Projects Made in Marine Engineer Corp, Branch Veracruz YEAR 2013

This document summarizes various ship repair projects completed in 2013 by Marine Engineer Corp in Veracruz, Mexico under the leadership of General Manager Nelson Aguirre. It describes work done on 6 vessels, including replacing steel and engines on a landing craft, refitting a patrol boat with a new pilot house, and general repairs to passenger and supply vessels. All projects involved sandblasting, painting, and engine or hull work to refurbish the vessels.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views

Projects Made in Marine Engineer Corp, Branch Veracruz YEAR 2013

This document summarizes various ship repair projects completed in 2013 by Marine Engineer Corp in Veracruz, Mexico under the leadership of General Manager Nelson Aguirre. It describes work done on 6 vessels, including replacing steel and engines on a landing craft, refitting a patrol boat with a new pilot house, and general repairs to passenger and supply vessels. All projects involved sandblasting, painting, and engine or hull work to refurbish the vessels.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 48

PROJECTS MADE IN MARINE

ENGINEER CORP, BRANCH


VERACRUZ
YEAR 2013
GENERAL AND PROJECT
MANAGER: NELSON
AGUIRRE B.

MR AGUIRRE IS A CHILEAN NAVAL ELECTRICAL ENGINEER


(RETIRED OFFICER OF CHILEAN NAVY), PLANNER AND
LEADER OF WORKING TEAM, WITH 25 YEARS WORKING IN
THE
CHILEAN
NAVY.
EXPERIENCE
IN
PLANNING,
COORDINATION, SUPERVISION AND CONTROL OF WORKS,
WORKING IN THE DIRECTION AND PLANNING OF LOGISTIC
PROCESSES AND MANAGEMENT.

PATROL VESSEL TABOGA


LOA : 31.2 MTS
BEAM
: 7.31 MTS
DWT : 167 TONS

PATROL VESSEL TABOGA AFTER ARRIVE TO SHIPYARD

SANDBLASTING COMP
(WITH NEW PILOT HO

STARTING THE SANDBLASTING

DISMANTLING THE OLD PILOT HOUSE

OLD PILOT HOUSE

MAKING THE NEW PILOT HOUSE

REPLACING PART OF THE SHELL PLATE

REPLACING BOTH PROPELLERS FOR


NEW ONES, ACCORDING WAS
DESIGNED

VERIFYING DEFLECTION OF THE TAIL SHAFT

PAINTING THE WHOLE VESSEL

UNDOCKING MANEUVERING

PATROL VESSEL TABOGA READY TO SAIL

PASSENGER VESSEL PACIFIC


QUEEN
LOA : 36.84 MTS
BEAM
: 7.74 MTS

CONDITION OF THE
HULL AT THE ARRIVING

PACIFIC QUEEN, ARRIVING TO SHIPYARD

RENWING PART OF THE SHELL PLATE

REPAIRING VALVE

REPAIRING THE LINE SHAFT

REPAIRING AND POLISHING PROPELLERS

UNDOCKING MANEUVERING OF PACIFIC QUEEN

LANDING CRAFT GENERAL ESTEBAN


HUERTAS
LOA : 38 MTS
BEAM
: 11 MTS
DWT : 313 TONS

GENERAL DEL ESTEBAN HUERTAS ARRIVING TO SHIPYARD

CONDITION OF HATCHES

DISALIGNMENT OF SHAFT LINE IN PORT


AND STARBOARD SIDE.
THE STRUT AND STERN TUBE, WAS
MACHINED
BASES OF WINCH AND CRANE IN BAD CONDI
WAS MADE NEW.

REPLACING PIPE IN BAD CONDITION

REPLACING THE MAIN


ENGINES AND
GENERATORS

REPLACING MORE THAN 38 TONS OF


STEEL, FROM THE HULL AND MAIN DECK

REPLACING MORE THAN 38 TONS OF


STEEL, FROM THE HULL AND MAIN DECK

STEEL REPLACED
NEW KEEL COOLERS WERE MADE

STEEL REPLACED
STEEL REPLACED

DISMANTLING THE OLD STRUCTUR

NEW STRUCTURE FINISHED

INSIDE OF THE STRUCTURE, BEFORE TO ST

INSIDE AFTER TO FINISH

UNDOCKING MANEUVERING

BARGE INTERCOASTAL IMI 102


LOA : 54.86 MTS
BEAM
: 16.4 MTS
DWT : 1,063 TONS

BARGE ARRIVING TO SHIPYARD

CONDITION OF THE HULL BEFORE TO


START WORKING

WASHING WITH H.P WATERJET

AFTER TO WASH THE BARGE

REPLACING STEEL PLATE

REPLACING STEEL PLATE

COMPLETE SANDBLASTING SA 2

PAITING THE WHOLE BARGE

CLEANING INSIDE THE TANKS

BARGE, PAITED AND FINISHED

UNDOCKING MANEUVERING

SUPPLY VESSEL CBACO BAY


LOA : 29.6 MTS
BEAM
: 7.9 MTS
DWT : 86 TONS

ARRIVING TO SHIPYARD

CONDITION OF THE HULL BEFORE TO START WORKING

SCRAPPING THE HULL

CONDITION OF THE VESSEL AFTER TO WASH WITH H.P. WATERJET

MAKING SANDBLASTING

PAINTING THE WHOLE VESSEL

STEEL WORK

MAKING NEW EXPANSION TANKS FOR THE MAIN ENGINES

FINISHING THE JOB

UNDOCKING MANEUVERING