floor after Structure
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2736
S2CON2737
002
S2CON2697
S2CON2698
S2CON2699
S2CON2700
S2CON2701
S2CON2702
S2CON2703
S2CON2704
S2CON2705
S2CON2706
S2CON2707
S2CON2708
S2CON2709
003
S2CON2711
05-Dec-2013
04-Jan-2014
05-Apr-2013
05-Apr-2013
17-Apr-2013
10-May-2013
14-Jun-2013
14-Jun-2013
14-Jun-2013
05-Aug-2013
18-Oct-2013
09-Sep-2013
27-Sep-2013
14-Oct-2013
30-Nov-2013
31-Dec-2013
16-Apr-2013
16-Apr-2013
02-Jan-2014
15-Jan-2014
10-Jan-2014
16-Apr-2013
09-May-2013
13-Jun-2013
18-Jul-2013
18-Jul-2013
12-Jul-2013
07-Sep-2013
03-Dec-2013
12-Oct-2013
31-Oct-2013
28-Nov-2013
28-Dec-2013
10-Jan-2014
21-Jan-2014
26-Apr-2013
02-APR-14
02-MAY-14
31-May-2013
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
27-DEC-13
02-JAN-14
08-JAN-14
20-JAN-14
13-FEB-14
15-MAR-14
31-May-2013
31-MAY-13
30-APR-14
13-MAY-14
26-Mar-2014
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
24-JAN-14
05-FEB-14
11-FEB-14
11-FEB-14
13-MAR-14
26-MAR-14
26-Mar-2014
11-JUN-13
-101d
-101d
-64d
-48d
-48d
-48d
-48d
-48d
-63d
-48d
-45d
-99d
-88d
-64d
-64d
-64d
-55d
-39d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z5-GRID E~J / 10~5
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2712
S2CON2713
S2CON2714
S2CON2715
S2CON2716
S2CON2717
S2CON2718
S2CON2719
S2CON2720
S2CON2721
S2CON2722
S2CON2723
005
S2CON2683
S2CON2684
S2CON2685
S2CON2686
S2CON2687
27-Apr-2013
21-May-2013
25-Jun-2013
25-Jun-2013
25-Jun-2013
15-Aug-2013
29-Oct-2013
19-Sep-2013
08-Oct-2013
24-Oct-2013
11-Dec-2013
10-Jan-2014
23-Apr-2013
23-Apr-2013
04-May-2013
28-May-2013
02-Jul-2013
02-Jul-2013
20-May-2013
24-Jun-2013
29-Jul-2013
29-Jul-2013
23-Jul-2013
18-Sep-2013
13-Dec-2013
23-Oct-2013
11-Nov-2013
09-Dec-2013
08-Jan-2014
21-Jan-2014
28-Jan-2014
03-May-2013
27-May-2013
01-Jul-2013
05-Aug-2013
05-Aug-2013
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
27-DEC-13
02-JAN-14
08-JAN-14
20-JAN-14
13-FEB-14
15-MAR-14
31-May-2013
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
24-JAN-14
05-FEB-14
11-FEB-14
11-FEB-14
13-MAR-14
26-MAR-14
04-Apr-2014
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
-39d
-39d
-39d
-39d
-54d
-39d
-36d
-90d
-79d
-55d
-55d
-55d
-57d
-33d
-33d
-33d
-33d
-33d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2688
S2CON2689
S2CON2690
S2CON2691
S2CON2692
S2CON2693
S2CON2694
S2CON2695
006
S2CON2669
S2CON2670
S2CON2671
S2CON2672
S2CON2673
S2CON2674
S2CON2675
S2CON2676
S2CON2677
02-Jul-2013
22-Aug-2013
05-Nov-2013
26-Sep-2013
15-Oct-2013
31-Oct-2013
18-Dec-2013
17-Jan-2014
22-Feb-2013
22-Feb-2013
13-Mar-2013
05-Apr-2013
10-May-2013
02-Apr-2013
08-May-2013
01-Jul-2013
06-Aug-2013
05-Aug-2013
30-Jul-2013
25-Sep-2013
20-Dec-2013
30-Oct-2013
18-Nov-2013
16-Dec-2013
15-Jan-2014
28-Jan-2014
25-Nov-2013
05-Mar-2013
04-Apr-2013
09-May-2013
13-Jun-2013
06-May-2013
05-Jun-2013
03-Aug-2013
20-Sep-2013
07-Sep-2013
27-AUG-13
30-SEP-13
06-JAN-14
11-JAN-14
17-JAN-14
29-JAN-14
22-FEB-14
25-MAR-14
05-Jun-2013
05-JUN-13
24-JUN-13
17-JUL-13
21-AUG-13
18-JUL-13
19-AUG-13
11-OCT-13
28-NOV-13
04-DEC-13
24-SEP-13
02-NOV-13
03-FEB-14
14-FEB-14
20-FEB-14
20-FEB-14
22-MAR-14
04-APR-14
13-Feb-2014
15-JUN-13
16-JUL-13
20-AUG-13
24-SEP-13
21-AUG-13
16-SEP-13
14-NOV-13
26-DEC-13
07-JAN-14
-48d
-33d
-38d
-92d
-81d
-57d
-57d
-57d
-69d
-88d
-88d
-88d
-88d
-92d
-88d
-88d
-83d
-104d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
9 4F
10 Z2-GRID A~E / 21~15
11 Workstations
11 Chairs, Blinds and Carpets
11 Floor Cabling and Ceiling Fixes
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2678
S2CON2679
S2CON2680
S2CON2681
005
002
S2CON2596
S2CON2597
S2CON2595
S2CON2585
S2CON2586
S2CON2587
S2CON2588
S2CON2589
S2CON2590
S2CON2591
S2CON2592
S2CON2593
23-Aug-2013
09-Sep-2013
21-Oct-2013
14-Nov-2013
14-Feb-2013
14-Mar-2013
08-Nov-2013
09-Dec-2013
21-Sep-2013
14-Mar-2013
26-Mar-2013
18-Apr-2013
23-May-2013
23-May-2013
23-May-2013
13-Jul-2013
26-Sep-2013
17-Aug-2013
26-Sep-2013
24-Oct-2013
18-Nov-2013
25-Nov-2013
09-Jan-2014
19-Dec-2013
06-Dec-2013
19-Dec-2013
06-Nov-2013
25-Mar-2013
17-Apr-2013
22-May-2013
26-Jun-2013
26-Jun-2013
20-Jun-2013
16-Aug-2013
11-Nov-2013
20-Sep-2013
10-DEC-13
21-DEC-13
09-JAN-14
03-FEB-14
31-May-2013
31-May-2013
21-JAN-14
20-FEB-14
27-DEC-13
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
04-DEC-13
10-DEC-13
13-JAN-14
13-JAN-14
06-FEB-14
13-FEB-14
19-Apr-2014
03-Mar-2014
18-FEB-14
03-MAR-14
18-JAN-14
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
01-JAN-14
13-JAN-14
-93d
-69d
-69d
-69d
-86d
-63d
-63d
-63d
-63d
-67d
-67d
-67d
-67d
-67d
-82d
-67d
-44d
-98d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Interior Works
10 Z3-GRID E~J / 15~10
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z4-GRID A~E / 15-10
11 Clearance of the Floor after Structure
11 Block Work
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2594
003
S2CON2599
S2CON2600
S2CON2601
S2CON2602
S2CON2603
S2CON2604
S2CON2605
S2CON2606
S2CON2607
S2CON2608
S2CON2609
S2CON2610
S2CON2611
004
S2CON2627
S2CON2628
05-Sep-2013
25-Mar-2013
25-Mar-2013
05-Apr-2013
29-Apr-2013
03-Jun-2013
03-Jun-2013
03-Jun-2013
24-Jul-2013
07-Oct-2013
28-Aug-2013
16-Sep-2013
02-Oct-2013
19-Nov-2013
19-Dec-2013
28-Mar-2013
28-Mar-2013
09-Apr-2013
09-Oct-2013
30-Dec-2013
04-Apr-2013
27-Apr-2013
01-Jun-2013
06-Jul-2013
06-Jul-2013
01-Jul-2013
27-Aug-2013
21-Nov-2013
01-Oct-2013
19-Oct-2013
16-Nov-2013
17-Dec-2013
30-Dec-2013
02-Jan-2014
08-Apr-2013
01-May-2013
16-DEC-13
31-May-2013
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
04-DEC-13
10-DEC-13
16-DEC-13
27-DEC-13
21-JAN-14
20-FEB-14
31-May-2013
31-MAY-13
12-JUN-13
18-JAN-14
03-Mar-2014
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
01-JAN-14
13-JAN-14
18-JAN-14
18-JAN-14
18-FEB-14
03-MAR-14
03-Mar-2014
11-JUN-13
04-JUL-13
-87d
-54d
-58d
-58d
-58d
-58d
-58d
-73d
-58d
-35d
-89d
-78d
-54d
-54d
-54d
-51d
-55d
-55d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
10 Z5-GRID E~J / 10~5
11 Clearance of the Floor after Structure
11 Block Work
11 Plastering
11 Painting
11 Race Ways
11 Screed Concrete & Tiling
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2629
S2CON2630
S2CON2631
S2CON2632
S2CON2633
S2CON2634
S2CON2635
S2CON2636
S2CON2637
S2CON2638
S2CON2639
005
S2CON2571
S2CON2572
S2CON2573
S2CON2574
S2CON2575
S2CON2576
02-May-2013
06-Jun-2013
06-Jun-2013
06-Jun-2013
27-Jul-2013
10-Oct-2013
31-Aug-2013
19-Sep-2013
05-Oct-2013
22-Nov-2013
23-Dec-2013
02-Apr-2013
02-Apr-2013
13-Apr-2013
07-May-2013
11-Jun-2013
11-Jun-2013
11-Jun-2013
05-Jun-2013
10-Jul-2013
10-Jul-2013
04-Jul-2013
30-Aug-2013
25-Nov-2013
04-Oct-2013
23-Oct-2013
20-Nov-2013
20-Dec-2013
02-Jan-2014
07-Jan-2014
12-Apr-2013
06-May-2013
10-Jun-2013
15-Jul-2013
15-Jul-2013
09-Jul-2013
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
30-SEP-13
04-DEC-13
10-DEC-13
16-DEC-13
27-DEC-13
21-JAN-14
20-FEB-14
31-May-2013
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
09-AUG-13
27-AUG-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
02-NOV-13
01-JAN-14
13-JAN-14
18-JAN-14
18-JAN-14
18-FEB-14
03-MAR-14
12-Mar-2014
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
12-SEP-13
24-SEP-13
-55d
-55d
-55d
-70d
-55d
-32d
-86d
-75d
-51d
-51d
-51d
-55d
-51d
-51d
-51d
-51d
-51d
-66d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2577
S2CON2578
S2CON2579
S2CON2580
S2CON2581
S2CON2582
S2CON2583
006
S2CON2557
S2CON2558
S2CON2559
S2CON2560
S2CON2561
S2CON2562
S2CON2563
S2CON2564
S2CON2565
S2CON2566
01-Aug-2013
15-Oct-2013
05-Sep-2013
24-Sep-2013
10-Oct-2013
27-Nov-2013
27-Dec-2013
14-Feb-2013
14-Feb-2013
05-Mar-2013
28-Mar-2013
02-May-2013
25-Mar-2013
30-Apr-2013
22-Jun-2013
29-Jul-2013
27-Jul-2013
15-Aug-2013
04-Sep-2013
29-Nov-2013
09-Oct-2013
28-Oct-2013
25-Nov-2013
25-Dec-2013
07-Jan-2014
16-Nov-2013
25-Feb-2013
27-Mar-2013
01-May-2013
05-Jun-2013
27-Apr-2013
28-May-2013
26-Jul-2013
12-Sep-2013
30-Aug-2013
18-Sep-2013
30-SEP-13
13-DEC-13
19-DEC-13
25-DEC-13
06-JAN-14
30-JAN-14
01-MAR-14
31-May-2013
31-MAY-13
19-JUN-13
12-JUL-13
16-AUG-13
18-JUL-13
14-AUG-13
07-OCT-13
05-NOV-13
11-NOV-13
16-NOV-13
02-NOV-13
10-JAN-14
22-JAN-14
28-JAN-14
28-JAN-14
27-FEB-14
12-MAR-14
07-Feb-2014
11-JUN-13
11-JUL-13
15-AUG-13
19-SEP-13
21-AUG-13
11-SEP-13
09-NOV-13
03-DEC-13
14-DEC-13
20-DEC-13
-51d
-36d
-90d
-79d
-55d
-55d
-55d
-71d
-91d
-91d
-91d
-91d
-99d
-91d
-91d
-70d
-91d
-80d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2567
S2CON2568
S2CON2569
007
S2CON2641
S2CON2642
S2CON2643
S2CON2644
S2CON2645
S2CON2646
S2CON2647
S2CON2648
S2CON2649
S2CON2650
S2CON2651
S2CON2652
S2CON2653
008
31-Aug-2013
12-Oct-2013
06-Nov-2013
19-Mar-2013
19-Mar-2013
06-Apr-2013
30-Apr-2013
04-Jun-2013
26-Apr-2013
01-Jun-2013
25-Jul-2013
30-Aug-2013
29-Aug-2013
17-Sep-2013
03-Oct-2013
14-Nov-2013
09-Dec-2013
09-Apr-2013
16-Oct-2013
09-Nov-2013
16-Nov-2013
19-Dec-2013
29-Mar-2013
29-Apr-2013
03-Jun-2013
08-Jul-2013
30-May-2013
29-Jun-2013
28-Aug-2013
15-Oct-2013
02-Oct-2013
21-Oct-2013
18-Nov-2013
12-Dec-2013
19-Dec-2013
09-Jan-2014
16-DEC-13
03-JAN-14
28-JAN-14
31-May-2013
31-MAY-13
19-JUN-13
12-JUL-13
16-AUG-13
18-JUL-13
14-AUG-13
07-OCT-13
04-DEC-13
10-DEC-13
16-DEC-13
27-DEC-13
15-JAN-14
08-FEB-14
31-May-2013
07-JAN-14
31-JAN-14
07-FEB-14
19-Feb-2014
11-JUN-13
11-JUL-13
15-AUG-13
19-SEP-13
21-AUG-13
11-SEP-13
09-NOV-13
01-JAN-14
13-JAN-14
18-JAN-14
18-JAN-14
12-FEB-14
19-FEB-14
19-Feb-2014
-71d
-71d
-71d
-53d
-63d
-63d
-63d
-63d
-71d
-63d
-63d
-67d
-88d
-77d
-53d
-53d
-53d
-35d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2655
S2CON2656
S2CON2657
S2CON2658
S2CON2659
S2CON2660
S2CON2661
S2CON2662
S2CON2663
S2CON2664
S2CON2665
S2CON2666
S2CON2667
001
S2CON2613
S2CON2614
S2CON2615
S2CON2616
09-Apr-2013
27-Apr-2013
21-May-2013
25-Jun-2013
17-May-2013
22-Jun-2013
15-Aug-2013
20-Sep-2013
19-Sep-2013
08-Oct-2013
24-Oct-2013
05-Dec-2013
30-Dec-2013
11-Mar-2013
11-Mar-2013
22-Mar-2013
15-Apr-2013
20-May-2013
19-Apr-2013
20-May-2013
24-Jun-2013
29-Jul-2013
20-Jun-2013
20-Jul-2013
18-Sep-2013
05-Nov-2013
23-Oct-2013
11-Nov-2013
09-Dec-2013
02-Jan-2014
09-Jan-2014
16-Dec-2013
21-Mar-2013
13-Apr-2013
18-May-2013
22-Jun-2013
31-MAY-13
19-JUN-13
12-JUL-13
16-AUG-13
18-JUL-13
14-AUG-13
07-OCT-13
04-DEC-13
10-DEC-13
16-DEC-13
27-DEC-13
15-JAN-14
08-FEB-14
31-May-2013
31-MAY-13
12-JUN-13
05-JUL-13
09-AUG-13
11-JUN-13
11-JUL-13
15-AUG-13
19-SEP-13
21-AUG-13
11-SEP-13
09-NOV-13
01-JAN-14
13-JAN-14
18-JAN-14
18-JAN-14
12-FEB-14
19-FEB-14
19-Apr-2014
11-JUN-13
04-JUL-13
08-AUG-13
12-SEP-13
-45d
-45d
-45d
-45d
-53d
-45d
-45d
-49d
-70d
-59d
-35d
-35d
-35d
-107d
-70d
-70d
-70d
-70d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
11 Race Ways
11 Screed Concrete & Tiling
11 Above False Ceiling Works
11 Facade Work (Erection)
11 False Ceiling
11 Interior Works
11 Floor Cabling and Ceiling Fixes
11 Workstations
11 Chairs, Blinds and Carpets
7 SUPERSTRUCTURE
8 4F (table form)
9 POUR-06 (GRID A-E / 10-5)
10 Starters for Columns
10 Staging for the Columns (1st Lift)
10 Rebar works for the Columns (1st Lift)
10 Form works for the Columns (1st Lift)
10 Concreting of the Columns (1st Lift)
10 Rebar works for the Columns (2nd Lift)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2617
S2CON2618
S2CON2619
S2CON2620
S2CON2621
S2CON2622
S2CON2623
S2CON2624
S2CON2625
1
005
006
S2CON1881
S2CON1882
S2CON1883
S2CON1884
S2CON1885
S2CON1886
20-May-2013
20-May-2013
10-Jul-2013
23-Sep-2013
14-Aug-2013
02-Sep-2013
18-Sep-2013
05-Nov-2013
05-Dec-2013
03-Nov-2012
18-Jan-2013
22-Jan-2013
22-Jan-2013
22-Jan-2013
23-Jan-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
22-Jun-2013
17-Jun-2013
13-Aug-2013
07-Nov-2013
17-Sep-2013
05-Oct-2013
02-Nov-2013
03-Dec-2013
16-Dec-2013
24-Sep-2013
30-Mar-2013
05-Feb-2013
22-Jan-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
28-Jan-2013
29-Jan-2013
09-AUG-13
27-AUG-13
30-SEP-13
21-JAN-14
27-JAN-14
01-FEB-14
13-FEB-14
10-MAR-14
09-APR-14
04-Dec-2012A
21-Mar-2013A
09-Apr-2013A
09-APR-13A
09-APR-13A
10-APR-13A
12-APR-13A
14-APR-13A
15-APR-13A
12-SEP-13
24-SEP-13
02-NOV-13
18-FEB-14
01-MAR-14
07-MAR-14
07-MAR-14
07-APR-14
19-APR-14
04-Oct-2013
31-May-2013
31-May-2013
09-APR-13A
11-APR-13A
11-APR-13A
13-APR-13A
14-APR-13A
15-APR-13A
-70d
-85d
-70d
-88d
-142d
-131d
-107d
-107d
-107d
-9d
-53d
-99d
-65d
-65d
-64d
-65d
-65d
-65d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1887
S2CON1888
S2CON1889
S2CON1890
S2CON1891
S2CON1892
004
S2CON1819
S2CON1820
S2CON1821
S2CON1822
S2CON1823
S2CON1824
S2CON1825
S2CON1826
S2CON1828
S2CON1829
S2CON1830
28-Jan-2013
29-Jan-2013
30-Jan-2013
31-Jan-2013
01-Feb-2013
05-Feb-2013
19-Feb-2013
19-Feb-2013
19-Feb-2013
20-Feb-2013
21-Feb-2013
22-Feb-2013
23-Feb-2013
25-Feb-2013
26-Feb-2013
14-Mar-2013
15-Mar-2013
19-Mar-2013
30-Jan-2013
31-Jan-2013
01-Feb-2013
02-Feb-2013
04-Feb-2013
05-Feb-2013
19-Mar-2013
19-Feb-2013
21-Feb-2013
22-Feb-2013
23-Feb-2013
25-Feb-2013
26-Feb-2013
27-Feb-2013
28-Feb-2013
16-Mar-2013
18-Mar-2013
19-Mar-2013
15-APR-13A
16-APR-13A
17-APR-13A
29-APR-13A
30-APR-13A
03-MAY-13A
05-Apr-2013A
05-APR-13A
06-APR-13A
08-APR-13A
08-APR-13A
11-APR-13A
12-APR-13A
12-APR-13A
15-APR-13A
17-APR-13A
18-APR-13A
23-APR-13A
17-APR-13A
18-APR-13A
04-MAY-13A
06-MAY-13A
09-MAY-13A
10-MAY-13A
31-May-2013
05-APR-13A
07-APR-13A
09-APR-13A
10-APR-13A
11-APR-13A
12-APR-13A
15-APR-13A
15-APR-13A
20-APR-13A
22-APR-13A
23-APR-13A
-66d
-66d
-79d
-78d
-80d
-80d
-63d
-38d
-38d
-38d
-38d
-38d
-38d
-39d
-39d
-30d
-29d
-29d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1827
005
S2CON1869
S2CON1870
S2CON1871
S2CON1872
S2CON1873
S2CON1874
S2CON1875
S2CON1876
S2CON1877
S2CON1878
S2CON1879
S2CON1880
010
S2CON3222
S2CON3223
S2CON3224
13-Mar-2013
23-Feb-2013
23-Feb-2013
23-Feb-2013
25-Feb-2013
26-Feb-2013
27-Feb-2013
28-Feb-2013
01-Mar-2013
02-Mar-2013
18-Mar-2013
19-Mar-2013
20-Mar-2013
23-Mar-2013
29-Jan-2013
08-Feb-2013
09-Feb-2013
11-Feb-2013
15-Mar-2013
23-Mar-2013
23-Feb-2013
26-Feb-2013
27-Feb-2013
28-Feb-2013
01-Mar-2013
02-Mar-2013
04-Mar-2013
05-Mar-2013
20-Mar-2013
21-Mar-2013
22-Mar-2013
23-Mar-2013
14-Feb-2013
11-Feb-2013
12-Feb-2013
13-Feb-2013
14-APR-13A
05-Apr-2013A
05-APR-13A
06-APR-13A
08-APR-13A
10-APR-13A
11-APR-13A
12-APR-13A
13-APR-13A
15-APR-13A
18-APR-13A
19-APR-13A
22-APR-13A
25-APR-13A
12-Apr-2013A
25-APR-13A
25-APR-13A
25-APR-13A
19-APR-13A
31-May-2013
05-APR-13A
07-APR-13A
09-APR-13A
11-APR-13A
11-APR-13A
12-APR-13A
15-APR-13A
15-APR-13A
19-APR-13A
21-APR-13A
26-APR-13A
25-APR-13A
31-May-2013
25-APR-13A
25-APR-13A
25-APR-13A
-29d
-59d
-34d
-34d
-34d
-35d
-34d
-34d
-35d
-35d
-26d
-26d
-30d
-27d
-91d
-62d
-61d
-60d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON3225
S2CON3226
S2CON3227
S2CON3228
S2CON3229
S2CON3230
S2CON3231
S2CON3232
009
S2CON3279
S2CON3280
S2CON3281
S2CON3282
S2CON3283
S2CON3284
S2CON3285
S2CON3286
S2CON3287
14-Feb-2013
29-Jan-2013
30-Jan-2013
31-Jan-2013
01-Feb-2013
02-Feb-2013
04-Feb-2013
06-Feb-2013
18-Jan-2013
29-Jan-2013
30-Jan-2013
31-Jan-2013
04-Feb-2013
18-Jan-2013
19-Jan-2013
21-Jan-2013
22-Jan-2013
23-Jan-2013
14-Feb-2013
31-Jan-2013
01-Feb-2013
02-Feb-2013
04-Feb-2013
05-Feb-2013
06-Feb-2013
08-Feb-2013
04-Feb-2013
31-Jan-2013
01-Feb-2013
02-Feb-2013
04-Feb-2013
21-Jan-2013
22-Jan-2013
23-Jan-2013
24-Jan-2013
25-Jan-2013
26-APR-13A
12-APR-13A
15-APR-13A
16-APR-13A
18-APR-13A
20-APR-13A
23-APR-13A
24-APR-13A
01-Apr-2013A
01-APR-13A
06-APR-13A
10-APR-13A
16-APR-13A
05-APR-13A
06-APR-13A
07-APR-13A
09-APR-13A
05-APR-13A
26-APR-13A
15-APR-13A
15-APR-13A
18-APR-13A
20-APR-13A
22-APR-13A
23-APR-13A
24-APR-13A
31-May-2013
11-APR-13A
15-APR-13A
16-APR-13A
17-APR-13A
07-APR-13A
08-APR-13A
09-APR-13A
11-APR-13A
07-APR-13A
-60d
-62d
-61d
-63d
-64d
-64d
-64d
-63d
-100d
-59d
-62d
-62d
-62d
-65d
-64d
-64d
-66d
-61d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Form works for the Lift & Shear Walls (2nd Lift)
10 Concreting of the Lift & Shear Walls (2nd Lift)
9 POUR-02 (GRID A-E / 21-15))
10 Starters for Columns
10 Staging for the Columns (1st Lift)
10 Rebar works for the Columns (1st Lift)
10 Form works for the Columns (1st Lift)
10 Concreting of the Columns (1st Lift)
10 Rebar works for the Columns (2nd Lift)
10 Form works for the Columns (2nd Lift)
10 Concreting of the Columns (2nd Lift)
10 Staging for the Slab
10 Form works for the slab
10 Rebar works for the slab
10 Concreting of the Slab
9 POUR-03 (GRID E-J / 15-10)
10 Starters for Columns
10 Staging for the Columns (1st Lift)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON3288
S2CON3289
002
S2CON1850
S2CON1851
S2CON1852
S2CON1853
S2CON1854
S2CON1855
S2CON1856
S2CON1857
S2CON1865
S2CON1866
S2CON1867
S2CON1868
003
S2CON1893
S2CON1894
24-Jan-2013
26-Jan-2013
05-Feb-2013
05-Feb-2013
05-Feb-2013
06-Feb-2013
07-Feb-2013
08-Feb-2013
09-Feb-2013
11-Feb-2013
12-Feb-2013
27-Feb-2013
28-Feb-2013
01-Mar-2013
05-Mar-2013
15-Feb-2013
15-Feb-2013
15-Feb-2013
26-Jan-2013
29-Jan-2013
05-Mar-2013
05-Feb-2013
07-Feb-2013
08-Feb-2013
09-Feb-2013
11-Feb-2013
12-Feb-2013
13-Feb-2013
14-Feb-2013
01-Mar-2013
02-Mar-2013
04-Mar-2013
05-Mar-2013
15-Mar-2013
15-Feb-2013
18-Feb-2013
07-APR-13A
10-APR-13A
27-Mar-2013A
27-MAR-13A
27-MAR-13A
28-MAR-13A
29-MAR-13A
01-APR-13A
02-APR-13A
29-MAR-13A
06-APR-13A
01-APR-13A
05-APR-13A
10-APR-13A
16-APR-13A
09-Apr-2013A
09-APR-13A
09-APR-13A
09-APR-13A
12-APR-13A
31-May-2013
27-MAR-13A
29-MAR-13A
30-MAR-13A
04-APR-13A
05-APR-13A
05-APR-13A
04-APR-13A
06-APR-13A
11-APR-13A
15-APR-13A
16-APR-13A
17-APR-13A
31-May-2013
09-APR-13A
11-APR-13A
-62d
-62d
-75d
-43d
-43d
-43d
-46d
-45d
-44d
-42d
-43d
-34d
-37d
-37d
-37d
-66d
-44d
-44d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1895
S2CON1896
S2CON1897
S2CON1898
S2CON1899
S2CON1900
S2CON1901
S2CON1902
S2CON1903
S2CON1904
007
S2CON1905
S2CON1906
S2CON1907
S2CON1908
S2CON1909
S2CON1910
S2CON1911
16-Feb-2013
18-Feb-2013
19-Feb-2013
20-Feb-2013
21-Feb-2013
22-Feb-2013
09-Mar-2013
11-Mar-2013
12-Mar-2013
15-Mar-2013
09-Feb-2013
09-Feb-2013
09-Feb-2013
11-Feb-2013
12-Feb-2013
13-Feb-2013
14-Feb-2013
15-Feb-2013
19-Feb-2013
20-Feb-2013
21-Feb-2013
22-Feb-2013
23-Feb-2013
25-Feb-2013
12-Mar-2013
13-Mar-2013
14-Mar-2013
15-Mar-2013
09-Mar-2013
09-Feb-2013
12-Feb-2013
13-Feb-2013
14-Feb-2013
15-Feb-2013
16-Feb-2013
18-Feb-2013
10-APR-13A
11-APR-13A
12-APR-13A
13-APR-13A
14-APR-13A
15-APR-13A
15-APR-13A
18-APR-13A
22-APR-13A
25-APR-13A
01-Apr-2013A
01-APR-13A
01-APR-13A
02-APR-13A
03-APR-13A
04-APR-13A
05-APR-13A
06-APR-13A
12-APR-13A
12-APR-13A
13-APR-13A
14-APR-13A
15-APR-13A
15-APR-13A
17-APR-13A
21-APR-13A
25-APR-13A
26-APR-13A
31-May-2013
02-APR-13A
03-APR-13A
04-APR-13A
04-APR-13A
06-APR-13A
08-APR-13A
09-APR-13A
-44d
-43d
-43d
-43d
-42d
-42d
-30d
-33d
-35d
-35d
-71d
-43d
-43d
-43d
-41d
-43d
-43d
-43d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1912
S2CON1920
S2CON1921
S2CON1922
S2CON1923
001
S2CON1831
S2CON1832
S2CON1833
S2CON1834
S2CON1835
S2CON1836
S2CON1837
S2CON1838
S2CON1839
S2CON1840
S2CON1841
S2CON1842
16-Feb-2013
04-Mar-2013
05-Mar-2013
06-Mar-2013
09-Mar-2013
01-Feb-2013
01-Feb-2013
01-Feb-2013
02-Feb-2013
04-Feb-2013
05-Feb-2013
06-Feb-2013
07-Feb-2013
08-Feb-2013
23-Feb-2013
25-Feb-2013
26-Feb-2013
01-Mar-2013
19-Feb-2013
06-Mar-2013
07-Mar-2013
08-Mar-2013
09-Mar-2013
01-Mar-2013
01-Feb-2013
04-Feb-2013
05-Feb-2013
06-Feb-2013
07-Feb-2013
08-Feb-2013
09-Feb-2013
11-Feb-2013
26-Feb-2013
27-Feb-2013
28-Feb-2013
01-Mar-2013
08-APR-13A
09-APR-13A
10-APR-13A
15-APR-13A
19-APR-13A
21-Mar-2013A
21-MAR-13A
21-MAR-13A
22-MAR-13A
23-MAR-13A
25-MAR-13A
26-MAR-13A
27-MAR-13A
28-MAR-13A
28-MAR-13A
31-MAR-13A
04-APR-13A
10-APR-13A
10-APR-13A
11-APR-13A
15-APR-13A
18-APR-13A
19-APR-13A
31-May-2013
21-MAR-13A
23-MAR-13A
25-MAR-13A
26-MAR-13A
27-MAR-13A
28-MAR-13A
29-MAR-13A
30-MAR-13A
05-APR-13A
07-APR-13A
09-APR-13A
11-APR-13A
-43d
-30d
-32d
-34d
-34d
-78d
-41d
-41d
-41d
-41d
-41d
-41d
-41d
-41d
-32d
-33d
-33d
-34d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
008
S2CON1924
S2CON1925
S2CON1926
S2CON1927
S2CON1928
S2CON1929
S2CON1930
S2CON1931
S2CON1939
S2CON1940
S2CON1941
S2CON1942
001
004
S2CON00285
S2CON00286
S2CON00287
05-Mar-2013
05-Mar-2013
05-Mar-2013
06-Mar-2013
07-Mar-2013
08-Mar-2013
11-Mar-2013
13-Mar-2013
15-Mar-2013
18-Mar-2013
21-Mar-2013
25-Mar-2013
30-Mar-2013
03-Nov-2012
08-Nov-2012
08-Nov-2012
08-Nov-2012
09-Nov-2012
30-Mar-2013
05-Mar-2013
07-Mar-2013
08-Mar-2013
09-Mar-2013
12-Mar-2013
14-Mar-2013
16-Mar-2013
19-Mar-2013
22-Mar-2013
26-Mar-2013
29-Mar-2013
30-Mar-2013
13-Dec-2012
05-Dec-2012
08-Nov-2012
10-Nov-2012
12-Nov-2012
11-Apr-2013A
11-APR-13A
15-APR-13A
16-APR-13A
17-APR-13A
17-APR-13A
18-APR-13A
19-APR-13A
21-APR-13A
22-APR-13A
22-APR-13A
23-APR-13A
26-APR-13A
04-Dec-2012A
07-Dec-2012A
07-DEC-12A
09-DEC-12A
10-DEC-12A
31-May-2013
12-APR-13A
17-APR-13A
18-APR-13A
19-APR-13A
19-APR-13A
19-APR-13A
20-APR-13A
22-APR-13A
24-APR-13A
24-APR-13A
25-APR-13A
26-APR-13A
31-May-2013
31-May-2013
13-JAN-13A
14-JAN-13A
15-JAN-13A
-53d
-32d
-35d
-35d
-35d
-33d
-30d
-29d
-28d
-27d
-24d
-23d
-22d
-145d
-152d
-56d
-54d
-54d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00288
S2CON00289
S2CON00290
S2CON00291
S2CON00292
S2CON00293
S2CON00294
S2CON00295
S2CON00296
006
S2CON00316
S2CON00317
S2CON00318
S2CON00319
S2CON00320
S2CON00321
S2CON00322
S2CON00323
10-Nov-2012
12-Nov-2012
13-Nov-2012
14-Nov-2012
15-Nov-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
05-Dec-2012
21-Nov-2012
21-Nov-2012
21-Nov-2012
22-Nov-2012
23-Nov-2012
24-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
13-Nov-2012
14-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
05-Dec-2012
21-Nov-2012
23-Nov-2012
24-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
29-Nov-2012
30-Nov-2012
11-DEC-12A
12-DEC-12A
18-DEC-12A
20-DEC-12A
22-DEC-12A
15-JAN-13A
17-JAN-13A
24-JAN-13A
28-JAN-13A
07-Dec-2012A
07-DEC-12A
08-DEC-12A
09-DEC-12A
10-DEC-12A
11-DEC-12A
18-DEC-12A
21-DEC-12A
22-DEC-12A
16-JAN-13A
17-JAN-13A
18-JAN-13A
18-JAN-13A
19-JAN-13A
25-JAN-13A
27-JAN-13A
27-JAN-13A
28-JAN-13A
31-May-2013
23-JAN-13A
24-JAN-13A
24-JAN-13A
25-JAN-13A
25-JAN-13A
27-JAN-13A
28-JAN-13A
29-JAN-13A
-54d
-54d
-54d
-53d
-53d
-46d
-47d
-46d
-45d
-152d
-53d
-52d
-51d
-51d
-50d
-51d
-50d
-50d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00324
S2CON00325
S2CON00326
S2CON00327
003
S2CON00273
S2CON00274
S2CON00275
S2CON00276
S2CON00277
S2CON00278
S2CON00279
S2CON00280
S2CON00281
S2CON00282
S2CON00283
S2CON00284
001
29-Nov-2012
30-Nov-2012
01-Dec-2012
05-Dec-2012
06-Nov-2012
06-Nov-2012
06-Nov-2012
07-Nov-2012
08-Nov-2012
09-Nov-2012
10-Nov-2012
12-Nov-2012
13-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
01-Dec-2012
03-Nov-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
01-Dec-2012
06-Nov-2012
08-Nov-2012
09-Nov-2012
10-Nov-2012
12-Nov-2012
13-Nov-2012
14-Nov-2012
15-Nov-2012
28-Nov-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
17-Nov-2012
15-JAN-13A
01-FEB-13A
05-FEB-13A
10-FEB-13A
06-Dec-2012A
06-DEC-12A
08-DEC-12A
10-DEC-12A
11-DEC-12A
13-DEC-12A
22-DEC-12A
24-DEC-12A
25-DEC-12A
02-JAN-13A
16-JAN-13A
20-JAN-13A
30-JAN-13A
04-Dec-2012A
05-FEB-13A
09-FEB-13A
10-FEB-13A
11-FEB-13A
31-May-2013
10-JAN-13A
11-JAN-13A
12-JAN-13A
13-JAN-13A
14-JAN-13A
15-JAN-13A
16-JAN-13A
17-JAN-13A
18-JAN-13A
20-JAN-13A
29-JAN-13A
30-JAN-13A
31-May-2013
-55d
-58d
-58d
-58d
-155d
-55d
-54d
-54d
-54d
-53d
-53d
-53d
-53d
-43d
-44d
-50d
-50d
-167d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00242
S2CON00243
S2CON00244
S2CON00245
S2CON00246
S2CON00247
S2CON00248
S2CON00249
S2CON00250
S2CON00251
S2CON00252
S2CON00253
005
S2CON00297
S2CON00298
S2CON00299
S2CON00300
S2CON00301
03-Nov-2012
03-Nov-2012
05-Nov-2012
06-Nov-2012
07-Nov-2012
08-Nov-2012
09-Nov-2012
10-Nov-2012
12-Nov-2012
13-Nov-2012
14-Nov-2012
17-Nov-2012
10-Nov-2012
10-Nov-2012
10-Nov-2012
12-Nov-2012
13-Nov-2012
14-Nov-2012
03-Nov-2012
06-Nov-2012
07-Nov-2012
08-Nov-2012
09-Nov-2012
10-Nov-2012
12-Nov-2012
13-Nov-2012
14-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
10-Dec-2012
10-Nov-2012
13-Nov-2012
14-Nov-2012
15-Nov-2012
16-Nov-2012
04-DEC-12A
04-DEC-12A
05-DEC-12A
06-DEC-12A
07-DEC-12A
08-DEC-12A
10-DEC-12A
11-DEC-12A
17-DEC-12A
21-DEC-12A
02-JAN-13A
11-JAN-13A
17-Dec-2012A
17-DEC-12A
18-DEC-12A
20-DEC-12A
21-DEC-12A
22-DEC-12A
20-DEC-12A
22-DEC-12A
23-DEC-12A
24-DEC-12A
25-DEC-12A
27-DEC-12A
27-DEC-12A
28-DEC-12A
08-JAN-13A
08-JAN-13A
10-JAN-13A
11-JAN-13A
31-May-2013
11-JAN-13A
12-JAN-13A
13-JAN-13A
14-JAN-13A
15-JAN-13A
-39d
-39d
-39d
-38d
-38d
-39d
-38d
-38d
-46d
-45d
-46d
-46d
-148d
-52d
-51d
-51d
-50d
-50d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00302
S2CON00303
S2CON00304
S2CON00312
S2CON00313
S2CON00314
S2CON00315
002
S2CON00254
S2CON00255
S2CON00256
S2CON00257
S2CON00258
S2CON00259
S2CON00260
S2CON00261
S2CON00269
S2CON00270
15-Nov-2012
16-Nov-2012
17-Nov-2012
04-Dec-2012
05-Dec-2012
06-Dec-2012
10-Dec-2012
07-Nov-2012
07-Nov-2012
07-Nov-2012
08-Nov-2012
09-Nov-2012
10-Nov-2012
12-Nov-2012
13-Nov-2012
14-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
19-Nov-2012
20-Nov-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
21-Nov-2012
07-Nov-2012
09-Nov-2012
10-Nov-2012
12-Nov-2012
13-Nov-2012
14-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
19-Nov-2012
26-DEC-12A
27-DEC-12A
28-DEC-12A
10-JAN-13A
19-JAN-13A
23-JAN-13A
01-FEB-13A
04-Dec-2012A
04-DEC-12A
05-DEC-12A
06-DEC-12A
07-DEC-12A
08-DEC-12A
10-DEC-12A
11-DEC-12A
12-DEC-12A
24-DEC-12A
28-DEC-12A
16-JAN-13A
17-JAN-13A
18-JAN-13A
25-JAN-13A
29-JAN-13A
30-JAN-13A
02-FEB-13A
31-May-2013
06-DEC-12A
07-DEC-12A
10-DEC-12A
11-DEC-12A
12-DEC-12A
12-DEC-12A
13-DEC-12A
14-DEC-12A
16-JAN-13A
18-JAN-13A
-50d
-50d
-50d
-42d
-45d
-44d
-46d
-164d
-24d
-23d
-24d
-24d
-24d
-23d
-23d
-23d
-50d
-51d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00271
S2CON00272
007
S2CON1333
S2CON1334
S2CON1335
S2CON1336
S2CON1337
S2CON1338
S2CON1339
S2CON1340
S2CON1348
S2CON1349
S2CON1350
S2CON1351
009
S2CON2908
S2CON2909
17-Nov-2012
21-Nov-2012
12-Nov-2012
12-Nov-2012
12-Nov-2012
13-Nov-2012
14-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
19-Nov-2012
20-Nov-2012
21-Nov-2012
22-Nov-2012
26-Nov-2012
07-Nov-2012
20-Nov-2012
21-Nov-2012
20-Nov-2012
21-Nov-2012
26-Nov-2012
12-Nov-2012
14-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
19-Nov-2012
20-Nov-2012
21-Nov-2012
22-Nov-2012
23-Nov-2012
24-Nov-2012
26-Nov-2012
26-Nov-2012
22-Nov-2012
23-Nov-2012
30-DEC-12A
20-JAN-13A
11-Dec-2012A
11-DEC-12A
12-DEC-12A
13-DEC-12A
14-DEC-12A
15-DEC-12A
17-DEC-12A
19-DEC-12A
21-DEC-12A
24-DEC-12A
10-JAN-13A
15-JAN-13A
23-JAN-13A
05-Dec-2012A
24-DEC-12A
28-DEC-12A
19-JAN-13A
20-JAN-13A
31-May-2013
08-JAN-13A
11-JAN-13A
13-JAN-13A
14-JAN-13A
15-JAN-13A
16-JAN-13A
17-JAN-13A
18-JAN-13A
18-JAN-13A
20-JAN-13A
22-JAN-13A
23-JAN-13A
31-May-2013
16-JAN-13A
18-JAN-13A
-51d
-51d
-160d
-48d
-49d
-50d
-49d
-49d
-49d
-49d
-49d
-49d
-49d
-49d
-49d
-160d
-46d
-47d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2910
S2CON2911
S2CON2895
S2CON2897
S2CON2899
S2CON2901
S2CON2903
S2CON2905
S2CON2907
S2CON2912
S2CON2913
S2CON2914
008
S2CON1352
S2CON1353
S2CON1354
S2CON1355
S2CON1356
22-Nov-2012
26-Nov-2012
07-Nov-2012
08-Nov-2012
09-Nov-2012
10-Nov-2012
12-Nov-2012
13-Nov-2012
15-Nov-2012
14-Nov-2012
16-Nov-2012
19-Nov-2012
29-Nov-2012
29-Nov-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
03-Dec-2012
24-Nov-2012
26-Nov-2012
09-Nov-2012
10-Nov-2012
12-Nov-2012
13-Nov-2012
14-Nov-2012
15-Nov-2012
17-Nov-2012
15-Nov-2012
17-Nov-2012
19-Nov-2012
13-Dec-2012
29-Nov-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
30-DEC-12A
20-JAN-13A
05-DEC-12A
06-DEC-12A
07-DEC-12A
08-DEC-12A
10-DEC-12A
11-DEC-12A
12-DEC-12A
24-DEC-12A
30-DEC-12A
20-JAN-13A
10-Dec-2012A
10-DEC-12A
12-DEC-12A
13-DEC-12A
15-DEC-12A
16-DEC-12A
19-JAN-13A
20-JAN-13A
07-DEC-12A
10-DEC-12A
11-DEC-12A
12-DEC-12A
12-DEC-12A
13-DEC-12A
14-DEC-12A
16-JAN-13A
19-JAN-13A
20-JAN-13A
31-May-2013
23-JAN-13A
24-JAN-13A
25-JAN-13A
25-JAN-13A
27-JAN-13A
-47d
-47d
-23d
-24d
-24d
-24d
-23d
-23d
-22d
-52d
-53d
-53d
-145d
-46d
-45d
-45d
-44d
-45d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1357
S2CON1358
S2CON1359
S2CON1367
S2CON1368
S2CON1369
S2CON1370
010
S2CON2924
S2CON2925
S2CON2926
S2CON2927
S2CON2928
S2CON2929
S2CON2930
S2CON2931
S2CON2932
S2CON2933
04-Dec-2012
05-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
13-Dec-2012
12-Nov-2012
30-Nov-2012
01-Dec-2012
03-Dec-2012
06-Dec-2012
12-Nov-2012
13-Nov-2012
14-Nov-2012
15-Nov-2012
24-Nov-2012
26-Nov-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
06-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
06-Dec-2012
14-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
27-Nov-2012
28-Nov-2012
18-DEC-12A
20-DEC-12A
24-DEC-12A
02-JAN-13A
21-JAN-13A
27-JAN-13A
02-FEB-13A
12-Dec-2012A
02-JAN-13A
21-JAN-13A
27-JAN-13A
02-FEB-13A
12-DEC-12A
13-DEC-12A
15-DEC-12A
16-DEC-12A
18-DEC-12A
20-DEC-12A
28-JAN-13A
29-JAN-13A
30-JAN-13A
30-JAN-13A
31-JAN-13A
01-FEB-13A
03-FEB-13A
31-May-2013
30-JAN-13A
31-JAN-13A
01-FEB-13A
03-FEB-13A
24-JAN-13A
25-JAN-13A
25-JAN-13A
27-JAN-13A
28-JAN-13A
29-JAN-13A
-44d
-44d
-44d
-44d
-43d
-43d
-44d
-151d
-49d
-49d
-49d
-50d
-60d
-60d
-59d
-60d
-52d
-52d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2934
S2CON2935
S2CON2936
S2CON2937
003
001
S2CON1583
S2CON1584
S2CON1585
S2CON1586
S2CON1587
S2CON1588
S2CON1589
S2CON1590
S2CON1591
S2CON1592
S2CON1593
S2CON1594
28-Nov-2012
19-Nov-2012
21-Nov-2012
23-Nov-2012
04-Dec-2012
04-Dec-2012
04-Dec-2012
04-Dec-2012
05-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
27-Dec-2012
28-Dec-2012
29-Dec-2012
02-Jan-2013
30-Nov-2012
20-Nov-2012
22-Nov-2012
23-Nov-2012
05-Feb-2013
02-Jan-2013
04-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
29-Dec-2012
31-Dec-2012
01-Jan-2013
02-Jan-2013
24-DEC-12A
02-JAN-13A
27-JAN-13A
02-FEB-13A
07-Feb-2013A
07-Feb-2013A
07-FEB-13A
08-FEB-13A
08-FEB-13A
08-FEB-13A
08-FEB-13A
08-FEB-13A
08-FEB-13A
08-FEB-13A
11-FEB-13A
19-FEB-13A
21-FEB-13A
24-FEB-13A
30-JAN-13A
30-JAN-13A
01-FEB-13A
03-FEB-13A
31-May-2013
31-May-2013
09-FEB-13A
12-FEB-13A
13-FEB-13A
14-FEB-13A
15-FEB-13A
13-FEB-13A
14-FEB-13A
15-FEB-13A
18-FEB-13A
22-FEB-13A
23-FEB-13A
24-FEB-13A
-51d
-60d
-60d
-61d
-99d
-128d
-57d
-57d
-57d
-57d
-57d
-54d
-54d
-54d
-42d
-45d
-45d
-45d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
007
S2CON1657
S2CON1658
S2CON1659
S2CON1660
S2CON1661
S2CON1662
S2CON1663
S2CON1664
S2CON1672
S2CON1673
S2CON1674
S2CON1675
010
S2CON3194
S2CON3195
S2CON3196
S2CON3197
12-Dec-2012
12-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
18-Dec-2012
19-Dec-2012
04-Jan-2013
05-Jan-2013
07-Jan-2013
10-Jan-2013
25-Dec-2012
04-Jan-2013
05-Jan-2013
07-Jan-2013
10-Jan-2013
10-Jan-2013
12-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
18-Dec-2012
19-Dec-2012
20-Dec-2012
21-Dec-2012
07-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
10-Jan-2013
07-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
18-Feb-2013A
18-FEB-13A
20-FEB-13A
23-FEB-13A
25-FEB-13A
26-FEB-13A
23-FEB-13A
25-FEB-13A
26-FEB-13A
03-MAR-13A
04-MAR-13A
05-MAR-13A
06-MAR-13A
18-Feb-2013A
03-MAR-13A
04-MAR-13A
05-MAR-13A
06-MAR-13A
31-May-2013
24-FEB-13A
26-FEB-13A
28-FEB-13A
01-MAR-13A
01-MAR-13A
02-MAR-13A
02-MAR-13A
03-MAR-13A
04-MAR-13A
05-MAR-13A
05-MAR-13A
06-MAR-13A
31-May-2013
04-MAR-13A
05-MAR-13A
05-MAR-13A
06-MAR-13A
-121d
-63d
-62d
-63d
-63d
-62d
-62d
-61d
-61d
-47d
-47d
-46d
-46d
-121d
-47d
-47d
-46d
-46d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON3198
S2CON3199
S2CON3200
S2CON3201
S2CON3202
S2CON3203
S2CON3204
002
S2CON1602
S2CON1603
S2CON1604
S2CON1605
S2CON1606
S2CON1607
S2CON1608
S2CON1609
S2CON1617
S2CON1618
25-Dec-2012
26-Dec-2012
27-Dec-2012
28-Dec-2012
29-Dec-2012
31-Dec-2012
02-Jan-2013
07-Dec-2012
07-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
31-Dec-2012
01-Jan-2013
27-Dec-2012
28-Dec-2012
29-Dec-2012
31-Dec-2012
01-Jan-2013
02-Jan-2013
04-Jan-2013
05-Jan-2013
07-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
02-Jan-2013
03-Jan-2013
18-FEB-13A
23-FEB-13A
26-FEB-13A
01-MAR-13A
02-MAR-13A
03-MAR-13A
04-MAR-13A
12-Feb-2013A
12-FEB-13A
14-FEB-13A
15-FEB-13A
18-FEB-13A
19-FEB-13A
20-FEB-13A
20-FEB-13A
20-FEB-13A
23-FEB-13A
26-FEB-13A
24-FEB-13A
26-FEB-13A
28-FEB-13A
01-MAR-13A
02-MAR-13A
03-MAR-13A
04-MAR-13A
31-May-2013
28-FEB-13A
28-FEB-13A
01-MAR-13A
02-MAR-13A
03-MAR-13A
03-MAR-13A
03-MAR-13A
04-MAR-13A
05-MAR-13A
05-MAR-13A
-50d
-50d
-51d
-51d
-51d
-51d
-49d
-125d
-70d
-68d
-68d
-68d
-68d
-67d
-66d
-65d
-52d
-51d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1619
S2CON1620
004
S2CON1571
S2CON1572
S2CON1573
S2CON1574
S2CON1575
S2CON1576
S2CON1577
S2CON1578
S2CON1579
S2CON1580
S2CON1581
S2CON1582
003
S2CON1645
S2CON1646
02-Jan-2013
05-Jan-2013
21-Dec-2012
21-Dec-2012
21-Dec-2012
22-Dec-2012
24-Dec-2012
25-Dec-2012
26-Dec-2012
27-Dec-2012
28-Dec-2012
14-Jan-2013
15-Jan-2013
16-Jan-2013
19-Jan-2013
18-Dec-2012
18-Dec-2012
18-Dec-2012
04-Jan-2013
05-Jan-2013
19-Jan-2013
21-Dec-2012
24-Dec-2012
25-Dec-2012
26-Dec-2012
27-Dec-2012
28-Dec-2012
29-Dec-2012
31-Dec-2012
16-Jan-2013
17-Jan-2013
18-Jan-2013
19-Jan-2013
16-Jan-2013
18-Dec-2012
20-Dec-2012
02-MAR-13A
04-MAR-13A
19-Feb-2013A
19-FEB-13A
21-FEB-13A
24-FEB-13A
26-FEB-13A
27-FEB-13A
24-FEB-13A
26-FEB-13A
27-FEB-13A
07-MAR-13A
08-MAR-13A
10-MAR-13A
12-MAR-13A
24-Feb-2013A
24-FEB-13A
26-FEB-13A
05-MAR-13A
06-MAR-13A
31-May-2013
28-FEB-13A
02-MAR-13A
03-MAR-13A
04-MAR-13A
05-MAR-13A
06-MAR-13A
06-MAR-13A
07-MAR-13A
08-MAR-13A
10-MAR-13A
11-MAR-13A
12-MAR-13A
31-May-2013
28-FEB-13A
01-MAR-13A
-50d
-50d
-113d
-59d
-59d
-58d
-57d
-57d
-57d
-56d
-56d
-43d
-44d
-43d
-43d
-116d
-62d
-61d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1647
S2CON1648
S2CON1649
S2CON1650
S2CON1651
S2CON1652
S2CON1653
S2CON1654
S2CON1655
S2CON1656
005
S2CON1621
S2CON1622
S2CON1623
S2CON1624
S2CON1625
S2CON1626
S2CON1627
19-Dec-2012
20-Dec-2012
21-Dec-2012
22-Dec-2012
24-Dec-2012
25-Dec-2012
10-Jan-2013
11-Jan-2013
12-Jan-2013
16-Jan-2013
26-Dec-2012
26-Dec-2012
26-Dec-2012
27-Dec-2012
28-Dec-2012
29-Dec-2012
31-Dec-2012
01-Jan-2013
21-Dec-2012
22-Dec-2012
24-Dec-2012
25-Dec-2012
26-Dec-2012
27-Dec-2012
12-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
24-Jan-2013
26-Dec-2012
28-Dec-2012
29-Dec-2012
31-Dec-2012
01-Jan-2013
02-Jan-2013
03-Jan-2013
26-FEB-13A
27-FEB-13A
03-MAR-13A
26-FEB-13A
27-FEB-13A
07-MAR-13A
08-MAR-13A
09-MAR-13A
11-MAR-13A
14-MAR-13A
24-Feb-2013A
24-FEB-13A
26-FEB-13A
26-FEB-13A
27-FEB-13A
01-MAR-13A
26-FEB-13A
27-FEB-13A
03-MAR-13A
04-MAR-13A
04-MAR-13A
05-MAR-13A
08-MAR-13A
09-MAR-13A
11-MAR-13A
12-MAR-13A
14-MAR-13A
15-MAR-13A
31-May-2013
28-FEB-13A
02-MAR-13A
04-MAR-13A
05-MAR-13A
06-MAR-13A
07-MAR-13A
08-MAR-13A
-61d
-60d
-59d
-59d
-62d
-62d
-49d
-49d
-49d
-49d
-109d
-55d
-55d
-55d
-55d
-55d
-55d
-55d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1628
S2CON1629
S2CON1630
S2CON1631
S2CON1632
008
S2CON1676
S2CON1677
S2CON1678
S2CON1679
S2CON1680
S2CON1681
S2CON1682
S2CON1683
S2CON1691
S2CON1692
S2CON1693
S2CON1694
02-Jan-2013
18-Jan-2013
19-Jan-2013
21-Jan-2013
24-Jan-2013
09-Jan-2013
09-Jan-2013
09-Jan-2013
10-Jan-2013
11-Jan-2013
14-Jan-2013
16-Jan-2013
18-Jan-2013
21-Jan-2013
23-Jan-2013
26-Jan-2013
30-Jan-2013
05-Feb-2013
04-Jan-2013
21-Jan-2013
22-Jan-2013
23-Jan-2013
24-Jan-2013
05-Feb-2013
09-Jan-2013
11-Jan-2013
12-Jan-2013
15-Jan-2013
17-Jan-2013
19-Jan-2013
22-Jan-2013
24-Jan-2013
28-Jan-2013
31-Jan-2013
04-Feb-2013
05-Feb-2013
03-MAR-13A
07-MAR-13A
11-MAR-13A
15-MAR-13A
18-MAR-13A
28-Feb-2013A
28-FEB-13A
28-FEB-13A
01-MAR-13A
02-MAR-13A
05-MAR-13A
07-MAR-13A
09-MAR-13A
12-MAR-13A
14-MAR-13A
16-MAR-13A
18-MAR-13A
20-MAR-13A
07-MAR-13A
09-MAR-13A
13-MAR-13A
17-MAR-13A
18-MAR-13A
31-May-2013
28-FEB-13A
02-MAR-13A
04-MAR-13A
06-MAR-13A
08-MAR-13A
10-MAR-13A
12-MAR-13A
13-MAR-13A
15-MAR-13A
17-MAR-13A
19-MAR-13A
20-MAR-13A
-52d
-41d
-43d
-45d
-44d
-99d
-43d
-43d
-43d
-43d
-43d
-42d
-41d
-40d
-39d
-38d
-36d
-36d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
009
S2CON3179
S2CON3180
S2CON3181
S2CON3182
S2CON3183
S2CON3184
S2CON3185
S2CON3186
S2CON3187
S2CON3188
S2CON3189
006
S2CON1633
S2CON1634
S2CON1635
S2CON1636
S2CON1637
14-Dec-2012
25-Dec-2012
26-Dec-2012
27-Dec-2012
31-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
18-Dec-2012
19-Dec-2012
20-Dec-2012
22-Dec-2012
21-Dec-2012
21-Dec-2012
21-Dec-2012
22-Dec-2012
24-Dec-2012
25-Dec-2012
31-Dec-2012
27-Dec-2012
28-Dec-2012
29-Dec-2012
31-Dec-2012
17-Dec-2012
18-Dec-2012
19-Dec-2012
20-Dec-2012
21-Dec-2012
22-Dec-2012
25-Dec-2012
05-Jan-2013
21-Dec-2012
24-Dec-2012
25-Dec-2012
26-Dec-2012
27-Dec-2012
14-Feb-2013A
23-FEB-13A
26-FEB-13A
02-MAR-13A
04-MAR-13A
14-FEB-13A
15-FEB-13A
18-FEB-13A
19-FEB-13A
20-FEB-13A
20-FEB-13A
20-FEB-13A
01-Mar-2013A
01-MAR-13A
01-MAR-13A
02-MAR-13A
04-MAR-13A
05-MAR-13A
31-May-2013
05-MAR-13A
05-MAR-13A
05-MAR-13A
06-MAR-13A
01-MAR-13A
02-MAR-13A
03-MAR-13A
03-MAR-13A
03-MAR-13A
03-MAR-13A
04-MAR-13A
31-May-2013
02-MAR-13A
05-MAR-13A
06-MAR-13A
07-MAR-13A
08-MAR-13A
-130d
-57d
-56d
-55d
-55d
-63d
-63d
-63d
-62d
-61d
-60d
-58d
-125d
-60d
-60d
-60d
-60d
-60d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1638
S2CON1639
S2CON1640
S2CON1641
S2CON1642
S2CON1643
S2CON1644
009
001
S2CON00707
S2CON00708
S2CON00709
S2CON00710
S2CON00711
S2CON00712
004
S2CON00728
S2CON00729
26-Dec-2012
27-Dec-2012
28-Dec-2012
31-Dec-2012
01-Jan-2013
02-Jan-2013
05-Jan-2013
28-Jan-2013
28-Jan-2013
28-Jan-2013
09-Mar-2013
19-Apr-2013
30-May-2013
10-Jul-2013
20-Aug-2013
22-Feb-2013
22-Feb-2013
29-Mar-2013
28-Dec-2012
29-Dec-2012
31-Dec-2012
02-Jan-2013
03-Jan-2013
04-Jan-2013
05-Jan-2013
09-Sep-2013
05-Sep-2013
13-Feb-2013
26-Mar-2013
06-May-2013
15-Jun-2013
26-Jul-2013
05-Sep-2013
29-Jul-2013
11-Mar-2013
15-Apr-2013
06-MAR-13A
07-MAR-13A
08-MAR-13A
09-MAR-13A
11-MAR-13A
12-MAR-13A
15-MAR-13A
01-Mar-2013A
31-May-2013
31-MAY-13
18-JUN-13
05-JUL-13
23-JUL-13
09-AUG-13
27-AUG-13
29-Apr-2013A
29-APR-13A
31-MAY-13
09-MAR-13A
11-MAR-13A
12-MAR-13A
13-MAR-13A
14-MAR-13A
15-MAR-13A
16-MAR-13A
12-Sep-2013
12-Sep-2013
17-JUN-13
04-JUL-13
22-JUL-13
08-AUG-13
26-AUG-13
12-SEP-13
08-Aug-2013
27-JUN-13A
17-JUN-13
-60d
-60d
-60d
-59d
-59d
-59d
-59d
-3d
-6d
-106d
-86d
-66d
-46d
-26d
-6d
-9d
-92d
-54d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Staircase from 2F ~ 3F
10 Staircase from 3f ~ 4F
10 Staircase from 4f ~ 5F
9 STAIRCASE B/N D~E & 18~19
10 Staircase from GF ~ 1F
10 Staircase from 1F ~ 2F
10 Staircase from 2F ~ 3F
10 Staircase from 3f ~ 4F
10 Staircase from 4f ~ 5F
10 Staircase from 5F ~ 6F
9 STAIRCASE B/N F~G & 9~10
10 Staircase from GF ~ 1F
10 Staircase from 1F ~ 2F
10 Staircase from 2F ~ 3F
9 STAIRCASE B/N E~F & 2~3
10 Staircase from GF ~ 1F
10 Staircase from 1F ~ 2F
10 Staircase from 2F ~ 3F
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00730
S2CON00731
S2CON00732
002
S2CON00714
S2CON00715
S2CON00716
S2CON00717
S2CON00718
S2CON00719
005
S2CON00735
S2CON00736
S2CON00737
003
S2CON00721
S2CON00722
S2CON00723
03-May-2013
07-Jun-2013
12-Jul-2013
31-Jan-2013
31-Jan-2013
13-Mar-2013
23-Apr-2013
03-Jun-2013
13-Jul-2013
23-Aug-2013
19-Feb-2013
19-Feb-2013
01-Apr-2013
11-May-2013
05-Feb-2013
05-Feb-2013
18-Mar-2013
27-Apr-2013
20-May-2013
24-Jun-2013
29-Jul-2013
09-Sep-2013
16-Feb-2013
29-Mar-2013
09-May-2013
19-Jun-2013
30-Jul-2013
09-Sep-2013
28-May-2013
07-Mar-2013
17-Apr-2013
28-May-2013
03-Aug-2013
21-Feb-2013
03-Apr-2013
14-May-2013
18-JUN-13
05-JUL-13
23-JUL-13
31-May-2013
31-MAY-13
18-JUN-13
05-JUL-13
23-JUL-13
09-AUG-13
27-AUG-13
01-Mar-2013A
01-MAR-13A
14-MAR-13A
01-APR-13A
29-Apr-2013A
29-APR-13A
31-MAY-13
18-JUN-13
04-JUL-13
22-JUL-13
08-AUG-13
12-Sep-2013
17-JUN-13
04-JUL-13
22-JUL-13
08-AUG-13
26-AUG-13
12-SEP-13
19-Jun-2013A
15-MAY-13A
01-JUN-13A
19-JUN-13A
08-Aug-2013
27-MAY-13A
17-JUN-13
04-JUL-13
-39d
-24d
-9d
-3d
-103d
-83d
-63d
-43d
-23d
-3d
-19d
-59d
-39d
-19d
-4d
-80d
-64d
-44d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Staircase from 3f ~ 4F
10 Staircase from 4f ~ 5F
8 5F (table form)
9 POUR-04 (GRID A-E / 15-10)
10 Starters for Columns
10 Staging for the Columns (1st Lift)
10 Rebar works for the Columns (1st Lift)
10 Form works for the Columns (1st Lift)
10 Concreting of the Columns (1st Lift)
10 Rebar works for the Columns (2nd Lift)
10 Form works for the Columns (2nd Lift)
10 Concreting of the Columns (2nd Lift)
10 Staging for the Slab
10 Form works for the slab
10 Rebar works for the slab
10 Concreting of the Slab
9 POUR-08 (GRID A-E / 5-1)
10 Starters for Columns
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00724
S2CON00725
006
004
S2CON1943
S2CON1944
S2CON1945
S2CON1946
S2CON1947
S2CON1948
S2CON1949
S2CON1950
S2CON1951
S2CON1952
S2CON1953
S2CON1954
008
S2CON2048
07-Jun-2013
18-Jul-2013
05-Feb-2013
20-Mar-2013
20-Mar-2013
20-Mar-2013
21-Mar-2013
22-Mar-2013
23-Mar-2013
25-Mar-2013
26-Mar-2013
27-Mar-2013
12-Apr-2013
13-Apr-2013
15-Apr-2013
18-Apr-2013
01-Apr-2013
01-Apr-2013
24-Jun-2013
03-Aug-2013
27-Apr-2013
18-Apr-2013
20-Mar-2013
22-Mar-2013
23-Mar-2013
25-Mar-2013
26-Mar-2013
27-Mar-2013
28-Mar-2013
29-Mar-2013
15-Apr-2013
16-Apr-2013
17-Apr-2013
18-Apr-2013
27-Apr-2013
01-Apr-2013
05-JUL-13
23-JUL-13
13-Apr-2013A
22-Apr-2013A
22-APR-13A
22-APR-13A
23-APR-13A
24-APR-13A
25-APR-13A
23-APR-13A
26-APR-13A
29-APR-13A
06-MAY-13A
09-MAY-13A
10-MAY-13A
18-MAY-13A
29-Apr-2013A
29-APR-13A
22-JUL-13
08-AUG-13
04-Jun-2013
31-May-2013
23-APR-13A
24-APR-13A
25-APR-13A
25-APR-13A
26-APR-13A
25-APR-13A
03-MAY-13A
06-MAY-13A
15-MAY-13A
16-MAY-13A
18-MAY-13A
19-MAY-13A
31-May-2013
29-APR-13A
-24d
-4d
-32d
-37d
-29d
-27d
-27d
-26d
-26d
-24d
-30d
-31d
-26d
-26d
-26d
-26d
-29d
-24d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2049
S2CON2050
S2CON2051
S2CON2052
S2CON2053
S2CON2054
S2CON2055
S2CON2063
S2CON2064
S2CON2065
S2CON2066
005
S2CON1993
S2CON1994
S2CON1995
S2CON1996
S2CON1997
S2CON1998
01-Apr-2013
03-Apr-2013
05-Apr-2013
06-Apr-2013
08-Apr-2013
10-Apr-2013
12-Apr-2013
15-Apr-2013
18-Apr-2013
22-Apr-2013
27-Apr-2013
25-Mar-2013
25-Mar-2013
25-Mar-2013
26-Mar-2013
27-Mar-2013
28-Mar-2013
29-Mar-2013
04-Apr-2013
06-Apr-2013
08-Apr-2013
09-Apr-2013
11-Apr-2013
13-Apr-2013
16-Apr-2013
19-Apr-2013
23-Apr-2013
26-Apr-2013
27-Apr-2013
22-Apr-2013
25-Mar-2013
27-Mar-2013
28-Mar-2013
29-Mar-2013
30-Mar-2013
01-Apr-2013
29-APR-13A
01-MAY-13A
03-MAY-13A
04-MAY-13A
03-MAY-13A
03-MAY-13A
04-MAY-13A
10-MAY-13A
14-MAY-13A
17-MAY-13A
21-MAY-13A
29-Apr-2013A
29-APR-13A
29-APR-13A
30-APR-13A
01-MAY-13A
02-MAY-13A
03-MAY-13A
02-MAY-13A
04-MAY-13A
06-MAY-13A
07-MAY-13A
09-MAY-13A
11-MAY-13A
14-MAY-13A
17-MAY-13A
21-MAY-13A
24-MAY-13A
25-MAY-13A
31-May-2013
29-APR-13A
01-MAY-13A
02-MAY-13A
03-MAY-13A
04-MAY-13A
06-MAY-13A
-24d
-24d
-24d
-24d
-24d
-24d
-24d
-24d
-24d
-24d
-24d
-34d
-30d
-30d
-30d
-30d
-30d
-30d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1999
S2CON2000
S2CON2001
S2CON2002
S2CON2003
S2CON2004
009
S2CON3294
S2CON3295
S2CON3296
S2CON3297
S2CON3298
S2CON3299
S2CON3300
S2CON3301
S2CON3302
S2CON3303
S2CON3304
30-Mar-2013
01-Apr-2013
16-Apr-2013
17-Apr-2013
18-Apr-2013
22-Apr-2013
05-Feb-2013
15-Feb-2013
16-Feb-2013
18-Feb-2013
21-Feb-2013
05-Feb-2013
06-Feb-2013
07-Feb-2013
08-Feb-2013
09-Feb-2013
11-Feb-2013
13-Feb-2013
02-Apr-2013
03-Apr-2013
18-Apr-2013
19-Apr-2013
20-Apr-2013
22-Apr-2013
21-Feb-2013
18-Feb-2013
19-Feb-2013
20-Feb-2013
21-Feb-2013
07-Feb-2013
08-Feb-2013
09-Feb-2013
11-Feb-2013
12-Feb-2013
13-Feb-2013
15-Feb-2013
04-MAY-13A
06-MAY-13A
09-MAY-13A
13-MAY-13A
15-MAY-13A
18-MAY-13A
19-Apr-2013A
01-MAY-13A
02-MAY-13A
03-MAY-13A
07-MAY-13A
19-APR-13A
20-APR-13A
22-APR-13A
23-APR-13A
24-APR-13A
25-APR-13A
29-APR-13A
07-MAY-13A
08-MAY-13A
17-MAY-13A
18-MAY-13A
20-MAY-13A
21-MAY-13A
31-May-2013
03-MAY-13A
04-MAY-13A
06-MAY-13A
07-MAY-13A
22-APR-13A
23-APR-13A
24-APR-13A
25-APR-13A
26-APR-13A
29-APR-13A
01-MAY-13A
-30d
-30d
-25d
-25d
-25d
-25d
-85d
-64d
-64d
-64d
-64d
-63d
-63d
-63d
-63d
-63d
-63d
-64d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
007
S2CON2029
S2CON2030
S2CON2031
S2CON2032
S2CON2033
S2CON2034
S2CON2035
S2CON2036
S2CON2044
S2CON2045
S2CON2046
S2CON2047
001
S2CON1955
S2CON1956
S2CON1957
S2CON1958
11-Mar-2013
11-Mar-2013
11-Mar-2013
12-Mar-2013
13-Mar-2013
14-Mar-2013
15-Mar-2013
16-Mar-2013
18-Mar-2013
02-Apr-2013
03-Apr-2013
04-Apr-2013
08-Apr-2013
02-Mar-2013
02-Mar-2013
02-Mar-2013
04-Mar-2013
05-Mar-2013
08-Apr-2013
11-Mar-2013
13-Mar-2013
14-Mar-2013
15-Mar-2013
16-Mar-2013
18-Mar-2013
19-Mar-2013
20-Mar-2013
04-Apr-2013
05-Apr-2013
06-Apr-2013
08-Apr-2013
01-Apr-2013
02-Mar-2013
05-Mar-2013
06-Mar-2013
07-Mar-2013
22-Apr-2013A
22-APR-13A
23-APR-13A
24-APR-13A
25-APR-13A
26-APR-13A
27-APR-13A
29-APR-13A
30-APR-13A
01-MAY-13A
02-MAY-13A
03-MAY-13A
07-MAY-13A
13-Apr-2013A
13-APR-13A
15-APR-13A
16-APR-13A
17-APR-13A
31-May-2013
22-APR-13A
24-APR-13A
25-APR-13A
26-APR-13A
26-APR-13A
29-APR-13A
01-MAY-13A
02-MAY-13A
03-MAY-13A
05-MAY-13A
09-MAY-13A
10-MAY-13A
31-May-2013
15-APR-13A
16-APR-13A
17-APR-13A
18-APR-13A
-46d
-35d
-35d
-35d
-35d
-34d
-35d
-37d
-37d
-25d
-25d
-27d
-27d
-52d
-36d
-35d
-35d
-35d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1959
S2CON1960
S2CON1961
S2CON1962
S2CON1963
S2CON1964
S2CON1965
S2CON1966
010
S2CON3236
S2CON3237
S2CON3238
S2CON3239
S2CON3240
S2CON3241
S2CON3242
S2CON3243
S2CON3244
06-Mar-2013
07-Mar-2013
08-Mar-2013
09-Mar-2013
26-Mar-2013
27-Mar-2013
28-Mar-2013
01-Apr-2013
15-Feb-2013
26-Feb-2013
27-Feb-2013
28-Feb-2013
04-Mar-2013
15-Feb-2013
16-Feb-2013
18-Feb-2013
19-Feb-2013
20-Feb-2013
08-Mar-2013
09-Mar-2013
11-Mar-2013
12-Mar-2013
28-Mar-2013
29-Mar-2013
30-Mar-2013
01-Apr-2013
04-Mar-2013
28-Feb-2013
01-Mar-2013
02-Mar-2013
04-Mar-2013
18-Feb-2013
19-Feb-2013
20-Feb-2013
21-Feb-2013
22-Feb-2013
18-APR-13A
16-APR-13A
17-APR-13A
18-APR-13A
23-APR-13A
19-APR-13A
20-APR-13A
29-APR-13A
29-Apr-2013A
09-MAY-13A
10-MAY-13A
11-MAY-13A
15-MAY-13A
29-APR-13A
30-APR-13A
01-MAY-13A
02-MAY-13A
03-MAY-13A
19-APR-13A
17-APR-13A
18-APR-13A
19-APR-13A
23-APR-13A
23-APR-13A
03-MAY-13A
03-MAY-13A
31-May-2013
13-MAY-13A
14-MAY-13A
15-MAY-13A
21-MAY-13A
01-MAY-13A
02-MAY-13A
03-MAY-13A
04-MAY-13A
06-MAY-13A
-35d
-32d
-32d
-32d
-21d
-20d
-28d
-27d
-76d
-63d
-63d
-63d
-66d
-62d
-62d
-62d
-62d
-62d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Form works for the Lift & Shear Walls (2nd Lift)
10 Concreting of the Lift & Shear Walls (2nd Lift)
9 POUR-03 (GRID E-J / 15-10)
10 Starters for Columns
10 Staging for the Columns (1st Lift)
10 Rebar works for the Columns (1st Lift)
10 Form works for the Columns (1st Lift)
10 Concreting of the Columns (1st Lift)
10 Rebar works for the Columns (2nd Lift)
10 Form works for the Columns (2nd Lift)
10 Concreting of the Columns (2nd Lift)
10 Staging for the Slab
10 Form works for the slab
10 Rebar works for the slab
10 Concreting of the Slab
9 POUR-06 (GRID A-E / 10-5)
10 Starters for Columns
10 Staging for the Columns (1st Lift)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON3245
S2CON3246
003
S2CON2017
S2CON2018
S2CON2019
S2CON2020
S2CON2021
S2CON2022
S2CON2023
S2CON2024
S2CON2025
S2CON2026
S2CON2027
S2CON2028
006
S2CON2005
S2CON2006
21-Feb-2013
23-Feb-2013
16-Mar-2013
16-Mar-2013
16-Mar-2013
18-Mar-2013
19-Mar-2013
20-Mar-2013
21-Mar-2013
22-Mar-2013
23-Mar-2013
09-Apr-2013
10-Apr-2013
11-Apr-2013
15-Apr-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
23-Feb-2013
26-Feb-2013
15-Apr-2013
16-Mar-2013
19-Mar-2013
20-Mar-2013
21-Mar-2013
22-Mar-2013
23-Mar-2013
25-Mar-2013
26-Mar-2013
11-Apr-2013
12-Apr-2013
13-Apr-2013
15-Apr-2013
21-Feb-2013
06-Feb-2013
08-Feb-2013
04-MAY-13A
07-MAY-13A
29-Apr-2013A
29-APR-13A
29-APR-13A
30-APR-13A
01-MAY-13A
02-MAY-13A
03-MAY-13A
04-MAY-13A
06-MAY-13A
07-MAY-13A
08-MAY-13A
09-MAY-13A
13-MAY-13A
04-May-2013A
04-MAY-13A
04-MAY-13A
07-MAY-13A
09-MAY-13A
31-May-2013
29-APR-13A
01-MAY-13A
02-MAY-13A
03-MAY-13A
04-MAY-13A
06-MAY-13A
07-MAY-13A
08-MAY-13A
11-MAY-13A
15-MAY-13A
16-MAY-13A
18-MAY-13A
04-Jun-2013
17-MAY-13A
21-MAY-13A
-62d
-62d
-40d
-37d
-37d
-37d
-37d
-37d
-37d
-37d
-37d
-25d
-27d
-27d
-28d
-88d
-85d
-87d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2007
S2CON2008
S2CON2009
S2CON2010
S2CON2011
S2CON2012
S2CON2013
S2CON2014
S2CON2015
S2CON2016
002
S2CON1974
S2CON1975
S2CON1976
S2CON1977
S2CON1978
S2CON1979
S2CON1980
07-Feb-2013
08-Feb-2013
09-Feb-2013
11-Feb-2013
12-Feb-2013
13-Feb-2013
15-Feb-2013
16-Feb-2013
18-Feb-2013
21-Feb-2013
06-Mar-2013
06-Mar-2013
06-Mar-2013
07-Mar-2013
08-Mar-2013
09-Mar-2013
11-Mar-2013
12-Mar-2013
09-Feb-2013
11-Feb-2013
12-Feb-2013
13-Feb-2013
14-Feb-2013
15-Feb-2013
18-Feb-2013
19-Feb-2013
20-Feb-2013
21-Feb-2013
04-Apr-2013
06-Mar-2013
08-Mar-2013
09-Mar-2013
11-Mar-2013
12-Mar-2013
13-Mar-2013
14-Mar-2013
06-MAY-13A
07-MAY-13A
08-MAY-13A
09-MAY-13A
10-MAY-13A
11-MAY-13A
13-MAY-13A
14-MAY-13A
25-MAY-13A
04-JUN-13
17-Apr-2013A
17-APR-13A
17-APR-13A
19-APR-13A
20-APR-13A
22-APR-13A
23-APR-13A
24-APR-13A
22-MAY-13A
23-MAY-13A
24-MAY-13A
22-MAY-13A
23-MAY-13A
24-MAY-13A
27-MAY-13A
28-MAY-13A
03-JUN-13
04-JUN-13
31-May-2013
18-APR-13A
20-APR-13A
22-APR-13A
23-APR-13A
24-APR-13A
25-APR-13A
26-APR-13A
-87d
-87d
-87d
-83d
-83d
-83d
-83d
-83d
-88d
-88d
-49d
-37d
-37d
-37d
-37d
-37d
-37d
-37d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1981
S2CON1989
S2CON1990
S2CON1991
S2CON1992
002
004
S2CON1447
S2CON1448
S2CON1449
S2CON1450
S2CON1451
S2CON1452
S2CON1453
S2CON1454
S2CON1455
S2CON1456
S2CON1457
13-Mar-2013
29-Mar-2013
30-Mar-2013
01-Apr-2013
04-Apr-2013
19-Nov-2012
06-Dec-2012
06-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
15-Mar-2013
01-Apr-2013
02-Apr-2013
03-Apr-2013
04-Apr-2013
08-Jan-2013
20-Dec-2012
06-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
18-Dec-2012
19-Dec-2012
25-APR-13A
29-APR-13A
30-APR-13A
01-MAY-13A
04-MAY-13A
12-Jan-2013A
29-Jan-2013A
29-JAN-13A
30-JAN-13A
30-JAN-13A
31-JAN-13A
01-FEB-13A
30-JAN-13A
31-JAN-13A
01-FEB-13A
04-FEB-13A
11-FEB-13A
13-FEB-13A
27-APR-13A
01-MAY-13A
04-MAY-13A
09-MAY-13A
10-MAY-13A
31-May-2013
31-May-2013
30-JAN-13A
09-FEB-13A
10-FEB-13A
11-FEB-13A
12-FEB-13A
10-FEB-13A
11-FEB-13A
12-FEB-13A
14-FEB-13A
15-FEB-13A
16-FEB-13A
-37d
-26d
-27d
-30d
-30d
-123d
-139d
-46d
-53d
-53d
-52d
-52d
-50d
-49d
-49d
-50d
-50d
-50d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1458
005
S2CON1497
S2CON1498
S2CON1499
S2CON1500
S2CON1501
S2CON1502
S2CON1503
S2CON1504
S2CON1505
S2CON1506
S2CON1507
S2CON1508
007
S2CON1533
S2CON1534
S2CON1535
20-Dec-2012
11-Dec-2012
11-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
18-Dec-2012
19-Dec-2012
20-Dec-2012
21-Dec-2012
25-Dec-2012
27-Nov-2012
27-Nov-2012
27-Nov-2012
28-Nov-2012
20-Dec-2012
25-Dec-2012
11-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
18-Dec-2012
19-Dec-2012
20-Dec-2012
21-Dec-2012
22-Dec-2012
24-Dec-2012
25-Dec-2012
11-Dec-2012
27-Nov-2012
29-Nov-2012
30-Nov-2012
16-FEB-13A
03-Feb-2013A
03-FEB-13A
04-FEB-13A
05-FEB-13A
06-FEB-13A
07-FEB-13A
05-FEB-13A
06-FEB-13A
07-FEB-13A
15-FEB-13A
17-FEB-13A
18-FEB-13A
19-FEB-13A
24-Jan-2013A
24-JAN-13A
24-JAN-13A
25-JAN-13A
17-FEB-13A
31-May-2013
04-FEB-13A
06-FEB-13A
08-FEB-13A
09-FEB-13A
10-FEB-13A
08-FEB-13A
09-FEB-13A
10-FEB-13A
17-FEB-13A
19-FEB-13A
19-FEB-13A
20-FEB-13A
31-May-2013
24-JAN-13A
04-FEB-13A
05-FEB-13A
-50d
-135d
-47d
-47d
-47d
-48d
-47d
-44d
-45d
-44d
-49d
-49d
-49d
-49d
-147d
-49d
-56d
-56d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1536
S2CON1537
S2CON1538
S2CON1539
S2CON1540
S2CON1548
S2CON1549
S2CON1550
S2CON1551
001
S2CON1459
S2CON1460
S2CON1461
S2CON1462
S2CON1463
S2CON1464
S2CON1465
S2CON1466
29-Nov-2012
30-Nov-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
06-Dec-2012
07-Dec-2012
11-Dec-2012
19-Nov-2012
19-Nov-2012
19-Nov-2012
20-Nov-2012
21-Nov-2012
22-Nov-2012
23-Nov-2012
24-Nov-2012
26-Nov-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
03-Dec-2012
19-Nov-2012
21-Nov-2012
22-Nov-2012
23-Nov-2012
24-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
25-JAN-13A
26-JAN-13A
25-JAN-13A
25-JAN-13A
26-JAN-13A
28-JAN-13A
30-JAN-13A
12-FEB-13A
15-FEB-13A
12-Jan-2013A
12-JAN-13A
13-JAN-13A
14-JAN-13A
15-JAN-13A
16-JAN-13A
14-JAN-13A
15-JAN-13A
16-JAN-13A
06-FEB-13A
07-FEB-13A
05-FEB-13A
06-FEB-13A
07-FEB-13A
12-FEB-13A
13-FEB-13A
15-FEB-13A
16-FEB-13A
31-May-2013
13-JAN-13A
15-JAN-13A
16-JAN-13A
17-JAN-13A
18-JAN-13A
16-JAN-13A
17-JAN-13A
18-JAN-13A
-56d
-56d
-53d
-53d
-53d
-56d
-56d
-57d
-57d
-154d
-47d
-46d
-46d
-46d
-46d
-43d
-43d
-43d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1467
S2CON1468
S2CON1469
S2CON1470
003
S2CON1521
S2CON1522
S2CON1523
S2CON1524
S2CON1525
S2CON1526
S2CON1527
S2CON1528
S2CON1529
S2CON1530
S2CON1531
S2CON1532
009
27-Nov-2012
28-Nov-2012
29-Nov-2012
03-Dec-2012
03-Dec-2012
03-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
17-Dec-2012
27-Nov-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
03-Dec-2012
17-Dec-2012
03-Dec-2012
05-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
13-Dec-2012
21-JAN-13A
21-JAN-13A
31-JAN-13A
06-FEB-13A
01-Feb-2013A
01-FEB-13A
03-FEB-13A
04-FEB-13A
05-FEB-13A
06-FEB-13A
04-FEB-13A
05-FEB-13A
06-FEB-13A
05-FEB-13A
13-FEB-13A
14-FEB-13A
19-FEB-13A
21-Jan-2013A
30-JAN-13A
01-FEB-13A
05-FEB-13A
06-FEB-13A
31-May-2013
03-FEB-13A
09-FEB-13A
10-FEB-13A
11-FEB-13A
12-FEB-13A
10-FEB-13A
11-FEB-13A
12-FEB-13A
15-FEB-13A
18-FEB-13A
19-FEB-13A
20-FEB-13A
31-May-2013
-52d
-53d
-55d
-55d
-142d
-53d
-56d
-56d
-55d
-55d
-53d
-52d
-52d
-54d
-55d
-55d
-55d
-145d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON3150
S2CON3151
S2CON3152
S2CON3153
S2CON3154
S2CON3155
S2CON3156
S2CON3157
S2CON3158
S2CON3159
S2CON3160
006
S2CON1509
S2CON1510
S2CON1511
S2CON1512
S2CON1513
S2CON1514
07-Dec-2012
08-Dec-2012
10-Dec-2012
13-Dec-2012
27-Nov-2012
28-Nov-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
03-Dec-2012
05-Dec-2012
06-Dec-2012
06-Dec-2012
06-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
07-Dec-2012
20-Dec-2012
06-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
28-JAN-13A
01-FEB-13A
03-FEB-13A
10-FEB-13A
21-JAN-13A
21-JAN-13A
22-JAN-13A
22-JAN-13A
21-JAN-13A
22-JAN-13A
22-JAN-13A
12-Feb-2013A
12-FEB-13A
14-FEB-13A
15-FEB-13A
15-FEB-13A
16-FEB-13A
15-FEB-13A
08-FEB-13A
09-FEB-13A
10-FEB-13A
11-FEB-13A
25-JAN-13A
29-JAN-13A
31-JAN-13A
02-FEB-13A
29-JAN-13A
31-JAN-13A
02-FEB-13A
31-May-2013
13-FEB-13A
15-FEB-13A
16-FEB-13A
17-FEB-13A
18-FEB-13A
16-FEB-13A
-51d
-51d
-51d
-50d
-48d
-50d
-51d
-52d
-47d
-48d
-48d
-139d
-59d
-58d
-59d
-58d
-58d
-55d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1515
S2CON1516
S2CON1517
S2CON1518
S2CON1519
S2CON1520
002
S2CON1478
S2CON1479
S2CON1480
S2CON1481
S2CON1482
S2CON1483
S2CON1484
S2CON1485
S2CON1493
S2CON1494
S2CON1495
12-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
20-Dec-2012
22-Nov-2012
22-Nov-2012
22-Nov-2012
23-Nov-2012
24-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
03-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
18-Dec-2012
19-Dec-2012
20-Dec-2012
06-Dec-2012
22-Nov-2012
24-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
29-Nov-2012
30-Nov-2012
01-Dec-2012
03-Dec-2012
04-Dec-2012
05-Dec-2012
15-FEB-13A
16-FEB-13A
17-FEB-13A
21-FEB-13A
22-FEB-13A
25-FEB-13A
20-Jan-2013A
20-JAN-13A
21-JAN-13A
21-JAN-13A
22-JAN-13A
22-JAN-13A
21-JAN-13A
22-JAN-13A
22-JAN-13A
28-JAN-13A
01-FEB-13A
03-FEB-13A
17-FEB-13A
18-FEB-13A
23-FEB-13A
23-FEB-13A
25-FEB-13A
26-FEB-13A
31-May-2013
22-JAN-13A
25-JAN-13A
29-JAN-13A
31-JAN-13A
02-FEB-13A
29-JAN-13A
31-JAN-13A
02-FEB-13A
08-FEB-13A
09-FEB-13A
10-FEB-13A
-55d
-54d
-58d
-57d
-57d
-57d
-151d
-51d
-52d
-54d
-55d
-56d
-51d
-52d
-53d
-57d
-57d
-57d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1496
010
S2CON3165
S2CON3166
S2CON3167
S2CON3168
S2CON3169
S2CON3170
S2CON3171
S2CON3172
S2CON3173
S2CON3174
S2CON3175
008
S2CON1552
S2CON1553
S2CON1554
S2CON1555
06-Dec-2012
07-Dec-2012
18-Dec-2012
19-Dec-2012
20-Dec-2012
24-Dec-2012
07-Dec-2012
08-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
15-Dec-2012
14-Dec-2012
14-Dec-2012
14-Dec-2012
15-Dec-2012
17-Dec-2012
06-Dec-2012
24-Dec-2012
20-Dec-2012
21-Dec-2012
22-Dec-2012
24-Dec-2012
10-Dec-2012
11-Dec-2012
12-Dec-2012
13-Dec-2012
14-Dec-2012
15-Dec-2012
18-Dec-2012
08-Jan-2013
14-Dec-2012
17-Dec-2012
18-Dec-2012
19-Dec-2012
10-FEB-13A
10-Feb-2013A
11-FEB-13A
19-FEB-13A
20-FEB-13A
24-FEB-13A
10-FEB-13A
11-FEB-13A
12-FEB-13A
13-FEB-13A
11-FEB-13A
12-FEB-13A
13-FEB-13A
04-Feb-2013A
04-FEB-13A
04-FEB-13A
05-FEB-13A
06-FEB-13A
11-FEB-13A
31-May-2013
16-FEB-13A
21-FEB-13A
22-FEB-13A
24-FEB-13A
13-FEB-13A
14-FEB-13A
14-FEB-13A
15-FEB-13A
13-FEB-13A
14-FEB-13A
15-FEB-13A
31-May-2013
09-FEB-13A
11-FEB-13A
13-FEB-13A
14-FEB-13A
-57d
-136d
-49d
-52d
-52d
-53d
-55d
-55d
-54d
-54d
-51d
-51d
-50d
-123d
-49d
-47d
-48d
-48d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1556
S2CON1557
S2CON1558
S2CON1559
S2CON1567
S2CON1568
S2CON1569
S2CON1570
007
002
S2CON2098
S2CON2099
S2CON2100
S2CON2101
S2CON2102
S2CON2103
S2CON2104
S2CON2105
18-Dec-2012
19-Dec-2012
21-Dec-2012
24-Dec-2012
26-Dec-2012
29-Dec-2012
02-Jan-2013
08-Jan-2013
22-Feb-2013
05-Apr-2013
05-Apr-2013
05-Apr-2013
06-Apr-2013
08-Apr-2013
09-Apr-2013
10-Apr-2013
11-Apr-2013
12-Apr-2013
20-Dec-2012
22-Dec-2012
25-Dec-2012
27-Dec-2012
31-Dec-2012
03-Jan-2013
07-Jan-2013
08-Jan-2013
24-May-2013
03-May-2013
05-Apr-2013
08-Apr-2013
09-Apr-2013
10-Apr-2013
11-Apr-2013
12-Apr-2013
13-Apr-2013
15-Apr-2013
07-FEB-13A
05-FEB-13A
06-FEB-13A
07-FEB-13A
11-FEB-13A
19-FEB-13A
20-FEB-13A
24-FEB-13A
30-Apr-2013A
06-May-2013A
06-MAY-13A
06-MAY-13A
07-MAY-13A
08-MAY-13A
09-MAY-13A
07-MAY-13A
08-MAY-13A
10-MAY-13A
15-FEB-13A
13-FEB-13A
14-FEB-13A
15-FEB-13A
16-FEB-13A
21-FEB-13A
22-FEB-13A
24-FEB-13A
28-Jun-2013
31-May-2013
06-MAY-13A
08-MAY-13A
09-MAY-13A
10-MAY-13A
16-MAY-13A
13-MAY-13A
14-MAY-13A
16-MAY-13A
-48d
-44d
-43d
-42d
-40d
-42d
-40d
-40d
-30d
-24d
-26d
-26d
-26d
-26d
-29d
-26d
-26d
-27d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2113
S2CON2114
S2CON2115
S2CON2116
004
S2CON2067
S2CON2068
S2CON2069
S2CON2070
S2CON2071
S2CON2072
S2CON2073
S2CON2074
S2CON2075
S2CON2076
S2CON2077
S2CON2078
007
27-Apr-2013
29-Apr-2013
30-Apr-2013
03-May-2013
19-Apr-2013
19-Apr-2013
19-Apr-2013
20-Apr-2013
22-Apr-2013
23-Apr-2013
24-Apr-2013
25-Apr-2013
26-Apr-2013
11-May-2013
13-May-2013
14-May-2013
17-May-2013
09-Apr-2013
30-Apr-2013
01-May-2013
02-May-2013
03-May-2013
17-May-2013
19-Apr-2013
22-Apr-2013
23-Apr-2013
24-Apr-2013
25-Apr-2013
26-Apr-2013
27-Apr-2013
29-Apr-2013
14-May-2013
15-May-2013
16-May-2013
17-May-2013
07-May-2013
14-MAY-13A
15-MAY-13A
16-MAY-13A
20-MAY-13A
20-May-2013A
20-MAY-13A
20-MAY-13A
21-MAY-13A
22-MAY-13A
23-MAY-13A
21-MAY-13A
25-MAY-13A
27-MAY-13A
28-MAY-13A
31-MAY-13
01-JUN-13
05-JUN-13
08-May-2013A
21-MAY-13A
23-MAY-13A
29-MAY-13A
31-MAY-13A
05-Jun-2013
20-MAY-13A
23-MAY-13A
23-MAY-13A
27-MAY-13A
28-MAY-13A
27-MAY-13A
29-MAY-13A
30-MAY-13A
31-MAY-13A
03-JUN-13
04-JUN-13
05-JUN-13
31-May-2013
-18d
-18d
-23d
-23d
-16d
-26d
-26d
-26d
-28d
-28d
-26d
-27d
-27d
-15d
-16d
-16d
-16d
-21d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2153
S2CON2154
S2CON2155
S2CON2156
S2CON2157
S2CON2158
S2CON2159
S2CON2160
S2CON2168
S2CON2170
S2CON2171
S2CON2169
006
S2CON2129
S2CON2130
S2CON2131
S2CON2132
S2CON2133
09-Apr-2013
09-Apr-2013
10-Apr-2013
11-Apr-2013
12-Apr-2013
13-Apr-2013
15-Apr-2013
16-Apr-2013
01-May-2013
03-May-2013
07-May-2013
02-May-2013
22-Feb-2013
22-Feb-2013
22-Feb-2013
23-Feb-2013
25-Feb-2013
26-Feb-2013
09-Apr-2013
11-Apr-2013
12-Apr-2013
13-Apr-2013
15-Apr-2013
16-Apr-2013
17-Apr-2013
18-Apr-2013
03-May-2013
06-May-2013
07-May-2013
04-May-2013
08-Mar-2013
22-Feb-2013
25-Feb-2013
26-Feb-2013
27-Feb-2013
28-Feb-2013
08-MAY-13A
08-MAY-13A
09-MAY-13A
10-MAY-13A
11-MAY-13A
11-MAY-13A
13-MAY-13A
14-MAY-13A
16-MAY-13A
18-MAY-13A
22-MAY-13A
17-MAY-13A
05-Jun-2013
05-JUN-13
05-JUN-13
06-JUN-13
07-JUN-13
08-JUN-13
10-MAY-13A
13-MAY-13A
14-MAY-13A
15-MAY-13A
18-MAY-13A
15-MAY-13A
16-MAY-13A
18-MAY-13A
21-MAY-13A
30-MAY-13A
31-MAY-13A
23-MAY-13A
19-Jun-2013
05-JUN-13
07-JUN-13
08-JUN-13
10-JUN-13
11-JUN-13
-27d
-27d
-27d
-27d
-28d
-25d
-25d
-25d
-15d
-20d
-20d
-15d
-88d
-88d
-88d
-88d
-88d
-88d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2134
S2CON2135
S2CON2136
S2CON2137
S2CON2138
S2CON2139
S2CON2140
001
S2CON2079
S2CON2080
S2CON2081
S2CON2082
S2CON2083
S2CON2084
S2CON2085
S2CON2086
S2CON2087
S2CON2088
27-Feb-2013
28-Feb-2013
01-Mar-2013
02-Mar-2013
04-Mar-2013
05-Mar-2013
08-Mar-2013
02-Apr-2013
02-Apr-2013
02-Apr-2013
03-Apr-2013
04-Apr-2013
05-Apr-2013
06-Apr-2013
08-Apr-2013
09-Apr-2013
24-Apr-2013
25-Apr-2013
01-Mar-2013
02-Mar-2013
04-Mar-2013
05-Mar-2013
06-Mar-2013
07-Mar-2013
08-Mar-2013
30-Apr-2013
02-Apr-2013
04-Apr-2013
05-Apr-2013
06-Apr-2013
08-Apr-2013
09-Apr-2013
10-Apr-2013
11-Apr-2013
26-Apr-2013
27-Apr-2013
10-JUN-13
11-JUN-13
12-JUN-13
13-JUN-13
14-JUN-13
15-JUN-13
19-JUN-13
30-Apr-2013A
30-APR-13A
30-APR-13A
01-MAY-13A
02-MAY-13A
03-MAY-13A
04-MAY-13A
06-MAY-13A
07-MAY-13A
08-MAY-13A
09-MAY-13A
12-JUN-13
13-JUN-13
14-JUN-13
15-JUN-13
17-JUN-13
18-JUN-13
19-JUN-13
31-May-2013
01-MAY-13A
03-MAY-13A
04-MAY-13A
06-MAY-13A
07-MAY-13A
08-MAY-13A
09-MAY-13A
10-MAY-13A
14-MAY-13A
15-MAY-13A
-88d
-88d
-88d
-88d
-88d
-88d
-88d
-27d
-25d
-25d
-25d
-25d
-25d
-25d
-25d
-25d
-15d
-15d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2089
S2CON2090
009
S2CON3309
S2CON3310
S2CON3311
S2CON3312
S2CON3313
S2CON3314
S2CON3315
S2CON3316
S2CON3317
S2CON3318
S2CON3319
010
S2CON3260
S2CON3259
S2CON3250
26-Apr-2013
30-Apr-2013
22-Feb-2013
05-Mar-2013
06-Mar-2013
07-Mar-2013
11-Mar-2013
22-Feb-2013
23-Feb-2013
25-Feb-2013
26-Feb-2013
27-Feb-2013
28-Feb-2013
02-Mar-2013
05-Mar-2013
13-Mar-2013
11-Mar-2013
15-Mar-2013
29-Apr-2013
30-Apr-2013
11-Mar-2013
07-Mar-2013
08-Mar-2013
09-Mar-2013
11-Mar-2013
25-Feb-2013
26-Feb-2013
27-Feb-2013
28-Feb-2013
01-Mar-2013
02-Mar-2013
05-Mar-2013
21-Mar-2013
15-Mar-2013
13-Mar-2013
18-Mar-2013
10-MAY-13A
14-MAY-13A
08-May-2013A
18-MAY-13A
20-MAY-13A
21-MAY-13A
24-MAY-13A
08-MAY-13A
09-MAY-13A
10-MAY-13A
11-MAY-13A
13-MAY-13A
14-MAY-13A
16-MAY-13A
16-May-2013A
24-MAY-13A
22-MAY-13A
31-MAY-13
23-MAY-13A
24-MAY-13A
31-May-2013
21-MAY-13A
22-MAY-13A
29-MAY-13A
30-MAY-13A
10-MAY-13A
11-MAY-13A
13-MAY-13A
14-MAY-13A
15-MAY-13A
16-MAY-13A
18-MAY-13A
06-Jun-2013
31-MAY-13A
29-MAY-13A
03-JUN-13
-20d
-21d
-70d
-64d
-64d
-68d
-68d
-64d
-64d
-64d
-64d
-64d
-64d
-64d
-66d
-66d
-66d
-66d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON3251
S2CON3252
S2CON3253
S2CON3254
S2CON3255
S2CON3256
S2CON3257
S2CON3258
005
S2CON2117
S2CON2118
S2CON2119
S2CON2120
S2CON2121
S2CON2122
S2CON2123
S2CON2124
S2CON2125
16-Mar-2013
18-Mar-2013
21-Mar-2013
05-Mar-2013
06-Mar-2013
07-Mar-2013
08-Mar-2013
09-Mar-2013
23-Apr-2013
23-Apr-2013
23-Apr-2013
24-Apr-2013
25-Apr-2013
26-Apr-2013
27-Apr-2013
29-Apr-2013
30-Apr-2013
15-May-2013
19-Mar-2013
20-Mar-2013
21-Mar-2013
07-Mar-2013
08-Mar-2013
09-Mar-2013
11-Mar-2013
12-Mar-2013
21-May-2013
23-Apr-2013
25-Apr-2013
26-Apr-2013
27-Apr-2013
29-Apr-2013
30-Apr-2013
01-May-2013
02-May-2013
17-May-2013
01-JUN-13
03-JUN-13
06-JUN-13
16-MAY-13A
17-MAY-13A
18-MAY-13A
20-MAY-13A
21-MAY-13A
18-May-2013A
18-MAY-13A
18-MAY-13A
20-MAY-13A
21-MAY-13A
23-MAY-13A
20-MAY-13A
21-MAY-13A
24-MAY-13A
25-MAY-13A
04-JUN-13
05-JUN-13
06-JUN-13
22-MAY-13A
23-MAY-13A
24-MAY-13A
27-MAY-13A
28-MAY-13A
07-Jun-2013
22-MAY-13A
24-MAY-13A
25-MAY-13A
27-MAY-13A
28-MAY-13A
29-MAY-13A
30-MAY-13A
31-MAY-13A
01-JUN-13A
-66d
-66d
-66d
-65d
-65d
-65d
-66d
-66d
-15d
-25d
-25d
-25d
-25d
-25d
-25d
-25d
-25d
-13d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2126
S2CON2127
S2CON2128
003
S2CON2141
S2CON2142
S2CON2143
S2CON2144
S2CON2145
S2CON2146
S2CON2147
S2CON2148
S2CON2149
S2CON2150
S2CON2151
S2CON2152
008
S2CON2172
16-May-2013
17-May-2013
21-May-2013
16-Apr-2013
16-Apr-2013
16-Apr-2013
17-Apr-2013
18-Apr-2013
19-Apr-2013
20-Apr-2013
22-Apr-2013
23-Apr-2013
08-May-2013
09-May-2013
10-May-2013
14-May-2013
29-Apr-2013
29-Apr-2013
18-May-2013
20-May-2013
21-May-2013
14-May-2013
16-Apr-2013
18-Apr-2013
19-Apr-2013
20-Apr-2013
22-Apr-2013
23-Apr-2013
24-Apr-2013
25-Apr-2013
10-May-2013
11-May-2013
13-May-2013
14-May-2013
24-May-2013
29-Apr-2013
27-MAY-13A
01-JUN-13
06-JUN-13
01-May-2013A
01-MAY-13A
02-MAY-13A
03-MAY-13A
05-MAY-13A
07-MAY-13A
03-MAY-13A
05-MAY-13A
07-MAY-13A
10-MAY-13A
23-MAY-13A
25-MAY-13A
04-JUN-13
23-May-2013A
23-MAY-13A
03-JUN-13
05-JUN-13
07-JUN-13
04-Jun-2013
14-MAY-13A
16-MAY-13A
17-MAY-13A
18-MAY-13A
20-MAY-13A
21-MAY-13A
22-MAY-13A
23-MAY-13A
24-MAY-13A
27-MAY-13A
03-JUN-13
04-JUN-13
28-Jun-2013
27-MAY-13A
-13d
-14d
-15d
-18d
-24d
-24d
-24d
-24d
-24d
-24d
-24d
-24d
-12d
-13d
-18d
-18d
-30d
-24d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2173
S2CON2174
S2CON2175
S2CON2176
S2CON2177
S2CON2178
S2CON2179
S2CON2187
S2CON2188
S2CON2189
S2CON2190
004
009
S2CON3264
S2CON3265
S2CON3266
S2CON3267
S2CON3268
29-Apr-2013
01-May-2013
02-May-2013
03-May-2013
04-May-2013
07-May-2013
09-May-2013
11-May-2013
15-May-2013
18-May-2013
24-May-2013
01-Jan-2013
01-Jan-2013
11-Jan-2013
12-Jan-2013
14-Jan-2013
17-Jan-2013
01-Jan-2013
02-May-2013
03-May-2013
04-May-2013
06-May-2013
08-May-2013
10-May-2013
13-May-2013
16-May-2013
20-May-2013
23-May-2013
24-May-2013
04-Mar-2013
17-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
17-Jan-2013
03-Jan-2013
23-MAY-13A
23-MAY-13A
24-MAY-13A
24-MAY-13A
23-MAY-13A
24-MAY-13A
25-MAY-13A
27-MAY-13A
06-JUN-13
13-JUN-13
22-JUN-13
26-Feb-2013A
28-Feb-2013A
08-MAR-13A
21-MAR-13A
22-MAR-13A
26-MAR-13A
28-FEB-13A
30-MAY-13A
31-MAY-13A
01-JUN-13A
03-JUN-13A
04-JUN-13A
05-JUN-13A
06-JUN-13A
07-JUN-13
14-JUN-13
21-JUN-13
28-JUN-13
31-May-2013
31-May-2013
21-MAR-13A
23-MAR-13A
25-MAR-13A
26-MAR-13A
28-FEB-13A
-24d
-24d
-24d
-24d
-23d
-22d
-21d
-19d
-22d
-25d
-30d
-76d
-115d
-56d
-57d
-57d
-57d
-47d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
10 Rebar works for the Lift & Shear Walls (1st Lift)
10 Form works for the Lift & Shear Walls (1st Lift)
10 Concreting of the Lift & Shear Walls (1st Lift)
10 Rebar works for the Lift & Shear Walls (2nd Lift)
10 Form works for the Lift & Shear Walls (2nd Lift)
10 Concreting of the Lift & Shear Walls (2nd Lift)
9 POUR-05 (GRID E-J / 10-5)
10 Starters for Columns
10 Staging for the Columns (1st Lift)
10 Rebar works for the Columns (1st Lift)
10 Form works for the Columns (1st Lift)
10 Concreting of the Columns (1st Lift)
10 Rebar works for the Columns (2nd Lift)
10 Form works for the Columns (2nd Lift)
10 Concreting of the Columns (2nd Lift)
10 Staging for the Slab
10 Form works for the slab
10 Rebar works for the slab
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON3269
S2CON3270
S2CON3271
S2CON3272
S2CON3273
S2CON3274
005
S2CON1745
S2CON1746
S2CON1747
S2CON1748
S2CON1749
S2CON1750
S2CON1751
S2CON1752
S2CON1753
S2CON1754
S2CON1755
02-Jan-2013
03-Jan-2013
04-Jan-2013
05-Jan-2013
07-Jan-2013
09-Jan-2013
25-Jan-2013
25-Jan-2013
25-Jan-2013
26-Jan-2013
28-Jan-2013
29-Jan-2013
30-Jan-2013
31-Jan-2013
01-Feb-2013
16-Feb-2013
18-Feb-2013
19-Feb-2013
04-Jan-2013
05-Jan-2013
07-Jan-2013
08-Jan-2013
09-Jan-2013
11-Jan-2013
22-Feb-2013
25-Jan-2013
28-Jan-2013
29-Jan-2013
30-Jan-2013
31-Jan-2013
01-Feb-2013
02-Feb-2013
04-Feb-2013
19-Feb-2013
20-Feb-2013
21-Feb-2013
28-FEB-13A
01-MAR-13A
01-MAR-13A
04-MAR-13A
05-MAR-13A
07-MAR-13A
11-Mar-2013A
11-MAR-13A
13-MAR-13A
16-MAR-13A
18-MAR-13A
19-MAR-13A
20-MAR-13A
22-MAR-13A
23-MAR-13A
24-MAR-13A
28-MAR-13A
30-MAR-13A
02-MAR-13A
04-MAR-13A
04-MAR-13A
06-MAR-13A
07-MAR-13A
09-MAR-13A
31-May-2013
12-MAR-13A
15-MAR-13A
17-MAR-13A
19-MAR-13A
20-MAR-13A
21-MAR-13A
23-MAR-13A
23-MAR-13A
27-MAR-13A
30-MAR-13A
05-APR-13A
-48d
-48d
-47d
-48d
-48d
-48d
-84d
-38d
-39d
-40d
-40d
-40d
-40d
-41d
-40d
-30d
-32d
-36d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1756
007
S2CON1781
S2CON1782
S2CON1783
S2CON1784
S2CON1785
S2CON1786
S2CON1787
S2CON1788
S2CON1796
S2CON1797
S2CON1798
S2CON1799
008
S2CON1800
S2CON1801
S2CON1802
22-Feb-2013
11-Jan-2013
11-Jan-2013
11-Jan-2013
12-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
17-Jan-2013
18-Jan-2013
02-Feb-2013
04-Feb-2013
05-Feb-2013
08-Feb-2013
06-Feb-2013
06-Feb-2013
06-Feb-2013
07-Feb-2013
22-Feb-2013
08-Feb-2013
11-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
17-Jan-2013
18-Jan-2013
19-Jan-2013
21-Jan-2013
05-Feb-2013
06-Feb-2013
07-Feb-2013
08-Feb-2013
04-Mar-2013
06-Feb-2013
08-Feb-2013
09-Feb-2013
07-APR-13A
28-Feb-2013A
28-FEB-13A
28-FEB-13A
01-MAR-13A
02-MAR-13A
04-MAR-13A
07-MAR-13A
12-MAR-13A
16-MAR-13A
21-MAR-13A
27-MAR-13A
28-MAR-13A
30-MAR-13A
21-Mar-2013A
21-MAR-13A
21-MAR-13A
22-MAR-13A
07-APR-13A
31-May-2013
28-FEB-13A
02-MAR-13A
04-MAR-13A
05-MAR-13A
06-MAR-13A
11-MAR-13A
15-MAR-13A
20-MAR-13A
28-MAR-13A
29-MAR-13A
30-MAR-13A
31-MAR-13A
31-May-2013
21-MAR-13A
23-MAR-13A
25-MAR-13A
-37d
-96d
-41d
-41d
-41d
-41d
-41d
-43d
-46d
-49d
-44d
-44d
-44d
-43d
-76d
-37d
-37d
-37d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1803
S2CON1804
S2CON1805
S2CON1806
S2CON1807
S2CON1815
S2CON1816
S2CON1817
S2CON1818
004
S2CON1695
S2CON1696
S2CON1697
S2CON1698
S2CON1699
S2CON1700
S2CON1701
S2CON1702
08-Feb-2013
09-Feb-2013
12-Feb-2013
14-Feb-2013
16-Feb-2013
19-Feb-2013
22-Feb-2013
26-Feb-2013
04-Mar-2013
21-Jan-2013
21-Jan-2013
21-Jan-2013
22-Jan-2013
23-Jan-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
28-Jan-2013
11-Feb-2013
13-Feb-2013
15-Feb-2013
18-Feb-2013
20-Feb-2013
23-Feb-2013
27-Feb-2013
02-Mar-2013
04-Mar-2013
18-Feb-2013
21-Jan-2013
23-Jan-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
28-Jan-2013
29-Jan-2013
30-Jan-2013
23-MAR-13A
25-MAR-13A
27-MAR-13A
29-MAR-13A
30-MAR-13A
30-MAR-13A
30-MAR-13A
02-APR-13A
09-APR-13A
28-Feb-2013A
28-FEB-13A
28-FEB-13A
01-MAR-13A
02-MAR-13A
04-MAR-13A
09-MAR-13A
15-MAR-13A
18-MAR-13A
26-MAR-13A
28-MAR-13A
30-MAR-13A
01-APR-13A
01-APR-13A
05-APR-13A
06-APR-13A
07-APR-13A
09-APR-13A
31-May-2013
28-FEB-13A
02-MAR-13A
04-MAR-13A
05-MAR-13A
08-MAR-13A
14-MAR-13A
17-MAR-13A
21-MAR-13A
-37d
-37d
-37d
-35d
-33d
-34d
-32d
-30d
-30d
-88d
-33d
-33d
-33d
-33d
-34d
-38d
-40d
-42d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1703
S2CON1704
S2CON1705
S2CON1706
003
S2CON1769
S2CON1770
S2CON1771
S2CON1772
S2CON1773
S2CON1774
S2CON1775
S2CON1776
S2CON1777
S2CON1778
S2CON1779
S2CON1780
001
12-Feb-2013
13-Feb-2013
14-Feb-2013
18-Feb-2013
17-Jan-2013
17-Jan-2013
17-Jan-2013
18-Jan-2013
19-Jan-2013
21-Jan-2013
22-Jan-2013
23-Jan-2013
24-Jan-2013
08-Feb-2013
09-Feb-2013
11-Feb-2013
14-Feb-2013
03-Jan-2013
14-Feb-2013
15-Feb-2013
16-Feb-2013
18-Feb-2013
14-Feb-2013
17-Jan-2013
19-Jan-2013
21-Jan-2013
22-Jan-2013
23-Jan-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
11-Feb-2013
12-Feb-2013
13-Feb-2013
14-Feb-2013
31-Jan-2013
22-MAR-13A
25-MAR-13A
27-MAR-13A
04-APR-13A
28-Feb-2013A
28-FEB-13A
28-FEB-13A
01-MAR-13A
02-MAR-13A
04-MAR-13A
10-MAR-13A
15-MAR-13A
20-MAR-13A
28-MAR-13A
29-MAR-13A
01-APR-13A
06-APR-13A
26-Feb-2013A
24-MAR-13A
27-MAR-13A
03-APR-13A
04-APR-13A
31-May-2013
28-FEB-13A
02-MAR-13A
04-MAR-13A
05-MAR-13A
09-MAR-13A
14-MAR-13A
19-MAR-13A
21-MAR-13A
30-MAR-13A
02-APR-13A
04-APR-13A
06-APR-13A
31-May-2013
-32d
-33d
-38d
-38d
-91d
-36d
-36d
-36d
-36d
-38d
-41d
-44d
-45d
-41d
-42d
-42d
-43d
-103d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1707
S2CON1708
S2CON1709
S2CON1710
S2CON1711
S2CON1712
S2CON1713
S2CON1714
S2CON1715
S2CON1716
S2CON1717
S2CON1718
002
S2CON1726
S2CON1727
S2CON1728
S2CON1729
S2CON1730
03-Jan-2013
03-Jan-2013
04-Jan-2013
05-Jan-2013
07-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
25-Jan-2013
26-Jan-2013
28-Jan-2013
31-Jan-2013
07-Jan-2013
07-Jan-2013
07-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
03-Jan-2013
05-Jan-2013
07-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
11-Jan-2013
12-Jan-2013
28-Jan-2013
29-Jan-2013
30-Jan-2013
31-Jan-2013
04-Feb-2013
07-Jan-2013
09-Jan-2013
10-Jan-2013
11-Jan-2013
12-Jan-2013
26-FEB-13A
28-FEB-13A
01-MAR-13A
02-MAR-13A
04-MAR-13A
05-MAR-13A
06-MAR-13A
07-MAR-13A
15-MAR-13A
18-MAR-13A
18-MAR-13A
21-MAR-13A
28-Feb-2013A
28-FEB-13A
28-FEB-13A
01-MAR-13A
02-MAR-13A
04-MAR-13A
28-FEB-13A
01-MAR-13A
02-MAR-13A
03-MAR-13A
06-MAR-13A
07-MAR-13A
08-MAR-13A
09-MAR-13A
17-MAR-13A
19-MAR-13A
20-MAR-13A
21-MAR-13A
31-May-2013
28-FEB-13A
02-MAR-13A
04-MAR-13A
05-MAR-13A
06-MAR-13A
-48d
-46d
-46d
-46d
-48d
-48d
-48d
-48d
-41d
-41d
-41d
-41d
-100d
-45d
-45d
-45d
-45d
-45d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1731
S2CON1732
S2CON1733
S2CON1741
S2CON1742
S2CON1743
S2CON1744
006
S2CON1757
S2CON1758
S2CON1759
S2CON1760
S2CON1761
S2CON1762
S2CON1763
S2CON1764
S2CON1765
S2CON1766
11-Jan-2013
12-Jan-2013
14-Jan-2013
29-Jan-2013
30-Jan-2013
31-Jan-2013
04-Feb-2013
07-Jan-2013
07-Jan-2013
07-Jan-2013
08-Jan-2013
09-Jan-2013
10-Jan-2013
11-Jan-2013
12-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
31-Jan-2013
01-Feb-2013
02-Feb-2013
04-Feb-2013
21-Jan-2013
07-Jan-2013
09-Jan-2013
10-Jan-2013
11-Jan-2013
12-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
17-Jan-2013
18-Jan-2013
05-MAR-13A
06-MAR-13A
07-MAR-13A
08-MAR-13A
21-MAR-13A
22-MAR-13A
26-MAR-13A
01-Mar-2013A
01-MAR-13A
01-MAR-13A
02-MAR-13A
04-MAR-13A
05-MAR-13A
10-MAR-13A
15-MAR-13A
18-MAR-13A
26-MAR-13A
27-MAR-13A
07-MAR-13A
08-MAR-13A
09-MAR-13A
21-MAR-13A
23-MAR-13A
25-MAR-13A
26-MAR-13A
31-May-2013
02-MAR-13A
05-MAR-13A
06-MAR-13A
07-MAR-13A
09-MAR-13A
14-MAR-13A
17-MAR-13A
22-MAR-13A
29-MAR-13A
30-MAR-13A
-45d
-45d
-45d
-42d
-43d
-43d
-43d
-112d
-46d
-46d
-46d
-46d
-47d
-50d
-52d
-56d
-60d
-60d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1767
S2CON1768
010
S2CON3208
S2CON3209
S2CON3210
S2CON3211
S2CON3212
S2CON3213
S2CON3214
S2CON3215
S2CON3216
S2CON3217
S2CON3218
008
S2CON00700
S2CON00701
S2CON00702
17-Jan-2013
21-Jan-2013
11-Jan-2013
22-Jan-2013
23-Jan-2013
24-Jan-2013
28-Jan-2013
11-Jan-2013
12-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
17-Jan-2013
19-Jan-2013
25-May-2013
25-May-2013
17-Jul-2013
09-Aug-2013
19-Jan-2013
21-Jan-2013
28-Jan-2013
24-Jan-2013
25-Jan-2013
26-Jan-2013
28-Jan-2013
14-Jan-2013
15-Jan-2013
16-Jan-2013
17-Jan-2013
18-Jan-2013
19-Jan-2013
22-Jan-2013
24-Sep-2013
16-Jul-2013
08-Aug-2013
31-Aug-2013
28-MAR-13A
04-APR-13A
21-Mar-2013A
25-MAR-13A
28-MAR-13A
29-MAR-13A
09-APR-13A
21-MAR-13A
22-MAR-13A
23-MAR-13A
25-MAR-13A
26-MAR-13A
27-MAR-13A
30-MAR-13A
29-Jun-2013
29-JUN-13
15-AUG-13
27-AUG-13
03-APR-13A
04-APR-13A
31-May-2013
27-MAR-13A
29-MAR-13A
07-APR-13A
09-APR-13A
23-MAR-13A
25-MAR-13A
26-MAR-13A
27-MAR-13A
28-MAR-13A
29-MAR-13A
30-MAR-13A
04-Oct-2013
24-AUG-13
11-SEP-13
23-SEP-13
-62d
-62d
-106d
-52d
-53d
-60d
-60d
-59d
-59d
-59d
-59d
-59d
-59d
-57d
-9d
-34d
-29d
-19d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00703
001
06
S2CON00125
S2CON00126
S2CON00127
S2CON00128
S2CON00129
S2CON00130
S2CON00131
S2CON00132
S2CON00133
S2CON00134
S2CON00135
S2CON00136
S2CON00137
S2CON00138
S2CON00139
02-Sep-2013
15-Sep-2012
26-Sep-2012
26-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
08-Oct-2012
09-Oct-2012
10-Oct-2012
11-Oct-2012
12-Oct-2012
24-Sep-2013
28-Nov-2012
20-Nov-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
08-Oct-2012
09-Oct-2012
10-Oct-2012
11-Oct-2012
12-Oct-2012
13-Oct-2012
15-Oct-2012
07-SEP-13
05-Sep-2012A
29-Sep-2012A
29-SEP-12A
03-OCT-12A
04-OCT-12A
05-OCT-12A
08-OCT-12A
09-OCT-12A
12-OCT-12A
16-OCT-12A
19-OCT-12A
22-OCT-12A
23-OCT-12A
24-OCT-12A
26-OCT-12A
28-OCT-12A
29-OCT-12A
04-OCT-13
31-May-2013
31-May-2013
18-OCT-12A
18-OCT-12A
19-OCT-12A
20-OCT-12A
13-OCT-12A
02-NOV-12A
05-NOV-12A
08-NOV-12A
10-NOV-12A
13-NOV-12A
14-NOV-12A
15-NOV-12A
12-NOV-12A
13-NOV-12A
14-NOV-12A
-9d
-158d
-165d
-16d
-15d
-15d
-15d
-8d
-24d
-25d
-27d
-28d
-29d
-29d
-29d
-25d
-25d
-25d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00140
S2CON00141
S2CON00142
S2CON00143
S2CON00144
S2CON00145
S2CON00146
S2CON00147
S2CON00148
S2CON00149
S2CON00150
S2CON00151
S2CON00152
S2CON00157
S2CON00158
S2CON00159
S2CON00160
S2CON00161
13-Oct-2012
15-Oct-2012
19-Oct-2012
20-Oct-2012
23-Oct-2012
24-Oct-2012
25-Oct-2012
27-Oct-2012
31-Oct-2012
02-Nov-2012
03-Nov-2012
06-Nov-2012
08-Nov-2012
09-Nov-2012
12-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
16-Oct-2012
25-Oct-2012
22-Oct-2012
24-Oct-2012
25-Oct-2012
24-Oct-2012
29-Oct-2012
30-Oct-2012
01-Nov-2012
03-Nov-2012
06-Nov-2012
07-Nov-2012
08-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
19-Nov-2012
20-Nov-2012
30-OCT-12A
29-OCT-12A
12-DEC-12A
17-DEC-12A
18-DEC-12A
20-DEC-12A
21-DEC-12A
22-DEC-12A
31-DEC-12A
02-JAN-13A
02-JAN-13A
03-JAN-13A
04-JAN-13A
12-DEC-12A
13-DEC-12A
14-DEC-12A
14-DEC-12A
15-DEC-12A
16-NOV-12A
01-DEC-12A
14-DEC-12A
18-DEC-12A
19-DEC-12A
20-DEC-12A
24-DEC-12A
25-DEC-12A
02-JAN-13A
03-JAN-13A
03-JAN-13A
04-JAN-13A
04-JAN-13A
27-JAN-13A
28-MAR-13A
29-MAR-13A
30-MAR-13A
02-APR-13A
-26d
-31d
-46d
-46d
-46d
-48d
-47d
-47d
-53d
-52d
-49d
-49d
-48d
-62d
-112d
-112d
-112d
-113d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00153
S2CON00154
S2CON00155
S2CON00156
05
S2CON00210
S2CON00211
S2CON00212
S2CON00213
S2CON00214
S2CON00215
S2CON00216
S2CON00217
S2CON00218
S2CON00219
S2CON00220
S2CON00221
S2CON00222
23-Oct-2012
25-Oct-2012
26-Oct-2012
27-Oct-2012
15-Sep-2012
15-Sep-2012
22-Sep-2012
24-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
26-Oct-2012
27-Oct-2012
29-Oct-2012
30-Oct-2012
09-Nov-2012
22-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
08-Oct-2012
04-DEC-12A
06-DEC-12A
08-DEC-12A
10-DEC-12A
01-Oct-2012A
01-OCT-12A
01-OCT-12A
03-OCT-12A
04-OCT-12A
06-OCT-12A
08-OCT-12A
11-OCT-12A
12-OCT-12A
13-OCT-12A
20-OCT-12A
23-OCT-12A
26-OCT-12A
29-OCT-12A
07-DEC-12A
10-DEC-12A
12-DEC-12A
13-DEC-12A
31-May-2013
03-OCT-12A
06-OCT-12A
03-NOV-12A
05-NOV-12A
06-NOV-12A
08-NOV-12A
10-NOV-12A
12-NOV-12A
14-NOV-12A
16-NOV-12A
17-NOV-12A
19-NOV-12A
22-NOV-12A
-35d
-36d
-37d
-37d
-174d
-9d
-9d
-32d
-32d
-32d
-33d
-34d
-34d
-35d
-36d
-36d
-36d
-38d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00223
S2CON00224
S2CON00225
S2CON00226
S2CON00227
S2CON00228
S2CON00229
S2CON00230
S2CON00231
S2CON00232
S2CON00234
S2CON00235
S2CON00236
S2CON00237
S2CON00233
08
S2CON1406
S2CON1407
06-Oct-2012
08-Oct-2012
09-Oct-2012
10-Oct-2012
11-Oct-2012
12-Oct-2012
20-Oct-2012
23-Oct-2012
24-Oct-2012
25-Oct-2012
29-Oct-2012
01-Nov-2012
03-Nov-2012
06-Nov-2012
26-Oct-2012
11-Oct-2012
11-Oct-2012
12-Oct-2012
09-Oct-2012
10-Oct-2012
11-Oct-2012
12-Oct-2012
13-Oct-2012
23-Oct-2012
24-Oct-2012
25-Oct-2012
26-Oct-2012
27-Oct-2012
02-Nov-2012
05-Nov-2012
07-Nov-2012
09-Nov-2012
01-Nov-2012
28-Nov-2012
13-Oct-2012
15-Oct-2012
30-OCT-12A
05-NOV-12A
07-NOV-12A
08-NOV-12A
12-NOV-12A
16-NOV-12A
10-DEC-12A
11-DEC-12A
12-DEC-12A
12-DEC-12A
10-DEC-12A
12-DEC-12A
13-DEC-12A
14-DEC-12A
05-DEC-12A
10-Sep-2012A
10-SEP-12A
11-SEP-12A
25-NOV-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
06-DEC-12A
11-DEC-12A
12-DEC-12A
14-DEC-12A
15-DEC-12A
05-JAN-13A
06-JAN-13A
07-JAN-13A
10-JAN-13A
03-JAN-13A
31-May-2013
08-NOV-12A
10-NOV-12A
-40d
-43d
-42d
-41d
-40d
-37d
-40d
-40d
-41d
-41d
-54d
-53d
-51d
-52d
-53d
-158d
-21d
-22d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1408
S2CON1409
S2CON1410
S2CON1411
S2CON1412
S2CON1413
S2CON1414
S2CON1415
S2CON1416
S2CON1417
S2CON1418
S2CON1419
S2CON1420
S2CON1421
S2CON1422
S2CON1423
S2CON1424
S2CON1425
13-Oct-2012
15-Oct-2012
16-Oct-2012
17-Oct-2012
18-Oct-2012
19-Oct-2012
20-Oct-2012
22-Oct-2012
23-Oct-2012
24-Oct-2012
25-Oct-2012
26-Oct-2012
27-Oct-2012
23-Oct-2012
24-Oct-2012
25-Oct-2012
27-Oct-2012
29-Oct-2012
16-Oct-2012
17-Oct-2012
18-Oct-2012
19-Oct-2012
20-Oct-2012
22-Oct-2012
23-Oct-2012
24-Oct-2012
25-Oct-2012
26-Oct-2012
27-Oct-2012
29-Oct-2012
30-Oct-2012
25-Oct-2012
26-Oct-2012
27-Oct-2012
30-Oct-2012
31-Oct-2012
12-SEP-12A
13-SEP-12A
14-SEP-12A
15-SEP-12A
17-SEP-12A
18-SEP-12A
19-SEP-12A
20-SEP-12A
21-SEP-12A
22-SEP-12A
24-SEP-12A
25-SEP-12A
26-SEP-12A
27-SEP-12A
24-SEP-12A
26-SEP-12A
28-SEP-12A
03-OCT-12A
12-NOV-12A
13-NOV-12A
14-NOV-12A
15-NOV-12A
16-NOV-12A
17-NOV-12A
19-NOV-12A
20-NOV-12A
21-NOV-12A
22-NOV-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
19-NOV-12A
20-NOV-12A
21-NOV-12A
24-NOV-12A
-22d
-22d
-22d
-22d
-22d
-22d
-22d
-22d
-22d
-22d
-27d
-26d
-25d
-29d
-19d
-19d
-18d
-20d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
9 Form Works for the Lift & Shear Walls (2nd Lift)
9 Concreting of the Lift & Shear Walls (2nd Lift)
9 Backfilling works-stg1
9 PCC for the Tie Beams
9 Rebar works for the Tie Beams
9 Form works for the Tie Beams
9 Concreting for the Tie Beams
9 Staging for the Lift & Shear Walls (3rd Lift)
9 Rebar works for the Lift & Shear Walls (3rd Lift)
9 Form works for the Lift & shear Walls (3rd Lift)
9 Concreting of the Lift & Shear Walls (3rd Lift)
9 Backfilling Works-stg2
9 Staging for the Columns (3rd Lift)
9 Rebar works for the Columns (3rd Lift)
9 Form works for the Columns (3rd Lift)
9 Concreting of the Columns (3rd Lift)
9 Concreting of the Lift & Shear Walls (1st Lift)
8 ZONE-02 (GRID A~E / 21~15)
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1426
S2CON1427
S2CON1428
S2CON1429
S2CON1430
S2CON1431
S2CON1432
S2CON1437
S2CON1438
S2CON1439
S2CON1440
S2CON1441
S2CON1442
S2CON1443
S2CON1444
S2CON1445
S2CON1446
02
30-Oct-2012
01-Nov-2012
03-Nov-2012
20-Nov-2012
23-Nov-2012
24-Nov-2012
26-Nov-2012
13-Nov-2012
14-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
12-Nov-2012
14-Nov-2012
15-Nov-2012
16-Nov-2012
26-Oct-2012
17-Sep-2012
01-Nov-2012
03-Nov-2012
14-Nov-2012
24-Nov-2012
26-Nov-2012
27-Nov-2012
28-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
19-Nov-2012
23-Nov-2012
15-Nov-2012
16-Nov-2012
17-Nov-2012
19-Nov-2012
29-Oct-2012
06-Nov-2012
05-OCT-12A
08-OCT-12A
10-OCT-12A
12-OCT-12A
06-DEC-12A
07-DEC-12A
08-DEC-12A
12-DEC-12A
14-DEC-12A
15-DEC-12A
17-DEC-12A
18-DEC-12A
12-DEC-12A
14-DEC-12A
15-DEC-12A
17-DEC-12A
28-SEP-12A
11-Sep-2012A
24-NOV-12A
10-DEC-12A
11-DEC-12A
03-DEC-12A
27-FEB-13A
24-JAN-13A
25-JAN-13A
14-JAN-13A
15-JAN-13A
16-JAN-13A
17-JAN-13A
12-JAN-13A
13-JAN-13A
14-JAN-13A
15-JAN-13A
16-JAN-13A
22-NOV-12A
31-May-2013
-19d
-30d
-22d
-7d
-79d
-50d
-49d
-50d
-50d
-50d
-50d
-42d
-50d
-49d
-49d
-49d
-20d
-177d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00006
S2CON00007
S2CON00008
S2CON00009
S2CON00010
S2CON00011
S2CON00012
S2CON00013
S2CON00014
S2CON00015
S2CON00016
S2CON00017
S2CON00018
S2CON00019
S2CON00020
S2CON00021
S2CON00022
S2CON00023
17-Sep-2012
18-Sep-2012
19-Sep-2012
20-Sep-2012
21-Sep-2012
22-Sep-2012
24-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
10-Oct-2012
19-Sep-2012
20-Sep-2012
21-Sep-2012
22-Sep-2012
24-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
16-Oct-2012
12-Oct-2012
11-SEP-12A
12-SEP-12A
14-SEP-12A
15-SEP-12A
18-SEP-12A
19-SEP-12A
21-SEP-12A
29-SEP-12A
01-OCT-12A
03-OCT-12A
05-OCT-12A
08-OCT-12A
15-OCT-12A
16-OCT-12A
17-OCT-12A
19-OCT-12A
26-SEP-12A
04-DEC-12A
10-OCT-12A
03-OCT-12A
05-OCT-12A
06-OCT-12A
08-OCT-12A
09-OCT-12A
13-OCT-12A
03-OCT-12A
05-OCT-12A
06-OCT-12A
08-OCT-12A
15-OCT-12A
27-OCT-12A
29-OCT-12A
03-NOV-12A
08-NOV-12A
03-DEC-12A
06-DEC-12A
-17d
-10d
-11d
-11d
-11d
-11d
-15d
-4d
-5d
-5d
-5d
-10d
-20d
-20d
-24d
-27d
-40d
-47d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00024
S2CON00025
S2CON00026
S2CON00027
S2CON00028
S2CON00029
S2CON00030
S2CON00031
S2CON00032
S2CON00033
S2CON00038
S2CON00039
S2CON00040
S2CON00041
S2CON00042
S2CON00034
S2CON00035
S2CON00036
11-Oct-2012
12-Oct-2012
13-Oct-2012
15-Oct-2012
17-Oct-2012
18-Oct-2012
20-Oct-2012
22-Oct-2012
24-Oct-2012
25-Oct-2012
26-Oct-2012
29-Oct-2012
01-Nov-2012
02-Nov-2012
03-Nov-2012
13-Oct-2012
16-Oct-2012
17-Oct-2012
13-Oct-2012
15-Oct-2012
13-Oct-2012
18-Oct-2012
19-Oct-2012
19-Oct-2012
22-Oct-2012
24-Oct-2012
25-Oct-2012
25-Oct-2012
01-Nov-2012
02-Nov-2012
03-Nov-2012
05-Nov-2012
06-Nov-2012
17-Oct-2012
18-Oct-2012
19-Oct-2012
06-DEC-12A
07-DEC-12A
09-DEC-12A
10-DEC-12A
10-DEC-12A
14-DEC-12A
13-DEC-12A
13-DEC-12A
14-DEC-12A
15-DEC-12A
26-NOV-12A
27-NOV-12A
29-NOV-12A
05-DEC-12A
08-DEC-12A
22-NOV-12A
23-NOV-12A
24-NOV-12A
07-DEC-12A
08-DEC-12A
09-DEC-12A
13-DEC-12A
13-DEC-12A
14-DEC-12A
14-DEC-12A
14-DEC-12A
14-DEC-12A
15-DEC-12A
12-DEC-12A
10-DEC-12A
12-DEC-12A
13-DEC-12A
14-DEC-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
-47d
-46d
-48d
-48d
-47d
-48d
-45d
-43d
-42d
-43d
-35d
-31d
-33d
-33d
-33d
-37d
-36d
-35d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00037
03
S2CON00092
S2CON00093
S2CON00094
S2CON00095
S2CON00096
S2CON00097
S2CON00098
S2CON00099
S2CON00100
S2CON00101
S2CON00102
S2CON00103
S2CON00104
S2CON00105
S2CON00106
S2CON00107
18-Oct-2012
18-Sep-2012
18-Sep-2012
19-Sep-2012
20-Sep-2012
21-Sep-2012
22-Sep-2012
24-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
20-Oct-2012
05-Nov-2012
20-Sep-2012
21-Sep-2012
22-Sep-2012
24-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
08-Oct-2012
24-NOV-12A
18-Sep-2012A
18-SEP-12A
18-SEP-12A
21-SEP-12A
29-SEP-12A
30-SEP-12A
01-OCT-12A
02-OCT-12A
03-OCT-12A
05-OCT-12A
06-OCT-12A
07-OCT-12A
08-OCT-12A
11-OCT-12A
12-OCT-12A
15-OCT-12A
17-OCT-12A
29-NOV-12A
31-May-2013
22-SEP-12A
19-OCT-12A
06-OCT-12A
08-OCT-12A
11-OCT-12A
22-OCT-12A
24-OCT-12A
26-OCT-12A
05-NOV-12A
08-NOV-12A
12-NOV-12A
15-NOV-12A
17-NOV-12A
13-NOV-12A
14-NOV-12A
16-NOV-12A
-34d
-178d
-1d
-24d
-11d
-11d
-13d
-21d
-22d
-23d
-30d
-32d
-34d
-36d
-37d
-32d
-32d
-33d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00108
S2CON00109
S2CON00110
S2CON00111
S2CON00112
S2CON00113
S2CON00115
S2CON00116
S2CON00117
S2CON00118
S2CON00114
04
S2CON1373
S2CON1374
S2CON1375
S2CON1376
S2CON1377
S2CON1378
06-Oct-2012
08-Oct-2012
16-Oct-2012
18-Oct-2012
19-Oct-2012
20-Oct-2012
24-Oct-2012
27-Oct-2012
30-Oct-2012
01-Nov-2012
22-Oct-2012
21-Sep-2012
21-Sep-2012
22-Sep-2012
24-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
09-Oct-2012
18-Oct-2012
19-Oct-2012
20-Oct-2012
22-Oct-2012
23-Oct-2012
29-Oct-2012
31-Oct-2012
02-Nov-2012
05-Nov-2012
27-Oct-2012
07-Nov-2012
24-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
18-OCT-12A
26-OCT-12A
20-NOV-12A
21-NOV-12A
22-NOV-12A
23-NOV-12A
27-NOV-12A
29-NOV-12A
29-NOV-12A
03-DEC-12A
24-NOV-12A
05-Sep-2012A
05-SEP-12A
06-SEP-12A
07-SEP-12A
08-SEP-12A
10-SEP-12A
11-SEP-12A
18-OCT-12A
06-DEC-12A
07-DEC-12A
08-DEC-12A
08-DEC-12A
10-DEC-12A
10-JAN-13A
11-JAN-13A
12-JAN-13A
13-JAN-13A
08-JAN-13A
31-May-2013
19-OCT-12A
06-OCT-12A
08-OCT-12A
11-OCT-12A
22-OCT-12A
24-OCT-12A
-7d
-41d
-41d
-41d
-40d
-40d
-62d
-61d
-60d
-59d
-61d
-176d
-22d
-9d
-9d
-11d
-19d
-20d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1379
S2CON1380
S2CON1381
S2CON1382
S2CON1383
S2CON1384
S2CON1385
S2CON1386
S2CON1387
S2CON1388
S2CON1389
S2CON1390
S2CON1391
S2CON1392
S2CON1393
S2CON1394
S2CON1395
S2CON1396
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
08-Oct-2012
09-Oct-2012
10-Oct-2012
18-Oct-2012
20-Oct-2012
22-Oct-2012
23-Oct-2012
26-Oct-2012
30-Oct-2012
01-Nov-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
08-Oct-2012
09-Oct-2012
10-Oct-2012
11-Oct-2012
20-Oct-2012
22-Oct-2012
23-Oct-2012
24-Oct-2012
25-Oct-2012
31-Oct-2012
02-Nov-2012
05-Nov-2012
12-SEP-12A
13-SEP-12A
14-SEP-12A
15-SEP-12A
17-SEP-12A
18-SEP-12A
19-SEP-12A
20-SEP-12A
21-SEP-12A
22-SEP-12A
26-OCT-12A
15-OCT-12A
16-OCT-12A
18-OCT-12A
22-OCT-12A
27-NOV-12A
29-NOV-12A
29-NOV-12A
26-OCT-12A
05-NOV-12A
08-NOV-12A
12-NOV-12A
15-NOV-12A
17-NOV-12A
13-NOV-12A
14-NOV-12A
16-NOV-12A
18-OCT-12A
06-DEC-12A
07-DEC-12A
08-DEC-12A
08-DEC-12A
10-DEC-12A
08-JAN-13A
10-JAN-13A
11-JAN-13A
-21d
-28d
-30d
-32d
-34d
-35d
-30d
-30d
-31d
-5d
-39d
-39d
-39d
-38d
-38d
-58d
-58d
-57d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON1397
S2CON1402
01
S2CON00050
S2CON00051
S2CON00052
S2CON00053
S2CON00054
S2CON00055
S2CON00056
S2CON00057
S2CON00058
S2CON00059
S2CON00060
S2CON00061
S2CON00062
S2CON00063
S2CON00064
03-Nov-2012
24-Oct-2012
15-Sep-2012
15-Sep-2012
17-Sep-2012
18-Sep-2012
19-Sep-2012
20-Sep-2012
21-Sep-2012
22-Sep-2012
24-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
07-Nov-2012
30-Oct-2012
02-Nov-2012
18-Sep-2012
19-Sep-2012
20-Sep-2012
21-Sep-2012
22-Sep-2012
24-Sep-2012
25-Sep-2012
26-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
03-DEC-12A
10-NOV-12A
19-Sep-2012A
19-SEP-12A
24-SEP-12A
26-SEP-12A
28-SEP-12A
29-SEP-12A
03-OCT-12A
05-OCT-12A
08-OCT-12A
09-OCT-12A
10-OCT-12A
11-OCT-12A
20-OCT-12A
26-OCT-12A
04-NOV-12A
08-NOV-12A
12-JAN-13A
05-DEC-12A
31-May-2013
02-OCT-12A
08-OCT-12A
11-OCT-12A
25-OCT-12A
28-OCT-12A
01-NOV-12A
09-OCT-12A
13-OCT-12A
25-OCT-12A
31-OCT-12A
15-NOV-12A
31-OCT-12A
07-NOV-12A
15-NOV-12A
18-NOV-12A
-56d
-30d
-180d
-11d
-15d
-17d
-28d
-30d
-32d
-12d
-14d
-23d
-27d
-39d
-25d
-30d
-36d
-38d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00065
S2CON00066
S2CON00067
S2CON00069
S2CON00070
S2CON00071
S2CON00072
S2CON00073
S2CON00083
S2CON00084
S2CON00085
S2CON00086
S2CON00078
S2CON00079
S2CON00080
S2CON00081
S2CON00082
S2CON00074
27-Sep-2012
28-Sep-2012
29-Sep-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
06-Oct-2012
09-Oct-2012
25-Oct-2012
29-Oct-2012
30-Oct-2012
31-Oct-2012
18-Oct-2012
19-Oct-2012
20-Oct-2012
22-Oct-2012
23-Oct-2012
17-Oct-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
09-Oct-2012
19-Oct-2012
30-Oct-2012
31-Oct-2012
01-Nov-2012
02-Nov-2012
20-Oct-2012
22-Oct-2012
23-Oct-2012
24-Oct-2012
29-Oct-2012
20-Oct-2012
05-NOV-12A
07-NOV-12A
10-NOV-12A
16-NOV-12A
19-NOV-12A
20-NOV-12A
22-NOV-12A
24-OCT-12A
06-DEC-12A
07-DEC-12A
08-DEC-12A
10-DEC-12A
03-DEC-12A
04-DEC-12A
05-DEC-12A
06-DEC-12A
21-NOV-12A
21-NOV-12A
09-NOV-12A
12-NOV-12A
16-NOV-12A
18-NOV-12A
20-NOV-12A
21-NOV-12A
23-NOV-12A
05-DEC-12A
23-JAN-13A
24-JAN-13A
25-JAN-13A
27-JAN-13A
05-DEC-12A
06-DEC-12A
07-DEC-12A
08-DEC-12A
10-DEC-12A
29-NOV-12A
-34d
-35d
-38d
-38d
-38d
-38d
-38d
-40d
-72d
-73d
-73d
-73d
-39d
-39d
-39d
-39d
-35d
-34d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00075
S2CON00076
S2CON00077
S2CON00068
07
S2CON00166
S2CON00167
S2CON00168
S2CON00169
S2CON00170
S2CON00171
S2CON00172
S2CON00173
S2CON00174
S2CON00175
S2CON00176
S2CON00177
S2CON00178
19-Oct-2012
20-Oct-2012
22-Oct-2012
01-Oct-2012
20-Sep-2012
20-Sep-2012
27-Sep-2012
28-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
08-Oct-2012
09-Oct-2012
10-Oct-2012
22-Oct-2012
23-Oct-2012
24-Oct-2012
03-Oct-2012
10-Nov-2012
27-Sep-2012
29-Sep-2012
01-Oct-2012
02-Oct-2012
03-Oct-2012
04-Oct-2012
05-Oct-2012
06-Oct-2012
08-Oct-2012
09-Oct-2012
10-Oct-2012
11-Oct-2012
12-Oct-2012
22-NOV-12A
23-NOV-12A
24-NOV-12A
12-NOV-12A
04-Oct-2012A
04-OCT-12A
05-OCT-12A
06-OCT-12A
08-OCT-12A
10-OCT-12A
12-OCT-12A
13-OCT-12A
13-OCT-12A
15-OCT-12A
17-OCT-12A
19-OCT-12A
22-OCT-12A
24-OCT-12A
30-NOV-12A
30-NOV-12A
01-DEC-12A
17-NOV-12A
31-May-2013
06-OCT-12A
08-OCT-12A
08-NOV-12A
10-NOV-12A
12-NOV-12A
13-NOV-12A
14-NOV-12A
15-NOV-12A
16-NOV-12A
17-NOV-12A
19-NOV-12A
20-NOV-12A
21-NOV-12A
-33d
-32d
-32d
-38d
-173d
-8d
-6d
-32d
-33d
-33d
-33d
-33d
-33d
-33d
-33d
-33d
-33d
-33d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON00179
S2CON00180
S2CON00181
S2CON00182
S2CON00183
S2CON00192
S2CON00202
S2CON00203
S2CON00204
S2CON00205
S2CON00201
S2CON00193
S2CON00194
S2CON00195
S2CON00196
002
08
S2CON3148
11-Oct-2012
12-Oct-2012
13-Oct-2012
15-Oct-2012
16-Oct-2012
17-Oct-2012
02-Nov-2012
06-Nov-2012
07-Nov-2012
08-Nov-2012
31-Oct-2012
25-Oct-2012
27-Oct-2012
29-Oct-2012
30-Oct-2012
30-Nov-2012
26-Dec-2012
31-Dec-2012
13-Oct-2012
15-Oct-2012
16-Oct-2012
17-Oct-2012
18-Oct-2012
27-Oct-2012
07-Nov-2012
08-Nov-2012
09-Nov-2012
10-Nov-2012
06-Nov-2012
29-Oct-2012
30-Oct-2012
31-Oct-2012
01-Nov-2012
08-Jan-2013
08-Jan-2013
07-Jan-2013
26-OCT-12A
27-OCT-12A
29-OCT-12A
30-OCT-12A
31-OCT-12A
05-NOV-12A
06-DEC-12A
07-DEC-12A
08-DEC-12A
09-DEC-12A
08-DEC-12A
12-DEC-12A
12-DEC-12A
13-DEC-12A
14-DEC-12A
25-Dec-2012A
29-Apr-2013A
03-JUN-13
22-NOV-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
29-NOV-12A
03-DEC-12A
03-JAN-13A
04-JAN-13A
05-JAN-13A
06-JAN-13A
02-JAN-13A
14-DEC-12A
14-DEC-12A
15-DEC-12A
17-DEC-12A
11-Jun-2013
11-Jun-2013
10-JUN-13
-33d
-38d
-37d
-36d
-35d
-31d
-48d
-48d
-48d
-48d
-48d
-40d
-39d
-39d
-39d
-132d
-132d
-132d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON3149
S2CON3146
S2CON3147
05
S2CON3134
S2CON3135
S2CON3136
S2CON3137
01
S2CON3122
S2CON3123
S2CON3124
S2CON3125
04
S2CON3130
S2CON3131
S2CON3132
S2CON3133
08-Jan-2013
26-Dec-2012
28-Dec-2012
22-Dec-2012
22-Dec-2012
25-Dec-2012
27-Dec-2012
04-Jan-2013
30-Nov-2012
30-Nov-2012
03-Dec-2012
05-Dec-2012
13-Dec-2012
18-Dec-2012
18-Dec-2012
20-Dec-2012
22-Dec-2012
31-Dec-2012
08-Jan-2013
02-Jan-2013
04-Jan-2013
04-Jan-2013
29-Dec-2012
01-Jan-2013
03-Jan-2013
04-Jan-2013
13-Dec-2012
07-Dec-2012
10-Dec-2012
12-Dec-2012
13-Dec-2012
31-Dec-2012
25-Dec-2012
27-Dec-2012
29-Dec-2012
31-Dec-2012
11-JUN-13
29-APR-13A
27-MAY-13A
15-Apr-2013A
15-APR-13A
18-APR-13A
29-APR-13A
08-JUN-13
21-Mar-2013A
21-MAR-13A
26-MAR-13A
26-MAR-13A
29-MAR-13A
18-Mar-2013A
18-MAR-13A
20-MAR-13A
22-MAR-13A
30-MAR-13A
11-JUN-13
31-MAY-13A
07-JUN-13
08-Jun-2013
17-APR-13A
20-APR-13A
07-JUN-13
08-JUN-13
31-May-2013
25-MAR-13A
27-MAR-13A
28-MAR-13A
29-MAR-13A
31-May-2013
26-MAR-13A
26-MAR-13A
26-MAR-13A
30-MAR-13A
-132d
-128d
-132d
-133d
-92d
-93d
-133d
-133d
-145d
-91d
-91d
-90d
-90d
-130d
-78d
-76d
-74d
-76d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
07
S2CON3142
S2CON3143
S2CON3144
S2CON3145
02
S2CON2977
S2CON2978
S2CON2979
S2CON2980
06
S2CON3138
S2CON3139
S2CON3140
S2CON3141
03
S2CON3126
S2CON3127
08-Dec-2012
08-Dec-2012
11-Dec-2012
13-Dec-2012
21-Dec-2012
04-Dec-2012
04-Dec-2012
06-Dec-2012
08-Dec-2012
17-Dec-2012
18-Dec-2012
18-Dec-2012
20-Dec-2012
22-Dec-2012
31-Dec-2012
14-Dec-2012
14-Dec-2012
17-Dec-2012
21-Dec-2012
15-Dec-2012
18-Dec-2012
20-Dec-2012
21-Dec-2012
17-Dec-2012
11-Dec-2012
13-Dec-2012
15-Dec-2012
17-Dec-2012
31-Dec-2012
25-Dec-2012
27-Dec-2012
29-Dec-2012
31-Dec-2012
27-Dec-2012
21-Dec-2012
24-Dec-2012
18-Mar-2013A
18-MAR-13A
20-MAR-13A
22-MAR-13A
30-MAR-13A
25-Dec-2012A
20-FEB-13A
22-FEB-13A
24-FEB-13A
25-DEC-12A
15-Apr-2013A
15-APR-13A
29-APR-13A
01-MAY-13A
09-MAY-13A
18-Mar-2013A
18-MAR-13A
20-MAR-13A
31-May-2013
17-APR-13A
17-APR-13A
17-APR-13A
17-APR-13A
31-May-2013
17-APR-13A
17-APR-13A
17-APR-13A
26-MAR-13A
31-May-2013
19-APR-13A
10-MAY-13A
25-MAY-13A
12-MAY-13A
31-May-2013
26-MAR-13A
26-MAR-13A
-138d
-104d
-102d
-100d
-100d
-142d
-108d
-106d
-104d
-85d
-130d
-98d
-114d
-126d
-113d
-133d
-81d
-79d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON3128
S2CON3129
5
CIVILDWG001
CIVILDWG002
CIVILDWG003
4
001
MEP001
MEP002
MEP003
MEP004
006
MEP021
MEP022
MEP023
MEP024
002
19-Dec-2012
27-Dec-2012
23-Aug-2012
23-Aug-2012
23-Aug-2012
14-Feb-2013
03-Nov-2012
06-Dec-2012
06-Dec-2012
29-Dec-2012
07-Jan-2013
15-Jan-2013
24-Nov-2012
24-Nov-2012
18-Dec-2012
26-Dec-2012
03-Jan-2013
03-Nov-2012
26-Dec-2012
27-Dec-2012
24-Apr-2013
31-Oct-2012
31-Oct-2012
24-Apr-2013
12-Apr-2013
22-Jan-2013
28-Dec-2012
05-Jan-2013
14-Jan-2013
22-Jan-2013
10-Jan-2013
17-Dec-2012
25-Dec-2012
02-Jan-2013
10-Jan-2013
20-Dec-2012
22-MAR-13A
30-MAR-13A
23-Aug-2012A
23-AUG-12A
23-AUG-12A
31-MAY-13
07-Jun-2013
12-Jul-2013
12-JUL-13
05-AUG-13
13-AUG-13
21-AUG-13
12-Jun-2013
12-JUN-13
05-JUL-13
13-JUL-13
22-JUL-13
07-Jun-2013
26-MAR-13A
30-MAR-13A
08-Aug-2013
06-JUN-13
03-JUN-13
08-AUG-13
18-Sep-2013
28-Aug-2013
03-AUG-13
12-AUG-13
20-AUG-13
28-AUG-13
29-Jul-2013
04-JUL-13
12-JUL-13
20-JUL-13
29-JUL-13
24-Jul-2013
-77d
-79d
-91d
-187d
-184d
-91d
-136d
-187d
-187d
-187d
-187d
-187d
-171d
-171d
-171d
-171d
-171d
-185d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
MEP005
MEP006
MEP007
MEP008
004
MEP013
MEP014
MEP015
MEP016
003
MEP009
MEP010
MEP011
MEP012
008
MEP029
MEP030
MEP031
03-Nov-2012
27-Nov-2012
05-Dec-2012
13-Dec-2012
05-Nov-2012
05-Nov-2012
28-Nov-2012
06-Dec-2012
14-Dec-2012
03-Nov-2012
03-Nov-2012
27-Nov-2012
05-Dec-2012
13-Dec-2012
25-Feb-2013
25-Feb-2013
20-Mar-2013
28-Mar-2013
26-Nov-2012
04-Dec-2012
12-Dec-2012
20-Dec-2012
21-Dec-2012
27-Nov-2012
05-Dec-2012
13-Dec-2012
21-Dec-2012
20-Dec-2012
26-Nov-2012
04-Dec-2012
12-Dec-2012
20-Dec-2012
12-Apr-2013
19-Mar-2013
27-Mar-2013
04-Apr-2013
07-JUN-13
01-JUL-13
09-JUL-13
17-JUL-13
07-Jun-2013
07-JUN-13
01-JUL-13
09-JUL-13
17-JUL-13
07-Jun-2013
07-JUN-13
01-JUL-13
09-JUL-13
17-JUL-13
02-Aug-2013
02-AUG-13
26-AUG-13
03-SEP-13
29-JUN-13
08-JUL-13
16-JUL-13
24-JUL-13
24-Jul-2013
29-JUN-13
08-JUL-13
16-JUL-13
24-JUL-13
24-Jul-2013
29-JUN-13
08-JUL-13
16-JUL-13
24-JUL-13
18-Sep-2013
24-AUG-13
02-SEP-13
10-SEP-13
-185d
-185d
-185d
-185d
-184d
-184d
-184d
-184d
-184d
-185d
-185d
-185d
-185d
-185d
-136d
-136d
-136d
-136d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
MEP032
007
MEP025
MEP026
MEP027
MEP028
005
MEP017
MEP018
MEP019
MEP020
2
1
7
S2CON2892
S2CON2794
S2CON2822
S2CON2808
05-Apr-2013
11-Feb-2013
11-Feb-2013
06-Mar-2013
14-Mar-2013
22-Mar-2013
06-Nov-2012
06-Nov-2012
29-Nov-2012
07-Dec-2012
15-Dec-2012
22-Mar-2013
24-Aug-2013
09-Nov-2013
29-Jan-2014
09-Nov-2013
09-Jan-2014
25-Jan-2014
12-Apr-2013
29-Mar-2013
05-Mar-2013
13-Mar-2013
21-Mar-2013
29-Mar-2013
22-Dec-2012
28-Nov-2012
06-Dec-2012
14-Dec-2012
22-Dec-2012
20-Feb-2014
20-Feb-2014
20-Feb-2014
20-Feb-2014
02-Dec-2013
31-Jan-2014
17-Feb-2014
11-SEP-13
15-Jun-2013
15-JUN-13
09-JUL-13
17-JUL-13
25-JUL-13
07-Jun-2013
07-JUN-13
01-JUL-13
09-JUL-13
17-JUL-13
03-Aug-2013
30-Nov-2013
15-Feb-2014
22-MAR-14
15-FEB-14
28-MAR-14
05-APR-14
18-SEP-13
01-Aug-2013
08-JUL-13
16-JUL-13
24-JUL-13
01-AUG-13
24-Jul-2013
29-JUN-13
08-JUL-13
16-JUL-13
24-JUL-13
06-Jun-2014
06-Jun-2014
06-Jun-2014
11-APR-14
10-MAR-14
19-APR-14
28-APR-14
-136d
-107d
-107d
-107d
-107d
-107d
-183d
-183d
-183d
-183d
-183d
-91d
-91d
-91d
-43d
-84d
-67d
-60d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2850
S2CON2878
S2CON2836
S2CON2864
5
S2CON2598
S2CON2612
S2CON2640
S2CON2584
S2CON2570
S2CON2654
S2CON2668
S2CON2626
6
S2CON2738
S2CON2710
S2CON2724
S2CON2752
06-Jan-2014
08-Jan-2014
20-Jan-2014
23-Jan-2014
26-Oct-2013
28-Nov-2013
09-Dec-2013
12-Dec-2013
17-Dec-2013
26-Oct-2013
28-Nov-2013
19-Dec-2013
25-Nov-2013
04-Nov-2013
25-Dec-2013
20-Dec-2013
31-Dec-2013
03-Jan-2014
28-Jan-2014
30-Jan-2014
11-Feb-2014
14-Feb-2014
10-Jan-2014
20-Dec-2013
31-Dec-2013
03-Jan-2014
08-Jan-2014
18-Nov-2013
20-Dec-2013
10-Jan-2014
17-Dec-2013
30-Jan-2014
16-Jan-2014
11-Jan-2014
22-Jan-2014
25-Jan-2014
15-MAY-14
17-MAR-14
28-MAR-14
28-MAR-14
17-Jan-2014
10-FEB-14
10-FEB-14
10-FEB-14
19-FEB-14
17-JAN-14
29-JAN-14
29-JAN-14
29-MAR-14
23-Jan-2014
22-APR-14
05-MAR-14
11-MAR-14
12-FEB-14
06-JUN-14
08-APR-14
19-APR-14
19-APR-14
21-Apr-2014
04-MAR-14
04-MAR-14
04-MAR-14
13-MAR-14
08-FEB-14
20-FEB-14
20-FEB-14
21-APR-14
14-May-2014
14-MAY-14
27-MAR-14
27-MAR-14
06-MAR-14
-111d
-58d
-58d
-55d
-86d
-63d
-54d
-51d
-55d
-71d
-53d
-35d
-107d
-89d
-101d
-64d
-55d
-34d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2696
S2CON2682
S2CON2766
S2CON2780
3
S2CON2430
S2CON2402
S2CON2374
S2CON2388
S2CON2416
S2CON2360
S2CON2346
S2CON2444
4
S2CON2542
S2CON2514
S2CON2458
S2CON2486
07-Jan-2014
04-Nov-2013
19-Dec-2013
08-Jan-2014
01-Oct-2013
05-Oct-2013
23-Oct-2013
18-Oct-2013
29-Oct-2013
01-Nov-2013
06-Nov-2013
01-Oct-2013
31-Oct-2013
11-Oct-2013
30-Oct-2013
26-Oct-2013
11-Oct-2013
30-Oct-2013
29-Jan-2014
26-Nov-2013
10-Jan-2014
30-Jan-2014
28-Nov-2013
28-Oct-2013
14-Nov-2013
09-Nov-2013
20-Nov-2013
23-Nov-2013
28-Nov-2013
23-Oct-2013
22-Nov-2013
14-Dec-2013
21-Nov-2013
18-Nov-2013
02-Nov-2013
21-Nov-2013
14-MAR-14
23-JAN-14
21-FEB-14
21-FEB-14
10-Jan-2014
17-JAN-14
11-FEB-14
10-JAN-14
10-JAN-14
10-JAN-14
22-JAN-14
17-JAN-14
17-JAN-14
17-Jan-2014
17-JAN-14
06-MAR-14
17-JAN-14
22-JAN-14
05-APR-14
14-FEB-14
15-MAR-14
15-MAR-14
05-Mar-2014
08-FEB-14
05-MAR-14
01-FEB-14
01-FEB-14
01-FEB-14
13-FEB-14
08-FEB-14
08-FEB-14
28-Mar-2014
08-FEB-14
28-MAR-14
08-FEB-14
13-FEB-14
-57d
-69d
-55d
-38d
-83d
-89d
-95d
-72d
-63d
-60d
-66d
-93d
-67d
-89d
-68d
-112d
-84d
-72d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2500
S2CON2528
S2CON2472
S2CON2556
1
S2CON00783
S2CON00811
S2CON00797
S2CON2206
S2CON2220
S2CON00769
S2CON00825
S2CON00755
2
S2CON2304
S2CON2318
S2CON2332
S2CON2248
09-Nov-2013
13-Nov-2013
18-Nov-2013
22-Nov-2013
24-Aug-2013
07-Sep-2013
16-Sep-2013
11-Sep-2013
28-Aug-2013
21-Sep-2013
28-Aug-2013
06-Sep-2013
24-Aug-2013
13-Sep-2013
10-Oct-2013
13-Sep-2013
02-Oct-2013
15-Oct-2013
02-Dec-2013
05-Dec-2013
10-Dec-2013
14-Dec-2013
25-Oct-2013
30-Sep-2013
08-Oct-2013
03-Oct-2013
19-Sep-2013
25-Oct-2013
19-Sep-2013
28-Sep-2013
16-Sep-2013
06-Nov-2013
01-Nov-2013
05-Oct-2013
05-Nov-2013
06-Nov-2013
22-JAN-14
22-JAN-14
27-JAN-14
17-JAN-14
11-Jan-2014
16-JAN-14
25-JAN-14
16-JAN-14
11-JAN-14
30-JAN-14
16-JAN-14
11-JAN-14
16-JAN-14
30-Nov-2013
07-FEB-14
30-NOV-13
05-DEC-13
10-FEB-14
13-FEB-14
13-FEB-14
18-FEB-14
08-FEB-14
05-Mar-2014
07-FEB-14
17-FEB-14
07-FEB-14
03-FEB-14
05-MAR-14
07-FEB-14
03-FEB-14
07-FEB-14
05-Mar-2014
01-MAR-14
23-DEC-13
08-JAN-14
05-MAR-14
-63d
-60d
-60d
-48d
-112d
-112d
-113d
-109d
-117d
-112d
-121d
-109d
-124d
-102d
-103d
-67d
-55d
-102d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CON2262
S2CON2234
S2CON2276
S2CON2290
2
3
2
S2CONP11650
S2CONP11566
S2CONP11578
S2CONP11590
1
S2CONP11662
S2CONP11674
S2CONP11686
S2CONP11698
S2CONP11710
S2CONP11722
26-Sep-2013
21-Sep-2013
07-Oct-2013
23-Sep-2013
22-Mar-2013
26-Jul-2013
26-Jul-2013
19-Sep-2013
26-Jul-2013
03-Aug-2013
10-Aug-2013
09-Sep-2013
09-Sep-2013
18-Sep-2013
25-Sep-2013
05-Oct-2013
11-Oct-2013
18-Oct-2013
18-Oct-2013
14-Oct-2013
29-Oct-2013
15-Oct-2013
23-Jan-2014
14-Nov-2013
05-Oct-2013
05-Oct-2013
12-Aug-2013
20-Aug-2013
27-Aug-2013
14-Nov-2013
25-Sep-2013
04-Oct-2013
11-Oct-2013
22-Oct-2013
28-Oct-2013
04-Nov-2013
10-JAN-14
17-JAN-14
29-JAN-14
18-JAN-14
03-Aug-2013
17-Aug-2013
17-Aug-2013
21-SEP-13
17-AUG-13
17-AUG-13
17-AUG-13
14-Nov-2013
14-NOV-13
20-DEC-13
14-NOV-13
15-NOV-13
06-DEC-13
29-NOV-13
01-FEB-14
08-FEB-14
20-FEB-14
10-FEB-14
15-Feb-2014
06-Jan-2014
08-Oct-2013
08-OCT-13
03-SEP-13
03-SEP-13
03-SEP-13
06-Jan-2014
30-NOV-13
06-JAN-14
30-NOV-13
02-DEC-13
23-DEC-13
16-DEC-13
-91d
-101d
-98d
-101d
-20d
-45d
-2d
-2d
-19d
-12d
-6d
-45d
-57d
-80d
-43d
-35d
-48d
-36d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11734
S2CONP11746
1
2
S2CONP11213
S2CONP11224
S2CONP11246
S2CONP11257
S2CONP11268
S2CONP11235
S2CONP11279
S2CONP11290
1
S2CONP11301
S2CONP11323
S2CONP11334
S2CONP11312
S2CONP11356
26-Oct-2013
29-Oct-2013
22-Mar-2013
22-Mar-2013
22-Mar-2013
25-Mar-2013
01-Apr-2013
08-Apr-2013
13-Apr-2013
29-Mar-2013
16-Apr-2013
12-Apr-2013
01-Apr-2013
01-Apr-2013
17-Apr-2013
27-Apr-2013
10-Apr-2013
10-May-2013
12-Nov-2013
14-Nov-2013
07-Jun-2013
02-May-2013
08-Apr-2013
10-Apr-2013
17-Apr-2013
24-Apr-2013
30-Apr-2013
15-Apr-2013
02-May-2013
29-Apr-2013
07-Jun-2013
17-Apr-2013
03-May-2013
14-May-2013
26-Apr-2013
27-May-2013
29-NOV-13
06-DEC-13
03-Aug-2013
03-Aug-2013
20-AUG-13
20-AUG-13
15-AUG-13
12-AUG-13
09-AUG-13
20-AUG-13
03-AUG-13
20-AUG-13
17-Aug-2013
17-AUG-13
17-AUG-13
17-AUG-13
26-AUG-13
17-AUG-13
17-DEC-13
24-DEC-13
11-Sep-2013
05-Sep-2013
05-SEP-13
05-SEP-13
31-AUG-13
28-AUG-13
26-AUG-13
05-SEP-13
20-AUG-13
05-SEP-13
11-Sep-2013
03-SEP-13
03-SEP-13
03-SEP-13
11-SEP-13
03-SEP-13
-29d
-33d
-82d
-108d
-129d
-127d
-117d
-108d
-101d
-123d
-94d
-111d
-82d
-119d
-105d
-96d
-118d
-85d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11345
S2CONP11367
S2CONP11378
2
2
S2CONP11389
S2CONP11400
S2CONP11411
S2CONP11422
S2CONP11433
S2CONP11444
S2CONP11455
S2CONP11466
1
S2CONP11477
S2CONP11488
S2CONP11499
S2CONP11510
03-May-2013
18-May-2013
22-May-2013
07-May-2013
07-May-2013
07-May-2013
15-May-2013
22-May-2013
31-May-2013
08-Jun-2013
17-Jun-2013
25-Jun-2013
01-Jul-2013
20-Jun-2013
20-Jun-2013
29-Jun-2013
06-Jul-2013
17-Jul-2013
20-May-2013
04-Jun-2013
07-Jun-2013
26-Aug-2013
17-Jul-2013
23-May-2013
31-May-2013
07-Jun-2013
17-Jun-2013
25-Jun-2013
03-Jul-2013
11-Jul-2013
17-Jul-2013
26-Aug-2013
06-Jul-2013
16-Jul-2013
23-Jul-2013
02-Aug-2013
17-AUG-13
17-AUG-13
17-AUG-13
17-Aug-2013
17-Aug-2013
17-AUG-13
17-AUG-13
17-AUG-13
17-AUG-13
17-AUG-13
17-AUG-13
17-AUG-13
17-AUG-13
17-Sep-2013
17-SEP-13
23-OCT-13
17-SEP-13
18-SEP-13
03-SEP-13
03-SEP-13
03-SEP-13
08-Nov-2013
03-Sep-2013
03-SEP-13
03-SEP-13
03-SEP-13
03-SEP-13
03-SEP-13
03-SEP-13
03-SEP-13
03-SEP-13
08-Nov-2013
03-OCT-13
08-NOV-13
03-OCT-13
04-OCT-13
-91d
-78d
-75d
-64d
-41d
-88d
-81d
-75d
-67d
-60d
-53d
-46d
-41d
-64d
-76d
-99d
-62d
-54d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
S2CONP11521
S2CONP11532
S2CONP11543
S2CONP11554
4
1
S2CONP11887
S2CONP11900
S2CONP11913
S2CONP11926
S2CONP11939
S2CONP11874
2
S2CONP11783
S2CONP11809
4
9
A5640
23-Jul-2013
30-Jul-2013
07-Aug-2013
09-Aug-2013
23-Oct-2013
28-Nov-2013
07-Dec-2013
14-Dec-2013
25-Dec-2013
31-Dec-2013
07-Jan-2014
28-Nov-2013
23-Oct-2013
23-Oct-2013
08-Nov-2013
05-May-2012
25-Jun-2012
25-Jun-2012
08-Aug-2013
15-Aug-2013
23-Aug-2013
26-Aug-2013
23-Jan-2014
23-Jan-2014
24-Dec-2013
31-Dec-2013
10-Jan-2014
16-Jan-2014
23-Jan-2014
14-Dec-2013
25-Nov-2013
08-Nov-2013
25-Nov-2013
12-Apr-2013
01-Oct-2012
25-Jun-2012
09-OCT-13
02-OCT-13
02-OCT-13
09-OCT-13
09-Nov-2013
25-Dec-2013
06-FEB-14
11-JAN-14
26-DEC-13
16-JAN-14
09-JAN-14
25-DEC-13
09-Nov-2013
09-NOV-13
09-NOV-13
04-May-2012A
24-Jul-2012A
24-JUL-12A
25-OCT-13
18-OCT-13
19-OCT-13
26-OCT-13
15-Feb-2014
15-Feb-2014
15-FEB-14
28-JAN-14
11-JAN-14
01-FEB-14
25-JAN-14
09-JAN-14
26-Nov-2013
26-NOV-13
26-NOV-13
06-Sep-2013
31-May-2013
24-JUL-12A
-67d
-55d
-48d
-52d
-20d
-20d
-46d
-24d
-1d
-14d
-2d
-22d
-1d
-15d
-1d
-126d
-208d
-24d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A5650
A5660
A5670
A5680
A5690
A5700
A5710
A5720
A5730
A5740
A5750
A5760
A5770
A5780
A5790
10
A5800
A5810
26-Jun-2012
16-Jul-2012
25-Jul-2012
28-Jul-2012
07-Aug-2012
15-Aug-2012
22-Aug-2012
27-Aug-2012
31-Aug-2012
05-Sep-2012
14-Sep-2012
18-Sep-2012
21-Sep-2012
26-Sep-2012
28-Sep-2012
25-Jun-2012
25-Jun-2012
26-Jun-2012
14-Jul-2012
24-Jul-2012
27-Jul-2012
06-Aug-2012
14-Aug-2012
21-Aug-2012
25-Aug-2012
30-Aug-2012
04-Sep-2012
13-Sep-2012
17-Sep-2012
20-Sep-2012
25-Sep-2012
27-Sep-2012
01-Oct-2012
01-Oct-2012
25-Jun-2012
14-Jul-2012
24-JUL-12A
26-JUL-12A
08-AUG-12A
09-AUG-12A
22-AUG-12A
04-SEP-12A
18-SEP-12A
08-OCT-12A
14-OCT-12A
19-OCT-12A
01-NOV-12A
14-DEC-12A
19-DEC-12A
03-JAN-13A
03-JAN-13A
24-Jul-2012A
24-JUL-12A
24-JUL-12A
26-JUL-12A
08-AUG-12A
09-AUG-12A
22-AUG-12A
04-SEP-12A
18-SEP-12A
08-OCT-12A
14-OCT-12A
19-OCT-12A
01-NOV-12A
14-DEC-12A
19-DEC-12A
03-JAN-13A
03-JAN-13A
03-JAN-13A
31-May-2013
24-JUL-12A
26-JUL-12A
-9d
-12d
-10d
-13d
-17d
-23d
-36d
-38d
-38d
-41d
-75d
-76d
-85d
-83d
-80d
-208d
-24d
-9d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 Main Contrctor 1
5 Pre-bid Meeting with Contractor
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A5820
A5830
A5840
A5850
A5860
A5870
A5880
A5890
A5900
A5910
A5920
A5930
A5940
A5950
31
A1040
A1060
A1070
16-Jul-2012
25-Jul-2012
28-Jul-2012
07-Aug-2012
15-Aug-2012
22-Aug-2012
27-Aug-2012
31-Aug-2012
05-Sep-2012
14-Sep-2012
18-Sep-2012
21-Sep-2012
26-Sep-2012
28-Sep-2012
05-May-2012
05-May-2012
09-Jun-2012
12-Jun-2012
24-Jul-2012
27-Jul-2012
06-Aug-2012
14-Aug-2012
21-Aug-2012
25-Aug-2012
30-Aug-2012
04-Sep-2012
13-Sep-2012
17-Sep-2012
20-Sep-2012
25-Sep-2012
27-Sep-2012
01-Oct-2012
16-Jul-2012
11-May-2012
11-Jun-2012
15-Jun-2012
26-JUL-12A
08-AUG-12A
09-AUG-12A
22-AUG-12A
04-SEP-12A
18-SEP-12A
08-OCT-12A
14-OCT-12A
19-OCT-12A
01-NOV-12A
14-DEC-12A
19-DEC-12A
03-JAN-13A
03-JAN-13A
04-May-2012A
04-MAY-12A
08-JUN-12A
13-JUN-12A
08-AUG-12A
09-AUG-12A
22-AUG-12A
04-SEP-12A
18-SEP-12A
08-OCT-12A
14-OCT-12A
19-OCT-12A
01-NOV-12A
14-DEC-12A
19-DEC-12A
03-JAN-13A
03-JAN-13A
03-JAN-13A
31-May-2013
17-MAY-12A
13-JUN-12A
20-JUN-12A
-12d
-10d
-13d
-17d
-23d
-36d
-38d
-38d
-41d
-75d
-76d
-85d
-83d
-80d
-274d
-4d
-1d
-3d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 Handrail
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A1080
A1090
A1100
A1110
A1120
A1130
A1140
A1150
24
A4230
A4240
A4250
A4260
A4270
A4280
A4290
A4300
A4310
16-Jun-2012
21-Jun-2012
27-Jun-2012
29-Jun-2012
05-Jul-2012
09-Jul-2012
11-Jul-2012
13-Jul-2012
13-Dec-2012
13-Dec-2012
15-Dec-2012
21-Dec-2012
28-Dec-2012
31-Dec-2012
03-Jan-2013
07-Jan-2013
10-Jan-2013
14-Jan-2013
20-Jun-2012
26-Jun-2012
28-Jun-2012
04-Jul-2012
07-Jul-2012
10-Jul-2012
12-Jul-2012
16-Jul-2012
24-Jan-2013
14-Dec-2012
20-Dec-2012
27-Dec-2012
29-Dec-2012
02-Jan-2013
05-Jan-2013
09-Jan-2013
12-Jan-2013
15-Jan-2013
20-JUN-12A
25-JUN-12A
01-JUL-12A
26-JUL-12A
26-JUL-12A
27-JUL-12A
09-AUG-12A
09-AUG-12A
12-Dec-2012A
12-DEC-12A
15-JAN-13A
21-JAN-13A
30-JAN-13A
14-FEB-13A
02-MAY-13A
10-MAY-13A
04-JUN-13
07-JUN-13
25-JUN-12A
01-JUL-12A
26-JUL-12A
26-JUL-12A
27-JUL-12A
09-AUG-12A
09-AUG-12A
09-AUG-12A
18-Jun-2013
15-JAN-13A
21-JAN-13A
30-JAN-13A
14-FEB-13A
07-MAY-13A
10-MAY-13A
03-JUN-13
06-JUN-13
08-JUN-13
-3d
-4d
-23d
-18d
-16d
-25d
-23d
-20d
-124d
-26d
-26d
-28d
-39d
-106d
-106d
-124d
-124d
-124d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A4320
A4330
A4340
A4350
22
A5330
A5340
A5350
A5360
A5370
A5380
A5390
A5400
A5410
A5420
A5430
A5440
A5450
16-Jan-2013
18-Jan-2013
21-Jan-2013
23-Jan-2013
29-Nov-2012
29-Nov-2012
04-Dec-2012
10-Dec-2012
11-Dec-2012
17-Dec-2012
24-Dec-2012
26-Dec-2012
29-Dec-2012
02-Jan-2013
07-Jan-2013
10-Jan-2013
12-Jan-2013
15-Jan-2013
17-Jan-2013
19-Jan-2013
22-Jan-2013
24-Jan-2013
19-Jan-2013
03-Dec-2012
08-Dec-2012
10-Dec-2012
15-Dec-2012
22-Dec-2012
25-Dec-2012
28-Dec-2012
01-Jan-2013
05-Jan-2013
09-Jan-2013
11-Jan-2013
14-Jan-2013
16-Jan-2013
10-JUN-13
12-JUN-13
14-JUN-13
17-JUN-13
20-Nov-2012A
20-NOV-12A
06-DEC-12A
28-DEC-12A
31-DEC-12A
04-JAN-13A
18-JAN-13A
25-JAN-13A
25-JAN-13A
29-JAN-13A
31-JAN-13A
01-FEB-13A
22-FEB-13A
22-APR-13A
11-JUN-13
13-JUN-13
15-JUN-13
18-JUN-13
31-May-2013
06-DEC-12A
28-DEC-12A
31-DEC-12A
04-JAN-13A
18-JAN-13A
25-JAN-13A
25-JAN-13A
29-JAN-13A
31-JAN-13A
01-FEB-13A
22-FEB-13A
22-APR-13A
23-MAY-13A
-124d
-124d
-124d
-124d
-113d
-2d
-16d
-17d
-16d
-22d
-26d
-23d
-23d
-21d
-19d
-35d
-83d
-108d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Draft WO
5 Issue of WO
4 IT Networking
5 Drawing Tender from consultant
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A5460
A5470
20
A3720
A3740
A3750
A3760
A3770
A3780
A3790
A3800
A3810
A3820
A3830
A3840
A3850
A3860
A3870
17-Jan-2013
18-Jan-2013
17-Nov-2012
17-Nov-2012
24-Nov-2012
01-Dec-2012
05-Dec-2012
12-Dec-2012
21-Dec-2012
25-Dec-2012
28-Dec-2012
01-Jan-2013
05-Jan-2013
16-Jan-2013
21-Jan-2013
23-Jan-2013
29-Jan-2013
31-Jan-2013
17-Jan-2013
19-Jan-2013
01-Feb-2013
17-Nov-2012
30-Nov-2012
04-Dec-2012
11-Dec-2012
20-Dec-2012
24-Dec-2012
27-Dec-2012
31-Dec-2012
04-Jan-2013
15-Jan-2013
19-Jan-2013
22-Jan-2013
28-Jan-2013
30-Jan-2013
01-Feb-2013
30-APR-13A
01-MAY-13A
20-Nov-2012A
20-NOV-12A
20-NOV-12A
17-DEC-12A
18-DEC-12A
26-DEC-12A
10-JAN-13A
18-JAN-13A
21-JAN-13A
27-JAN-13A
31-JAN-13A
01-FEB-13A
28-FEB-13A
28-FEB-13A
04-MAY-13A
07-MAY-13A
23-MAY-13A
23-MAY-13A
31-May-2013
20-NOV-12A
17-DEC-12A
18-DEC-12A
26-DEC-12A
10-JAN-13A
18-JAN-13A
21-JAN-13A
27-JAN-13A
31-JAN-13A
01-FEB-13A
28-FEB-13A
28-FEB-13A
23-MAY-13A
23-MAY-13A
23-MAY-13A
-107d
-105d
-102d
-1d
-13d
-11d
-12d
-17d
-21d
-20d
-23d
-22d
-14d
-33d
-31d
-98d
-96d
-94d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
4 Fire Doors
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 Fire Protection System
5 Review of Tender TCS/TCE
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
21
A3910
A3920
A3930
A3940
A3950
A3960
A3970
A3980
A3990
A4000
A4010
A4020
A4030
2
A1490
A1500
A1510
05-Dec-2012
05-Dec-2012
08-Dec-2012
13-Dec-2012
24-Dec-2012
28-Dec-2012
31-Dec-2012
04-Jan-2013
09-Jan-2013
12-Jan-2013
14-Jan-2013
16-Jan-2013
19-Jan-2013
22-Jan-2013
15-Jun-2012
15-Jun-2012
23-Jun-2012
27-Jun-2012
22-Jan-2013
07-Dec-2012
12-Dec-2012
22-Dec-2012
27-Dec-2012
29-Dec-2012
03-Jan-2013
08-Jan-2013
11-Jan-2013
12-Jan-2013
15-Jan-2013
18-Jan-2013
21-Jan-2013
22-Jan-2013
23-Aug-2012
22-Jun-2012
26-Jun-2012
29-Jun-2012
04-Dec-2012A
04-DEC-12A
03-JAN-13A
10-JAN-13A
18-JAN-13A
14-FEB-13A
01-MAY-13A
10-MAY-13A
05-JUN-13
08-JUN-13
10-JUN-13
12-JUN-13
15-JUN-13
18-JUN-13
15-Jun-2012A
15-JUN-12A
13-AUG-12A
16-AUG-12A
18-Jun-2013
03-JAN-13A
10-JAN-13A
18-JAN-13A
14-FEB-13A
01-MAY-13A
10-MAY-13A
04-JUN-13
07-JUN-13
08-JUN-13
11-JUN-13
14-JUN-13
17-JUN-13
18-JUN-13
31-May-2013
13-AUG-12A
16-AUG-12A
16-AUG-12A
-126d
-22d
-24d
-22d
-41d
-104d
-108d
-126d
-126d
-126d
-126d
-126d
-126d
-126d
-241d
-43d
-43d
-40d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A1520
A1530
A1540
A1550
A1560
A1570
A1580
A1590
A1600
A1610
A1620
A1630
23
A4040
A4050
A4060
A4070
A4080
30-Jun-2012
06-Jul-2012
16-Jul-2012
21-Jul-2012
27-Jul-2012
01-Aug-2012
04-Aug-2012
09-Aug-2012
11-Aug-2012
15-Aug-2012
18-Aug-2012
21-Aug-2012
29-Nov-2012
29-Nov-2012
30-Nov-2012
05-Dec-2012
10-Dec-2012
13-Dec-2012
05-Jul-2012
14-Jul-2012
20-Jul-2012
26-Jul-2012
31-Jul-2012
03-Aug-2012
08-Aug-2012
10-Aug-2012
14-Aug-2012
17-Aug-2012
20-Aug-2012
23-Aug-2012
22-Jan-2013
29-Nov-2012
04-Dec-2012
08-Dec-2012
12-Dec-2012
18-Dec-2012
16-AUG-12A
23-AUG-12A
05-SEP-12A
27-SEP-12A
04-OCT-12A
12-OCT-12A
22-OCT-12A
22-OCT-12A
05-NOV-12A
05-NOV-12A
03-JAN-13A
03-JAN-13A
31-May-2013
31-MAY-13
01-JUN-13
06-JUN-13
11-JUN-13
14-JUN-13
23-AUG-12A
05-SEP-12A
27-SEP-12A
04-OCT-12A
12-OCT-12A
22-OCT-12A
22-OCT-12A
05-NOV-12A
05-NOV-12A
03-JAN-13A
03-JAN-13A
03-JAN-13A
24-Jul-2013
31-MAY-13
05-JUN-13
10-JUN-13
13-JUN-13
19-JUN-13
-41d
-44d
-58d
-59d
-62d
-67d
-63d
-73d
-70d
-118d
-116d
-113d
-157d
-157d
-157d
-157d
-157d
-157d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A4090
A4100
A4110
A4120
A4130
A4140
A4150
A4160
A4170
A4180
A4190
25
A4360
A4370
A4380
A4390
A4400
A4410
19-Dec-2012
25-Dec-2012
28-Dec-2012
31-Dec-2012
04-Jan-2013
08-Jan-2013
12-Jan-2013
15-Jan-2013
17-Jan-2013
18-Jan-2013
21-Jan-2013
13-Dec-2012
13-Dec-2012
14-Dec-2012
18-Dec-2012
24-Dec-2012
26-Dec-2012
01-Jan-2013
24-Dec-2012
27-Dec-2012
29-Dec-2012
03-Jan-2013
07-Jan-2013
11-Jan-2013
14-Jan-2013
16-Jan-2013
17-Jan-2013
19-Jan-2013
22-Jan-2013
02-Feb-2013
13-Dec-2012
17-Dec-2012
22-Dec-2012
25-Dec-2012
31-Dec-2012
05-Jan-2013
20-JUN-13
26-JUN-13
29-JUN-13
02-JUL-13
06-JUL-13
10-JUL-13
15-JUL-13
17-JUL-13
19-JUL-13
20-JUL-13
23-JUL-13
16-Jan-2013A
16-JAN-13A
16-JAN-13A
04-JUN-13
10-JUN-13
12-JUN-13
18-JUN-13
25-JUN-13
28-JUN-13
01-JUL-13
05-JUL-13
09-JUL-13
13-JUL-13
16-JUL-13
18-JUL-13
19-JUL-13
22-JUL-13
24-JUL-13
20-Jul-2013
16-JAN-13A
03-JUN-13
08-JUN-13
11-JUN-13
17-JUN-13
22-JUN-13
-157d
-157d
-157d
-157d
-157d
-157d
-157d
-157d
-157d
-157d
-157d
-144d
-28d
-144d
-144d
-144d
-144d
-144d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A4420
A4430
A4440
A4450
A4460
A4470
A4480
A4490
A4500
A4510
8
A2440
A2450
A2460
A2470
A2480
A2490
A2500
07-Jan-2013
09-Jan-2013
12-Jan-2013
16-Jan-2013
21-Jan-2013
23-Jan-2013
25-Jan-2013
28-Jan-2013
30-Jan-2013
01-Feb-2013
21-Jun-2012
21-Jun-2012
22-Jun-2012
10-Jul-2012
18-Jul-2012
21-Jul-2012
30-Jul-2012
07-Aug-2012
08-Jan-2013
11-Jan-2013
15-Jan-2013
19-Jan-2013
22-Jan-2013
24-Jan-2013
26-Jan-2013
29-Jan-2013
31-Jan-2013
02-Feb-2013
01-Oct-2012
21-Jun-2012
09-Jul-2012
17-Jul-2012
20-Jul-2012
28-Jul-2012
06-Aug-2012
11-Aug-2012
24-JUN-13
26-JUN-13
29-JUN-13
03-JUL-13
08-JUL-13
10-JUL-13
12-JUL-13
15-JUL-13
17-JUL-13
19-JUL-13
14-Jul-2012A
14-JUL-12A
14-JUL-12A
20-JUL-12A
24-JUL-12A
25-JUL-12A
02-AUG-12A
05-SEP-12A
25-JUN-13
28-JUN-13
02-JUL-13
06-JUL-13
09-JUL-13
11-JUL-13
13-JUL-13
16-JUL-13
18-JUL-13
20-JUL-13
31-May-2013
14-JUL-12A
20-JUL-12A
24-JUL-12A
25-JUL-12A
02-AUG-12A
05-SEP-12A
27-SEP-12A
-144d
-144d
-144d
-144d
-144d
-144d
-144d
-144d
-144d
-144d
-208d
-19d
-9d
-5d
-3d
-3d
-25d
-39d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 Carpets
5 Drawing Tender from consultant
5 Review of Tender TCS/TCE
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A2510
A2520
A2530
A2540
A2550
A2560
A2570
A2580
A2590
34
A52130
A52140
A52150
A52160
A52170
A52180
A52190
A52200
13-Aug-2012
17-Aug-2012
21-Aug-2012
25-Aug-2012
04-Sep-2012
07-Sep-2012
10-Sep-2012
15-Sep-2012
18-Sep-2012
28-Dec-2012
28-Dec-2012
29-Dec-2012
03-Jan-2013
09-Jan-2013
11-Jan-2013
16-Jan-2013
24-Jan-2013
26-Jan-2013
16-Aug-2012
20-Aug-2012
24-Aug-2012
03-Sep-2012
06-Sep-2012
08-Sep-2012
14-Sep-2012
17-Sep-2012
01-Oct-2012
20-Feb-2013
28-Dec-2012
02-Jan-2013
08-Jan-2013
10-Jan-2013
15-Jan-2013
23-Jan-2013
25-Jan-2013
29-Jan-2013
27-SEP-12A
08-OCT-12A
19-OCT-12A
22-OCT-12A
26-OCT-12A
07-DEC-12A
19-DEC-12A
03-JAN-13A
03-JAN-13A
16-Jan-2013A
16-JAN-13A
16-JAN-13A
05-JUN-13
11-JUN-13
13-JUN-13
18-JUN-13
26-JUN-13
28-JUN-13
08-OCT-12A
19-OCT-12A
22-OCT-12A
26-OCT-12A
07-DEC-12A
19-DEC-12A
03-JAN-13A
03-JAN-13A
03-JAN-13A
23-Jul-2013
16-JAN-13A
04-JUN-13
10-JUN-13
12-JUN-13
17-JUN-13
25-JUN-13
27-JUN-13
01-JUL-13
-44d
-51d
-49d
-45d
-78d
-86d
-94d
-92d
-80d
-131d
-15d
-131d
-131d
-131d
-131d
-131d
-131d
-131d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 Cafeteria
5 Drawing Tender from consultant
5 Review of Tender TCS/TCE
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
5 Revised Offer
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A52210
A52220
A52230
A52240
A52250
A52260
A52270
A52280
35
A52290
A52300
A52310
A52320
A52330
A52340
A52350
A52360
A52370
30-Jan-2013
04-Feb-2013
07-Feb-2013
11-Feb-2013
13-Feb-2013
14-Feb-2013
16-Feb-2013
19-Feb-2013
28-Dec-2012
28-Dec-2012
29-Dec-2012
03-Jan-2013
09-Jan-2013
11-Jan-2013
16-Jan-2013
24-Jan-2013
26-Jan-2013
30-Jan-2013
02-Feb-2013
06-Feb-2013
09-Feb-2013
12-Feb-2013
13-Feb-2013
15-Feb-2013
18-Feb-2013
20-Feb-2013
20-Feb-2013
28-Dec-2012
02-Jan-2013
08-Jan-2013
10-Jan-2013
15-Jan-2013
23-Jan-2013
25-Jan-2013
29-Jan-2013
02-Feb-2013
02-JUL-13
06-JUL-13
10-JUL-13
13-JUL-13
16-JUL-13
17-JUL-13
19-JUL-13
22-JUL-13
16-Jan-2013A
16-JAN-13A
16-JAN-13A
05-JUN-13
11-JUN-13
13-JUN-13
18-JUN-13
26-JUN-13
28-JUN-13
02-JUL-13
05-JUL-13
09-JUL-13
12-JUL-13
15-JUL-13
16-JUL-13
18-JUL-13
20-JUL-13
23-JUL-13
23-Jul-2013
16-JAN-13A
04-JUN-13
10-JUN-13
12-JUN-13
17-JUN-13
25-JUN-13
27-JUN-13
01-JUL-13
05-JUL-13
-131d
-131d
-131d
-131d
-131d
-131d
-131d
-131d
-131d
-15d
-131d
-131d
-131d
-131d
-131d
-131d
-131d
-131d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 Bio digestor Works
5 Drawing Tender from consultant
5 Review of Tender TCS/TCE
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A52380
A52390
A52400
A52410
A52420
A52430
A52440
36
A52450
A52460
A52470
A52480
A52490
A52500
A52510
A52520
A52530
A52540
04-Feb-2013
07-Feb-2013
11-Feb-2013
13-Feb-2013
14-Feb-2013
16-Feb-2013
19-Feb-2013
25-Jun-2012
25-Jun-2012
26-Jun-2012
16-Jul-2012
25-Jul-2012
28-Jul-2012
07-Aug-2012
15-Aug-2012
22-Aug-2012
27-Aug-2012
31-Aug-2012
06-Feb-2013
09-Feb-2013
12-Feb-2013
13-Feb-2013
15-Feb-2013
18-Feb-2013
20-Feb-2013
01-Oct-2012
25-Jun-2012
14-Jul-2012
24-Jul-2012
27-Jul-2012
06-Aug-2012
14-Aug-2012
21-Aug-2012
25-Aug-2012
30-Aug-2012
04-Sep-2012
06-JUL-13
10-JUL-13
13-JUL-13
16-JUL-13
17-JUL-13
19-JUL-13
22-JUL-13
31-May-2013
31-MAY-13
01-JUN-13
21-JUN-13
01-JUL-13
04-JUL-13
13-JUL-13
22-JUL-13
29-JUL-13
02-AUG-13
07-AUG-13
09-JUL-13
12-JUL-13
15-JUL-13
16-JUL-13
18-JUL-13
20-JUL-13
23-JUL-13
06-Sep-2013
31-MAY-13
20-JUN-13
29-JUN-13
03-JUL-13
12-JUL-13
20-JUL-13
27-JUL-13
01-AUG-13
06-AUG-13
10-AUG-13
-131d
-131d
-131d
-131d
-131d
-131d
-131d
-292d
-292d
-292d
-292d
-292d
-292d
-292d
-292d
-292d
-292d
-292d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A52550
A52560
A52570
A52580
A52590
A52600
33
A51970
A51980
A51990
A52000
A52010
A52020
A52040
A52050
A52060
A52070
A52080
05-Sep-2012
14-Sep-2012
18-Sep-2012
21-Sep-2012
26-Sep-2012
28-Sep-2012
28-Dec-2012
28-Dec-2012
29-Dec-2012
03-Jan-2013
09-Jan-2013
11-Jan-2013
16-Jan-2013
26-Jan-2013
30-Jan-2013
04-Feb-2013
07-Feb-2013
11-Feb-2013
13-Sep-2012
17-Sep-2012
20-Sep-2012
25-Sep-2012
27-Sep-2012
01-Oct-2012
20-Feb-2013
28-Dec-2012
02-Jan-2013
08-Jan-2013
10-Jan-2013
15-Jan-2013
23-Jan-2013
29-Jan-2013
02-Feb-2013
06-Feb-2013
09-Feb-2013
12-Feb-2013
12-AUG-13
21-AUG-13
24-AUG-13
28-AUG-13
02-SEP-13
04-SEP-13
16-Jan-2013A
16-JAN-13A
16-JAN-13A
05-JUN-13
11-JUN-13
13-JUN-13
18-JUN-13
28-JUN-13
02-JUL-13
06-JUL-13
10-JUL-13
13-JUL-13
20-AUG-13
23-AUG-13
27-AUG-13
31-AUG-13
03-SEP-13
06-SEP-13
23-Jul-2013
16-JAN-13A
04-JUN-13
10-JUN-13
12-JUN-13
17-JUN-13
25-JUN-13
01-JUL-13
05-JUL-13
09-JUL-13
12-JUL-13
15-JUL-13
-292d
-292d
-292d
-292d
-292d
-292d
-131d
-15d
-131d
-131d
-131d
-131d
-131d
-131d
-131d
-131d
-131d
-131d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A52090
A52100
A52110
A52120
A52030
27
A5160
A5170
A5180
A5190
A5200
A5210
A5220
A5230
A5240
A5250
A5260
A5270
13-Feb-2013
14-Feb-2013
16-Feb-2013
19-Feb-2013
24-Jan-2013
01-Dec-2012
01-Dec-2012
03-Dec-2012
13-Dec-2012
21-Dec-2012
24-Dec-2012
27-Dec-2012
04-Jan-2013
09-Jan-2013
12-Jan-2013
17-Jan-2013
21-Jan-2013
25-Jan-2013
13-Feb-2013
15-Feb-2013
18-Feb-2013
20-Feb-2013
25-Jan-2013
08-Feb-2013
01-Dec-2012
12-Dec-2012
20-Dec-2012
22-Dec-2012
26-Dec-2012
03-Jan-2013
08-Jan-2013
11-Jan-2013
16-Jan-2013
19-Jan-2013
24-Jan-2013
28-Jan-2013
16-JUL-13
17-JUL-13
19-JUL-13
22-JUL-13
26-JUN-13
31-May-2013
31-MAY-13
01-JUN-13
12-JUN-13
20-JUN-13
22-JUN-13
26-JUN-13
04-JUL-13
09-JUL-13
12-JUL-13
17-JUL-13
20-JUL-13
25-JUL-13
16-JUL-13
18-JUL-13
20-JUL-13
23-JUL-13
27-JUN-13
08-Aug-2013
31-MAY-13
11-JUN-13
19-JUN-13
21-JUN-13
25-JUN-13
03-JUL-13
08-JUL-13
11-JUL-13
16-JUL-13
19-JUL-13
24-JUL-13
27-JUL-13
-131d
-131d
-131d
-131d
-131d
-155d
-155d
-155d
-155d
-155d
-155d
-155d
-155d
-155d
-155d
-155d
-155d
-155d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A5280
A5290
A5300
A5310
11
A5960
A5970
A6020
A6030
A6040
A6050
A6060
A6070
A6080
A6090
A6100
A6110
32
29-Jan-2013
31-Jan-2013
04-Feb-2013
07-Feb-2013
21-Jun-2012
21-Jun-2012
22-Jun-2012
22-Aug-2012
27-Aug-2012
05-Sep-2012
11-Sep-2012
14-Sep-2012
18-Sep-2012
21-Sep-2012
24-Sep-2012
29-Sep-2012
02-Oct-2012
05-May-2012
30-Jan-2013
02-Feb-2013
06-Feb-2013
08-Feb-2013
04-Oct-2012
21-Jun-2012
13-Jul-2012
25-Aug-2012
04-Sep-2012
10-Sep-2012
13-Sep-2012
17-Sep-2012
20-Sep-2012
22-Sep-2012
28-Sep-2012
01-Oct-2012
04-Oct-2012
16-Jul-2012
29-JUL-13
31-JUL-13
03-AUG-13
07-AUG-13
18-Jul-2012A
18-JUL-12A
18-JUL-12A
16-AUG-12A
03-SEP-12A
17-SEP-12A
21-SEP-12A
08-OCT-12A
12-OCT-12A
22-OCT-12A
05-NOV-12A
03-JAN-13A
03-JAN-13A
04-May-2012A
30-JUL-13
02-AUG-13
06-AUG-13
08-AUG-13
31-May-2013
18-JUL-12A
18-JUL-12A
03-SEP-12A
17-SEP-12A
21-SEP-12A
08-OCT-12A
12-OCT-12A
22-OCT-12A
05-NOV-12A
03-JAN-13A
03-JAN-13A
03-JAN-13A
31-May-2013
-155d
-155d
-155d
-155d
-205d
-22d
-3d
-6d
-10d
-9d
-20d
-21d
-26d
-36d
-82d
-80d
-77d
-274d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A1200
A1220
A1230
A1240
A1250
A1260
A1270
A1280
A1290
A1300
A1310
6
A2120
A2130
A2140
A2150
A2160
A2170
05-May-2012
09-Jun-2012
12-Jun-2012
16-Jun-2012
21-Jun-2012
27-Jun-2012
29-Jun-2012
05-Jul-2012
09-Jul-2012
11-Jul-2012
13-Jul-2012
20-Jun-2012
20-Jun-2012
21-Jun-2012
06-Jul-2012
17-Jul-2012
20-Jul-2012
30-Jul-2012
11-May-2012
11-Jun-2012
15-Jun-2012
20-Jun-2012
26-Jun-2012
28-Jun-2012
04-Jul-2012
07-Jul-2012
10-Jul-2012
12-Jul-2012
16-Jul-2012
24-Sep-2012
20-Jun-2012
05-Jul-2012
16-Jul-2012
19-Jul-2012
28-Jul-2012
07-Aug-2012
04-MAY-12A
08-JUN-12A
13-JUN-12A
20-JUN-12A
25-JUN-12A
01-JUL-12A
26-JUL-12A
26-JUL-12A
27-JUL-12A
09-AUG-12A
09-AUG-12A
07-Sep-2012A
07-SEP-12A
07-SEP-12A
25-OCT-12A
25-OCT-12A
26-OCT-12A
05-NOV-12A
17-MAY-12A
13-JUN-12A
20-JUN-12A
25-JUN-12A
01-JUL-12A
26-JUL-12A
26-JUL-12A
27-JUL-12A
09-AUG-12A
09-AUG-12A
20-AUG-12A
31-May-2013
07-SEP-12A
25-OCT-12A
25-OCT-12A
26-OCT-12A
05-NOV-12A
21-NOV-12A
-4d
-1d
-3d
-3d
-4d
-23d
-18d
-16d
-25d
-23d
-29d
-214d
-67d
-95d
-86d
-84d
-84d
-90d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A2180
A2190
A2200
A2210
A2220
A2230
A2240
A2250
A2260
A2270
7
A2280
A2290
A2300
A2310
A2320
A2330
A2340
08-Aug-2012
15-Aug-2012
21-Aug-2012
24-Aug-2012
28-Aug-2012
06-Sep-2012
11-Sep-2012
13-Sep-2012
18-Sep-2012
21-Sep-2012
21-Jun-2012
21-Jun-2012
22-Jun-2012
10-Jul-2012
18-Jul-2012
21-Jul-2012
30-Jul-2012
07-Aug-2012
14-Aug-2012
20-Aug-2012
23-Aug-2012
27-Aug-2012
05-Sep-2012
10-Sep-2012
12-Sep-2012
17-Sep-2012
20-Sep-2012
24-Sep-2012
01-Oct-2012
21-Jun-2012
09-Jul-2012
17-Jul-2012
20-Jul-2012
28-Jul-2012
06-Aug-2012
11-Aug-2012
21-NOV-12A
23-NOV-12A
07-DEC-12A
31-DEC-12A
02-JAN-13A
06-FEB-13A
06-MAR-13A
17-APR-13A
02-MAY-13A
06-MAY-13A
14-Jul-2012A
14-JUL-12A
14-JUL-12A
20-JUL-12A
24-JUL-12A
25-JUL-12A
02-AUG-12A
05-SEP-12A
23-NOV-12A
07-DEC-12A
31-DEC-12A
02-JAN-13A
06-FEB-13A
06-MAR-13A
17-APR-13A
23-MAY-13A
23-MAY-13A
23-MAY-13A
31-May-2013
14-JUL-12A
20-JUL-12A
24-JUL-12A
25-JUL-12A
02-AUG-12A
05-SEP-12A
27-SEP-12A
-86d
-93d
-110d
-109d
-131d
-151d
-185d
-212d
-209d
-206d
-208d
-19d
-9d
-5d
-3d
-3d
-25d
-39d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 Signages Works
5 Drawing Tender from consultant
5 Review of Tender TCS/TCE
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A2350
A2360
A2370
A2380
A2390
A2400
A2410
A2420
A2430
28
A4680
A4690
A4700
A4710
A4720
A4730
A4740
A4750
13-Aug-2012
17-Aug-2012
21-Aug-2012
25-Aug-2012
04-Sep-2012
07-Sep-2012
10-Sep-2012
15-Sep-2012
18-Sep-2012
21-Dec-2012
21-Dec-2012
22-Dec-2012
25-Dec-2012
31-Dec-2012
03-Jan-2013
08-Jan-2013
15-Jan-2013
18-Jan-2013
16-Aug-2012
20-Aug-2012
24-Aug-2012
03-Sep-2012
06-Sep-2012
08-Sep-2012
14-Sep-2012
17-Sep-2012
01-Oct-2012
12-Feb-2013
21-Dec-2012
24-Dec-2012
29-Dec-2012
02-Jan-2013
07-Jan-2013
14-Jan-2013
17-Jan-2013
19-Jan-2013
27-SEP-12A
08-OCT-12A
19-OCT-12A
22-OCT-12A
26-OCT-12A
07-DEC-12A
19-DEC-12A
03-JAN-13A
03-JAN-13A
31-May-2013
31-MAY-13
01-JUN-13
04-JUN-13
10-JUN-13
13-JUN-13
18-JUN-13
25-JUN-13
28-JUN-13
08-OCT-12A
19-OCT-12A
22-OCT-12A
26-OCT-12A
07-DEC-12A
19-DEC-12A
03-JAN-13A
03-JAN-13A
03-JAN-13A
23-Jul-2013
31-MAY-13
03-JUN-13
08-JUN-13
12-JUN-13
17-JUN-13
24-JUN-13
27-JUN-13
29-JUN-13
-44d
-51d
-49d
-45d
-78d
-86d
-94d
-92d
-80d
-138d
-138d
-138d
-138d
-138d
-138d
-138d
-138d
-138d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 Solar Power System
5 Drawing Tender from consultant
5 Review of Tender TCS/TCE
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
5 Revised Offer
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A4760
A4770
A4780
A4790
A4800
A4810
A4820
A4830
29
A4840
A4850
A4860
A4870
A4880
A4890
A4900
A4910
A4920
21-Jan-2013
25-Jan-2013
29-Jan-2013
01-Feb-2013
04-Feb-2013
06-Feb-2013
08-Feb-2013
11-Feb-2013
24-Dec-2012
24-Dec-2012
25-Dec-2012
29-Dec-2012
03-Jan-2013
07-Jan-2013
11-Jan-2013
19-Jan-2013
22-Jan-2013
25-Jan-2013
24-Jan-2013
28-Jan-2013
31-Jan-2013
02-Feb-2013
05-Feb-2013
07-Feb-2013
09-Feb-2013
12-Feb-2013
15-Feb-2013
24-Dec-2012
28-Dec-2012
02-Jan-2013
05-Jan-2013
10-Jan-2013
18-Jan-2013
21-Jan-2013
24-Jan-2013
28-Jan-2013
01-JUL-13
05-JUL-13
09-JUL-13
12-JUL-13
15-JUL-13
17-JUL-13
19-JUL-13
22-JUL-13
31-May-2013
31-MAY-13
01-JUN-13
06-JUN-13
11-JUN-13
14-JUN-13
19-JUN-13
27-JUN-13
29-JUN-13
03-JUL-13
04-JUL-13
08-JUL-13
11-JUL-13
13-JUL-13
16-JUL-13
18-JUL-13
20-JUL-13
23-JUL-13
24-Jul-2013
31-MAY-13
05-JUN-13
10-JUN-13
13-JUN-13
18-JUN-13
26-JUN-13
28-JUN-13
02-JUL-13
05-JUL-13
-138d
-138d
-138d
-138d
-138d
-138d
-138d
-138d
-136d
-136d
-136d
-136d
-136d
-136d
-136d
-136d
-136d
-136d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 IBMS Works
5 Drawing Tender from consultant
5 Review of Tender TCS/TCE
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A4930
A4940
A4950
A4960
A4970
A4980
A4990
13
A2760
A2770
A2780
A2790
A2800
A2810
A2820
A2830
A2840
A2850
29-Jan-2013
01-Feb-2013
05-Feb-2013
07-Feb-2013
09-Feb-2013
12-Feb-2013
14-Feb-2013
04-Aug-2012
04-Aug-2012
06-Aug-2012
16-Aug-2012
31-Aug-2012
04-Sep-2012
11-Sep-2012
19-Sep-2012
26-Sep-2012
02-Oct-2012
05-Oct-2012
31-Jan-2013
04-Feb-2013
06-Feb-2013
08-Feb-2013
11-Feb-2013
13-Feb-2013
15-Feb-2013
05-Nov-2012
04-Aug-2012
15-Aug-2012
30-Aug-2012
03-Sep-2012
10-Sep-2012
18-Sep-2012
25-Sep-2012
01-Oct-2012
04-Oct-2012
09-Oct-2012
06-JUL-13
10-JUL-13
13-JUL-13
16-JUL-13
18-JUL-13
20-JUL-13
23-JUL-13
06-Sep-2012A
06-SEP-12A
06-SEP-12A
26-OCT-12A
26-OCT-12A
19-NOV-12A
26-NOV-12A
04-JAN-13A
11-JAN-13A
15-JAN-13A
24-JAN-13A
09-JUL-13
12-JUL-13
15-JUL-13
17-JUL-13
19-JUL-13
22-JUL-13
24-JUL-13
11-Jun-2013
06-SEP-12A
26-OCT-12A
26-OCT-12A
19-NOV-12A
26-NOV-12A
04-JAN-13A
11-JAN-13A
15-JAN-13A
24-JAN-13A
31-JAN-13A
-136d
-136d
-136d
-136d
-136d
-136d
-136d
-187d
-27d
-61d
-48d
-65d
-65d
-92d
-92d
-90d
-95d
-97d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A2860
A2870
A2880
A2890
A2900
A2910
14
A2930
A2980
A2990
A3000
A3010
A3020
A3030
A3040
A3050
A3060
A3070
10-Oct-2012
19-Oct-2012
23-Oct-2012
26-Oct-2012
31-Oct-2012
03-Nov-2012
13-Aug-2012
14-Aug-2012
02-Oct-2012
09-Oct-2012
15-Oct-2012
18-Oct-2012
23-Oct-2012
02-Nov-2012
06-Nov-2012
08-Nov-2012
14-Nov-2012
16-Nov-2012
18-Oct-2012
22-Oct-2012
25-Oct-2012
30-Oct-2012
02-Nov-2012
05-Nov-2012
19-Nov-2012
31-Aug-2012
08-Oct-2012
13-Oct-2012
17-Oct-2012
22-Oct-2012
01-Nov-2012
05-Nov-2012
07-Nov-2012
13-Nov-2012
15-Nov-2012
19-Nov-2012
31-JAN-13A
01-FEB-13A
08-MAR-13A
31-MAY-13
05-JUN-13
08-JUN-13
06-Sep-2012A
06-SEP-12A
02-OCT-12A
10-OCT-12A
20-OCT-12A
26-OCT-12A
16-NOV-12A
26-NOV-12A
26-DEC-12A
26-DEC-12A
31-JAN-13A
26-FEB-13A
01-FEB-13A
08-MAR-13A
31-MAY-13
05-JUN-13
08-JUN-13
11-JUN-13
31-May-2013
07-SEP-12A
10-OCT-12A
20-OCT-12A
26-OCT-12A
16-NOV-12A
26-NOV-12A
26-DEC-12A
26-DEC-12A
31-JAN-13A
26-FEB-13A
08-MAR-13A
-90d
-117d
-186d
-186d
-186d
-186d
-166d
-5d
-1d
-5d
-7d
-21d
-20d
-43d
-41d
-67d
-87d
-93d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A2920
17
A3240
A3250
A3260
A3270
A3280
A3290
A3300
A3310
A3320
A3330
A3340
A3350
A3360
A3370
A3380
A3390
13-Aug-2012
12-Oct-2012
12-Oct-2012
13-Oct-2012
26-Oct-2012
03-Nov-2012
07-Nov-2012
13-Nov-2012
22-Nov-2012
27-Nov-2012
03-Dec-2012
06-Dec-2012
11-Dec-2012
17-Dec-2012
20-Dec-2012
22-Dec-2012
25-Dec-2012
27-Dec-2012
13-Aug-2012
28-Dec-2012
12-Oct-2012
25-Oct-2012
02-Nov-2012
06-Nov-2012
12-Nov-2012
21-Nov-2012
26-Nov-2012
01-Dec-2012
05-Dec-2012
10-Dec-2012
15-Dec-2012
19-Dec-2012
21-Dec-2012
24-Dec-2012
26-Dec-2012
28-Dec-2012
06-SEP-12A
20-Nov-2012A
20-NOV-12A
20-NOV-12A
06-MAR-13A
20-MAR-13A
20-MAR-13A
02-APR-13A
16-APR-13A
04-JUN-13
10-JUN-13
13-JUN-13
18-JUN-13
24-JUN-13
27-JUN-13
29-JUN-13
02-JUL-13
04-JUL-13
06-SEP-12A
05-Jul-2013
20-NOV-12A
20-MAR-13A
20-MAR-13A
20-MAR-13A
02-APR-13A
16-APR-13A
03-JUN-13
08-JUN-13
12-JUN-13
17-JUN-13
22-JUN-13
26-JUN-13
28-JUN-13
01-JUL-13
03-JUL-13
05-JUL-13
-20d
-162d
-32d
-124d
-117d
-114d
-120d
-124d
-162d
-162d
-162d
-162d
-162d
-162d
-162d
-162d
-162d
-162d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
4 Workstations
5 Drawing Tender from consultant
5 Review of Tender TCS/TCE
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 Workstation Chairs
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
18
A3400
A3410
A3420
A3430
A3440
A3450
A3460
A3470
A3480
A3490
A3500
A3510
A3520
A3530
A3540
A3550
26
16-Oct-2012
16-Oct-2012
17-Oct-2012
26-Oct-2012
03-Nov-2012
06-Nov-2012
13-Nov-2012
23-Nov-2012
01-Dec-2012
05-Dec-2012
10-Dec-2012
14-Dec-2012
25-Dec-2012
27-Dec-2012
31-Dec-2012
04-Jan-2013
08-Jan-2013
08-Jan-2013
09-Jan-2013
16-Oct-2012
25-Oct-2012
02-Nov-2012
05-Nov-2012
12-Nov-2012
22-Nov-2012
30-Nov-2012
04-Dec-2012
08-Dec-2012
13-Dec-2012
24-Dec-2012
26-Dec-2012
29-Dec-2012
03-Jan-2013
07-Jan-2013
09-Jan-2013
12-Apr-2013
16-Jan-2013A
16-JAN-13A
16-JAN-13A
22-APR-13A
24-APR-13A
30-APR-13A
07-MAY-13A
27-MAY-13A
08-JUN-13
12-JUN-13
17-JUN-13
21-JUN-13
02-JUL-13
04-JUL-13
08-JUL-13
12-JUL-13
16-JUL-13
16-Jan-2013A
17-Jul-2013
16-JAN-13A
22-APR-13A
24-APR-13A
10-MAY-13A
22-MAY-13A
27-MAY-13A
07-JUN-13
11-JUN-13
15-JUN-13
20-JUN-13
01-JUL-13
03-JUL-13
06-JUL-13
11-JUL-13
15-JUL-13
17-JUL-13
12-Jul-2013
-162d
-78d
-152d
-147d
-159d
-163d
-158d
-162d
-162d
-162d
-162d
-162d
-162d
-162d
-162d
-162d
-162d
-78d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A4520
A4530
A4540
A4550
A4560
A4570
A4580
A4590
A4600
A4610
A4620
A4630
A4640
A4650
A4660
A4670
1
A1320
08-Jan-2013
09-Jan-2013
15-Jan-2013
18-Jan-2013
19-Jan-2013
28-Jan-2013
01-Mar-2013
05-Mar-2013
09-Mar-2013
15-Mar-2013
22-Mar-2013
25-Mar-2013
01-Apr-2013
04-Apr-2013
08-Apr-2013
10-Apr-2013
18-May-2012
18-May-2012
08-Jan-2013
14-Jan-2013
17-Jan-2013
18-Jan-2013
26-Jan-2013
28-Feb-2013
04-Mar-2013
08-Mar-2013
14-Mar-2013
21-Mar-2013
23-Mar-2013
30-Mar-2013
03-Apr-2013
06-Apr-2013
09-Apr-2013
12-Apr-2013
11-Aug-2012
18-May-2012
16-JAN-13A
16-JAN-13A
22-APR-13A
24-APR-13A
29-APR-13A
07-MAY-13A
27-MAY-13A
04-JUN-13
08-JUN-13
14-JUN-13
21-JUN-13
24-JUN-13
01-JUL-13
04-JUL-13
08-JUL-13
10-JUL-13
16-Jun-2012A
16-JUN-12A
16-JAN-13A
22-APR-13A
24-APR-13A
10-MAY-13A
22-MAY-13A
27-MAY-13A
03-JUN-13
07-JUN-13
13-JUN-13
20-JUN-13
22-JUN-13
29-JUN-13
03-JUL-13
06-JUL-13
09-JUL-13
12-JUL-13
31-May-2013
16-JUN-12A
-6d
-83d
-82d
-95d
-98d
-74d
-78d
-78d
-78d
-78d
-78d
-78d
-78d
-78d
-78d
-78d
-251d
-24d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A1330
A1340
A1350
A1360
A1370
A1380
A1390
A1400
A1410
A1420
A1430
A1440
A1450
A1460
A1470
15
A5480
A5490
19-May-2012
30-May-2012
11-Jun-2012
13-Jun-2012
20-Jun-2012
30-Jun-2012
07-Jul-2012
11-Jul-2012
14-Jul-2012
17-Jul-2012
25-Jul-2012
28-Jul-2012
31-Jul-2012
04-Aug-2012
08-Aug-2012
12-Sep-2012
12-Sep-2012
13-Sep-2012
29-May-2012
09-Jun-2012
12-Jun-2012
19-Jun-2012
29-Jun-2012
06-Jul-2012
10-Jul-2012
13-Jul-2012
16-Jul-2012
24-Jul-2012
27-Jul-2012
30-Jul-2012
03-Aug-2012
07-Aug-2012
11-Aug-2012
10-Dec-2012
12-Sep-2012
22-Sep-2012
16-JUN-12A
17-JUN-12A
26-JUN-12A
28-JUN-12A
05-JUL-12A
23-JUL-12A
16-AUG-12A
22-AUG-12A
30-AUG-12A
17-SEP-12A
24-SEP-12A
22-OCT-12A
26-OCT-12A
11-DEC-12A
11-DEC-12A
29-Apr-2013A
29-APR-13A
30-APR-13A
17-JUN-12A
26-JUN-12A
28-JUN-12A
05-JUL-12A
23-JUL-12A
16-AUG-12A
22-AUG-12A
30-AUG-12A
17-SEP-12A
24-SEP-12A
22-OCT-12A
26-OCT-12A
11-DEC-12A
11-DEC-12A
11-DEC-12A
14-Aug-2013
01-MAY-13A
10-MAY-13A
-16d
-13d
-13d
-13d
-19d
-34d
-36d
-40d
-53d
-52d
-73d
-75d
-110d
-107d
-103d
-212d
-197d
-196d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 HVAC Works
5 Drawing Tender from consultant
5 Review of Tender TCS/TCE
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A5500
A5510
A5520
A5530
A5540
A5550
A5560
A5570
A5580
A5590
A5600
A5610
A5620
A5630
3
A1640
A1650
A1660
24-Sep-2012
05-Oct-2012
08-Oct-2012
15-Oct-2012
24-Oct-2012
31-Oct-2012
05-Nov-2012
09-Nov-2012
15-Nov-2012
24-Nov-2012
27-Nov-2012
30-Nov-2012
05-Dec-2012
08-Dec-2012
09-Jun-2012
09-Jun-2012
11-Jun-2012
28-Jun-2012
04-Oct-2012
06-Oct-2012
13-Oct-2012
23-Oct-2012
30-Oct-2012
03-Nov-2012
08-Nov-2012
14-Nov-2012
23-Nov-2012
26-Nov-2012
29-Nov-2012
04-Dec-2012
07-Dec-2012
10-Dec-2012
03-Sep-2012
09-Jun-2012
27-Jun-2012
07-Jul-2012
10-MAY-13A
15-MAY-13A
18-MAY-13A
29-MAY-13A
10-JUN-13
18-JUN-13
25-JUN-13
01-JUL-13
09-JUL-13
20-JUL-13
24-JUL-13
30-JUL-13
05-AUG-13
10-AUG-13
04-Sep-2012A
04-SEP-12A
04-SEP-12A
01-OCT-12A
21-MAY-13A
23-MAY-13A
30-MAY-13A
08-JUN-13
18-JUN-13
25-JUN-13
01-JUL-13
09-JUL-13
19-JUL-13
24-JUL-13
30-JUL-13
05-AUG-13
10-AUG-13
14-AUG-13
31-May-2013
04-SEP-12A
01-OCT-12A
03-OCT-12A
-196d
-196d
-196d
-196d
-198d
-199d
-201d
-202d
-204d
-206d
-207d
-209d
-210d
-212d
-232d
-73d
-81d
-74d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 LT Works
5 Drawing Tender from consultant
5 Review of Tender TCS/TCE
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A1670
A1680
A1690
A1700
A1710
A1720
A1730
A1740
A1750
A1760
A1770
A1780
A1790
4
A1800
A1810
A1820
A1830
09-Jul-2012
12-Jul-2012
19-Jul-2012
26-Jul-2012
02-Aug-2012
06-Aug-2012
09-Aug-2012
14-Aug-2012
17-Aug-2012
22-Aug-2012
25-Aug-2012
29-Aug-2012
31-Aug-2012
14-Jun-2012
14-Jun-2012
15-Jun-2012
30-Jun-2012
11-Jul-2012
11-Jul-2012
18-Jul-2012
25-Jul-2012
01-Aug-2012
04-Aug-2012
08-Aug-2012
13-Aug-2012
16-Aug-2012
21-Aug-2012
24-Aug-2012
28-Aug-2012
30-Aug-2012
03-Sep-2012
06-Sep-2012
14-Jun-2012
29-Jun-2012
10-Jul-2012
13-Jul-2012
03-OCT-12A
03-OCT-12A
05-OCT-12A
15-JAN-13A
16-JAN-13A
01-FEB-13A
06-FEB-13A
13-FEB-13A
22-FEB-13A
26-FEB-13A
28-FEB-13A
07-MAR-13A
07-MAR-13A
23-Aug-2012A
23-AUG-12A
23-AUG-12A
24-AUG-12A
06-SEP-12A
03-OCT-12A
05-OCT-12A
15-JAN-13A
16-JAN-13A
01-FEB-13A
06-FEB-13A
13-FEB-13A
22-FEB-13A
26-FEB-13A
28-FEB-13A
23-MAY-13A
23-MAY-13A
23-MAY-13A
31-May-2013
23-AUG-12A
24-AUG-12A
06-SEP-12A
07-SEP-12A
-71d
-67d
-148d
-143d
-154d
-155d
-157d
-162d
-161d
-160d
-229d
-227d
-224d
-229d
-59d
-47d
-49d
-47d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A1840
A1850
A1860
A1870
A1880
A1890
A1900
A1910
A1920
A1930
A1940
A1950
5
A1960
A1970
A1980
A1990
A2000
14-Jul-2012
23-Jul-2012
31-Jul-2012
03-Aug-2012
07-Aug-2012
11-Aug-2012
16-Aug-2012
21-Aug-2012
24-Aug-2012
28-Aug-2012
31-Aug-2012
04-Sep-2012
18-Jun-2012
18-Jun-2012
19-Jun-2012
30-Jun-2012
07-Jul-2012
11-Jul-2012
21-Jul-2012
30-Jul-2012
02-Aug-2012
06-Aug-2012
10-Aug-2012
15-Aug-2012
20-Aug-2012
23-Aug-2012
27-Aug-2012
30-Aug-2012
03-Sep-2012
06-Sep-2012
12-Sep-2012
18-Jun-2012
29-Jun-2012
06-Jul-2012
10-Jul-2012
16-Jul-2012
07-SEP-12A
21-SEP-12A
04-OCT-12A
05-OCT-12A
25-OCT-12A
02-NOV-12A
16-NOV-12A
21-NOV-12A
14-DEC-12A
14-DEC-12A
03-JAN-13A
03-JAN-13A
10-Jul-2012A
10-JUL-12A
10-JUL-12A
12-JUL-12A
17-JUL-12A
18-JUL-12A
21-SEP-12A
04-OCT-12A
05-OCT-12A
25-OCT-12A
02-NOV-12A
16-NOV-12A
21-NOV-12A
14-DEC-12A
14-DEC-12A
03-JAN-13A
03-JAN-13A
03-JAN-13A
31-May-2013
10-JUL-12A
12-JUL-12A
17-JUL-12A
18-JUL-12A
25-JUL-12A
-52d
-56d
-54d
-68d
-71d
-79d
-79d
-96d
-93d
-107d
-104d
-101d
-224d
-18d
-10d
-8d
-6d
-7d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A2010
A2020
A2030
A2040
A2050
A2060
A2070
A2080
A2090
A2100
A2110
16
A3080
A3090
A3100
A3110
A3120
A3130
17-Jul-2012
31-Jul-2012
07-Aug-2012
11-Aug-2012
14-Aug-2012
17-Aug-2012
25-Aug-2012
30-Aug-2012
03-Sep-2012
06-Sep-2012
10-Sep-2012
05-Oct-2012
05-Oct-2012
06-Oct-2012
17-Oct-2012
26-Oct-2012
30-Oct-2012
07-Nov-2012
30-Jul-2012
06-Aug-2012
10-Aug-2012
13-Aug-2012
16-Aug-2012
24-Aug-2012
29-Aug-2012
01-Sep-2012
05-Sep-2012
08-Sep-2012
12-Sep-2012
03-Jan-2013
05-Oct-2012
16-Oct-2012
25-Oct-2012
29-Oct-2012
06-Nov-2012
17-Nov-2012
25-JUL-12A
16-AUG-12A
05-SEP-12A
17-SEP-12A
21-SEP-12A
03-OCT-12A
05-OCT-12A
22-OCT-12A
05-NOV-12A
03-JAN-13A
03-JAN-13A
06-Nov-2012A
06-NOV-12A
06-NOV-12A
10-DEC-12A
25-JAN-13A
28-JAN-13A
13-FEB-13A
16-AUG-12A
05-SEP-12A
17-SEP-12A
21-SEP-12A
03-OCT-12A
05-OCT-12A
22-OCT-12A
05-NOV-12A
03-JAN-13A
03-JAN-13A
03-JAN-13A
14-Jun-2013
06-NOV-12A
10-DEC-12A
25-JAN-13A
28-JAN-13A
13-FEB-13A
20-FEB-13A
-14d
-25d
-31d
-33d
-40d
-35d
-45d
-54d
-102d
-99d
-96d
-139d
-26d
-46d
-78d
-77d
-84d
-80d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A3140
A3150
A3160
A3170
A3180
A3190
A3200
A3210
A3220
A3230
12
A2600
A2610
A2620
A2630
A2640
A2650
A2660
19-Nov-2012
27-Nov-2012
01-Dec-2012
05-Dec-2012
11-Dec-2012
20-Dec-2012
24-Dec-2012
27-Dec-2012
01-Jan-2013
03-Jan-2013
19-Jul-2012
19-Jul-2012
20-Jul-2012
03-Aug-2012
16-Aug-2012
20-Aug-2012
27-Aug-2012
06-Sep-2012
26-Nov-2012
30-Nov-2012
04-Dec-2012
10-Dec-2012
19-Dec-2012
22-Dec-2012
26-Dec-2012
31-Dec-2012
02-Jan-2013
03-Jan-2013
23-Oct-2012
19-Jul-2012
02-Aug-2012
15-Aug-2012
18-Aug-2012
25-Aug-2012
05-Sep-2012
11-Sep-2012
20-FEB-13A
12-APR-13A
12-APR-13A
19-APR-13A
23-APR-13A
23-APR-13A
04-JUN-13
07-JUN-13
12-JUN-13
14-JUN-13
25-Sep-2012A
25-SEP-12A
25-SEP-12A
15-OCT-12A
02-NOV-12A
06-NOV-12A
14-NOV-12A
30-NOV-12A
12-APR-13A
12-APR-13A
19-APR-13A
23-APR-13A
04-MAY-13A
03-JUN-13
06-JUN-13
11-JUN-13
13-JUN-13
14-JUN-13
18-Jun-2013
25-SEP-12A
15-OCT-12A
02-NOV-12A
06-NOV-12A
14-NOV-12A
30-NOV-12A
19-DEC-12A
-117d
-113d
-116d
-114d
-117d
-139d
-139d
-139d
-139d
-139d
-204d
-57d
-62d
-67d
-67d
-68d
-73d
-84d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Techno-Commercial Meeting - 1
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
4 Modular Furniture
5 Drawing Tender from consultant
5 Review of Tender TCS/TCE
5 Modification of Tender & Submitting in PDF file & In Hard Copy for Tender Launch
5 Issue of Tender
5 Pre-bid Meeting with Contractor
5 Technical / Price Bid Receipt
5 Technical Evalution Report
5 Techno-Commercial Meeting - 1
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A2670
A2680
A2690
A2700
A2710
A2720
A2730
A2740
A2750
19
A3560
A3570
A3580
A3590
A3600
A3610
A3620
A3630
12-Sep-2012
17-Sep-2012
22-Sep-2012
26-Sep-2012
04-Oct-2012
09-Oct-2012
12-Oct-2012
17-Oct-2012
20-Oct-2012
16-Oct-2012
16-Oct-2012
17-Oct-2012
26-Oct-2012
03-Nov-2012
06-Nov-2012
13-Nov-2012
23-Nov-2012
01-Dec-2012
15-Sep-2012
21-Sep-2012
25-Sep-2012
03-Oct-2012
08-Oct-2012
11-Oct-2012
16-Oct-2012
19-Oct-2012
23-Oct-2012
09-Jan-2013
16-Oct-2012
25-Oct-2012
02-Nov-2012
05-Nov-2012
12-Nov-2012
22-Nov-2012
30-Nov-2012
04-Dec-2012
19-DEC-12A
29-JAN-13A
08-FEB-13A
15-APR-13A
15-APR-13A
04-JUN-13
07-JUN-13
12-JUN-13
15-JUN-13
16-Jan-2013A
16-JAN-13A
16-JAN-13A
22-APR-13A
24-APR-13A
30-APR-13A
07-MAY-13A
27-MAY-13A
08-JUN-13
29-JAN-13A
08-FEB-13A
15-APR-13A
15-APR-13A
03-JUN-13
06-JUN-13
11-JUN-13
14-JUN-13
18-JUN-13
17-Jul-2013
16-JAN-13A
22-APR-13A
24-APR-13A
10-MAY-13A
22-MAY-13A
27-MAY-13A
07-JUN-13
11-JUN-13
-115d
-119d
-172d
-165d
-204d
-204d
-204d
-204d
-204d
-162d
-78d
-152d
-147d
-159d
-163d
-158d
-162d
-162d
Delay Report
Project Name: Adibatla - SEZ
Project ID: 1009058
Data Date: 31-May-2013
Activity Name
5 Revised Offer
5 Commercial Meeting - 2
5 Final Offer Submission
5 Recommendation & Finalisation of Vendor
5 PNC Sign Off
5 Award of Contract (LOI)
5 Draft WO
5 Issue of WO
Activity
ID
BL Project
Start
BL Project
Finish
Start
Finish
VarianceBL Finish
Date
A3640
A3650
A3660
A3670
A3680
A3690
A3700
A3710
05-Dec-2012
10-Dec-2012
14-Dec-2012
25-Dec-2012
27-Dec-2012
31-Dec-2012
04-Jan-2013
08-Jan-2013
08-Dec-2012
13-Dec-2012
24-Dec-2012
26-Dec-2012
29-Dec-2012
03-Jan-2013
07-Jan-2013
09-Jan-2013
12-JUN-13
17-JUN-13
21-JUN-13
02-JUL-13
04-JUL-13
08-JUL-13
12-JUL-13
16-JUL-13
15-JUN-13
20-JUN-13
01-JUL-13
03-JUL-13
06-JUL-13
11-JUL-13
15-JUL-13
17-JUL-13
-162d
-162d
-162d
-162d
-162d
-162d
-162d
-162d